2City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Purpose and Limits
3City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Purpose
Existing Access – Evelyn Avenue Intersection
4City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Purpose
Existing Access – Central Expressway Intersection
5City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Purpose
Existing Bicycle and Pedestrian Routes
1.5 miles, 8 min
Bicycle Route
1.6 miles, 25 min
Pedestrian Route
6City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Description and Partners
Central Expressway
Undercrossing
Caltrain
Undercrossing
7City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Agreement with Mountain View
Awarded consultant contract
Developed conceptual options
Joint Bicycle and Pedestrian Advisory
Commission/Committee (BPAC) Presentation
Caltrain/Joint Powers Board project approval
Refined options
Public outreach
On-going stakeholder coordination
Project to Date
8City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Alternatives
Western Alternative
9City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Alternatives
Western Alternative
Pros:
One tunnel
Straight
Shorter
Cons:
More utilities
Construction staging in
roadways
Small skylight option
Tree loss in Central
median
10City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Alternatives
Eastern Alternative
11City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Project Alternatives
Eastern Alternative
Pros:
Less utilities
Opening in middle lets
in air and light
Open space for
construction staging
Less tree loss
Cons:
Two tunnel segments
Visibility
Longer
12City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Local Examples – Santa Clara Caltrain Station
Comfort, Accessibility, Lighting, etc.
13City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Local Examples – California Ave, Palo Alto
14City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Local Examples
Homer Avenue, Palo Alto
Stevens Creek Trail at El Camino Real,
Mountain View
15City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Significant outreach effort
Supportive of project
Eastern option preferred
Mid-crossing opening
Natural light
Less expensive
Drainage concerns
Community Meeting, Feb. 2, 2023
Other comments:
Separation of bicyclists and pedestrians
Flatten ramp areas
Concerns about sharp turns
Protect ramp openings
16City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Supportive of project
Comments:
Most like midway opening
Ramp and tunnel widths
Connections to roadways
Compatibility with Evelyn
Avenue plans
Prefer no bollards or chicanes
Mountain View BPAC Meeting, Feb. 22, 2023
Passed motion to recommend eastern option
4 in favor
1 abstention
17City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Supportive of project
Comments:
Like midway opening
Interest in protected intersection
Compatibility with Evelyn
Avenue plans
Concerns about sharp turns at
tunnel
Interest in including art
Sunnyvale BPAC Meeting, March 16, 2023
Passed motion to recommend eastern option to
Sunnyvale City Council
5 in favor
1 absence
18City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Supportive of project
Comments:
Like eastern option
Interest in funding plan
Interest in including art
Include safety/security
considerations
Mountain View Council Transportation
Committee Meeting, April 10, 2023
Passed motion to recommend eastern option to
Mountain View City Council
3 in favor
19City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Consent calendar
No public comments
No Councilmember comments
Passed on consent to recommend eastern option
7 in favor
Mountain View City Council Meeting, April 25,
2023
20City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Finalize Caltrain Agreement
Complete environmental clearance
Caltrain to develop Request for Proposals for final
design
Secure remaining funding
Approximate gap of $44M
Next steps
21City of Sunnyvale – Bernardo Avenue Undercrossing – May 2023 Staff Recommendation
Selection of the Eastern Alignment as the Preferred
Alignment of the Bernardo Avenue Undercrossing
Project