Assigned Planner Approval
PA Number Project Address APN Apply Date Date Applicant Company Owner Plan Type Status PA22-0654 44758 Longfellow Ave 966-200-034 Scott Cooper 06/13/2022 06/27/2022 Stephen CHRISTINA PL Modifications Approved Temecula, CA 92592 Magerkurth GARCIA-VASQU
EZ
Case Title / Description: Garcia -Vasquez Garage Conversion MOD: A Modification to convert an existing single car garage to a bedroom, add 86 square feet to the bedroom, and revise the street facing elevation located at 44758 Longfellow Avenue
PA22-0665 27555 Ynez Rd 921-270-054 Jaime Cardenas 06/15/2022 Leticia Smith
PL Wireless
Corrections
Temecula, CA 92591
Antenna Facility
Case Title / Description: Verizon Tower Plaza WTF: A Wireless Telecommunication Facility Application for the removal and replacement of existing equipment with new antennas, RRUs, hybrid cables, ground equipment, and other miscellaneous equipment within the tower of the existing building located at 27555 Ynez Road.

PA22-0669 42540 Rio Nedo 909-290-031 Jaime Cardenas 06/16/2022 Richard Valdez Richard Valdez
PL Modifications
Plan Review
Temecula, CA 92590
Case Title / Description: 42540 Rio Nedo MOD: a Minor Modification Application to remove and replace slide gates, construct a new 225 linear feet of new block walls and a new 4800 square -foot concrete pad in the industrial property located at 42540 Rio Nedo.

PA22-0670 28721 Old Town Front St 922-073-026 Eric Jones 06/16/2022 Neil Cleveland
PL Conditional
Plan Review
Temecula, CA 92590
Use Permit
Case Title / Description: The Warehouse on Front Conditional Use Permit: A Conditional Use Permit for a restaurant to offer live entertainment and alcohol service with a Type 47 License. The project is located at 28721 Old Town Front Street.

PA22-0673 41280 Placer Lafite 953-390-002 Jaime Cardenas 06/16/2022 06/29/2022 Deanna Lynn
Rancho PL Wireless
Approved
Temecula, CA 92591
California Water Antenna Facility
District
Case Title / Description: AT&T Placer Lafite WTF MOD: a Wireless Telecommunication Facility to remove and replace existing wireless equipment with new antennas, surge suppressors, and other miscellaneous equipment located at 41280 Placer Lafite.

PA22-0674 27590 Jefferson Ave 910-310-004 Jaime Cardenas 06/16/2022 06/27/2022 Lawrence Wilson
PL Zoning or
Completed
Temecula, CA 92590
Planning Letter
Case Title / Description: 27590 Jefferson ZL: a zoning verification letter for the property located at 27590 Jefferson Avenue.

PA22-0678 27740 Jefferson Ave 921-050-001 Jaime Cardenas 06/20/2022 06/29/2022 Julio Colomba
River Springs PL Zoning or
Completed
Temecula, CA 92590
Charter School Planning Letter
Case Title / Description: 27740 Jefferson ZL: a zoning verification letter for the property located at 27740 Jefferson Avenue.

Page 2 of 4 ends

Assigned Planner Approval
PA Number Project Address APN Apply Date Date
Applicant Company
Owner Plan Type
Status
PA22-0680 32470 Corte Zaragoza 962-242-014 Jaime Cardenas 06/20/2022 07/01/2022 Xavier
PL Accessory
Approved
Temecula, CA 92592
Hernandez
Dwelling Unit
Case Title / Description: Wendel ADU: an Accessory Dwelling Unit Application for the construction of a proposed attached ADU located at 32470 Corte Zaragoza.

PA22-0682 28718 Old Town Front St 922-072-022 Jaime Cardenas 06/20/2022 Jeanne Miller
PL Modifications
Corrections
Temecula, CA 92590
Case Title / Description: Rodeway Inn Solar MOD: a modification application for the addition of roof mounted panels and supporting equipment at the Rodeway Inn Motel located at 28718 Old Town Front Street.

PA22-0684 42775 Margarita Rd 945-050-014 Jaime Cardenas 06/21/2022 Jared Hermelin
CITY OF PL Wireless
Plan Review
Temecula, CA 92592
TEMECULA Antenna Facility
Case Title / Description: Ronald Reagan Park T-Mobile WTF: a wireless telecommunication facilities application for T-Mobile to install new antennas, modules, electrical cabinets and other miscellaneous equipment to the existing wireless facility on Ronald Reagan Sports Park located at 42775 Margarita.

PA22-0687 27500 Jefferson Ave 910-310-007 Eric Jones 06/21/2022 Jessica Grevin
Heritage Inn of PL Wireless
Plan Review
Temecula, CA 92590
Temecula, LLC Antenna Facility
Case Title / Description: AT&T Wireless Modification Application: A Wireless Modification Application to replace existing antennas with new antennas. The project is located at 27500 Jefferson Avenue.

PA22-0703 40375 Winchester Rd 920-080-008 Jaime Cardenas 06/27/2022 Cassandra
DEL TACO PL Modifications
Plan Review
Temecula, CA 92591
Gallardo
Case Title / Description: Del Taco Facade MOD: a Modification Application to alter the paint, signage and facade of the existing Del Taco located at 40375 Winchester Road.

PA22-0706 40460 Calle Tiara 919-230-020 Parker De Klotz 06/27/2022 06/30/2022 Garrett Childers
PL Zoning or
Plan Review
Temecula, CA 92591
Planning Letter
Case Title / Description: 40460 Calle Tiara ZL: A zoning letter verification for the property located at 40460 Calle Tiara.

