Assigned Planner Approval
PA Number Project Address APN Apply Date Date Applicant Company Owner Plan Type Status PA24-0159 31797 Temecula Pky 961-080-012 Yannin Marquez 04/11/2024 Matt Millon GALILEO VAIL PL Modifications Plan Review Temecula, CA 92592 RANCH LP
Case Title / Description: Harbor Freight Tools MOD: A Modification Application for exterior modifications that include a new storefront system, cart corral at the front of the building, removal of a drive-thru window, a new door at the rear with concrete pad, and upgrade a door at the front of the existing commercial building located at 31797 Temecula Parkway.

PA24-0160 40910 Temecula Center Dr 916-400-025 Yannin Marquez 04/11/2024 Julie Morrow Lightbox/PZR Temecula Auto PL Zoning or Approved Temecula, CA 92591
Prop Planning Letter
Case Title / Description: 40910 Temecula Center Drive ZL: A Zoning Verification Letter for 40910 Temecula Center Drive (APN 916-400-029) and the adjacent lot to the east (916-400-025) PA24-0162 32525 Zinna Ct 964-850-009 Katie Garcia 04/15/2024 Stephen Sigler Axis3architects Tom McEnroe PL Modifications Approved Temecula, CA 92591
Case Title / Description: McEnroe Garage Conversion MOD: a Modification Application (Planning Review Only) for the conversion of one (1) of the three (3) car garages to a 250 square foot office for the residence located at 32525 Zinna Court
PA24-0167 31709 Temecula Pky 961-080-004 Yannin Marquez 04/17/2024 Noelia Santiago Brian Kritz PL Modifications Plan Review Temecula, CA 92592
Case Title / Description: Cava MOD: A Minor Modification Application for the exterior changes that include, facade, color scheme and reversal of the flow of the drive -through to accommodate a new pick-up window at the existing commercial building located at 31709 Temecula Parkway.

PA24-0169 45533 Via Puebla 962-143-037 Yannin Marquez 04/17/2024 Bobby Berrera Steven Strepek PL Modifications Approved
Temecula, CA 92592
Case Title / Description: Strepek Residence Deck MOD: A Modification Application (Planning Review Only) for the construction of a new two-story deck on the rear of the existing residence located at 45533 Via Puebla.

PA24-0170 29375 Rancho California Rd 944-330-015 Katie Garcia 04/22/2024 Erin Gonzalez Tamera Moore PL Temporary Plan Review
Temecula, CA 92592
Use Permit
Case Title / Description: Misfit Made Market TUP: a Major Temporary Use Permit Application for a vendor market with 30 vendors to occur on May 19, 2024 from 11:00 AM - 3:00 PM in the parking lot of Oscar's Brewing Company located at 29375 Rancho California Road.

PA24-0171 27430 Ynez Rd 921-290-014 Scott Cooper 04/23/2024 Armen BTAA Prop Inv II PL Modifications Plan Review Temecula, CA 92591 Kazanchyan
Case Title / Description: Temecula Hyundai Coolant Enclosure MOD: A Modification to an existing building for the addition of an approximately 47 square foot oil and coolant tank enclosure located at 27430 Ynez Road.

Page 2 of 4 ends

Assigned Planner Approval
PA Number Project Address APN Apply Date Date
Applicant Company Owner Plan Type Status
PA24-0172 43513 Ventana St 944-330-046 Scott Cooper 04/23/2024 Casey Harris Ynez Road PL Modifications Plan Review
Temecula, CA 92592
Housing Partners
LP
Case Title / Description: Arrive @ Rancho Highlands MOD: A Modification to a previously approved Development Plan (PA19-1448) to add fire alarm closets to three (3) buildings located adjacent to the Temecula Duck Pond approximately 775 feet southeast of Rancho California Road on the north side of Ynez Road.

PA24-0173 28975 Old Town Front St 922-110-042 Yannin Marquez 04/23/2024 Stephen Peebles 28795 PL Modifications Approved
Temecula, CA 92590

VENTURES
Case Title / Description: Ahmed Medical Center MOD: A Modification Application for the installation of a black iron fence to enclose the exterior foyer at the front and rear of the existing building located at 28975 Old Town Front Street.

PA24-0174 28820 Single Oak Dr 921-020-051 Yannin Marquez 04/24/2024 Juan Noe Chemicon PL Modifications Plan Review
Temecula, CA 92590
International Inc.

Case Title / Description: Millipore Sigma MOD: A Modification Application (Planning Review Only) for the construction of a 1,395 square foot mezzanine inside an existing industrial building located at 28820 Single Oak Drive.

PA24-0177 28676 Old Town Front St 922-044-009 Yannin Marquez 04/30/2024 Megan Coleman FRONT STREET PL Temporary Approved
Temecula, CA 92590
HOLDINGS Use Permit
Case Title / Description: Swing Inn TUP: a Temporary Use Permit for selling food and alcohol at 28676 Old Town Front Street during the Rod Run event on May 3, 2024, from, 12:00 PM to 12:00 AM & May 4, 2024, from 10:00 AM to 12:00 AM.

