Cities Index.
Attachment 4 City Council Resolution

Thousand Oaks City Council
April 25, 2023

Document
Attachment 4 City Council Resolution
Meeting
April 25, 2023
Body
Thousand Oaks City Council
Pages
43
Original file
254 KB
Text extracted from the city's file for reading and search. Open the original on toaks.primegov.com. That file is the official record.

cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 1 ends

3 0
4 6
2 8
5 8
RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL OF THE

CITY OF THOUSAND OAKS DETERMINING THAT

THE PROJECT IS CATEGORICALLY EXEMPT

FROM CEQA AND APPROVING A GENERAL PLAN
AMENDMENT; DEVELOPMENT PERMIT;
DEVELOPMENT AGREEMENT; PROTECTED TREE

PERMIT FOR THE USE OF CERTAIN PROPERTY
WITHIN SAID CITY AT 88 LONG COURT (APN # 669-
0-202-260) [APPLICATIONS: 2021-70182-LU; 2022-
70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
(SJG LONG INVESTMENT)]
SECTION 1
WHEREAS, the applicant has filed with the City an application under the provisions of the City of Thousand Oaks Municipal Code requesting the following:

1. To find that the project qualifies for a Categorical Exemption under the California Environmental Quality Act (CEQA).

2. 2021-70182-LU: To conditionally assign the permanent allocation of 54 dwelling units of citywide Measure E capacity to the project site, which is located within the Thousand Oaks Boulevard Specific Plan (SP 20).

3. 2022-70269-DP: To allow the demolition of the existing commercial development and the construction of a 73-unit apartment project with a density bonus, including eight (8) affordable units and three (3) live/work units, consisting of one building, and a basement parking structure.

Applicant is requesting concessions through the State density bonus to allow the following:
a) A twenty-five (25%) to forty-six (46%) percent reduction of the 100 square foot minimum private open space area requirement for fifty- seven (57%) percent of units.
b) An increase from thirty-five (35%) percent maximum building coverage to fifty-four (54%) percent.

And waivers to allow:
a) A removal of the increased front yard setback required for below ground parking structures;
ATTACHMENT #4
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 2 ends

3 0
4 6
2 8
5 8
b) A removal of the increased rear yard setback required for below ground parking structures;
c) Trash enclosures within the parking structure.
d) A three (3’) foot reduction of the eight (8’) foot wide minimum sidewalk requirement on Long Court;

4. 2022-70535-PTP: To allow the removal of one (1) coast live oak (Quercus agrifolia) and three (3) California sycamore (Platanus racemosa) trees; and encroachment within the protected zones of twenty-four (24) trees.

5. 2022-70822-DAGR: To specify public and private benefits, party responsibilities, and other terms related to the proposal, including allocation of 54 units of citywide residential capacity to the project.

WHEREAS, on July 22, 2022, a Notice of Application was mailed to all property owners and occupants within a 500-foot radius of the subject property; and
WHEREAS, on July 22, 2022, a Notice of Application sign was posted on the subject property; and
WHEREAS, on March 13, 2023, Notice of Planning Commission Public Hearing was mailed to all property owners of record within a 500- foot radius of the subject site; and
WHEREAS, on March 13, 2023, Notice of Planning Commission Public Hearing was published in a newspaper of general circulation within the City of Thousand Oaks; and
WHEREAS, the Planning Commission, upon giving the required notice, did, on the 27 th day of March 2023, conduct a duly advertised public hearing as prescribed by law to consider said application; and
WHEREAS, at the March 27, 2023, Planning Commission public hearing, oral and written evidence, including a staff report, were presented and received, and comments and arguments were heard from all interested parties appearing in the matter; and
WHEREAS, the City Council, upon giving the required notice, did, on the 25th day of April 2023, conduct a duly-advertised public hearing as prescribed by law to consider said application; and
WHEREAS, at the April 25, 2023, City Council public hearing, oral and written evidence, including a staff report, were presented and received, and comments and arguments were heard from all interested parties appearing in the matter.
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 3 ends

3 0
4 6
2 8
5 8
SECTION 2
WHEREAS, the finding of the City Council in approval of said 2021-70182- LU is as follows:

1. The amendment is consistent with the goals and policies of the Thousand Oaks General Plan, since the proposed allocation of residential units under Measure E is consistent with the “Commercial/Residential” land use designation under the General Plan for the subject property.