PA22-0712 959-400-001 Scott Cooper 06/28/2022
Mike Jagels
WOODSIDE 05S PL Temporary
Plan Review
Temecula, CA
Use Permit
Case Title / Description: Paseo Del Sol Stockpile TUP: A Temporary Use Permit a stockpile permit for the Paseo Del Sol Tentative Tract Map No. 36483 project.

PA22-0722 27425 Ynez Rd 921-260-023 Eric Jones 06/29/2022 maikel faragalla
AmericanWest PL Modifications
Plan Review
Temecula, CA 92591
Bank
Case Title / Description: Starbucks Ynez Road Modification: A Major Modification application to allow revisions to an existing commercial site. Revisions will include facade and site improvements. The project is located at 27425 Ynez Road.

Page 3 of 4 ends

Assigned Planner Approval
PA Number Project Address APN Apply Date Date
Applicant Company
Owner Plan Type
Status
PA22-0731 31141 Temecula Pky 961-410-049 Jaime Cardenas 06/30/2022 Kevin Brooks
PL Massage
Plan Review
Temecula, CA 92592
Permits
Case Title / Description: Simply Kneaded MEP: a massage establishment permit renewal for Simply Kneaded located at 31141 Temecula Parkway, Suite B/H2.

PREAPP22-0 922-210-042 Jaime Cardenas 06/06/2022
Brandon Humann Catalyst
PL
Plan Review
614 CA
Commercial
Pre -Application
Group, LLC
Case Title / Description: Bedford Court Pre -Application: A Pre -Application to review an express carwash and fast food structure with a drive-thru. The project is generally located approximately 250 feet south from the Temecula Parkway and Bedford Court intersection.

PREAPP22-0 28613 Pujol St 922-054-011 06/16/2022
Kate Du
PL
Plan Review
672 Temecula, CA 92590
Pre -Application
Case Title / Description: JMK Residential Pre -Application Review: A Pre -Application to review a proposed nine unit multi -family project. The project is located at 28613 Pujol Street.

PREAPP22-0 43995 Mahlon Vail Rd 960-020-077 Scott Cooper 06/21/2022 Chris Post
PL
Plan Review
686 Temecula, CA 92592
Pre -Application
Case Title / Description: Rally's Burger Pre App: A Pre -Application for an approximately 998 square foot Rally's Burger restaurant located at 43995 Mahlon Vail Rd.

PREAPP22-0 27468 Ynez Rd 921-320-058 Scott Cooper 06/21/2022 Jonathan
PL
Plan Review
689 Temecula, CA 92591
Cornelius
Pre -Application
Case Title / Description: Fore Temecula Pre-App: A Pre -Application for a 220 unit apartment community located on 5.85 acres at Temecula Town Center
PREAPP22-0 28115 Del Rio Rd 921-060-022 Parker De Klotz 06/30/2022 Lindsey Sands
Lynn Ladenes PL
Plan Review
728 Temecula, CA 92590
Pre -Application
Case Title / Description: TLC Storage Yard: A Pre -Application for Total Lawn Care to occupy the lot for storage containers, landscape equipment, work trucks, and material storage at 28115 Del Rio Road.

PREAPP22-0 910-272-002 Scott Cooper 06/30/2022
Joe Holasek
Hoff Investments PL
Plan Review
729 Temecula, CA
Pre -Application
Case Title / Description: Apollo Self Storage Preapp: a Pre -Application for a proposed 4-story, 130,000 square foot building with about 90,000 square feet of net rentable storage space on the vacant parcel at 910-272-002.

Page 4 of 4 ends

Item No. 19

CITY OF TEMECULA

AGENDA REPORT
TO: City Manager/City Council
FROM: John Crater, Division Chief
DATE: July 26, 2022
SUBJECT: Fire Department Monthly Report
PREPARED BY:

RECOMMENDATION:

Report.

Wendy Miller, Management Analyst
That the City Council receive and file the Fire Department Monthly

City of Temecula Fire Department
Temecula Fire Department Service Calls
June 2022
Incident Type
Commercial Fire 1 •
False Alarms 69 s""°°= •
Haz Mat 6 � '• '°k8tx ,a;
• • • _ , v,F
dei., • b+ • ° mm way y
Medical 611
�� .. �.�_-.. . �a ,T..,�'r ' • • � • • •+ ~ 5"' ,Wro �,rSaAe vava ° p 1989 Multi-Fam 0 .. ,. ..
` o° 0 NVw 0V ' Other Fire 6 ' . �: . *' : •
Other Misc 12 .. .. •
saw 6 ,l ' r s r ° • I IT
6t rr •'•.yi _ ; • PAU6A tALLEY
Public Assist 46 ""° "°�s '
Residential Fire 5_.-
•
Rescue IN Ai
�'�- s'+ �• • � • �'. •'� •.
.rE� i _ ..� • .i• • .t • .. - 7
Ringing Alarm 0 •.r
7 Standby 9°' r . • s
Re, oZ y
•.T
l � //!'• � ANGA PCCHCASINO''JW�RY
Traffic Collision 64 ,, �* - At,. �� ,,` •�,°k °°oz r a.aga� Wildland/Vehicle Fire 3 F,
Total 833

City of Temecula Fire Department
Temecula Fire Department
Plan Review and Inspections
June 2022
�116 0481959/y i1
10 Plan Review and Inspections June Year to Date
Plan Review 597 2896
Construction Inspections 243 2361
Annual Inspections 588 3729
Counter/Public Inquiries 30 191
------------
1 Item No. 20