PA24-0178 42081 3Rd St 922-046-012 Yannin Marquez 04/30/2024 Marx Cellars LLC Marx Cellars FI ADCO 16 LLC PL Modifications Plan Review Temecula, CA 92590
LLC
Case Title / Description: Humble Somm Patio MOD: A Modification Application (Planning Review Only) for an outdoor dining patio that includes a decorative iron fence located at 42081 3rd Street.

PA24-0179 42225 Remington Ave , A21 909-374-021 Scott Cooper 04/30/2024 Sherrie Munroe NP5 LLC PL Modifications Plan Review
Temecula, CA 92590
Case Title / Description: 42225 Remington Ave. Mezzanine MOD: A Modification to an existing building for the addition of a second floor office mezzanine located at 42225 Remington Ave., Suite A21

Page 3 of 4 ends

Assigned Planner Approval
PA Number Project Address APN Apply Date Date
Applicant Company
Owner
Plan Type
Status
PA24-0180 921-281-014 Jaime Cardenas 04/30/2024
Mike Bareh

SMALL STEPS
PL Development
Plan Review
Temecula, CA
1934 INC
Plan
Case Title / Description: Small Steps Industrial: a Development Plan application for a proposed 8,000 square foot industrial building on the vacant .59-acre parcel located on the northwest corner of Felix Valdez Avenue and Baldaray Circle.

PREAPP24-0 40426 Winchester Rd 910-470-015 Jaime Cardenas 04/05/2024 Andrew Proctor
Inland Western
PL
Plan Review
148 Temecula, CA 92591
Temecula
Pre -Application
Commons LLC
Case Title / Description: USAgain Clothing Container Preapp: a pre -application for a proposed 8'x20' storage container located on The Commons' shopping center parking lot (APN 910-470-015).

PREAPP24-0 28950 Old Town Front St 922-120-011 Jaime Cardenas 04/05/2024 Ana Salazar
Temecula Brand
PL
Plan Review
149 Temecula, CA 92590
Investing LLC
Pre -Application
Case Title / Description: Shooter's Patio Preapp: a preapplication review for a proposed 26'x57' patio with seating on the parking lot of the existing Shooter's building located at 28950 Old Town Front Street.

PREAPP24-0 28535 Old Town Front St 922-035-011 Jaime Cardenas 04/08/2024 Dan Gibson
PL
Plan Review
151 Temecula, CA 92590
Pre -Application
Case Title / Description: Small Barn BBQ: a preapplication for a proposed outdoor BBQ grill at Small Barn located at 28535 Old Town Front Street.

Page 4 of 4 ends

Item No. 17

CITY OF TEMECULA

AGENDA REPORT
TO: City Manager/City Council
FROM: John Crater, Division Chief
DATE: May 28, 2024
SUBJECT: Fire Department Monthly Report
PREPARED BY:

RECOMMENDATION:

Report.

Tyren Hundley, Management Analyst
That the City Council receive and file the Fire Department Monthly

CITY OF TEMECULA

FIRE DEPARTMENT
Operations Prevention I Training I Emergency Management MONTHLY REPORT I APRIL 2024
�+
d 0 �frl�Ilf., Ira' i�=i i= =i '•rrr�fi�ff{f������ � ! ++{�ri - PRISM —
= 5 Stations 7 Engines I USAR 2 Truck I Squad
r
opu ation - Il ISO RaT
APRIL CALL BREAKDOWNni
•.T _ �,,� �-
�t.,. False Alarm
TYPE: >I # TYPE: '+s.r ,� #
COMMERCIAL FIRE I� 1ires
TRAFFIC COLLISION 77
MULTI -FAMILY FIRE_ O MEDICAL EMERGENCY 5E7
TC
RESIDENTIAL FIRE - D— OTHER MISCELLANEOUS 15 -
- PUBLIC ASSIST , 32
WILDLAND FIRE -- STANDBY} : , ::...; f ;
VEHICLE FIRE r 4 � �- . - ' € y.r
Medical Emergencies
OTHER FIRE �- :. .` """ 696 .

RESCUE
RINGING ALARM�r

4. = FALSE ALARM
HAZMAT
TOTAL:
-------------
10 w nr
d. Tr7ww
2024 Year
Calls .
3,388

CITY OF TEMECULA

FIRE DEPARTMENT
Operations Prevention I Training I Emergency Management PLAN

CHECKS/REVIEWS
542
YTD: 2,174
Map
AL
MONTHLY REPORT APRIL 7024
„APRIL INSPECTION BREAKDOWN ���"�`�"12

ANNUALS STATE
P70

SPECIAL EVENT

MANDATED

PERMITS INSPECTIONS
■. r a -r .

YTD: O
� ��� yr.

