RECOMMENDED

CONDITIONS OF APPROVAL AND

STANDARD DEVELOPMENT REQUIREMENTS
MARCH 9, 2026
Planning Application 2022-7041
800 Carlisle Way
USE PERMIT: To allow construction of a replacement groundwater extraction well at approximately 800 to 1,000 feet below the ground surface, an approximately 50,000-gallon and 17-foot-tall water storage tank, chemical storage cabinets, and associated utility and right-of-way improvements; and EIR:
800 Carlisle Way Well & Water Tank Project Environmental Impact Report, State Clearinghouse No. 2023020080,
City Council Resolution No. _____________.

The following Conditions of Approval [COA] and Standard Development

Requirements [SDR] apply to the project referenced above. The COAs are specific conditions applicable to the proposed project. The SDRs are items which are codified or adopted by resolution and have been included for ease of reference, they may not be appealed or changed. The COAs and SDRs are grouped under specific headings that relate to the timing of required compliance. Additional language within a condition may further define the timing of required compliance. Applicable mitigation measures are noted with “Mitigation Measure” and placed in the applicable phase of the project.

In addition to complying with all applicable City, County, State and Federal Statutes, Codes, Or
dinances, Resolutions and Regulations, Permittee expressly accepts and agrees to comply with the following Conditions of Approval and Standard Development Requirements of this Permit:

GC: THE FOLLOWING GENERAL CONDITIONS AND STANDARD

DEVELOPMENT REQUIREMENTS SHALL APPLY TO THE APPROVED
PROJECT.

GC-1. CONFORMANCE WITH APPROVED PLANNING APPLICATION:

All building permit drawings and subsequent construction and operation shall substantially conform with the approved planning application, including: drawings/plans, materials samples, building color s, and other
items submitted as part of the approved application. Any proposed amendments to the approved plans or Conditions of Approval are subject to review and approval by the City. The Director of Community Development shall determine whether revisions are considered major or minor. Minor changes are subject to review and approval by the Director of Community Development. Major changes are subject to review at a public hearing. [COA] [PLANNING]
Attachment 5

Page 1 of 30 ends

2022-7041
800 Carlisle Way
GC-2. ENTITLEMENTS—EXERCISE AND EXPIRATION:

The approved entitlements shall be null and void two years from the date of approval by the final review authority if the approval is not exercised, unless a written request for an extension is received prior to the expiration date and is approved by the Director of Community Development. [SDR] (PLANNING)
GC-3. INDEMNITY:

The applicant shall defend, indemnify, an
d hold harmless the City, or any
of its boards, commissions, agents, officers, and employees (collectively, "City") from any claim, action, or proceeding against the City to attack, set aside, void, or annul, the approval of the project when such claim, action, or proceeding is brought within the time period provided for in applicable state and/or local statutes. The City shall promptly notify the applicant of any such claim, action or proceeding. The City shall have the option of coordinating the defense. Nothing contained in this condition shall prohibit the City from participating in a defense of any claim, action, or proceeding if the City bears its own attorney's fees and costs, and the City defends the action in good faith. [COA] [OFFICE OF THE CITY ATTORNEY]
GC-4. NOTICE OF FEES PROTEST:

As required by California Government C
ode Section 66020, the project
applicant is hereby notified that the 90- day period has begun as of the date of the approval of this application, in which the applicant may protest any fees, dedications, reservations, or other exactions imposed by the city as part of the approval or as a condition of approval of this development.

The fees, dedications, reservations, or other exactions are described in the approved plans, conditions of approval, and/or adopted city impact fee schedule. [SDR] [PLANNING / OCA]
GC-5. ENVIRONMENTAL MITIGATION MEASURES:

The project shall comply with all mitigation measures required in the Environmental Impact Report. The Mitigation Monitoring and Reporting Program (MMRP) has been included as conditions and the applicant shall be responsible for addressing all required mitigations for each phase of the project. [COA] [PUBLIC WORKS/PLANNING] MITIGATION

MEASURE
GC-6. ACOUSTIC BARRIERS:

Prior to initiation of any drilling activiti
es, the applicant shall apply for
and obtain approval of a Miscellaneous Plan Permit from the Director of Community Development no less than sixty (60) days in advance. The permit application shall include final plans specifying the design, dimensions, materials, and exact location of all acoustic barriers. The acoustic barriers shall be designed and located in substantial Attachment 5

Page 2 of 30 ends

2022-7041
800 Carlisle Way
conformance with approved Noise Assessment Report (DEIR Appendix B), subject to City of Sunnyvale review and approval of the final plans prior to initiation of drilling activities. The acoustic barriers shall include the following:
a. Approximately 600 linear feet of 32-foot-high, Sound Transmission Class (STC) rated 32 acoustic barrier wall shall be installed parallel to the site boundaries. The acoustic barrier wall shall be installed with no openings or gaps except for an acoustic gate on the north side of the project site to facilitate site access during drilling activities. This acoustic gate shall remain closed during drilling operations. b. Approximately 190 linear feet of 20-foot-high, STC rated 32 dual K- rail mounted acoustic barriers shall be installed on the south and north sides of drilling equipment. These acoustic barriers shall also be installed on portions of the east and west sides of drilling equipment as shown in Figure 7-3 of the Noise Assessment Report. c. Approximately 72 linear feet of 12-foot- high, STC rated 25 acoustic barrier walls shall be installed on the north, west and south sides of mud pump and air compressor.
d. Approximately 96 linear feet of 8-foot-high, STC rated 25 acoustical blankets shall be installed on the rig floor. [COA] [PLANNING]

MITIGATION MEASURE
GC-7.