CITY OF TEMECULA

AGENDA REPORT
TO: City Manager/City Council
FROM: Patrick Thomas, Director of Public Works/City Engineer DATE: July 26, 2022
SUBJECT: Public Works Department Monthly Report
RECOMMENDATION: Receive and file the Public Works Department Monthly Report for Capital Improvement Projects, Maintenance Projects, and Land Development Projects. This report may also be viewed on the City's website at:
http://temeculaca.gov/270/Cqpital-Improvement-Projects-CIP

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022

CAPITAL IMPROVEMENT PROJECTS

CIRCULATION PROJECTS
Cherry Street Extension & Murrieta Creek Crossing, PW19-15 Description: Preliminary design of the Extension of Cherry Street from Adams Avenue to Diaz Road, including a new crossing of Murrieta Creek.

Cost: $37,248,262
Status: The City received 30% plans for a low flow crossing. Environmental agencies have stated that a low -flow crossing is a non -starter. Design consultant is preparing a bridge planning study.

Diaz Road Expansion, PW17-25
Description Improve Diaz Road to meet the roadway classification of Major Arterial (4 Lanes Divided), between Cherry Street and Rancho California Road. The 2.2-mile stretch will be widened, extended, and/or improved to create a contiguous Major Arterial segment. The project will be developed and constructed in two phases.

Phase 1 will include improvements on Diaz Road from Winchester Road to Rancho California Road. Phase 2 will include improvements on Diaz Road from Cherry Street to Winchester Road.

Cost: $14,255,991
Status: Phase 1 design, Phase 1 & 2 environmental studies, and Phase 1 permitting November 2019 — January 2023. The Initial Study has been approved, Mitigated Negative Declaration adopted, and Notice of Determination filed in May 2022. Design is 90% complete. Regulatory permit applications have been submitted for USACoE 404 Nationwide Permit and CDFW Streambed Alteration 1602. Current activities include consultant review of 90% plan check comments, design coordination with utility purveyors (SCE, RCWD, and EMWD), Riverside County Flood Control review of 90% design plans and Encroachment Permit application, and preparation of regulatory permit application for SWRCB 401 Water Quality Certification.

French Valley Parkway/Interstate 15 Improvements- Phase II, PW16-01 Description: Design and construction of the two-lane northbound collector/distributer road system beginning north of the Winchester Road interchange on -ramps and ending just north of the Interstate 15/Interstate 215 junction with connection to Interstate 15 and Interstate 215.

Cost: $138,736,346
Status: Design and environmental revalidation is complete. Right of way acquisition process is nearly complete.

Requests for funding authorization/obligation have been submitted. Pending authorization/obligation of funds, a Request for Proposals (RFP) for Construction Management/Resident Engineer services will begin advertisement in July/August and the Construction Contract will be advertised in August/September.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
CIRCULATION PROJECTS (Continued)
1-15 Congestion Relief, PW19-02
Description Design and construction of a single auxiliary lane, northbound Interstate 15 connecting the Temecula Parkway on -ramp to the Rancho California Road off -ramp.

Cost: $8,971,710
Status: Design and environmental studies November 2019 — September 2022. Current activities include City revision of 95% Roadway and Structures PSE, Storm Water Data Report, Drainage Report, and Permit Engineering Evaluation Report. Caltrans has tentatively approved the CEQA Categorical Exemption. The Notice of Determination will be filed upon project approval under the Permit Engineering Evaluation Report.

Murrieta Creek Bridge at Overland Drive, PW16-05
Description: Design and construction of a new bridge crossing over Murrieta Creek between Rancho California Road and Winchester Road.

Cost: $26,073,374
Status: The City applied and was approved to receive Federal Highway Bridge Program (HBP) funds. City Council approved the design agreement with CNS Engineers Inc. at the March 12, 2019, meeting. Preliminary Environmental Study (PES) approved by Caltrans on August 15, 2019. Plans are 30% complete. RCA JPR Conformance is approved. NEPA approval is anticipated in Summer of 2022, Caltrans review time has been longer than anticipated. Biological monitoring in Temecula Creek for potential mitigation site is complete as of July 2021. Project has received MSHCP conformance. Staff continues to work with Caltrans to advance HBP Grant Funds to earlier fiscal years. Caltrans HBP Program management had proposed reducing the curb -to -curb width of the bridge that is considered "participating" for grant funding purposes.

Staff has been able to address this issue with Caltrans and the majority of the bridge width will remain as a participating cost.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
CIRCULATION PROJECTS (Continued)
Overland Drive Widening, PW 20-11
Description This project includes widening Overland Drive from Jefferson Avenue to Commerce Center Drive, to two lanes in each direction, and the completion of missing segments of sidewalk, streetlights, and installation of the traffic signal at Commerce Center Drive and the modification of the traffic signal at Jefferson Avenue.

Cost: $2,894,420
Status: Design is at 60%.

Traffic Signal Installation — Citywide, Rancho California Road and Tee Drive, PW19-19 Description: This project includes the installation of a traffic signal on Rancho California Road at Tee Drive.

Cost: $346,646.50
Status: Design is completed. Construction plans and specifications are being finalized. City approval of plans and authorization to solicit construction bids is scheduled for the May 24, 2022, City Council meeting. Project is currently bidding with e a bid opening on July 20, 2022.