INSPECTIONS
. -
��5
YTD:2,2DO - -
-
YTO:1,995
PUBLIC

INQUIRIES
47 YTD:14B

CITY OF TEMECULA

FIRE DEPARTMENT
Operations I Prevention I Training I Emergency Management _ - MONTHLY REPORT AWRIL 2024
PROGRAM HIGHLIGHTS: f�rr,
.rIllllllll�11t�,ti,,.
• Hosted a TEEN Cert Course AprQtht(7th graduating 32 Students • OEM is working with ITSS to implement Desktop Alerting for emergency notifications OEM and TEE attended the Wolf Creek Safety Fair sharing preparedness information OEM continues to work with TCSD on increasing Community Outreach for a relhs nts-)�-' GRANTS U CLAIMS:
jo
• Awarded FY23 EMPG: $24,475-
• Awarded FY23 SHSP: $15 79
TEE VOLUNTEER PROGRAM._ -:-
# of hours contributed: 468 =.
# of hours YTD:1,777 �l` _ �~- �.N
# of TEE Volunteers: 45 ,--
# of volunteer meetings: 3
# of training events: I (TEEN CERT)
PLANNED CDMMUNITY EVENTS SUPPORTED: I
CITYRESPONSE:0
PREPAREDNESS TRAINING / EVENTS;
Community Presentations: 0
Community Training: 2
• TEEN Cert/Wolf Creek Safety Fa
community Preparedness Backpac

EMERGENCY OPERATIONS CENTER -
Activations: 0
Current Status: Normal Operations -

CITY OF TEMECULA
l�
FIRE DEPARTMENT %
(7eox,
Operations I Prevention I Training I Emergency Management Temecula Citiz ,/,,,
III
l �
MID
N
Wy �
,was A
yl
IN

Item No. 18

CITY OF TEMECULA

AGENDA REPORT
TO: City Manager/City Council
FROM: Chris Durham, Captain
DATE: May 28, 2024
SUBJECT: Temecula Sheriff's Monthly Report (April 2024) PREPARED BY: Chris Mattson, Sergeant
RECOMMENDATION: That the City Council receive and file monthly report for April 2024.

The following report reflects the Temecula Sheriff's Station activity for April 2024.

PATROL SERVICES
Overall calls for police service.................................................................................................5,792 "Priority One" calls for service......................................................................................................65 Average response time for "Priority One" calls.........................................................................5.46

VOLUNTEERS
Chaplain....................................................................................................................................47.50 Community Action Patrol (CAP) hours..................................................................................658.25 Reserve officer hours (patrol)........................................................................................................13 Explorer........................................................................................................................................102 Station/Administration................................................................................................................33.5 Total Volunteer hours.............................................................................................................854.25

OLD TOWN STOREFRONT
Total customers served.....................................................................................568 Fingerprints/Live Scan.....................................................................................148 Policereports filed..............................................................................................4 Citationssigned off..........................................................................................23 Totalreceipts...........................................................................................................................$5,102

CRIME PREVENTION
Crime prevention/Neighborhood watch meetings...........................................................................5 Safety presentations/Training................................................................................0 Specialevents...................................................................................................................................5 Residential/Business security surveys conducted............................................................................0 Residences/Businesses visited for past crime follow-up.................................................................0 StationTours....................................................................................................................................2 Planning Review Projects.......................................................................................4 Temp Outdoor Use Permits....................................................................................9

SPECIAL TEAMS (CORE)
ReportsWritten...............................................................................................34 Onsight felony arrests.....................................................................................................................3 On sight misdemeanor arrests.................................................................................7 Felony arrest warrants served.................................................................................3 Misdemeanor arrest warrants served
...............................................................................................2 AreaChecks.....................................................................................................52 CampChecks................................................................................................33 PedestrianChecks.....................................................................................................59 Traffic Stops/Vehicle Checks..................................................................................................... 0/0
Outreachattempts / Success...................................................................................................... 20/1
SPECIAL TEAMS (Metro District Team)
Onsight, felony arrests........................................................................................4 On sight, misdemeanor arrests.......................................................................................................26 Felony arrest warrants served..........................................................................................................5 Misdemeanor arrest warrants served
...............................................................................................8 Bar/Business checks......................................................................................................................64 D.U.I. Arrests ... .............................................................................................................................

I I
Traffic/Parking citations...............................................................................................................93 FirearmsSeized................................................................................................

I
SPECIAL TEAMS (Special Enforcement Team)
Onsight felony arrests.................................................................................................................... I I On sight misdemeanor arrests.........................................................................................................19 Felony arrest warrants served...........................................................................................................3 Misdemeanor arrest warrants served................................................................................................3 Follow-up investigations/search warrants.....................................................................2 Parole/Probation Searches...............................................................................................................3 PedestrianChecks.................................................................................................12 Traffic Stops/Vehicle Checks...................................................................................................38/13 Marijuana Dispensary Checks.........................................................................................................0

ROBBERY/BURGLARY SUPPRESSION TEAM
BeginningCaseload.......................................................................................................................86 TotalCases Assigned....................................................................................................................14 TotalCases Closed..........................................................................................................................7 Search Warrants prepared/served.................................................................................................I I Arrests..............................................................................................................................................6 Outof Custody Filings............................................................................................4

TRAFFIC
Citations issued for hazardous violations....................................................................................917 Non -hazardous citations.................................................................................................................82 Parkingcitations...........................................................................................................................183