PROVISION OF VOUCHERS FOR ALTERNATIVE ACCOMMODATIONS:
a. Notification: Cal Water shall notify all adjacent residents, including residents of 1394 Arleen Avenue; 1393 and 1394 Lillian Avenue; 819, 823, and 827 Coventry Court; and 1371, 1403, 1409, and 1415 Kingfisher Way, in writing of the drilling schedule no less than forty- five (45) days prior to the commencement of drilling activities. b. Provision of Vouchers: Cal Water shall provide hotel vouchers for the specific dates of scheduled nighttime drilling activities to residents of 819 and 823 Coventry Court at a rate of three hundred dollars ($300) per night per room, with the number of rooms determined in consultation with the residents, and shall provide vouchers to the remaining listed addresses upon request under the same terms. c. Accessibility Accommodations: Cal Water shall make reasonable accommodations for residents with mobility restrictions or other accessibility needs to facilitate their temporary relocation to and from the hotel, including arranging appropriate transportation or other necessary assistance in consultation with the affected resident. d. Proof of Compliance: Prior to the commencement of drilling activities, Cal Water shall submit a confirmation memorandum to the City verifying provision of the required vouchers. [COA] [PLANNING]

MITIGATION MEASURE
Attachment 5

Page 3 of 30 ends

2022-7041
800 Carlisle Way
GC-8. DESIGN LEVEL GEOTECHNICAL REPORT:

Prior to issuance of Valley Water permits for drilling and well construction, the applicant shall prepare and submit a design-level geotechnical report as part of the permitting process. The report shall identify site-specific design recommendations necessary to address geological and soil conditions and to ensure compliance with the California Building Code. The project design shall be revised as necessary to incorporate all recommendations in the approved geotechnical report.

Valley Water shall review and approve the geotechnical report and project plans for consistency with the report recommendations and California Building Code requirements prior to permit issuance. [COA] [PLANNING]

GC-9. PERMITS FOR WATER TANK:

Prior to commencement of the water tank construction, Cal Water shall submit applications for separate Design Review and Building Permits with the City of Sunnyvale. During the Design Review process, the Director of Community Development shall review and approve the final tank design to ensure it minimizes visual impacts and remains compatible with the character of the surrounding neighborhood. [COA] [PLANNING]

GC-10. ENCROACHMENT PERMIT:

Prior to any work in the public right-of -way, obtain an encroachment permit with insurance requirements for all public improvements including a traffic control plan per the latest California Manual on Uniform Traffic Control Devices (MUTCD) standards to be reviewed and approved by the Department of Public Works. [COA] [PUBLIC WORKS]

GC-11. STORMWATER DISCHARGE FROM PRODUCTION TEST:

Discharge of water generated during production testing to the storm drain system shall not exceed 1,200 gallons per minute (gpm). Any discharge to the storm drain system shall occur only during the dry weather conditions, to avoid overloading the storm drainage system. [COA] [ENVIRONMENTAL SERVICES]

GC-12. GROUNDWATER DISCHARGE TO SANITARY SEWER:

Prior to any discharge of groundwater to the sanitary sewer system, obtain a groundwater discharge permit from the City's Environmental Services Department. Notify the Department no less than two (2) weeks before the commencement of discharge activities. The discharge rate shall not exceed 200 gpm (approximately 0.3 million gallons per day (MGD)) and shall occur only during dry weather conditions. [COA] [ENVIRONMENTAL SERVICES]

GC-13. NOISE AND VIBRATION MONITORING:

Conduct noise and vibration monitoring throughout drilling activities in accordance with the recommendations of the noise and vibration Attachment 5

Page 4 of 30 ends

2022-7041
800 Carlisle Way
consultant and the City-approved Noise and Vibration Monitoring Plan.

Monitoring and reporting shall be implemented for the duration of drilling operations, and any exceedances of applicable thresholds shall be addressed through corrective actions as specified in the approved plan. [COA] [PLANNING]
BP: THE FOLLOWING CONDITIONS SHALL BE ADDRESSED ON THE

CONSTRUCTION PLANS SUBMITTED FOR ANY BUILDING PERMIT
AND SHALL BE MET PRIOR TO THE ISSUANCE OF SAID PERMIT(S).

BP-1. CONDITIONS OF APPROVAL:

Final plans shall include all Conditions of Approval included as part of

the approved application starting on sheet 2 of the plans. [COA] [PLANNING]
BP-2. RESPONSE TO CONDITIONS OF APPROVAL:

A written response indicating how each c
ondition has or will be addressed
shall accompany the building permit set of plans. [COA] [PLANNING] BP-3. NOTICE OF CONDITIONS OF APPROVAL:

A Notice of Conditions of Approval
shall be filed in the official records of
the County of Santa Clara and provide proof of such recordation to the City prior to issuance of any City permit, allowed use of the property, as applicable. The Notice of Conditions of Approval shall be prepared by the Planning Division and shall include a description of the subject property, the Planning Application number, attached conditions of approval and any accompanying subdivision or parcel map, including book and page and recorded document number, if any, and be signed and notarized by each property owner of record.

For purposes of determining the property owner on record, the applicant shall provide the City with evidence in the form of a report from a title insurance company indicating that the record owner(s) are the person(s) who have signed the Notice of Conditions of Approval. [COA] [PLANNING] BP-4. BLUEPRINT FOR A CLEAN BAY:

The building permit plans shall include
a “Blueprint for a Clean Bay” on
one full sized sheet of the plans. [SDR] [PLANNING]
BP-5. COMPLETION OF PUBLIC IMPROVEMENTS:

Applicant shall complete all required public improvements as required and in accordance with City approved plans, prior to any buil ding permit
issuance or the commencement of any onsite work, or as determined by the Department of Public Works. [COA] [PUBLIC WORKS]
BP-6. CONSTRUCTION MATERIAL AND STAGING:

Attachment 5

Page 5 of 30 ends

2022-7041
800 Carlisle Way
All construction related materials, equipment, and construction workers parking need to be managed on-site and not located in the public right- of-ways or public easements. [COA] [PUBLIC WORKS]
BP-7. TREE PROTECTION PLAN:

Prior to issuance of Building Permit for the proposed water tank, obtain approval of a tree protection plan from the Director of Community Development. The tree protection plan shall include measures noted in Title 19 of the Sunnyvale Municipal Code and at a minimum:
a. An inventory shall be taken of all existing trees on the plan including the valuation of all
‘protected trees’ by a certified arborist, using the
latest version of the “Guide for Plant Appraisal” published by the International Society of Arboriculture (ISA).
b. All existing (non-orchard) trees on the plans, showing size and varieties, and clearly specify which are to be retained. c. Provide fencing around the drip line of the trees that are to be saved and ensure that no construction debris or equipment is stored within the fenced area during the course of demolition and construction. d. The tree protection plan shall be installed prior to issuance of any Building or Grading Permits, subject to the on-site inspection and approval by the City Arborist and shall be maintained in place during the duration of construction and shall be added to any subsequent building permit plans. [COA] [PLANNING/CITY ARBORIST]
BP-8. BEST MANAGEMENT PRACTICES - STORMWATER:

