Study Issue OCM-22-01—
Permanently Close the 100 Block
of S. Murphy Ave to Vehicular
Traffic
Connie Verceles,
Assistant to the City Manager/Economic Development
Attachment 4

Page 1 of 11 ends

2 • Issue proposed by Staff to:
 Conduct extensive outreach
• Determine Support for Closure
 Consider and evaluate impacts
 Review operational and one-time improvements
OCM-22-01— Permanently Close the 100 Block of
Murphy Avenue to Vehicular Traffic
Attachment 4

Page 2 of 11 ends

3 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Community Outreach
Attachment 4

Page 3 of 11 ends

4 Downtown Businesses Outreach
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Attachment 4

Page 4 of 11 ends

5 Current
Fee
Proposed
Fee (annual)
Sidewalk Permit Fee $214 $214
Street Permit Fee $0 $453
Sidewalk Maintenance $0 $1210
Street Maintenance
(+storm drains)
$0 $1400
Fire Prevention Permit $942 $942
Total $1,156 $4,219
Permit/Operational Costs
Attachment 4

Page 5 of 11 ends

6 Accessibility Improvements
Attachment 4

Page 6 of 11 ends

7 One-time Costs
Storm Drain Covers (need 9) $18,000
Accessibility Improvements $92,000
Total $120,000
Per Business (based on 20) $6,000
Proposed Accessibility Improvement Costs
Attachment 4

Page 7 of 11 ends

8 SDA Feedback
• Support Permanent Closure
• Mixed Support for
M
aintenance Cost Recovery
• Mixed Support—
A
ccessibility Improvements
Costs
• Want Consistency
(
furniture, Umbrellas, etc.)
Attachment 4

Page 8 of 11 ends

9 Preliminary Findings
• Strong Support for Permanent Street Closure
• Accessibility Improvements Needed
• Address Equity
 Maintenance Costs
• Businesses want current closure until 6/30/2023
• Consistency in Street’s Look/Feel/Operation
Attachment 4

Page 9 of 11 ends

10 Next Steps
Return to Council with following recommendations:
 Permanently Close Street
 Extend current closure until June 30, 2023
 Update Council Policy 1.1.10— Use of the Public
Sidewalk on the 100 Block of South Murphy Avenue
• Include Street Permit Process, Furniture
C
onsistency, Annual Review
 Proposed Maintenance Cost Recovery Amount
 Proposed Accessibility Improvement Cost Recovery
Amount
Attachment 4

Page 10 of 11 ends

11 Council Feedback/Input
• Move Forward with Closure
• Extend current closure until 6/30/2023
• Maintenance Cost Recovery
• Accessibility Improvements Cost Recovery
Attachment 4

Page 11 of 11 ends