Stop Light Abuse/Intersection Program (S.L.A.P.) citations.........................................................81 Seatbelts.........................................................................................................................................17 CellPhone Cites...........................................................................................................................306 Injurycollisions.............................................................................................................................22 D.U.I. Arrests.................................................................................................................................28 Grant -funded D.U.I. Traffic safety checkpoints/saturation enforcement........................................0 Grant -funded traffic click it or ticket/traffic enforcement..............................................................4

INVESTIGATIONS
BeginningCaseload.......................................................................................................................91 TotalCases Assigned..................................................................................................................217 TotalCases Closed........................................................................................................................35 Search Warrants prepared/served
.................................................................................................31 Arrests..............................................................................................................................................6 Outof Custody Filings..........................................................................................10 Sex Offenders Processed....................................................................................20

PROMENADE MALL TEAM
Callsfor service...........................................................................................................................227 Felonyarrest/filings.......................................................................................................................10 Misdemeanor arrest/filings............................................................................................................10 TrafficCitations................................................................................................I Total customers served................................................................................................................641 Fingerprints/Live Scans...............................................................................................................149 Totalreceipts............................................................................................ $6,546

SCHOOL RESOURCE DEPUTIES
Felonyarrest.....................................................................................................................................0 Misdemeanor arrests........................................................................................................................7 Reports...........................................................................................................................................20 Citations.........................................................................................................................................39 Meetings/Presentations................................................................................................................176

Item No. 19

CITY OF TEMECULA

AGENDA REPORT
TO: City Manager/City Council
FROM: Patrick Thomas, Director of Public Works/City Engineer DATE: May 28, 2024
SUBJECT: Public Works Department Monthly Report
RECOMMENDATION: Receive and file the Public Works Department Monthly Report for Capital Improvement Projects, Maintenance Projects, and Land Development Projects. This report may also be viewed on the City's website at:
hlt2://temeculaca.gov/270/Cqpital-improvement-Projects-CIP

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024

CAPITAL IMPROVEMENT PROJECTS

CIRCULATION PROJECTS
Cherry Street Extension & Murrieta Creek Crossing, PW19-15 Description: Preliminary design of the Extension of Cherry Street from Adams Avenue to Diaz Road, including a new crossing of Murrieta Creek.

Cost: $36,200,000
Status: Preliminary design, environmental evaluation, and cost estimate is complete. The final report includes 30% design plans for a two -span, 250-foot long bridge and for a two -span, 250-foot long bridge plus 12-span, 500-foot long viaduct. These options were selected to address concerns received from environmental resource agencies to preserve species corridors and from the Riverside County Flood Control & Water Conservation District to minimize impacts to flood protection.

Diaz Road Expansion, PW17-25
Description Improve Diaz Road to meet the roadway classification of Major Arterial (4 Lanes Divided), between Cherry Street and Rancho California Road. The 2.2-mile stretch will be widened, extended, and/or improved to create a contiguous Major Arterial segment. The project will be developed and constructed in two phases.

Phase 1 will include improvements on Diaz Road from Winchester Road to Rancho California Road. Phase 2 will include improvements on Diaz Road from Cherry Street to Winchester Road.

Cost: $14,255,991
Status: The environmental Initial Study has been approved, Mitigated Negative Declaration adopted, and Notice of Determination filed in May 2022. Design is 90% complete. Regulatory permit applications have been submitted for USACE 404 Nationwide Permit and CDFW Streambed Alteration 1602. Current activities include consultant review of 90% plan check comments, design coordination with utility purveyors (SCE, RCWD, and EMWD) and City project PW16-05 Murrieta Creek Bridge at Overland Drive, Riverside County Flood Control review of 90% design plans and Encroachment Permit application, and preparation of regulatory permit applications for SWRCB 401 Water Quality Certification and USACE Section 408.

Construction previously anticipated to start in Spring of 2024 is now delayed to Spring/Summer of 2025 due to EMWD sewer line project on Diaz Rd as well as coordination with ACOE and RCFC on their Murrietta Creek Phase 2B Project. Potential for further delays as potential federal funding being added to the project in federal fiscal year 2025 would require project compliance with NEPA.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
CIRCULATION PROJECTS (Continued)
French Valley Parkway/Interstate 15 Improvements- Phase 11, PW16-01 Description: Design and construction of the two-lane northbound collector/distributer road system beginning north of the Winchester Road interchange on -ramps and ending just north of the Interstate 15/Interstate 215 junction with connection to Interstate 15 and Interstate 215.

Cost: $138,736,346
Status: Project is under construction May 2023 — May 2025. For detailed information, please visit the project website at TemeculaCA.gov/FVP2.
1-15 Congestion Relief, PW19-02
Description: Design and construction of a single auxiliary lane, northbound Interstate 15 connecting the Temecula Parkway on -ramp to the Rancho California Road off -ramp.

Cost: $8,971,710
Status: Project is under construction March 2024 — October 2024. For detailed information, please visit the project website at TemeculaCA.gov/Congestion Relief.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
CIRCULATION PROJECTS (Continued)
Murrieta Creek Bridge at Overland Drive, PW16-05
Description: Design and construction of a new bridge crossing over Murrieta Creek between Rancho California Road and Winchester Road.