Traffic Signal and Park & Ride Access Improvements, PW18-11 Description: This project includes the installation of a traffic signal on Temecula Parkway at Wabash Lane. The project also includes relocating the access to the Park and Ride facility on Temecula Parkway at La Paz Road from Vallejo Avenue to Wabash Lane.

Cost: $1,347,674
Status: The traffic signal and the new access road to the Park and Ride are fully operational. Access to Park and Ride from Vallejo Ave. has been closed and a permanent block wall will be constructed in the next few weeks. Construction completion is anticipated in August of 2022.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022

INFRASTRUCTURE PROJECTS
Bike and Trail Program — Great Oak Trail Lighting
Description: Project includes the installation of solar lights along the Great Oak Trail adjacent to the northeast side of Pechanga Parkway from Deer Hollow Way to Loma Linda Road.

Cost: $400,000
Status: Project is currently in design.

Citywide Drainage Master Plan
Description: Project will prepare a report that shows all drainage courses within the City. Also includes a master hydrology study showing the anticipated storm flows at build -out.

Cost: $600,000
Status: Kickoff meeting was on June 30, 2022. Project is anticipated to last for one year.

Community Recreation Center (CRC) Renovations, PW19-07
Description: The project facilitates the rehabilitation, improvement, and reconfiguration of the Community Recreation Center. This project includes expansion and reconfiguration of teen center; conversion of office space to accommodate a dedicated police substation; renovation of key components of the building including safety features, flooring, roof, and restroom facility access; ADA compliance; renovation and expansion of existing office space and rec rooms including AV upgrades; expanded storage space and upgraded kitchen equipment.

Cost: $10,708,232
Status: Phase 1 design is progressing. City Council Authorization to bid was received on 7/12/2022. 4 City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
INFRASTRUCTURE PROJECTS (Continued)
Interstate 15 / State Route 79 South Interchange Enhanced Landscaping, PW17-19 Description: Landscape beautification of the Interstate 15 corridor between French Valley Parkway and Temecula Parkway, including each interchange, in association with Visit Temecula Valley and the Pechanga Tribe.

This project includes the design and construction of enhanced landscaping, hardscape, and irrigation between the freeway and ramps on the west side of the Interstate 15 / State Route 79S (Temecula Parkway) interchange.

Cost: $3,58,483
Status: Design and environmental studies August 2019 — October 2022. Environmental revalidation completed October 2020. Current activities include 90% design plans, design of new power and irrigation water service, and Design Engineering Evaluation Report.

Margarita Recreation Center, PW17-21
Description: Demolition and Reconstruction of New Margarita Recreation Center Building and Pool Cost: $12,601,508
Status: RFP responses were received on August 27, 2020. The project was re -advertised on November 25, 2020, to account for increased project budget and proposals were received on December 23, 2020. The Design - Build Contract was awarded at the March 9, 2021, City Council Meeting to De La Secura Builders, Inc., for a Guaranteed Maximum Price of $8,680,459.00. Design phase is well underway. The second building plan review was completed on January 25, 2022, and the Design Builder is working to address comments.

The existing MRC building was vacated by City Staff and all salvageable equipment removed on January 28, 2022. The Fire Department used the existing building for training the week of February 7, 2022. The demolition of the existing MRC building started on February 14, 2022. Major demolition activities commenced mid -March. City Groundbreaking occurred on March 31, 2022. Building and foundation demolition is complete. Work is currently progressing on underground utilities. It is anticipated building construction will be complete in spring 2023 with a grand opening in Summer 2023.

Mary Phillips Senior Center Enhancement and Renovation, PW20-13 Description: The project includes the enhancement and renovation of the Mary Phillips Senior Center. Work includes new exterior siding, painting, replacement of perimeter soffits, fascia boards, eaves, and select doors & windows.

Cost: $1,262,025
Status: Project is being advertised for construction bids. Bid opening is scheduled for July 21, 2022.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
INFRASTRUCTURE PROJECTS (Continued)
Santa Gertrudis Creek Pedestrian/Bicycle Trail Extension and Interconnect, PW08-04 Description: Design, environmental document, and construction of the extension of the existing trail from Ynez Road to the Murrieta Creek Trail. The extension includes access and under -crossing at Ynez Road, Interstate 15 and Jefferson Avenue and a continuous paved trail along Santa Gertrudis Creek to connect to Murrieta Creek trail.

Cost: $7,173,595
Status: The California Transportation Commission (CTC) has approved $3,759,000 State S131 Alternative Transportation Program (ATP) Augmentation funds for this project. The Notice to Proceed for construction was issued to the contractor with a work start date of April 19, 2021. Groundbreaking event occurred on May 4, 2021. Jefferson undercrossing section is complete. Asphalt paving between Jefferson and Winchester near Diaz is complete. Ynez undercrossing section is complete. Tieback wall section under I- 15 section is complete. Contractor is currently working to lower wall section of 1-15. Completion is anticipated in September 2022.The current concrete shortage has significantly extended the completion date as most of the remaining work requires concrete.

Santa Gertrudis Creek Phase II — Margarita Under -Crossing, PW19-04 Description: Design, environmental document, and construction of the undercrossing in Santa Gertrudis Creek at Margarita Road to connect to the pedestrian/bicycle trail. The under -crossing at Margarita Road will provide a continuous paved trail along Santa Gertrudis Creek at this location.

Cost: $2,716,764
Status: The project is in design. 100% Plans, Specifications, and Estimate (PSE) expected in December 2022.

Sidewalks — Citywide (Ynez Road, Rancho Highland to Tierra Vista Road), PW17-28 Description: New sidewalks on the west side of Ynez Road from Rancho Highland to Tierra Vista Road.

