Project Financial Summary
Project Costs Revenues Operating Costs
Prior Actual 1,024,484 - -
2023-24 32,766,232 30,393,497 -
2024-25 887,000 - -
2025-26 - - -
2026-27 - - -
2027-28 - - -
2028-29 - - -
2029-30 - - -
2030-31 - - -
2031-32 - - -
2032-33 - - -
2033-34 - - -
2034-35 - - -
2035-36 - - -
2036-37 - - -
2037-38 - - -
2038-39 - - -
2039-40 - - -
2040-41 - - -
2041-42 - - -
2042-43 - - -
2043-44 - - -
20 Year Total 887,000 - -
Grand Total 34,677,716 30,393,497 -
Project Description/Scope/Purpose
This project upgrades the city-owned Sunnyvale Materials Recovery and Transfer Station (SMaRT® Station) with new sorting and recycling equipment. This facility will have been in operation for 30 years by FY 2023/24. At the present time, the facility serves Sunnyvale and Mountain View under a Memorandum of Understanding (MOU) that expires in CY 2036. The preliminary cost estimate for design, installation, and construction is $34 million. The retrofit project will help us embrace cutting-edge recycling technologies, become a power-efficient facility, prepare for a more sustainable future and it will optimize efficiencies using automation. The project will entail installing optical sorters, separators and screens, metering bins, compactor, and other equipment. The project is expected to be complete by the summer of 2025. The estimate will be reviewed and confirmed in the final design stage of the project.

Project Evaluation and Analysis
The upgrades will retrofit the existing facility that has been in operation for 30 years. The original 1994 NRT mixed waste processing equipment line was replaced in a 2009 infrastructure project. The SMaRT Station exists in a corrosive bay-side environment and feasibility studies show that the metal building and much of the equipment it houses are in need of replacement. It will be designed to match the anticipated delivery quantities and needs of the ongoing facility participants. This will include (1) continued truck transfer to Kirby Canyon Landfill and/or another landfill, and (2) preparation of incoming waste for some to-be-determined waste conversion or energy recovery process.

Fiscal Impact
The design and construction of the $34 million project will be funded by the sale of utility revenue bonds. Debt service on the bonds is anticipated to be approximately the same (after inflation) as current SMaRT Station debt service costs. Facility participants other than Sunnyvale will pay proportional shares of the debt service in a manner to be described in a new MOU or other participation agreement.

Funding Sources
SMaRT Station Equipment Replacement Fund
Plans and Goals
EM - Environmental Management - EM-15: Environmentally-Sound Disposal 828260 - SMaRT Station Post-2021 Rebuild
Originating Year: 2009 Project Type: Solid Waste Department: 270 - Environmental Services Planned Completion Year: 2024/25 Category: Infrastructure Project Manager: Deepti Jain Attachment 3