Cost: $26,073,374
Status: The City applied and was approved to receive Federal Highway Bridge Program (HBP) funds. City Council approved the design agreement with CNS Engineers Inc. at the March 12, 2019, meeting. Preliminary Environmental Study (PES) approved by Caltrans on August 15, 2019. Plans are 90% complete. RCA JPR Conformance is approved. Biological monitoring in Temecula Creek for potential mitigation site is complete as of July 2021. Project has received MSHCP conformance. Staff continues to work with Caltrans to advance HBP Grant Funds to earlier fiscal years. Caltrans HBP Program management had proposed reducing the curb -to -curb width of the bridge that is considered "participating" for grant funding purposes.

Staff has been able to address this issue with Caltrans and the majority of the bridge width will remain as a participating cost. 2023 HBP Bridge Update was submitted in August 2023. Caltrans NEPA review took much longer than anticipated but approval was received in October of 2023. CEQA ISMND is complete and the 30-day public review has ended. CEQA was approved at the February 27, 2024, City Council meeting.

Construction start is anticipated in FY 2026 / early 2027 depending on availability of HBP funds. Also, additional coordination is required with ACOE and RCFC as Murrietta Creek Phase 2B will likely be in construction concurrently with this project.

Overland Drive Widening, PW 20-11
Description This project includes widening Overland Drive from Jefferson Avenue to Commerce Center Drive, to two lanes in each direction, and the completion of missing segments of sidewalk, streetlights, and installation of the traffic signal at Commerce Center Drive and the modification of the traffic signal at Jefferson Avenue.

Cost: $2,894,420
Status: 90% plan check submittal package was submitted in July 2023, and it has been reviewed by staff.

Environmental documents are anticipated to be returned to Consultant during the week of May 201" Rainbow Canyon Road Pavement Rehabilitation, PW22-15
Description Design and construction of pavement rehab for Rainbow Canyon Rd from Pechanga Parkway to southern City Limits.

Cost: $2,900,000
Status: Plans and Specs have been completed and signed. The project will be posted on PlanetBids during the week of 5/6/24 and bids will be opened on 6/6/24. Anticipated award will take place at the 7/9/24 meeting.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
CIRCULATION PROJECTS (Continued)
Rancho California Road Median Improvements, PW23-04
Description: Design and construction of missing raised concrete medians with landscaping between Humber Drive and Butterfield Stage Road. In addition, there will also be construction of missing improvements on the north side of Rancho California Road, between Riesling Court and Promenade chardonnay Hills. The improvements will include median curbs, curb and gutter, sidewalks, and landscape and irrigation.

Cost: $3,855,000
Status: RFP for design is anticipated to be posted on PlanetBids in Q2 2024.

Ynez Road Improvements — Phase I, PW23-02
Description: This project includes widening the easterly side of Ynez Road, from Rancho Vista Road north roughly 1600 feet, to two lanes in each direction, and the completion of missing segments of curb and gutter, sidewalk, and striped medians, in coordination with adjacent development.

Cost: $2,950,000
Status: This project is currently in design.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024

INFRASTRUCTURE PROJECTS
Bike and Trail Program — Great Oak Trail Lighting, PW21-16 Description: Project includes the installation of solar lights along the Great Oak Trail adjacent to the northeast side of Pechanga Parkway from Deer Hollow Way to Loma Linda Road.

Cost: $828,600
Status: Project is currently in design.

Citywide Concrete Repairs FY2022-23, PW23-17
Description: The Citywide Concrete Repairs is an annual maintenance project to repair various concrete facilities within the City's public right-of-way. The Department of Public Works, Maintenance Division surveys the City and compiles a list of the improvements that are in need of repair. This year's project will remove and replace curb & gutter, sidewalk, access ramps, driveways, cross gutters, and under sidewalk drains at more than one hundred and six (106) locations. In addition, an added alternate concrete repair area for this project is located at the Community Recreation Center (CRC) parking area.

Cost: $350,068.70
Status: Project was publicly bid from 8/31/2023-9/19/2023. Construction contract was awarded at the 10/10/2023 City Council Meeting. The notice to proceed was issued on November 13, 2023. The project is expected to be completed in May 2024.

Citywide Drainage Master Plan, PW19-16
Description: Project will prepare a report that shows all drainage courses within the City. Also includes a master hydrology study showing the anticipated storm flows at build -out.

Cost: $600,000
Status: GIS database has been 90% updated and is being used by staff. Potential future CIP projects/locations have been reviewed by City staff. Consultant is adding CIP project locations into the overall drainage model. Completed model in June 2024.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
INFRASTRUCTURE PROJECTS (Continued)
Citywide Slurry Seal FY2022-23, PW23-16
Description: The Citywide Slurry Seal Program - Fiscal Year 2022-23 is an annual project that will utilize slurry to seal the project roadways against water intrusion and deterioration of the asphalt concrete pavement wearing surface. This year's project location is in Rancho Vista, Los Ranchitos, and Rancho Vista East areas.