The project shall comply with the following source control measures as outlined in the BMP Guidance Manual and SMC 12.60.230. Best management practices shall be identified on the building permit set of plans and shall be subject to review and
approval by the Director of Public
Works:
a. Storm drain stenciling. The stencil is available from the City's Environmental Services Department, which may be reached by calling (408) 730-7717.
b. Appropriate covers, drains, and storage precautions for outdoor material storage areas
BP-9. EXTERIOR LIGHTING PLAN:

Prior to the commencement of drilling activities and prior to the issuance of a Building Permit (for the proposed water tank) submit an exterior lighting plan, including fixture and pole designs, for review and approval by the Director of Community Development. Driveway and parking area lights shall include the following:
a. Sodium vapor (or illumination with an equivalent energy savings). b. Pole heights to be uniform and compatible with the areas, including the adjacent residential areas. Light standards shall not exceed 18 Attachment 5

Page 6 of 30 ends

2022-7041
800 Carlisle Way
feet on the interior of the project and 8 feet in height on the periphery of the project near residential uses.
c. Provide photocells for on/off control of all security and area lights. d. All exterior security lights shall be equipped with vandal resistant covers.
e. Wall packs shall not extend above the roof of the building. f. Lights shall have shields to prevent glare onto adjacent properties. [COA] [PLANNING]
BP-10.

PHOTOMETRIC PLAN:

Prior to the commencement of drilling activities and prior to the issuance of a Building Permit (for the proposed water tank) submit a contour photometric plan for approval by the Director of Community Development. The plan shall meet the specifications noted in the Standard Development Requirements. [COA] [PLANNING]
BP-11.

CONSTRUCTION MANAGEMENT PLAN:

The project applicant shall implement a Construction Management Plan (CMP) to minimize impacts of drilling and tank construction on surrounding residential uses to the extent possible. The CMP shall be subject to review and approval by the Director of Community Development and Director of Public Works with a separate Miscellaneous Plan Permit (MPP) no less than sixty (60) days prior to the commencement of drilling and tank construction activities. The CMP shall identify measures to minimize the impacts of drilling and tank construction including the following:
a. Measures to control noise by limiting water tank construction hours to those allowed by the SMC, avoiding sensitive early morning and evening hours, notifying residents prior to major construction activities, and appropriately scheduling use of noise-generating equipment.
b. Comply with all applicable mitigation measures identified in the MMRP (Attachment 6) of the Environmental Impact Report, as incorporated herein as conditions of approval.
c. Use ‘quiet’ models of air compressors and other stationary noise sources where such technology exists.
d. Equip all internal combustion engine-driven equipment with mufflers, which are in good condition and appropriate for the equipment. e. Locate all stationary noise-generating equipment, such as air compressors and portable power generators, as far away as possible from residences or other noise-sensitive land uses.
f. Locate staging areas and construction material areas as far away as possible from residences or noise-sensitive land uses.

Attachment 5

Page 7 of 30 ends

2022-7041
800 Carlisle Way
g. Route all construction traffic to and from the project site via designated truck routes where possible. Prohibit construction-related heavy truck traffic in residential areas where feasible. Obtain approval of proposed construction vehicle truck routes from the Department of Public Works.
h. Manage construction parking so that neighbors are not impacted by construction vehicles. When the site permits, all construction parking shall be on-site and not on the public streets.
i. Prohibit unnecessary idling of internal combustion engine -driven equipment and vehicles.
j. Notify all adjacent business, residents, and noise-sensitive land uses of the construction schedule in writing. Notify nearby residences of significant upcoming construction activities at appropriate stages in the project using mailing or door hangers.
k. Designate a “disturbance coordinator” who would be responsible for responding to any local complaints about construction noise. The disturbance coordinator will determine the cause of the noise complaint and will require that reasonable measures warranted to correct the problem be implemented. Conspicuously post a telephone number for the disturbance coordinator at the construction site and include it in the notice sent to neighbors regarding the construction schedule. [COA] [PLANNING] [PUBLIC WORKS]

BP-12. CONSTRUCTION AIR QUALITY MITIGATION MEASURES:

Prior to the issuance of building permits, the Bay Area Air Quality Management District’s (BAAQMD) basic construction mitigation measures from Table 8-1 of the BAAQMD 2011 CEQA Air Quality Guidelines (or subsequent updates) shall be noted on the construction documents, including the following:
a) All exposed surfaces (e.g., parking areas, staging areas, soil piles, graded areas, and unpaved access roads) shall be watered two times per day.
b) All haul trucks transporting soil, sand, or other loose material off- site shall be covered.
c) All visible mud or dirt track-out onto adjacent public roads shall be removed using wet power vacuum street sweepers at least once per day. The use of dry power sweeping is prohibited.
d) All vehicle speeds on unpaved roads shall be limited to 15 miles per hour (mph).
e) All roadways, driveways, and sidewalks to be paved shall be completed as soon as possible. Building pads shall be laid as soon as possible after grading unless seeding or soil binders are used. f) Idling times shall be minimized either by shutting equipment off when not in use or reducing the maximum idling time to 5 minutes (as required by the California airborne toxics control measure Title Attachment 5

Page 8 of 30 ends

2022-7041
800 Carlisle Way
13, Section 2485 of California Code of Regulations [CCR]). Clear signage shall be provided for construction workers at all access points.
g) All construction equipment shall be maintained and properly tuned in accordance with manufacturers’ specifications. All equipment shall be checked by a certified mechanic and determined to be running in proper condition prior to operation.
h) Post a publicly visible sign with the telephone number and person to contact at the Lead Agency regarding dust complaints. This person shall respond and take corrective action within 48 hours.

The Air District’s phone number shall also be visible to ensure compliance with applicable regulations. [COA] [PLANNING]

MITIGATION MEASURE
BP-13.