2. The amendment is consistent with Measure E (Municipal Code Sec. 9-2.203 and Sec. 9-2.204) because it will not increase the citywide residential or commercial capacity above that which existed on November 5, 1996, when Measure E was adopted.

3. The project has been reviewed in conformance with the provisions of the California Environmental Quality Act (CEQA). The project was analyzed for conformance with the California Environmental Quality Act (CEQA). It has been determined that the proposed project is categorically exempt from the provisions of CEQA pursuant to Class 32 Section 15332 – Infill Development, which consists of an urban infill development project that is less than five (5) acres in size and meets the other requirements of CEQA Guidelines Section 15332 including that the project site has no value as habitat for endangered, rare or threatened species, there is existing street access, and is served by all required utilities and public services. The Community Development Department has further determined that none of the six exceptions to the use of a categorical exemption apply to this project (CEQA Guidelines Section 15300.2).

4. In addition, the General Plan Amendment is exempt under Section 15061(b)(3) of the CEQA Guidelines, as “…CEQA applies only to projects, which have the potential for causing a significant impact on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA.” In this case “the activity” is simply assigning available residential capacity to this specific parcel, which already allows residential uses per SP-20 and its General Plan Land Use designation, which is Commercial/ Residential. The act of assigning these units itself would not have an environmental impact as the General Plan overall anticipates residential capacity.
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 4 ends

3 0
4 6
2 8
5 8
SECTION 3
WHEREAS, the findings of the City Council in approval of said 2022-70269- DP are as follows:

1. 1. The design of the new 73-unit multi-family residential complex complies with all applicable laws, regulations, and policies, including Specific Plan No. 20, 101 Freeway Design Guidelines (Res. No. 1991-172), and Precise Plan of Design Guidelines (Res. No. 2006-108). The proposed buildings are comparable in massing and scale with other similar buildings within the vicinity of the subject property and incorporates enhanced architectural design, including vertical and horizontal design elements and decorative material finishes and colors.

2. The project is consistent with the Thousand Oaks General Plan and SP 20. a. The multi-family apartment project meets the purpose of SP 20 in that it creates a pedestrian-oriented and interactive environment with ground floor units which provide access directly to the sidewalks and walkways as well as publicly accessible open space including a small playground.
b. Along with the companion land use amendment to the General Plan to allocate 54 dwelling units of the citywide Measure E capacity to the subject property, the multifamily apartment project is consistent with all Elements of the Thousand Oaks General Plan.
c. The project is consistent with all applicable Elements of the Thousand Oaks General Plan, including the Land Use Element designation of “Commercial/Residential” and with the General Plan goal, “to provide the framework for a planned and unified community containing a balance of living, working, shopping, educational, civic, cultural and recreational facilities.”

3. The project complies with SP 20 which allows for a maximum height of three stories and a maximum average height of 50 feet as the building is a maximum of three stories above the basement parking structure and an average height of approximately 34 feet.

4. The project will be consistent with the housing element by providing rental housing in the form of six very low-income affordable units and two moderate-income affordable units.
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 5 ends

3 0
4 6
2 8
5 8

5. The project is consistent with the City’s Architectural Guidelines as conditioned in that the project design provides for vertical and horizontal building articulation and a variety of colors/materials.

6. The project is consistent with all applicable laws, regulations and policies, including the Thousand Oaks Municipal Code, with the approval of concessions including a reduction in the amount of required useable open space for individual apartment units and increase in the proportion of total structural lot coverage, as well as waiver requests for the front and rear yard basement parking structure setbacks, sidewalk width reduction, and trash facilities within the parking garage.

7. The project will not be detrimental to public health, safety, or general welfare because the project has been reviewed and recommended for approval by the Community Development Department, Public Works Department, Police Department, and the Ventura County Fire Department (VCFD), and in compliance with the California Environmental Quality Act (CEQA). With the incorporation of the conditions set forth by these departments and agencies, the project will not be detrimental to public health, safety, or general welfare.

8. The proposed multi-family residential development is compatible with the surrounding land uses in the vicinity because it is located within an urbanized setting with established infrastructure and nearby comparable uses.