Cost: $198,920
Status: Design is complete. The project is scheduled to be advertised for construction bids in July 2022.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
INFRASTRUCTURE PROJECTS (Continued)
Sidewalks — DLR Drive, PW19-18
Description: New sidewalks on the north and west side of DLR Drive.

Cost: $464,866
Status: Currently in construction. Construction completion is scheduled in August.

Sidewalks — Citywide (Pauba Road, Elinda Road to Showalter Road), PW 19-20 Description: New sidewalks and street widening on the South side of Pauba Road from Elinda Road to Showalter Road.

Cost: $467,403
Status: Project is currently in design.

Fire Station 84 Renovation, PW19-14
Description: This project includes the design, construction, and renovation to Fire Station 84. The renovations include, adding a Wellness Room, expanding the Storage Room, and upgrading the Training Room. Also, the upgrades include, electrical, windows, flooring, paint, tile, HVAC, cabinets, plumbing fixtures, garage bay doors and any necessary improvements needed to conform to ADA accessibility access.

Cost: $1,641,028
Status: Project is currently being advertised for construction bids with a bid opening date of July 28, 2022. 7 City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022

PARKS AND RECREATION PROJECTS
Flood Control Channel Reconstruction and Repair, PW11-10 Description: This project repairs and reinforces the earth and berms between Pala Park and Temecula Creek and fortifies the banks to prevent further erosion into the park site.

Cost: $1,280,284
Status: Construction was completed on March 20, 2022. Final project acceptance is anticipated in August 2022.

Park Restroom Renovations, Expansion and Americans with Disabilities Act (ADA), PW17-06 Description: Renovation of various park site restroom facilities, including Ronald Reagan Sports Park North/South Ball Field (new roof, cabinets, fixtures, and other building improvements), Vail Ranch Park and Long Canyon Creek Park.

Cost: $1,127,800
Status: Project is currently in design.

Playground Equipment Enhancement and Safety Surfacing
Description: Re -design, enhancement of playground equipment, and safety surfacing to comply with current state and federal regulations and enhance the quality of the parks.

Cost: $800,000
Status: An RFP is being prepared for the design, purchase & installation for three playground project sites — Redhawk Community Park, Long Canyon Creek Park & Temecula Creek Park.

Ronald Reagan Sports Park Restroom Expansion and Renovation, PW18-03 Description: Design and construction of a new restroom building, including additional stalls and urinals, a large snack bar and a dedicated storage case.

Cost: $1,120,000
Status: The construction contract was awarded at the April 12, 2022, City Council meeting. Construction began on May 16, 2022. Construction completion is anticipated in August 2022.

K

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022

LAND DEVELOPMENT OVERSIGHT PROJECTS
American Tire Depot
Description: A 7,303 square foot building to be used for tire retail and repair, as well as minor auto repair services, located at the southwest corner of Ynez Road and DLR Drive.

Status: Parking lot has been paved. Wet utility tie-in construction has commenced.

Arrive @ Rancho Highlands
Description: A 270-unit multi -family community built on 12.32 acres that includes 55 affordable units. The project is located adjacent to the Temecula Duck Pond approximately 775 feet southeast of Rancho California Road on the north side of Ynez Road.

Status: Grading and onsite storm drain permits were issued in October 2021. Grading and onsite storm drain construction has commenced. Overflow parking lot has been paved.

Better Buzz
Description: Demolition of 445 square feet of an existing commercial building (former Corner Bakery), the addition of a drive-thru, the addition of tower with trellis, and changes to the elevations of the existing building located at 32435 Temecula Parkway
Status: Precise grading permit has been issued. Grading and construction has commenced and is ongoing.

Chick-fil-a
Description: Existing fast-food restaurant to reconfigure the existing drive-thru, relocate an existing trash enclosure and add square footage and landscaping.

Status: Precise grading permit was issued January 13, 2022. Grading and construction has commenced and is ongoing.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
LAND DEVELOPMENT OVERSIGHT PROJECTS (Continued)
Heirloom Farms
Description: A Development Plan for a 321-unit single family residential community built on 27.86 acres consisting of detached homes and attached townhomes located on the southwest corner of Date Street and Ynez Road.

Includes the installation of a new Traffic Signal at the intersection of Ynez Rod and Waverly Lane/Temecula Center Drive
Status: Rough grading permit has been issued in July 2021, the offsite and private onsite street and storm drain improvements permits were issued in October 2021 and the traffic signal permit was issued in September 2021. Grading, street, and storm drain improvements and the traffic signal installation has commenced.

Precise Grading plans are currently being reviewed.

Las Haciendas Apartments
Description: A Development Plan to construct a 77-unit affordable housing project located at 28715 Las Haciendas Street in Uptown Temecula
Status: Precise grading permit was issued in December 2021. Grading has commenced in January 2022 and is ongoing.

Longhorn Steakhouse
Description: 5,708 square foot restaurant with outdoor patio located at 29363 Rancho California Road Status: Precise grading permit is approved. Construction expected to begin soon.

Mountain View
Description: Thirteen industrial buildings on Avenida Alvarado Status: Eight precise grading permits have been issued and construction has commenced. Improvements on Avenida Alvarado, along with street light installations is in process. Onsite storm drain installation has commenced.
10 City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
July 26, 2022
LAND DEVELOPMENT OVERSIGHT PROJECTS (Continued)
Solana Assisted Living
Description: A 90,000 square foot, two-story, Senior Assisted Living Facility located on the southeast corner of the Margarita Road and Solana Way.