LOW DIESEL PARTICULATE MATTER EXHAUST EMISSIONS:

Incorporating measures to control diesel particulate matter emissions into the final Building plan set for review and approval by the Director of Community Development. Implement a feasible plan to reduce DPM emissions by 35 percent such that increased cancer risk from construction would be reduced below the Air District significance threshold:
a) All construction equipment larger than 25 horsepower used at the site for more than two continuous days or 20 hours total shall meet U.S. EPA Tier 4 emission standards for PM (PM10 and PM2.5), if feasible, otherwise,
- If use of Tier 4 equipment is not available, alternatively use equipment that meets U.S. EPA emission standards for Tier 2 or 3 engines and include particulate matter emissions control equivalent to CARB Level 3 verifiable diesel emission control devices that altogether achieve a 35 percent reduction in particulate matter exhaust in comparison to uncontrolled equipment; alternatively (or in combination).
- Use of electrical or non-diesel fueled equipment.
b) Alternatively, develop another construction operations plan demonstrating that the construction equipment used on-site would achieve a reduction in construction diesel particulate matter emissions by 35 percent or greater. Elements of the plan could include a combination of some of the following measures:
- Implementation of No. 1 above to use Tier 4 or alternatively fueled equipment,
- Installation of electric power lines during early construction phases to avoid use of diesel generators and compressors, - Use of electrically-powered equipment,
Attachment 5

Page 9 of 30 ends

2022-7041
800 Carlisle Way
- Forklifts and aerial lifts used for exterior and interior building construction shall be electric or propane/natural gas powered, - Change in construction build-out plans to lengthen phases, and - Implementation of different building techniques that result in less diesel equipment usage. [COA] [PLANNING] MITIGATION

MEASURE

BP-14. CONSTRUCTION NOISE MITIGATION MEASURES:

The project shall employ site-specific noise attenuation measures during construction to reduce the generation of construction noise and vibration.

These measures shall be included in a noise control plan that shall be submitted for review and approval by the Director of Community Development. Measures specified in the noise control plan and implemented during construction shall include, at a minimum, the following noise control strategies:
a) Equipment and trucks used for construction shall use the best available noise control techniques (e.g., improved mufflers, equipment redesign, use of intake silencers, ducts, engine enclosures, and acoustically attenuating shields or shrouds); b) Impact tools (e.g., jackhammers, pavement breakers, and rock drills) used for construction shall be hydraulically or electrically powered wherever possible to avoid noise associated with compressed air exhaust from pneumatically powered tools; and c) Stationary noise sources shall be located as far from adjacent receptors as possible, and they shall be muffled and enclosed within temporary sheds, incorporate insulation barriers, or include other measures.
d) Pile-driving is prohibited unless authorized by the Director of Community Development. If authorized, noise and vibration reducing pile-driving techniques shall be employed during construction and will be monitored to ensure no damage to nearby structures occurs (i.e., vibrations above peak particle velocity (PPVs) of 0.25 inches per second at nearby structures). These techniques shall include:
- Installing intake and exhaust mufflers on pile-driving equipment; - Vibrating piles into place when feasible, and installing shrouds around the pile-driving hammer where feasible as determined by the Director of Community Development;
- Implementing “quiet” pile-driving technology (such as pre-drilling of piles and the use of more than one pile driver to shorten the total pile driving duration), where feasible, in consideration of geotechnical and structural requirements and conditions; - Using cushion blocks to dampen impact noise, if feasible based on soil conditions as determined by the Director of Community Attachment 5

Page 10 of 30 ends

2022-7041
800 Carlisle Way
Development. Cushion blocks are blocks of material that are used with impact hammer pile drivers. They consist of blocks of material placed atop a piling during installation to minimize noise generated when driving the pile. Materials typically used for cushion blocks include wood, nylon and micarta (a composite material); and
− At least 48 hours prior to pile-driving activities, notifying building owners and occupants within 600 feet of the project area of the dates, hours, and expected duration of such activities. [COA][PLANNING]
BP-15.

NESTING BIRDS:

All construction and clearing activities shall be conducted outside of the avian nesting season (January 15-August 31), when feasible. If clearing and/or construction activities occur during the nesting season, preconstruction surveys for nesting raptors, special-status resident birds, and other migratory birds protected by the Migratory Bird Treaty Act shall be conducted by a qualified biologist, up to three days before initiation of construction activities, including tree removal and/or site preparation involving removal of vegetation.

The qualified biologi
st shall survey the construction zone to determine
whether the activities taking place have the potential to disturb or otherwise harm nesting birds. If an active nest is located within 100 feet (250 feet for raptors) of construction activities, the project applicant shall establish an exclusion zone (no ingress of personnel or equipment at a minimum radius of 100 feet or 250 feet, as appropriate, around the nest).

Alternative exclusion zones may be established through consultation with the CDFW and USFWS, as necessary. The City shall be notified if altered exclusion zone widths are authorized by these agencies prior to the initiation of work. The exclusion zones shall remain in force until all young have fledged.

A final report of
nesting birds, including any protection measures, shall be submitted to the Director of Community Development prior to initiation of construction activities, including tree removal and/or site preparation involving removal of vegetation. [COA] [PLANNING]

MITIGATION MEASURE
BP-16.

ARCHAEOLOGICAL RESOURCES:

Prior to the issuance of grading or building permits, the project applicant is required to include information on the improvement plans that if, during the course of grading or construction, cultural resources (i.e. prehistoric or historic sites) are discovered, work will stop in that area and within 100 feet of the find until a qualified archeologist can assess Attachment 5

Page 11 of 30 ends

2022-7041
800 Carlisle Way
the significance of the find and, if necessary, develop appropriate treatment measures as part of a treatment plan in consultation with the City and all other appropriate agencies. The treatment plan shall include measures to document and protect the discovered resource. Consistent with CEQA Guidelines Section 15126.4(b)(3), preservation in place will be the preferred method of mitigating impacts to the discovered resource.

Pursuant to Government Code Section 6254.10, information on the discovered resource shall be confidential. [COA] [PLANNING]

MITIGATION MEASURE

BP-17. CULTURAL RESOURCES:

In the event of the discovery of human remains during construction, there shall be no further excavation or disturbance of the site within a 50-foot radius of the remains or any nearby area reasonably suspected to overlie adjacent remains. The Santa Clara County Coroner shall be notified and shall make a determination as to whether the remains are Native American. If the Coroner determines that the remains are not subject to his authority, the Coroner shall notify the Native American Heritage Commission who shall attempt to identify descendants of the deceased Native American. If no satisfactory agreement can be reached as to the disposition of the remains pursuant to State law, then the land owner shall re-inter the human remains and items associated with Native American burials on the property in a location not subject to further subsurface disturbance.