Cost: $2,460,421.82
Status: Project was publicly bid from 8/31/2023-9/19/2023. Construction contract was awarded at the 10/10/2023 City Council Meeting. The Notice to Proceed was signed on 10/11/2023 and construction began. The slurry seal placement started on November 27, 2023. The project is expected to be completed in May 2024.

Community Recreation Center (CRC) Renovations, PW19-07
Description: The project facilitates the rehabilitation, improvement, and reconfiguration of the Community Recreation Center. This project includes expansion and reconfiguration of teen center; conversion of office space to accommodate a dedicated police substation; renovation of key components of the building including safety features, flooring, roof, and restroom facility access; ADA compliance; renovation and expansion of existing office space and rec rooms including AV upgrades; expanded storage space and upgraded kitchen equipment.

Cost: $10,708,232
Status: The facility was re -opened to the public following completion of Phase 1 in mid -June, 2023. Design for Phase 2 is continuing.

Fiber Optic Communications Systems - Citywide (System Master Plan), PW 22-03 Description: This project will develop a communications masterplan that will provide a strategic plan outlining the approach and buildout design of fiber optic cable and conduit throughout the City. The masterplan document will provide a roadmap to connect all existing and future traffic signals, traffic monitoring devices, surveillance cameras, and City facilities to City -owned fiber communication lines. The ultimate project goal is to enhance the City's existing fiber optic communication system to ensure it can handle the future needs of the City.

Cost: $120,150
Status: The project has just commenced, and the consultant is working on an existing systems assessment.

Documents are being developed.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
INFRASTRUCTURE PROJECTS (Continued)
Fire Station 73 Gym/Garage, PW19-13
Description: Project consists of adding a second garage in the rear of the property to park the squad and Urban Search and Rescue (USR) vehicle, along with a gym and storage rooms. The construction is anticipated to be completed in the Fiscal Year 2024-25.

Cost: $3,477,515
Status: Architect has prepared a schematic design and exterior rendering, which was reviewed by the Fire Department. The project geotechnical report is complete. The consultant has started developing construction plans. First submittal plans expected in June 2024.

Fire Station 84 Renovation, PW19-14
Description: This project includes the design, construction, and renovation to Fire Station 84. The renovations include adding a Wellness Room, expanding the Storage Room, and upgrading the Training Room. Also, the upgrades include electrical, windows, flooring, paint, tile, HVAC, cabinets, plumbing fixtures, garage bay doors and any necessary improvements needed to conform to ADA accessibility access.

Cost: $1,955,309
Status: Preparing a phasing plan that will allow the Fire personnel to maintain their occupancy of the building during construction. Plans and specifications were revised. Anticipate re -bidding the construction contract in June 2024.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
INFRASTRUCTURE PROJECTS (Continued)
Interstate 15 / State Route 79 South Interchange Enhanced Landscaping, PW17-19 Description: Landscape beautification of the Interstate 15 corridor between French Valley Parkway and Temecula Parkway, including each interchange, in association with Visit Temecula Valley and the Pechanga Tribe.

This project includes the design and construction of enhanced landscaping, hardscape, and irrigation between the freeway and ramps on the west side of the Interstate 15 / State Route 79S (Temecula Parkway) interchange.

Cost: $3,558,483
Status: Design and environmental studies August 2019 — March 2024. Caltrans is currently reviewing 100% plans.

At the 01/09/2024, the City Council approved the plans and specifications and authorized staff to advertise the project for construction bids. Upon Caltrans approval of the plans, the construction contract will be advertised for bids. Estimate bidding in June 2024.

Margarita Recreation Center, PW17-21
Description: Demolition and Reconstruction of New Margarita Recreation Center Building and Pool Cost: $12,601,508
Status: The Design -Build Contract was awarded at the March 9, 2021, City Council Meeting to De La Secura Builders, Inc., for a Guaranteed Maximum Price of $8,680,459.00. Major demolition activities commenced mid -March 2022. City Groundbreaking occurred on March 31, 2022. Permanent power installed in July of 2023 and gas installed in October of 2023. Ribbon cutting was held on December 14, 2023. Building occupancy was approved in January 2024 and the building is fully operational now. Punchlist, warranty, and final closeout are the only remaining activities.

Santa Gertrudis Creek Phase II, Margarita Road Under -crossing, PW19-04 Description: Construction of the under -crossing in Santa Gertrudis Creek at Margarita Road to connect the pedestrian/bicycle trail.

Cost: $4,037,215
Status: Project was advertised for construction bids on 02/12/2024 through 03/21/2024. Planning to award construction contract on 05/14/2024.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
INFRASTRUCTURE PROJECTS (Continued)
Sidewalks — Citywide (Ynez Road, Rancho Highland to Tierra Vista Road), PW17-28 Description: New sidewalks on the west side of Ynez Road from Rancho Highland to Tierra Vista Road.

Cost: $197,000
Status: ADA Access Ramps have been revised and currently being reviewed. The project is scheduled to be advertised for construction bids in May 2024.

Sidewalks — Citywide (Pauba Road, Elinda Road to Showalter Road), PW 19-20 Description: New sidewalks and street widening on the South side of Pauba Road from Elinda Road to Showalter Road.