Status: A rough grading permit was issued in January 2022. Grading began on February 7, 2022. Street improvements and precise grading plans have been submitted for review.

Sommers Bend
Description: Land Development has provided oversight of the following submittals for plan check and inspections: final maps, Community Sports Park, and recreation lots, precise grading; street and storm drain improvements; traffic signals; street lighting; and signing & striping.

Status: The mass grading permit was issued in September 2018. Sommers Bend has been paved with streetlights installed. The community sports park, Ranch at Sommers Bend, construction is complete and has been accepted at the February 8, 2022, Council Meeting with its Ribbon Cutting ceremony scheduled for February 12, 2022. The Sommers Bend recreation center construction is complete. Bond release for Long Valley Wash in process. Installation of streets, storm drains and streetlights on east end of project is in process. Grading has been completed in the Density Core, currently installing sewer. Installation of Santa Gertrudis Creek Channel improvements northwest end of project is in process. 11 REQUESTS TO SPEAK

AND COMMENTS

SUBMITTED FOR

THE RECORD

REQUEST TO SPEAK
---K. CITY OF TEMECULA
1489 7/2/
/Z,
Date:

Public Comment: Non-Agenda Item: Agenda Item: ' N" \`.

Agenda Item No. For Against
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come f rward to the podium and state your name for the recur /� /, A �e vaOS
` �� 'N U
Name: "4 `l NV 1) es �� Phonne Number: — Address:

Email address:

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

"`'� REQUEST TO SPEAK
., CITY OF TEMECULA
„itti_ -- ..
,vHv
Date: V... 4/A
Public Comment: Non-Agenda Item: N Agenda Item:

Agenda Item No. For n Against n
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record. A , /
Name: b JA/V Si TAR Phone Number:-/ + ��
Address: , 7- E& 9cs9 ' Email address:

If you are representing an organization or group, please give the name: t4e4(4_,4 calm mt tom// )STm ks A/"V d
Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

REQUEST TO SPEAK

CITY OF TEMECULA
Date:

Public Comment: Non-Agenda Item: Agenda Item:

Agenda Item No. For Against
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record. 1 l

Address: - -��Q,up C C,_ e_ Email address: vv53nr If you are representing an organization o� up, please give the name:

C, © WA lit vk -�i C� r, v"C S -(` v, Please note that all information presented at a CityCouncil meetingbecomes public record.

P
All information provided is optional.

cE
D
July 1, 2022 JUt 0?202?
errylluxAGER S Opprez
District Secretary R clvED
41000 Main Street
Temecula, CA 92590 JUL 08 2022
CITY eLE Rics DEPT.

Attention District Secretary, Public Hearing
To Whom it May Concern:

This letter is in reference to the City of Temecula Services District notification of Fiscal Year 2022-2023 July 1, 2022-June 2023) Levy and Collection of Rates and Charges.

Would you please provide information as to why there have been increases for Service Level D— Recycling and Refuse Collection for the last two years? CR&R is the service provider and are not regular in their pick-ups. It takes two to three days for them to fully pick-up all the trash.

CR&R is also the company that provides the street sweeping service in the Paloma Del Sol community. I am curious as to why he bothers and why we pay for nothing regarding the services.

I see the sweeper every Thursday coming down our street with his brushes up driving down the middle of the street. He's not sweeping.

I will say in his defense everyone has their cars parked on the street so no sweeping along the curb can be done. I would think the City of Temecula would post the streets with notification signs to keep cars off the street on Thursday or pay a penalty.Think of the revenue for the City of Temecula. On my street people park in areas that are not large enough for a car to park partially blocking driveways.The drivers don't even park their cars in the correct direction.Another source of income for the City of Temecula.

This week(and most every week) I receive a recorded telephone message from CR&R advising they are having difficulties picking up the trash.They advise to leave the trash receptacle on the sidewalk not in the street because it will block the street when the sweeper comes.

My trash pick-up day is on Tuesday.The street sweeper is on Thursday.

Item #15

Please help me understand the logic in providing less service and paying more.

Thank you,
Jaynet Stevens

Temecula, CA 92592

REQUEST TO SPEAK
A �f +, CITY OF TEMECULA
44-igtflOV
iosv - l'
Date: U L-
Public Comment: Non-Agenda Item: -_,P111 Agenda Item: l;7 Agenda Item No. For Against n
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record.

Name: SA.L�I 0t6) L(�( Phone NumbeN
Address: t`-'1\ 2 643
�'

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

July 26. 2022
City of Temecula

CITY COUNCIL PUBLIC HEARING
Re: Weed Case Number:

Amount Due: $982.00
Dear Council Members:

I, Sal Simonetti,have been the owner of the subject vacant parcel since 1977 and am here to oppose the proposed SPECIAL ASSESSMENT for weed abatement of my property. I am most aware and responsive to the annual Weed Abatement program the City performs.

Upon determination of the need for Weed Abatement of the various parcels,the City mails out a certified registered letter to each property owner directing them to do the necessary weed abatement by a certain date and to notify the City when the work has been completed. The City then visits the site to confirm the work has been completed.

Within the 45 year period I have owned this property, I have changed residence FOUR TIMES: (

On my last move to I filed a"Change of Address"form with the U.S.

Post Office. Enclosed please find the U.S. Post Office"Official Change-of Address Confirmation Letter"forwarding all First Class Mail, Priority Mail&Priority Express Mail effective on May 2, 2022 through May 2, 2023 (see Enclosure 1).