All measures shall be printed on all construction documents, contracts, and project plans, and reviewed by the Community Development Director prior to issuance of grading and building permits. During construction, the project applicant and contractor shall be responsible for, implementing these measures. [COA] [PLANNING] MITIGATION

MEASURE

BP-18. PALEONTOLOGICAL RESOURCES:

Prior to the issuance of grading or building permits, the project is required to include information on the improvement plans that if, during the course of grading or construction, fossils are discovered, work shall be halted immediately within 50 feet of the discovery, the City of Sunnyvale Community Development Department shall be notified, and the significance of the find and recommended actions must be determined by a qualified paleontologist. In addition, prior to the commencement of a project site preparation, all construction personnel shall be informed of the potential to discover fossils and the procedures to follow. [COA] [PLANNING] MITIGATION MEASURE

Attachment 5

Page 12 of 30 ends

2022-7041
800 Carlisle Way
EP: THE FOLLOWING CONDITIONS SHALL BE ADDRESSED AS PART OF AN ENCROACHMENT PERMIT APPLICATION.

EP-1.

UTILITY CONNECTION:

This project requires connection to all City utilities or private utilities operating under a City or State franchise which provide adequate levels of service. [COA] [PUBLIC WORKS] (SMC 18.08.030, SMC 12.08.010) EP-2
UTILITY CONNECTION TO THE MAIN:

All storm drain laterals connecting to the main shall be at a new storm drain manhole, except where a pipe to pipe connection is permitted if the mainline is 36” or larger, or a junction structure is permitted where the point of connection is within close vicinity of an existing down-stream manhole. [SDR] [PUBLIC WORKS]
EP-3.

WET UTILITIES:

All wet utilities (water, storm drain) on private property shall be privately owned and maintained. The domestic water systems shall be privately owned and maintained beyond the meter. [COA] [PUBLIC WORKS] EP-4.

TRAFFIC CONTROL PLAN:

Submit a traffic control plan with the off-site improvement plans for review and approval. Per the City’s Temporary Traffic Control Checklist, the traffic control plan shall include a summary of the traffic control types, dates, times and blocks affected. All construction related materials, equipment, and construction workers parking need to be stored on-site and the public streets need to be kept free and clear of construction debris. [COA] [PUBLIC WORKS]
EP-5.

DAMAGE TO EXISTING PUBLIC IMPROVEMENTS:

The applicant shall be responsible for rectifying any damage to the existing public improvements fronting and adjacent to the project site as a result of project construction, to City’s satisfaction by the Public Works Department. [COA] [PUBLIC WORKS]
DC: THE FOLLOWING CONDITIONS SHALL BE COMPLIED AT ALL TIMES DURING THE CONSTRUCTION PHASE OF THE PROJECT.

DC-1. BLUEPRINT FOR A CLEAN BAY:

The project shall be in compliance with stormwater best management practices for general construction activity until the project is completed. [SDR] [PLANNING]
DC-2.

TREE PROTECTION:

Attachment 5

Page 13 of 30 ends

2022-7041
800 Carlisle Way
All tree protection shall be maintained, as indicated in the tree protection plan, until construction has been completed and the installation of landscaping has begun. [COA] [PLANNING]

DC-3. CLIMATE ACTION PLAN – OFF ROAD EQUIPMENT REQUIREMENT:

OR 2.1: Idling times will be minimized either by shutting equipment off when not in use or reducing the maximum idling time to 5 minutes (as required by the California airborne toxics control measure Title 13, Section 2485 of California Code of Regulations [CCR]), or less. Clear signage will be provided at all access points to remind construction workers of idling restrictions.

OR 2.2: Construction equipment must be maintained per manufacturer’s specifications.

OR 2.3: Planning and Building staff will work with project applicants to limit GHG emissions from construction equipment by selecting one of the following measures, at a minimum, as appropriate to the construction project:
a) Substitute electrified or hybrid equipment for diesel and gasoline powered equipment where practical.
b) Use alternatively fueled construction equipment on-site, where feasible, such as compressed natural gas (CNG), liquefied natural gas (LNG), propane, or biodiesel.
c) Avoid the use of on-site generators by connecting to grid electricity or utilizing solar-powered equipment.
d) Limit heavy-duty equipment idling time to a period of 3 minutes or less, exceeding CARB regulation minimum requirements of 5 minutes. [COA] [PLANNING]

DC-4. DUST CONTROL:

At all times, the Bay Area Air Quality Management District’s CEQA Guidelines and “Basic Construction Mitigation Measures Recommended for All Proposed Projects”, shall be implemented. [COA] [PLANNING] Attachment 5

Page 14 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # PLN2022-7041, SCH # 2023020080
January 2026
Attachment 5

Page 15 of 30 ends

2022-7041
800 Carlisle Way

P R E F A C E
Section 210

81.6 of the California Environmental Quality Act (CEQA) requires a Lead Agency to adopt a Mitigation Monitoring and Reporting Program
(MMRP) whenever it approves a project for which measures have been required to mitigate or avoid significant effects on the environment. The purpose of the monitoring and rep orting program is to ensure compliance with the mi ti gation meas ures during project implementation.

On July 21, 2026, the City Council certified the Environmental Impact Report (EIR) for the 800 C arlisle Way Well and Water Tank project.

The Final EIR concluded that the implementation of the project could result in significant effects on the environment and mitigation measures were identified to reduce significant impacts identified. This MMRP addresses those measures in terms of how and when they will be implemented.

Attachment 5

Page 16 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation

AIR QUALITY
Impact AIR-1: The
project would not
conflict with or obstruct
implementation of the
applicable air quality
plan with mitigation
incorporated.

I
mpact AIR-2: The
project would not result
in a cumulatively
considerable net increase
of any criteria pollutant
for which the project
region is non-attainment
under an applicable
federal or state ambient
air quality standard with
mitigation incorporated.

L UTE DEIR MM 3.5.3: Basic BMPs – Include measures to
control dust and exhaust during construction.

D
uring any construction period ground disturbance, the
applicant shall ensure that the project contractor implement measures to control dust and exhaust. Implementation of the measures recommended by BAAQMD and listed below
would reduce the air quality impacts associated with grading and new construction to a less-than-significant level.