9. The project was analyzed for conformance with the California Environmental Quality Act (CEQA). It has been determined that the proposed project is categorically exempt from the provisions of CEQA pursuant to Class 32 Section 15332 – Infill Development, which consists of an urban infill development project that is less than five (5) acres in size and meets the other requirements of CEQA Guidelines Section 15332 including that the project site has no value as habitat for endangered, rare or threatened species, there is existing street access, and is served by all required utilities and public services. The Community Development Department has further determined that none of the six exceptions to the use of a categorical exemption apply to this project (CEQA Guidelines Section 15300.2).
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 6 ends

3 0
4 6
2 8
5 8
SECTION 4
WHEREAS, the findings of the City Council in approval of said 2022-70535- PTP are as follows:

1. Approval is consistent with the intent of the Oak Tree Preservation and Protection Ordinance since the proposed removal of one (1) coast live oak (Quercus agrifolia) and three (3) California sycamore (Platanus racemosa) trees will be replaced in accordance with standards adopted by the Oak Tree Preservation and Protection Guidelines Resolution 2010-14.

2. The project is consistent with the Thousand Oaks General Plan, including the Conservation Element, in that conditions have been applied to the minimize impacts from encroachment within the protected zone of the twenty-two (22) protected oak trees and two (2) California sycamore trees.

With the inclusion of conditions, the proposed encroachment within the trees’ protected zone is not likely to result in a decline in the health of the trees.

3. Removal of the one (1) coast live oak and three (3) California sycamore trees as well as the encroachment within the protected zone of twenty-two (22) oak and two (2) sycamore trees is necessary to accommodate proposed improvements and grading activities associated with construction of the new multi-family residential building.

4. A City Tree Consultant inspected the affected trees and determined that the proposed encroachment will not be detrimental to the health of the subject oak and landmark trees. Appropriate project conditions are in place to safeguard the oak and landmark trees, including installation of fencing around the protected zones and on-site monitoring by the applicant’s consultant during all encroachment and pruning operations.

5. Each protected tree to be removed must be replaced with three (3) trees (two 24-inch and one 36-inch box-sized trees) of the same species. The three required replacement coast live oak trees and six of the required replacement sycamore trees are to be planted on-site per the proposed landscape plan. Any required replacement trees not able to be placed on- site would be mitigated with an in-lieu fee provided to the Conejo Open Space Conservation Fund used toward acquisition of open space.

6. With the inclusion of the recommended conditions, approval of this request will not be contrary to, or be in conflict with, the general purpose and intent of the Oak Tree Ordinance (Article 42 of Title 9 of the Municipal Code) and Oak Tree Preservation and Protection Guidelines, Resolution Number 2010-14, as well as the Landmark Tree Preservation and Protection Ordinance (Article 43 of Title 9 of the Municipal Code). cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 7 ends

3 0
4 6
2 8
5 8

7. The Protected Tree Permit request has been reviewed in conformance with the provisions of the California Environmental Quality Act. The project has been reviewed in conformance with the provisions of the California Environmental Quality Act (CEQA). The project was analyzed for conformance with the California Environmental Quality Act (CEQA). It has been determined that the proposed project is categorically exempt from the provisions of CEQA pursuant to Class 32 Section 15332 – Infill Development, which consists of an urban infill development project that is less than five (5) acres in size and meets the other requirements of CEQA Guidelines Section 15332 including that the project site has no value as habitat for endangered, rare or threatened species, there is existing street access, and is served by all required utilities and public services. The Community Development Department has further determined that none of the six exceptions to the use of a categorical exemption apply to this project (CEQA Guidelines Section 15300.2).

SECTION 5
WHEREAS, the findings of the City Council in approval of said 2022-70822- DAGR are as follows:

1. Approval is consistent with the objectives, policies, general land uses and programs specified in the General Plan and SP 20;

2. The Development Agreement is compatible with the uses authorized in, and the regulations prescribed for, the land use district in which the real property is located;

3. The Development Agreement is in conformity with public convenience, general welfare and good land use practice;

4. Approval will not be detrimental to the health, safety and general welfare; and;

5. Approval will not adversely affect the orderly development of property or the preservation of property values.

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Thousand Oaks that based on substantial evidence contained within the record, the analysis in the agenda report, and the findings of fact below, and recommendation of the Planning Commission, the City Council approves said 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR, subject to conformance with the conditions set forth and attached hereto and made a part hereof. Except as otherwise expressly indicated, said conditions shall be cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 8 ends

3 0
4 6
2 8
5 8
fully performed and completed, or at the City’s discretion, shall be secured by bank or cash deposit or other security satisfactory to the City Attorney before the use or occupancy of the property is commenced and before a Certificate of Occupancy is issued. The violation of any of the conditions of said permit shall be grounds for revocation by the City Council.

