FIRE STATION 2 – NEW CONSTRUCTION
Conceptual Design
Marlon Quiambao
December 10, 2024
2City of Sunnyvale – Fire Station 2–New Construction – December 2024 • 1st Project from Fire Station
Master Plan (FSMP , 2021)
• Includes new Fire Station
2 and Training Center
Existing Training Tower toremain
and apparatus bay restored
• Project design began in early
2024
Sept 2024 - Planning Staff Review
Oct 2024 - Sustainability
Commission Review
Background
3City of Sunnyvale – Fire Station 2–New Construction – December 2024 Improve Dept. of Public
Safety staff health and
safety
Provide updated fire
service facilities
Provide a high level of
fire protection services
to the community
Project Goals
4City of Sunnyvale – Fire Station 2–New Construction – December 2024 Sustainability Goals
• LEED Gold Equivalency
• All-Electric Building
• Public EV Chargers
• Buildings will be "solar
ready" at a minimum
5City of Sunnyvale – Fire Station 2–New Construction – December 2024 • Fire Station and Training Operations
Circulation
Return Routes
Open Training Area
• Parking
25 marked unsecured stalls for the
public/trainees
20 unmarked secured stalls for staff
FSMP noted 60 total stalls
Conceptual Site Plan
6City of Sunnyvale – Fire Station 2–New Construction – December 2024 • Total: 15,870 sq. ft.
• 1st Floor: ~10,950 sq. ft.
• Enhanced layout with:
Apparatus Bay (4 bays)
Decontamination/Hazmat/
Turnout Rooms
Shop and SCBA Rooms
Offices and Storage
BC and TC Dorm Suites
Fitness Room
Lobby/Conference Room
Fire Station 2 Floor Plan
7City of Sunnyvale – Fire Station 2–New Construction – December 2024 • Total: 15,870 sq. ft.
• 2nd Floor: ~5,960 sq. ft.
• Enhanced layout with:
Kitchen and Dining Room
Enclosed Day Room
Outdoor Patio
Dorms and Restrooms
Laundry and Storage
Elevator and Support
Spaces
Fire Station 2 Floor Plan
8City of Sunnyvale – Fire Station 2–New Construction – December 2024 • Approx. 5,850 sq. ft.
• Significant improvement for training
• Improved and Enhanced layout with:
Classroom (indoor and outdoor seating)
Fitness area
Separate Mens and Womens Locker Rooms
• Allows the Training Tower Apparatus Bay to be
restored to use
Turnout Gear Room
Decontamination Room
Shop and Storage
Training Center Floor Plan
9City of Sunnyvale – Fire Station 2–New Construction – December 2024 • Phase 0 (prior to construction): Relocate
EMS trailer (by others) and relocate/sell
existing training center modular building.
• Phase 1: Demo Drafting Pit and SCBA
Annex. Build new Fire Station 2.
• Phase 1a: Move staff into new Fire
Station 2.
• Phase 2: Demo existing station. Build
new training center.
• Phase 3: Complete site and frontage
improvements and install Public Art.
Construction Phasing
10City of Sunnyvale – Fire Station 2–New Construction – December 2024 Fire Station 2 Public Entrance
• Simple Massing
• Materials
• Subtle Angles
11City of Sunnyvale – Fire Station 2–New Construction – December 2024 Training Center and Public Parking Lot
• Consistent Massing
and Materials
• “Wedge” Shape
• Optimized space
around tower
• Secured site
12City of Sunnyvale – Fire Station 2–New Construction – December 2024 Training Center Entrance
13City of Sunnyvale – Fire Station 2–New Construction – December 2024 East Arques Frontage and Façade
14City of Sunnyvale – Fire Station 2–New Construction – December 2024 Corner Aerial Perspective (Wolfe/Arques)
15City of Sunnyvale – Fire Station 2–New Construction – December 2024 Schedule
Construction
BiddingCity Permitting Construction Grand
Opening
• Complete by late
2025
• Contract Award by
Spring 2026
• Complete by late
2027
• Early 2028
16City of Sunnyvale – Fire Station 2–New Construction – December 2024 Recommendation
Alternative 1: Approve the Recommended Conceptual Design for the Fire Station 2 – New Construction Project
17City of Sunnyvale – Fire Station 2–New Construction – December 2024 Thank you
Questions?