Additional measures are identified to reduce construction equipment exhaust emissions. The contractor shall implement the following best management practices that are required of all projects:
• All exposed surfaces (e.g., parking areas, staging
areas, soil piles, graded areas, and unpaved access
roads) shall be watered two times per day.
• All haul trucks transporting soil, sand, or other loose material off-site shall be covered.
• All visible mud or dirt track-out onto adjacent public roads shall be removed using wet power vacuum
street sweepers at least once per day. The use of dry
power sweeping is prohibited.

Prior to issuance of
building permits, the
applicant is responsible
for incorporating the
measures to control
dust, particulate matter,
and diesel emissions
included in this
mitigation measure into
the final plan set. The
City is responsible for
reviewing the final plan
set for compliance.

D
uring construction,
the applicant and its
contractors are
responsible for
implementing the
measures identified in
the mitigation measure.

A ll measures to
control dust,
particulate matter,
and diesel
emissions during
construction listed
in this mitigation
measure shall be
printed on all
construction
documents,
contracts, and
project plans.

Co mmunity
Development
Director
Attachment 5

Page 17 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
• All vehicle speeds on unpaved roads shall be limited
to 15 miles per hour (mph).
• All roadways, driveways, and sidewalks to be paved
shall be completed as soon as possible. Building
pads shall be laid as soon as possible after grading
unless seeding or soil binders are used.
• Idling times shall be minimized either by shutting
equipment off when not in use or reducing the
maximum idling time to 5 minutes (as required by
the California airborne toxics control measure Title
13, Section 2485 of California Code of Regulations
[CCR]). Clear signage shall be provided for
construction workers at all access points.
• All construction equipment shall be maintained and
properly tuned in accordance with manufacturer’s
specifications. All equipment shall be checked by a
certified mechanic and determined to be running in
proper condition prior to operation.
• Post a publicly visible sign with the telephone
number and person to contact at the Lead Agency
regarding dust complaints. This person shall respond
and take corrective action within 48 hours. The Air
District’s phone number shall also be visible to
ensure compliance with applicable regulations.

Attachment 5

Page 18 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
Impact AIR-3: The
project would not expose
sensitive receptors to
substantial pollutant
concentrations with
mitigation incorporated.

Refer to LUTE DEIR MM 3.5.3 above.

MM AIR-3.1: Use construction equipment that has low
diesel particulate matter exhaust emissions.

Implement a feas
ible plan to reduce DPM emissions by 35
percent such that increased cancer risk from construction would be reduced below the Air District significance
threshold as follows:

1. All construction
equipment larger than 25
horsepower used at the site for more than two
continuous days or 20 hours total shall meet U.S.

EPA Tier 4 emission standards for PM (PM
10 and
PM2.5), if feasible, otherwise,
a. If use of Tier 4 equipment is not available,
alternatively use equipment that meets U.S.

EPA emission standards for Tier 2 or 3
engines and include particulate matter
emissions control equivalent to CARB
Level 3 verifiable diesel emission control
devices that altogether achieve a 35 percent
reduction in particulate matter exhaust in
comparison to uncontrolled equipment;
alternatively (or in combination).
b. Use of electrical or non-diesel fueled
equipment.

2. Alternatively, the applicant may develop another
construction operations plan demonstrating that the
Prior to issuance of
building permits, the
applicant is responsible
for incorporating the
measures to control
diesel particulate matter
emissions into the final
plan set. The City is
responsible for
reviewing the final plan
set for compliance.

During construction,
th
e applicant and its
contractors are
responsible for
implementing the diesel
particulate matter
control measures
identified in the
mitigation measure.

All measures to
reduce diesel
particulate matter
emissions shall be
printed on all
construction
documents,
contracts, and
project plans.

Community
Developm
ent
Director
Attachment 5

Page 19 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
construction equipment used on-site would achieve a
reduction in construction diesel particulate matter
emissions by 35 percent or greater. Elements of the
plan could include a combination of some of the
following measures:
a. Implementation of No. 1 above to use Tier
4 or alternatively fueled equipment,
b. Installation of electric power lines during
early construction phases to avoid use of
diesel generators and compressors,
c. Use of electrically-powered equipment,
d. Forklifts and aerial lifts used for exterior
and interior building construction shall be
electric or propane/natural gas powered,
e. Change in construction build-out plans to
lengthen phases, and
f. Implementation of different building
techniques that result in less diesel
equipment usage.

Such a cons
truction operations plan would be subject to
review by an air quality expert and approved by the City prior to construction.

BIOLOGICAL RESOURCES
Impact BIO-1: The
project would not have a
substantial effect, either
directly or through
habitat modifications, on
MM BIO-1.1: When possible, construction shall be
scheduled to avoid the nesting season to the extent feasible.

The nesting season for most birds, including most raptors, in The applicant is
responsible for ensuring
construction activities
avoid the nesting
All mitigation
measures shall be
printed on all
construction
documents,
Community
Development
Director
Attachment 5

Page 20 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
any special status species
identified as a candidate,
sensitive, or special
status species in local or
regional plans, policies,
or regulations, or by the
CDFW or USFWS with
mitigation incorporated.

Impact BI
O-4: The
project would not
interfere substantially
with the movement of
any native resident or
migratory fish or wildlife
species or with
established native
resident or migratory
wildlife corridors, or
impede the use of native
wildlife nursery sites
with mitigation
incorporated.
the San Francisco Bay area extends from February 1 through August 31.

If it is
not possible to schedule construction and tree removal
between September and January, then pre-construction
surveys for nesting birds shall be completed by a qualified ornithologist to ensure that no nests shall be disturbed during project implementation. This survey shall be completed no more than 14 days prior to the initiation of grading, tree removal, or other demolition or construction activities during the early part of the breeding season (February through April) and no more than 30 days prior to the initiation of these activities during the late part of the breeding season (May through August).

During t
his survey, the ornithologist shall inspect all trees and other possible nesting habitats within and immediately
adjacent to the construction area for nests. If an active nest is found sufficiently close to work areas to be disturbed by construction, the ornithologist shall determine the extent of a construction-free buffer zone to be established around the nest to ensure that nests of bird species protected by the MBTA or Fish and Game code shall not be disturbed during project construction.

A final r
eport of nesting birds, including any protection
measures, shall be submitted to the Director of Community Development prior to the start of grading or tree removal. season to the extent
feasible.

