52 FY 2026/27 BUDGET AND RESOURCE ALLOCATION PLAN
Project Financial Summary
Project Costs Revenues Operating Costs
Prior Actual 627,934 265,719 -
2024-25 433,551 127,231 -
2025-26 244,343 - -
2026-27 144,356 - -
2027-28 291,641 - -
2028-29 303,306 - -
2029-30 90,557 - -
2030-31 98,142 - -
2031-32 62,946 - -
2032-33 89,552 - -
2033-34 - - -
2034-35 - - -
2035-36 90,557 - -
2036-37 98,142 - -
2037-38 98,142 - -
2038-39 89,552 - -
2039-40 - - -
2040-41 - - -
2041-42 90,557 - -
2042-43 153,048 - -
2043-44 - - -
2044-45 - - -
20 Year Total 1,944,842 - -
Grand Total 3,006,327 392,949 -
Project Description/Scope/Purpose
This project funds the replacement costs of the battery backup systems that have been installed on all the traffic signals in the City. Batteries have between five to six years of life expectancy. The City currently operates and maintains 138 traffic signals.

Batteries are replaced over a seven-year period concurrent with the installation of the original devices. Inverters and wiring, separate from batteries, typically last 15-20 years. Replacement of the inverters and wiring is scheduled to start in FY 2024/25 concurrent with installation of original devices.

Project Evaluation and Analysis
Installation of uninterruptible power supplies at traffic signals reduces congestion and improves safety for all users of the City’s roadway system during planned and unplanned power outages. If Pacific Gas and Electric (PG&E) power is lost, the traffic signals will continue to function in a normal fashion and motorists will not be required to treat dark signalized intersections as All- Way Stop controlled intersections.

Fiscal Impact
About 20 inverters and wiring of UPS systems and batteries for approximately 25 locations are expected to be replaced every year; however, depending on current market pricing and adjusted for inflation, less than 20 inverters and wiring for UPS systems and batteries for approximately 25 locations could be replaced.

Funding Sources
Gas Tax Fund
Plans and Goals
LT - Land Use and Transportation - LT-2: Environmentally Sustainable Land Use & Transportation Planning and Development 825740 - Battery Backup System for Traffic Signals Maintenance Originating Year: 2006 Project Type: Traffic and Transportation Department: 250 - Public Works Planned Completion Year: Ongoing Category: Infrastructure Project Manager: Carmen Talavera Attachment 3