PASSED AND ADOPTED this 25th day of April, 2023, by the following vote:

Ayes:

Noes:

Absent:

Kevin McNamee, Mayor
City of Thousand Oaks, California
ATTEST/CERTIFY:
__________________________
Laura B. Maguire, City Clerk
Date Attested: ______________
APPROVED AS TO FORM:

Office of the City Attorney
___________________________________
Patrick J. Hehir, Chief Assistant City Attorney
APPROVED AS TO ADMINISTRATION:
___________________________________
Andrew P. Powers, City Manager
The presence of electronic signature certifies that the foregoing is a true and correct copy as approved by the City of Thousand Oaks City Council on the date cited above.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 9 ends

3 0
4 6
2 8
5 8
CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022- 70535-PTP; and 2022-70822-DAGR

COMMUNITY DEVELOPMENT DEPARTMENT

PLANNING DIVISION

1.Land and Application – The General Plan Amendment; Development Permit; Protected Tree Permit; and Development Agreement are adopted, granted or accepted for the land described in the application, any attachment thereto, and as shown on the submitted “Project Plan Set,” dated February 27, 2023, attachment to the Planning Commission staff report dated March 27, 2023.

2.Scope of Permit Approval – A General Plan Amendment to allocate 54 residential dwelling units of citywide Measure E residential capacity to the subject property within Thousand Oaks Boulevard Specific Plan (Specific Plan No. 20); a Development Agreement specifying development performance; a Development Permit allowing the demolition of the existing commercial development and the construction of a 73-unit apartment project with a density bonus, including eight (8) affordable units and three (3) live/work units, consisting of one building and a single-level semi- subterranean podium parking structure; a Protected Tree Permit to allow the removal of one (1) coast live oak (Quercus agrifolia) and three (3) California sycamore (Platanus racemosa) trees; and encroachment within the protected zones of twenty-four (24) trees, as shown on project plans labeled “Project Plan Set,” dated February 27, 2023, and the Tree Report (November 3, 2022) unless conditioned otherwise herein. The General Plan Amendment and all entitlements associated with this approval shall only be effective once the Development Agreement is in effect.

3.Approval Period – The above permits are granted for the period identified in Development Agreement 2022-70822-DAGR and contingent on compliance with the terms set forth therein.

4.Final Plans – Prior to the issuance of a building permit, final site, grading, floor, elevation and roof plans shall be submitted for the review and approval of the Community Development Department. Said plans shall incorporate any design change and other requirement as conditioned herein.

5.Project Changes/Modifications – Minor changes to 2022-70269-DP and 2022-70535-PTP may be approved by the Community Development Department, provided such changes achieve substantially the same results and the project is still in compliance with the Specific Plan, including all development standards, and, as applicable, the Thousand Oaks Municipal Code. Revised plans reflecting the minor changes and additional fees shall be required.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 10 ends

3 0
4 6
2 8
5 8

6.Condition Compliance – All development on the subject property shall be constructed and thereafter maintained in accordance with the conditions of this permit, and the Development Agreement.

7.Compliance with Applicable Laws, Rules, and Regulations – In accordance with the vested rights as provided for in the Government Code and the Development Agreement 2022-70822-DAGR, the applicant shall at all times comply with any and all local, city, county, state and federal laws, regulations and orders now in effect or which may hereafter be enacted pertaining to the approved modification or affecting the installation, operation or maintenance of the residential development.

8.Regulatory Agency Approval – The requirements of all applicable regulatory agencies shall be met, and approval obtained, prior to gas service release. Copies of all required licenses shall be submitted to the Community Development Department.