The applic
ant is
responsible for ensuring
pre-construction
surveys are completed
(as described in
mitigation measure
MM BIO-1.1) if
construction and tree
removal cannot occur
between September and
January. Any
construction buffer
zones determined to be
required shall be
implemented and
maintained during
construction activities.

Prior to
the start of
grading or tree removal,
the applicant is
responsible for
submitting a final report
of nesting birds
(including any
protection measures) to
the City.
contracts, and
project plans.

A final re
port of
nesting birds,
including any
protection
measures shall be
submitted by the
applicant to the
City.

Attachment 5

Page 21 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation

CULTURAL RESOURCES
Impact CUL-2: The
project would not cause a
substantial change in the
significance of an
archaeological resource
pursuant to CEQA
Guidelines Section
1564.5 with mitigation
incorporated.

MM CUL-2.1: Prior to ground-disturbing activities, a
qualified archaeologist shall provide cultural resources training to all contractors and employees involved in
trenching and excavation. The training shall inform
participants how to recognize archaeological artifacts and deposits, and discuss their obligations under the law and the project mitigation measures.

Prior to ground-
disturbing activities, the
applicant is responsible
for having a qualified
archeologist provide a
cultural resources
training to all
contractors as described
in mitigation measure
MM CUL-2.1.

All mitigation
measures shall be
printed on all
construction
documents,
contracts, and
project plans.

Community
Development
Director

MM CUL-2.2: A qualified archaeologist shall monitor the demolition of the building foundations and any other below surface disturbances, such as but not limited to, grading, excavation, roadway improvements, and utility connections and improvements. If any cultural resources are identified, all activity in the vicinity of such resources shall stop until a research design and treatment plan is prepared to address those types of resources encountered and such plan is
approved by the City, as described in mitigation measure MM CUL-2.3 below. Any cultural resources identified shall be evaluated to determine if these resources would qualify for the NRHP or CRHR. If no resources are found during
excavation work, the implementation of mitigation measures MM CUL-2.3 is not required.

During demolition of
the building
foundations and any
other below surface
disturbances, the
applicant is responsible
for having a qualified
archaeologist monitor
construction activities.

All mitigation
measures shall be
printed on all
construction
documents,
contracts, and
project plans.

Community
Development
Director
Attachment 5

Page 22 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
M M CUL-2.3: In the event that buried, or previously
unrecognized archaeological deposits or materials of any kind are inadvertently exposed during any construction activity, all activity within a 50-foot radius of the find shall be stopped until a qualified archaeologist can assess the find and provide recommendations for further treatment, if warranted.

Preservation in place is the preferred treatment of an
archeological resource. When preservation in place of an archeological resource is not feasible, data recovery, in accordance with a data recovery plan prepared by a qualified archaeologist and adopted by the City, is the appropriate mitigation. Construction and potential impacts to the area within a radius determined by the archaeologist shall not recommence until the assessment is complete.

If archaeological
deposits are found, the
applicant and its
contractor are
responsible for
implementing
mitigation measure
MM CUL-2.3 at the
time of discovery.

A ll mitigation
measures shall be
printed on all
construction
documents,
contracts, and
project plans.

Co mmunity
Development
Director
Impact CUL-3: The
project would not disturb
any human remains,
including those interred
outside of dedicated
cemeteries with
mitigation incorporated.

MM CUL-3.1: In the event that human remains are
discovered during excavation and/or grading of the site, all activity within a 50-foot radius of the find shall be stopped.

The Santa Clara County Coroner shall be notified and shall make a determination as to whether the remains are of Native American origin or whether an investigation into the cause of death is required. If the remains are determined to be Native American, the Coroner shall notify the NAHC immediately.

Once NAHC identifies the most likely descendants, the
descendants shall make recommendations regarding proper burial, which shall be implemented in accordance with
Section 15064.5 of the CEQA Guidelines.

If human remains are
found, the applicant and
its contractor are
responsible for
implementing
mitigation measure
MM CUL-3.1 at the
time of discovery.

All mitigation
measures shall be
printed on all
construction
documents,
contracts, and
project plans.

Community
Development
Director
Attachment 5

Page 23 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
ENERGY
Impact EN-1: The
project would not result
in a potentially
significant environmental
impact due to wasteful,
inefficient, or
unnecessary consumption
of energy resources,
during project
construction or operation
with mitigation
incorporated.

Refer to LUTE DEIR MM 3.5.3 and MM AIR-3.1 above.

GEOLOGY AND SOILS
Impact GEO-6: The
project would not
directly or indirectly
destroy a unique
paleontological resource
or site or unique
geological feature with
mitigation incorporated.

MM GEO-6.1: Should a unique paleontological resource or site or unique geological feature be identified at the project site during any phase of construction, all ground disturbing activities within 25 feet shall cease and the Sunnyvale Community Development Director notified immediately. A
qualified paleontologist shall evaluate the find and prescribe measures to preserve the find. Work may proceed on other parts of the project site while measures to preserve the paleontological resources or geologic features are
implemented. One such measure would be a buffer that
would be established by the qualified paleontologist. This buffer would preserve the area immediately surrounding the discovered resource while allowing work to happen beyond the buffer. Upon completion of the paleontological
assessment, a report shall be submitted to the City and, if paleontological materials are recovered, a paleontological All miti gation
measures shall be
printed on all
construction
documents,
contracts, and
project plans.

Community
Development
Director
Attachment 5

Page 24 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
repository, such as the University of California Museum of Paleontology shall also be submitted to the City.

GREENHOUSE GAS EMISSIONS
Impact GHG-1: The
project would not
generate GHG emissions,
either directly or
indirectly, that may have
a significant impact on
the environment with
mitigation incorporated.

I
mpact GHG-2: The
project would not
conflict with an
applicable plan, policy,
or regulation adopted for
the purpose of reducing
the emissions of GHGs
with mitigation
incorporated.

Refer to LUTE DEIR MM 3.5.3 and MM AIR-3.1 above.

Attachment 5

Page 25 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation

NOISE AND VIBRATION
Impact NOI-1: The
project would result in
generation of a
substantial temporary or
permanent increase in
ambient noise levels
(specifically the project
construction drilling
phase) in the vicinity of
the project in excess of
standards established in
the local general plan or
noise ordinance, or
applicable standards of
other agencies, even with
mitigation incorporated.