Cost: $369,795.

Status: Project is at 95% design stage.95% plan check comments were returned to Consultant in December 2023.

Plans anticipated to be completed in May 2024. The project is scheduled on the May 14, 2024, City Council Meeting to solicit bids.

Sidewalks - Old Town Improvements - South Side of Sixth Street (Old Town Front Street to Mercedes Street), PW22-16
Description: This project involves adding and improving sidewalk on the south side Sixth Street in Old Town from Old Town Front Street to Mercedes Street. The improvements include adding sidewalks, concrete ramp bulb outs, rolled curb and gutter, streetlights, and trees in accordance with the Old Town Specific Plan.

Cost: $591,194
Status: This project is at the 95% design stage. The Consultant is finalizing the plans and specifications.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
INFRASTRUCTURE PROJECTS (Continued)
Sidewalks - Old Town Improvements - Additional Streetlights on Moreno Road and Mercedes Street (East of Old Town Front Street), PW22-17
Description: This project involves eight additional old town streetlights for Moreno Road and Mercedes Street. The tree existing streetlights will be removed and replaced with the proposed decorative streetlights to match the old town aesthetic.

Cost: $175,337
Status: Construction is complete. The project was accepted at the 04/23/2024 City Council meeting and the Notice of Completion has been filed.

Southside Parking Lot Reconfiguration, PW15-07
Description: This project includes rehabilitation and reconstruction of the existing parking lot. Work includes removal, rehabilitation, and/or replacement of pavement, restriping the parking to the temporary and final conditions, modification of the existing lighting system, construction curbs and islands, installation of bollards, installation of wheel stops, construction of water quality treatment features, and planting of trees and shrubs.

Cost: $1,250,750
Status: Advertisement for construction contract bids began on May 2, 2024, and the bid opening is scheduled for May 29, 2024.

Utility Undergrounding - Citywide - Power Pole Serving 28551 and 28561 Old Town Front Street (Between Fifth and Fourth Street), PW22-18
Description: This project includes undergrounding the power pole serving 28551 and 28561 Old Town Front Street with the goal of beautifying Old Town.

Cost: $20,000
Status: A Right of Entry Agreement with the property owner has been completed. Construction began in March 2024. Completion is anticipated in June 2024.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024

PARKS AND RECREATION PROJECTS
Community Recreation Center Splash Pad & Shade Structures, PW21-07 Description: This project provides for the conversion of the CRC's wading pool into a splash pad, and the addition of shade structures in the area.

Cost: $1,100,000
Status: Bids were opened on November 30, 2023. The City Council awarded the construction contract on 01/23/2024. Construction began on 03/11/2024 with estimated completion in August 2024.

Dog Park Renovation, PW21-14
Description: Design and construct a dog park including a small dog pen and large dog pen at Michael "Mike" Naggar Community Park.

Cost: $1,040,000
Status: Project is 21 working days into the 35 working day duration. Majority of construction to be completed late May. Shade structures and light pole foundation will be installed once the permit is approved by building and safety and the shade structures are delivered to the site. Estimated completion of construction is July 2024.

Murrieta Creek Improvements — Trail Lights, PW21-13
Description: This part of the project involves installing 27 solar lights along the Murrieta Creek trail on the east side of the creek from Rancho California Road to First Street.

Cost: $200,000
Status: Riverside County Flood Control Permit submitted as of January 4, 2023. A US Army Corps of Engineers (USACE) 408 permit is required and an application has already been submitted.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
PARKS AND RECREATION PROJECTS (Continued)
Park Restroom Renovations, Expansion and Americans with Disabilities Act (ADA), PW17-06 Description: Renovation of various park site restroom facilities, including Ronald Reagan Sports Park North/South Ball Field (new roof, cabinets, fixtures, and other building improvements), Vail Ranch Park (PW23-06) and Long Canyon Creek Park (PW23-18).

Cost: $1,127,800
Status: Project is ongoing. Ronald Reagan Sports Park North/South Ball Field Restroom building is currently in the design phase and the project will be advertised for construction bids in Spring 2024, with construction in Summer 2024. Vail Ranch Park, PW23-06, and Long Canyon Creek Park, PW23-18, are in the scoping phase.

Pickleball Courts, PW21-03
Description: Design and construct 17 dedicated pickleball courts at Ronald Reagan Sports Park.

Cost: $3,300,878
Status: Project was publicly advertised from 3/25/24 — 4/23/24. Construction contract is scheduled for award by City Council at the May 14t" Meeting. The project is expected to be completed October 2024.

Ronald Reagan Sports Park Hockey Rink, PW22-06
Description: This project will include the renovation of the existing hockey rink to install new flooring material, arena style roof structure, bleachers, and various ADA compliance improvements.

Cost: $2,085,000
Status: A shortlist of Pre -Qualified Firms was approved by City Council on November 14, 2023.

Design Build Proposals have been reviewed and a Design Build team has been selected.