9.Payment of Fees – Approval is subject to the applicant paying all fees and assessments to the City of Thousand Oaks, as required by the Municipal Code, except as otherwise modified by, and in accordance with the Project conditions of approval or the Development Agreement 2022-70822-DAGR.

10.Dedications/Reservations and Public Improvements – With respect to dedications, reservations, construction of public improvements and fees as required by the project development conditions, the applicant is advised, pursuant to Government Code Section 66020, that the ninety (90) day protest period commences upon the date of approval of 2022-70822-DP by the City.

11.Preconstruction Meeting – Prior to issuance of a grading permit, the applicant shall coordinate with the Community Development and Public Works Departments including, a preconstruction meeting at the job site to review field conditions, project conditions, methods and procedures, individual and City department responsibilities associated with the project.

Members attending this meeting shall include but not be limited to City department representatives, City landscape consultant/arborist, owner or designated project coordinator, architect, project consultants, project landscape consultant general contractor and other representatives associated with the project. The meeting shall be arranged no sooner than one (1) week prior to commencement of work.

12.Construction Progress – Once permits have been issued to commence work on the improvements, it is the applicant’s/owner’s responsibility to diligently pursue completion per all conditions, requirements and as represented on the approved plans. Reasonable progress shall occur on a continual basis until completion to the satisfaction of the Community Development Director. Work shall not be discontinued for a period

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 11 ends

3 0
4 6
2 8
5 8
exceeding 30 days, without acceptable cause. The intent is to have the project completed in a timely fashion to prevent a potential blight from partially completed construction.

13.Occupancy – No final inspection or occupancy permit shall be granted until construction and landscaping are complete in accordance with the approved plans and the conditions required herein.

14.Hours of Construction – All grading and construction activities shall be limited to the hours of 7:00 a.m. to 7:00 p.m., Monday through Saturday with no construction activity permitted on Sunday. Construction workers and vehicles shall not be permitted to park on off-site properties or congregate onsite before and after the construction hours authorized herein. Likewise, warming of equipment engines shall not be permitted outside the permitted construction hours.

15.Approval Inclusion – The following shall apply:
•This approval, in its entirety as adopted, shall be included in the initial plan-check submittal that is submitted to the Building Division. The approval and conditions shall be copied directly onto plan sheets and included as part of the project plans throughout the plan-check process and shall be part of the project plans for which building permits are issued.
•All agreements, obligations, conditions, development standards, and use allowances contained in Specific Plan 20 and Development Agreement 2022-70822-DAGR shall apply to this approval.

16.Unauthorized Changes – The applicant acknowledges that the exterior treatment, location of structures and architectural features of the development are of special concern to, and regulated by, the City of Thousand Oaks, which has established criteria and standards concerning development within the City. Any substantial change, modification, or alteration to the architectural design, or in the exterior treatment of any building and structure, including building colors, materials, changes in walkways, doorway, window locations, or in the parking, landscaping and other related features, must first be approved by the City of Thousand Oaks prior to performing the work. Unauthorized change(s) or failure to comply with the conditions of this permit may require future corrective work and result in a City Code violation and appropriate action.

17.Indemnification – The applicant agrees to defend, indemnify and hold harmless the City, its agents, officials, and employees from any claim, action or proceeding against the City or its agents, officials or employees to attack, set aside, void or annul an approval of the City subject to, and to the extent set forth in, the Development Agreement 2022-70822-DAGR.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 12 ends

3 0
4 6
2 8
5 8
The City shall promptly notify the applicant of any claim, action or proceeding and the City shall cooperate fully in the defense.

18.Signed Acceptance of Conditions – A signed Acceptance of Conditions affidavit shall be executed by the applicant and property owner, or his duly authorized representative, and shall be returned to the Community Development Department prior to the issuance of a building permit.

19.Affordable Housing Agreement – The applicant shall submit to the City an affordable housing agreement for review and approval by the Community Development Department that provides for the on-going affordability of the project.

Approval of this residential project is subject to execution of an Affordable Housing Covenant entered into between the Applicant and City of Thousand Oaks. Said Affordable Housing covenant shall incorporate the following conditions and is subject to approval by the City Attorney and Community Development Director.

A. Affordable Housing Covenant shall be recorded prior to final building permit issuance. Covenant shall be recorded to provide notice to any future owners.