MM NOI-1.1: Installation of Acoustic Barriers: During
drilling activities on-site, the project shall install the following acoustic barriers (the installation of which shall take place during regular, daytime construction hours):
• Approximately 600 linear feet of 32-foot-high,
Sound Transmission Class (STC) rated 32 acoustic
barrier wall shall be installed parallel to the site
boundaries. The acoustic barrier wall shall be
installed with no openings or gaps except for an
acoustical gate on the north side of the project site to facilitate site access during drilling activities. This acoustical gate shall remain closed during drilling
operations.
• Approximately 190 linear feet of 20-foot-high, STC
rated 32 dual K-rail mounted acoustic barriers shall
be installed on the south and north sides of drilling
equipment. These acoustic barriers shall also be
installed on portions of the east and west sides of
drilling equipment as shown in Figure 7-3 of the
Noise Assessment Report.
• Approximately 72 linear feet of 12-foot-high, STC
rated 25 acoustic barrier walls shall be installed on
the north, west and south sides of mud pump and air
compressor.
• Approximately 96 linear feet of 8-foot-high, STC
rated 25 acoustical blankets shall be installed on the
rig floor.

The applicant shall
apply for a
Miscellaneous Plan
Permit with the City at
least 60 days prior to
initiation of drilling
activities to finalize the
design, size, and
location of the acoustic
barriers. The design of
the barriers shall be
consistent with the
placement indicated on
Figure 7-3 of the Noise
Assessment Report.

The City is responsible
for reviewing the final
plan set for consistency.

Prior to the
commencement of
drilling activities on
site, the applicant is
responsible for
installing acoustic
barriers.

The location and
size of the acoustic
barriers shall be
identified on the
final plan set.

The acoustic
barriers shall be
installed on-site as
noted in the final
plan set.

Community
Development
Director

Attachment 5

Page 26 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
MM NOI-1.2: Provision o f Vouchers for Alternative
Accommodations. California Water Service (Cal Water) shall provide the two nearest residences adjacent to the
southwestern portion of the project site (i.e., 819 and 823 Coventry Court as identified in the Noise Assessment Report dated July 24, 2024 in Appendix B of the Draft EIR) with the potential to exceed 50 dBA noise levels during nighttime drilling activities, with vouchers for alternative
accommodations. At least 45 days prior to the initiation of nighttime drilling activities, Cal Water shall communicate the anticipated drilling schedule to the affected residents at 819 and 823 Coventry Court. Vouchers shall be offered based on the needs of each household for the specific dates that nighttime drilling activities are scheduled. It is anticipated that the nighttime drilling activities would occur over two separate phases. Vouchers for alternative accommodations shall be issued for each of the two phases based on the finalized construction schedule and be for $300/night/room, with the necessary number of rooms being determined
through consultation with the affected residents.

Confirmation regarding the provision of vouchers for
alternative accommodations shall be provided by Cal Water to the City prior to the initiation of nighttime drilling activities.

Prior to the
commencement of
nighttime drilling
activities, the applicant
is responsible for
providing the City and
residents of the affected
households with the
proposed construction
schedule. The applicant
is responsible for
providing vouchers for
alternative
accommodations to the
affected residents
during the periods of
nighttime drilling
activities and
submitting proof of
issuance to the City.

The City is responsible
for confirming issuance
of the vouchers.

A memorandum
from the applicant
documenting the
issuance of
vouchers for
alternative
accommodation to
the affected
residents.

Community
Developmen
t
Director
MM NOI-1.3: Ongoing Noise Monitoring and
Implementation of Portable Acoustic Barriers: During
demolition, grading, excavation, trenching, and tank
construction activities on-site, the project shall conduct ongoing noise monitoring to determine when the use of
Prior to the
commencement of
demolition, grading,
excavation, trenching,
and tank construction
The monitoring
plan shall be
printed on all
construction
documents,
Community
Development
Director
Attachment 5

Page 27 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
portable acoustic barriers is required to the prevent the exceedance of the applicable 80 dBA threshold as measured at surrounding sensitive receptors. If noise levels during these construction activities are measured within one dBA of the 80 dBA threshold at surrounding sensitive receptors, then
portable acoustic barriers shall be installed between the noise generating equipment and the impacted sensitive receptor prior to initiating any additional noise generating construction activities.
activities on-site, the
project applicant shall
submit a monitoring
plan to the City for
review and approval.

During demolition,

grading, excavation,
trenching, and tank
construction activities
on-site, the applicant
shall conduct ongoing
noise monitoring to
determine when the use
of portable acoustic
barriers is required to
the prevent the
exceedance of the
applicable 80 dBA
threshold per mitigation
measure MM NOI-1.3.

The applicant is
responsible for
installing portable
acoustic barriers
between the noise
generating equipment
and the impacted
sensitive receptor as
required per mitigation
measure MM NOI-1.3.
contracts, and
project plans.

Ongoing noise
monitoring sh
all be
conducted during
all demolition,
grading,
excavation,
trenching, and tank
construction
activities on-site.

Portable acoustic
barriers shall be
installed if
construction noise
is within one dBA
of the 80 dBA
threshold.

Attachment 5

Page 28 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation

TRIBAL CULTURAL RESOURCES
Impact TCR-1: The
project would not cause a
substantial adverse
change in the
significance of a tribal
cultural resource that is
listed or eligible for
listing in the California
Register of Historical
Resources, or in a local
register of historical
resources as defined in
Public Resources Code
Section 5020.1(k) with
mitigation incorporated.

Impact TCR-2: The
project would not cause a
substantial adverse
change in the
significance of a tribal
cultural resource that is
determined by the lead
agency, in its discretion
and supported by
substantial evidence, to
be significant pursuant to
Refer to MM CUL-2.1, MM CUL-2.2, MM CUL-2.3, and
MM CUL-3.1 above.

Attachment 5

Page 29 of 30 ends

2022-7041
800 Carlisle Way
Mitigation Monitoring and Reporting Program
800 Carlisle Way Well and Water Tank Project
File # 2022-7041, SCH # 2023020080
Impact Mitigation Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
criteria set forth in
subdivision (c) of Public
Resources Code Section
5024.1 with mitigation
incorporated.

Sources: 1) City of Sunnyvale. 800 Carlisle Way Well & Water Tank Draft EIR (including Appendix A). January 2026. 2) City of Sunnyvale. 800 Carlisle Way Well & Water Tank Final EIR. February 2026.

Attachment 5

Page 30 of 30 ends