Negotiations are taking place with the best value proponent. Award of design build contract anticipated to take place at 6/11/24 City Council meeting. Design is anticipated to begin Q2 2024 and start of construction is estimated to begin Q1 of 2025.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
PARKS AND RECREATION PROJECTS (Continued)
Ronald Reagan Sports Park Skate Park, PW22-07
Description: Remove and replace the existing skate park and install state-of-the-art skate plaza elements Cost: $4,060,000
Status: Project is in the design stage. Final Design began in February 2024 and construction is anticipated to begin in Winter 2024/25.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024

LAND DEVELOPMENT OVERSIGHT PROJECTS
Arrive @ Rancho Highlands
Description: A 270-unit multi -family community built on 12.32 acres that includes 55 affordable units. The project is located adjacent to the Temecula Duck Pond approximately 775 feet southeast of Rancho California Road on the north side of Ynez Road.

Status: Grading and onsite storm drain permits were issued in October 2021. Grading and onsite storm drain construction has commenced. Overflow parking lot has been paved.

Heirloom Farms
Description: A Development Plan for a 321-unit single family residential community built on 27.86 acres consisting of detached homes and attached townhomes located on the southwest corner of Date Street and Ynez Road.

Includes the installation of a new Traffic Signal at the intersection of Ynez Rod and Waverly Lane/Temecula Center Drive.

Status: Rough grading permit has been issued in July 2021, the offsite and private onsite street and storm drain improvements permits were issued in October 2021 and the traffic signal permit was issued in September 2021. Precise grading is approved and in progress. Street Improvements in progress.

Las Haciendas Apartments
Description: A Development Plan to construct a 77-unit affordable housing project located at 28715 Las Haciendas Street in Uptown Temecula.

Status: Precise grading permit was issued in December 2021. Grading has commenced in January 2022 and is ongoing.

Mountain View
Description: Thirteen industrial buildings on Avenida Alvarado Status: Thirteen precise grading permits have been issued and construction has commenced. Improvements on Avenida Alvarado, along with street light installations is in process. Onsite storm drain installation has commenced.

City of Temecula

DEPARTMENT OF PUBLIC WORKS

PROJECT STATUS REPORT
May 28, 2024
LAND DEVELOPMENT OVERSIGHT PROJECTS (Continued)
Solana Assisted Living
Description: A 90,000 square foot, two-story, Senior Assisted Living Facility located on the southeast corner of the Margarita Road and Solana Way.

Status: A rough grading permit was issued in January 2022. Grading began on February 7, 2022. Street improvements and precise grading plans are near approval.

Sommers Bend
Description: Land Development has provided oversight of the following submittals for plan check and inspections: final maps, Community Sports Park, and recreation lots, precise grading; street and storm drain improvements; traffic signals; street lighting; and signing & striping.

Status: The mass grading permit was issued in September 2018. Sommers Bend has been paved with streetlights installed. The community sports park, Ranch at Sommers Bend, construction is complete and has been accepted at the February 8, 2022, Council Meeting. The Sommers Bend recreation center construction is complete. Installation of streets, storm drains and streetlights on east end of project is in process. Grading has been completed in the Density Core, currently installing sewer. Installation of Santa Gertrudis Creek Channel improvements northwest end of project is in process.

REQUESTS TO SPEAK

REQUEST TO SPEAK

CITY OF TEMECULA
E1989)
Date:

Public Comment: Non -Agenda Item: Agenda Item: ❑
Item Description or Item No
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk rp for to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record. G' f)60V_(00)11VAC-t(t?Name: ��J'� Phone Number:

Address
Email address:

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

REQUEST TO SPEAK

CITY OF TEMECULA
ivxv
Public Comment: Non -Agenda Item: �4 Agenda Item:

Item Description or Item No.

Date:19�O U(
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk rp for to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record.. _ i%
Name: w"" Phone Number.

Address
Email address:

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

REQUEST TO SPEAK
690_3_1_�7

CITY OF TEMECULA
Public Comment: Non -Agenda Item: Agenda Item: ❑
Item Description or Item No
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record.

Name: Phone Number: 6WAddress:

Email address:

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

REQUEST TO SPEAK

CITY OF TEMECULA
Date:

Public Comment: Non -Agenda Item: V Agenda Item: ❑
Item Description or Item No. ( _ .0
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk rp for to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the rec%rd. )
Name: Fl o-�0� 1/1 k < < 4 C' r'/ Phone Number:

Address:

Email address:

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

REQUEST TO SPEAK

CITY OF TEMECULA
2 X 2 cz y
Date:

Public Comment: Non -Agenda Item: V❑ Agenda Item: ❑
n
Item Description or Item No. -SA �) A
Request to Speak forms for Public Comments or items listed on the Consent Calendar may be submitted to the City Clerk prior to the City Council commencing the Public Comment period. For all Public Hearing or Council Business items on the Agenda, a Request to Speak form may be submitted to the City Clerk prior to the City Council addressing that item. Once the speaker is called to speak, please come forward to the podium and state your name for the record. ()
Name:I �'/ �� I ` (� /�"' " Phone Number:

Address: ��^�%
Email address:

If you are representing an organization or group, please give the name:

Please note that all information presented at a City Council meeting becomes public record.

All information provided is optional.

← All documents from this meeting