Project Financial Summary
Project Costs Revenues Operating Costs
Prior Actual - - -
2022-23 492,650 492,650 -
2023-24 - - -
2024-25 - - -
2025-26 - - -
2026-27 - - -
2027-28 - - -
2028-29 - - -
2029-30 - - -
2030-31 - - -
2031-32 - - -
2032-33 - - -
2033-34 - - -
2034-35 - - -
2035-36 - - -
2036-37 - - -
2037-38 - - -
2038-39 - - -
2039-40 - - -
2040-41 - - -
2041-42 - - -
2042-43 - - -
20 Year Total - - -
Grand Total 492,650 492,650 -
Project Description/Scope/Purpose
The project goal is to reduce delays, queues, pollutant air emissions and collisions. Improve traffic flow, and facilitate safe pedestrians and bicyclists travel throughout along these corridors especially at signalized locations. The project scope includes data collection, analysis, computer modeling and development of new traffic signal coordination timing plans including revision and updating bike and pedestrian crossing times as well as clearance times at all traffic signals included in this project. As part of this project the current Traffic Management System software will be upgraded as it is no longer compatible with City's server platform and therefore no longer supported.
Project Evaluation and Analysis
The Moffett Park/Innovation corridor has never been retimed for coordinated signal operations. Per industry standards, traffic signal timing should be updated on a 2 to 4-year cycle. This corridor currently operates on a free operations mode; with this project new traffic volume data will be collected to develop and implement updated traffic signal coordination timing along the corridor. Clearance, pedestrian and bicycle timing for each location part of this project will be updated in compliance with latest Caltrans requirements.
Regular retiming of traffic signal systems is important to account for the changes in vehicular, bicyclists and pedestrian traffic demand, and to help reduce congestion, delays and improve travel times.
Fiscal Impact
This project is funded by Santa Clara Valley Transportation Authority (VTA) Transportation Fund for Clean Air (TFCA) grant funds in the amount of $492,650.00. No local matching funds are required. The total project cost is $492,650.00.
Funding Sources
Santa Clara Valley Transportation Authority (VTA) Transportation Fund for Clean Air (TFCA) Grant.
Plans and Goals
LT - Land Use and Transportation - LT-1: Coordinated Regional and Local Planning LT - Land Use and Transportation - LT-3: An Effective Multimodal Transportation System 835900 - Moffett Park Drive/Innovation Way Corridor Retiming Originating Year: 2021 Project Type: Traffic and Transportation Department: 250 - Public Works Planned Completion Year: 2024/25 Category: Capital Project Manager: Carmen Talavera 174
Attachment 1
1 of 1