I received my very first City of Temecula forwarded letter dated July 12, 2022 on July 16,2022. It was a DEMAND FOR PAYMENT for weed abatement costs. On July 18, 2022 I received the very same letter,with a second page announcing the Public Hearing on July 26, 2022. As of this date,these are the only two documents I have received from the City.

On Monday morning,July 18,2022, I went to Temecula City Hall, Weed Abatement to find out why I never received a letter to do weed abatement. A clerk came out to the lobby with the parcel folder of my property. I noticed there was a returned certified letter from the Post Office with my new address on the envelope(see Enclosure 2).

It was obvious the clerk knew something went wrong. She advised the person handling this matter was Sophia Lewing(Administrative Assistant, Code Enforcement). The clerk further advised Sophia Lewing was currently out of the office and would telephone me at 11:00 AM,but if I didn't hear from her by that time, I should give her a call. Since Ms.

Lewing didn't call me,I called her at 11:30 AM and left a message. At 3:30 PM I finally 1 got a call from Mr. Tom Cole, Field Supervisor-Code Enforcement. He said he was Ms.

Lewing's supervisor and would be responding to my inquiry. I explained to him that I had moved on May 1, 2022, I filed a U.S. Post Office "Change of Address" and that I never received a notice to do weed abatement on my property.

Mr. Cole then proceeded to make the following assertions:

A. The City did comply with the notification by mailing the certified registered letter to the Owner of Record shown on the County Assessor's Office.

B. Temecula has no further notification requirement. It was my fault that I didn't file a Change of Address with the County Assessor.

C. You know that weed abatement is required every year and I should have done my weed abatement on the property without even being notified.

I will now present my responses to Mr. Coles A, B and C assertions:

A. The certified letter was mailed to my old address on the 27th of April. It was returned to Temecula Code Enforcement on or soon after the 2"d of May. The Code Enforcement inspection of the property did not occur until the 8th of June. In other words. Code Enforcement, having my new address, did nothing to put the certified letter in a new envelope before even inspecting the property for over 5 weeks.

Which raises another question...How does Code Enforcement know my property needed weed abatement before the property was even inspected? It should also be noted that the actual weed abatement did not occur until the 7th of July. This is a period of over two months that Code Enforcement had my new address and did absolutely nothing to inform me of the need to do weed abatement.

B. Mr. Cole said the City handles over 800 Weed Abatement notices each year. Of this number, how many of these land owners changed their residence address? How many had a change of address between April Ilth and June 30th and of these how many filed a Change of Address with the County Assessor's Office? The Change of Address with the County Assessor's Office is usually done when the property tax payment is mailed in. Ironically,the County Assessor's Office did mail me six individual correspondences to my old address and all were forwarded to my new address,simply because I filed a " Change of Address" with the U.S. Post Office (see Enclosure 2). Mr. Cole says Code Enforcement annually mails out 800 Weed Abatement notices. Out of 800 certified letters being mailed out annually,there surely must be a certain percentage returned to the City due to a change of address (1%would be 8 returned letters,5%would be 40 returned letters). Mr. Cole knows or should know the U.S. Post Office DOES NOT forward certified registered letters and automatically returns such letters back to the Sender(with the new address label attached, if a Change of Address was filed by the land owner). 2 C. Contrary to Mr. Cole's assertion that Weed Abatement is required to be done every year, this is not a fact. There have been years, granted not very often, that Weed Abatement was not required by Code Enforcement. There have been times, probably due to drought conditions,when weed growth was minimal. I do not make that decision, Mr. Cole's staff is the decision maker. Additionally, this year I was preoccupied in April and May of this year with the moving out of one house and moving into another house. Regardless of my moving situation, it is very unreasonable to suggest that everyone should do their weed abatement of a vacant lot, without being directed to do so.

On July 25, 2022 I again went to Temecula City Hall and met with Mr. Tom Cole. His position had not changed at all since our last telephone conversation a week prior. I argued how he could still insist he met the notification requirement when the Code Enforcement Certified registered letter was returned to them was in the Case Folder with my changed mailing address on the envelope? He again simply replied he met his notification requirement. I again must reiterate the fact that CODE ENFORCEMENT,

HAVING THEIR CERTIFIED LETTER UNDELIVERED AND RETURNED TO THEM,WITH MY NEW ADDRESS ON THEIR ENVELOPE FOR OVER 5

WEEKS BEFORE A FIELD INSPECTION OF MY PROPERTY WAS EVEN PERFORMED.

Mr. Cole did disclose Sophia Lewing went on Maternity Leave at some point during this period. When and how long her leave lasted is unknown to me. She was the Code Enforcement Administrative Assistant in charge of my case. I have not been afforded the opportunity to discuss my case with her.

It is apparent that the management of my case slipped through the cracks of Code Enforcement. Rather than concede mistakes were made by Code Enforcement, Mr. Cole insists that the notification process was followed.

I do not want the City Council to think that I am trying to get away with the City absorbing the entire cost of$982.00 for the weed abatement of my parcel. I am willing to pay $400.00 of this cost, which is what I normally pay to for the weed abatement of my property.

I urge the City Council to consider and accept this proposed fair and equitable resolution of this matter.

Respectfully,
Sal Simonetti
3 * Officiali
Change-of-Address
auN�rE�sT�TEs Confirmation Letter
POSTAL SERVICE® '„�,„.,

IERIFICATION REQUIRED

YOUR OLD ADDRESS
Mail will be forwarded for the SIMONETTI
following individual only:

Your mail will be forwarded to your NEW address,
as you requested,on:MAY 2,2022
If you want to view or cancel this YOUR NEW ADDRESS Change-of-Address order or change the
date to start forwarding your mail,visit
managemymove.usps.com and enter your 034 B921 00001021 00046596 1 1 Confirmation Code or scan the UR code to IIIIIIIIIIII'IIIIIII'llIllIlIlIl'IlrrllllIlII'llIlIlIlIlIIII'I"I get started.

CONFIRMATION CODE:

SAL SIMONETTI
2212 4095 2000 3840

0i 1
Don't miss any mail) Extend your Mail

MAIL FORWARDING EXPIRATION DATES
Forwarding End Date now for$19.95 for a v
First Class Mail®,Priority Mail®6-month extension,$29.95 for a 12-month May 2,2023 &Priority Express Mail®
extension,or$39.95 for a 18-month extension. Jul 1,2022 To purchase Extended Mail Forwarding please Newspapers,Magazines go to managemymove.usps.com.* Packages' Not Forwarded Extended Mail Forwarding Catalogs Not Forwarded2 Standard Mail Not Forwarded2

1.Some restrictions apply 2.Unless requested by mailer
ss and receive
nders of mail
expiration
es.

Visit c a change-of-address
ad ress.comrr addt r email have note received mail at your)newladdress for 10 Postal business daysdortmore, If your change-of-address is correct and you *To begin your extension process,please take this letter to your local USPS location. please call 1 800 ASK-LISPS(1-800-275 87771•
IMPORTANT MESSAGES FROM THE U.S.POSTAL SERVICE REGARDING YOUR MAIL FORWARDING REQUEST Please retain this Official Change-of-Addressresources Coe firma ion page f of your move.
your
records WHY THE YELLOW OR WHITE LABS
as logical agencies and/or fYellow or White stickers with your new address are placed on mail forwarded by the U.S.Postal Service.These labels indicate EvenR
vmembeu v updateei your voteristregistration:edooe, the correspondent doesn't know your new address. if you've previously registered to vote,you need to reregister VOTE To receive your mail faster,notify the sender of your new address. 41111, after you move(or if you change your last name).Filing a change- of-address with the United States Postal Service does not automatically update your voter registration information.To fill out your voter registration form and receive a pre-addressed mailer, 160� 5 11I1„I ;.
p1�j53poB
visit app.mymove.comlwelcome and enter code:4xy4ytn7uu 6'111 4 50
5 1'r5 4 260'7 15 12 r2 A1/.ah.
3t�I0Y 14 03.pp3 021153000
B OV7i 6HZTi50
Note.North Dakota residents are not required to register to vote. plu ulll , TGB sai� p�•(S0�1rN3 MN 55603-0094
III;I:c„I:::,�111„tl,d1,1,11,11d1,d „I,n,11,M,1,1,111,1 All of the paper used to produce the USPS�Official Change-of-Address O �� 1 Confirmation Letter was sourced from sustainable forests. C 220505.034-00046596

crs
V___
_ CERTIFIED MAIL` g
,4 Ft't f
1 ,4111 Di 2S8" :PEIR'RN2AORD22 IFIt:C:r;C:tA: 923' \ , / T
7021 1970 0001 3915 9197
4 P I
945120007 \ V,‘ S\
` SAL SIYIGNETTI —2— , C

NIXIE ices LEA. :i s , 1:0005 1'
.., tTI F 5 AL 1'

9441XIKSZ3i.$'f : Z.A$9il; ( > ] -t , 4 .1 13ywa ajg t']�S ){.a (}j}2�itli j lj 0 — CIE '.g {4— 2 �—4 1. -......... 'I�{ i t4 eE.4)'ys t": }Itj1} ilib 1i li iiiiiiiji•!j f Oil IN' 1} i F:I M

;� Case Number:
tio* rF.Nf� �; Demand for Payment
\,. City of Temecula
Finance Department Date:07/12/2022
1' 1 41000 Main Street
l Temecula, CA 92590
a
'4 1989

SAL SIMONETTI

Property: Parcel# --
Location Address

,TEMECULA,CA
You are shown as the owner of record for Assessor's Parcel Number by the Riverside County Assessor's records.

On or about 4/28/2022 you were notified to abate the following violation(s)on the above listed property:

Temecula Municipal Code# Description
TMC 8.16.020 Duty to abate hazardous vegetation.

Upon inspection on 06/06/2022,this parcel was not in compliance.As the owner of record you are liable for costs incurred on your parcel.

If payment is not received by 7/25/2022,the amount will be entered as a SPECIAL ASSESSMENT on the next TAX STATEMENT, against your parcel.

A Public Hearing has been scheduled before the City Council to occur on 7/26/2022 at 6:00pm to adopt a resolution ordering confirmation of the special assessment against parcels of land within the City of Temecula for costs of abatement and removal of hazardous vegetation. Published Notice of Public Hearing is attached to this Demand for Payment.

If you have any questions, please call Code Enforcement at(951)302-4144 Monday through Friday, 8:00 AM to 5:00 PM.

MAIL TO: City of Temecula Weed Case Number:

41000 Main Street Due Before: 7/25/2022
Temecula, CA 92590 Amount Due: $982.00
MAKE CHECK PAYABLE TO CITY OF TEMECULAAND INCLUDE YOUR CASE NUMBER ON YOUR CHECK.

Case Detail:WA22-0997 #' rR ' r
. tf
Ho• ` N/
Report Printed:711212022 ,�,r

← All documents from this meeting