B. The Affordable Housing Covenant shall require eight (8) units as affordable units. Two (2) units will be preserved at the moderate- income level of 120% of the Ventura County median income and six (6) will be preserved at the very-low-income level of 50% of the Ventura County median income.

C. Applicant agrees to execute an Affordable Rental Housing Regulatory Agreement and Declaration of Restrictive Covenant with City that provides for the on-going affordability of these eight (8) restricted units for 70 years from the date the units initially become available for lease.

D. The City may extend affordable period if owner does not comply with Affordable Housing Covenant.

E. Affordable units should be comparable in exterior appearance and overall quality of construction to market-rate dwelling units in the same residential development. The design and appearance of the affordable units shall be compatible with the design of the market- rate units.

F. Affordable units should be dispersed throughout the development in a manner acceptable to the City.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 13 ends

3 0
4 6
2 8
5 8
G. The Affordable Housing Covenant shall be in compliance with the latest California State requirements.

The Affordable Agreement shall be reviewed and approved by the Community Development Department and City Attorney’s office prior to the issuance of a grading permit.

20.Mitigation Measure Compliance – All applicable mitigation measures contained in Appendix C of the Thousand Oaks Boulevard Specific Plan (SP 20, Amended August 2016) shall apply to this entitlement.

CULTURAL RESOURCES

21.Evaluation – In the event that potentially important cultural resources are found in the course of geologic testing or during construction, work shall immediately cease until a qualified archaeologist can provide an evaluation of the nature and significance of the resources and until the Community Development Department can review this information.

22.Native American Heritage Commission – If human bone is discovered during geologic testing or during construction, work shall immediately cease, and the procedures described in Section 7050.5 of the California Health and Safety Code shall be followed. Section 7050.5 requires notification of the coroner. If the coroner determines that the remains are those of a Native American, the applicant shall notify the Native American Heritage Commission by phone within 24 hours. Following notification of the Native American Heritage Commission, the procedures described in Section 5097.94 and Section 5097.98 of the California Public Resources Code shall be followed.

BIOLOGICAL RESOURCES

23.Nesting Birds – Any site preparation activity, including removal of vegetation, between February 1 and September 15 will require nesting bird surveys by a qualified biologist at least 5 days prior to initiation of activities.

Should active nests be identified, a buffer area no less than 150 feet (300 feet for raptors) shall be fenced off until it is determined by a qualified biologist that the nest is no longer active. A report discussing the results of nesting bird surveys shall be submitted to the Community Development Department prior to ANY vegetation removal on site.

RESIDENTIAL PLANNED DEVELOPMENT PERMIT 2022-70269-DP

SETBACKS, HEIGHTS, BUILDING MATERIALS, OPEN SPACE,

ARCHITECTURAL TREATMENT

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 14 ends

3 0
4 6
2 8
5 8

24.Direct Access from Unit Patios – All ground floor units on the first floor facing the southern parking lot must have direct access to the outside from the patio per plans, subject to approval by the Community Development Department.

25.Setback standards – All development standards shall be satisfied to include the following per the submitted plan:

Development Standards - Setbacks
Adjacent
Street/ Use Required Provided Third
Floor
Front
(West) Long Court
8’ sidewalk +
10’ landscaped yard+
avg. 10’ at third floor
11’ 8” (with 5’
sidewalk)
Waiver
Requested
Avg.
10’
Rear
(East) Moody Court
8’ sidewalk +
10’ yard +
avg. 10’ at third floor
10’ (with 8’
sidewalk)
Avg.
10’
Side
(North) Daycare/Vacant 4’ 54’ (at
daycare) N/A
Side
(South) Office 4’ 67’ 9” N/A

26.Architectural Building Design – The architectural design shall comply with the building plans as shown in the attachments labeled “Project Plan Set,” dated February 27, 2023, to the Planning Commission staff report dated March 27, 2023.

27.Exterior Building Colors/Materials – All exterior materials and colors depicted on the attachments labeled “Project Plan Set” dated February 27, 2023 to the Planning Commission staff report dated March 27, 2023, are approved in concept only. Prior to the issuance of a grading permit, a final color and materials sample board, including, but not limited to, specific materials and paint manufacturer colors, shall be submitted for the review and approval by the Community Development Department. The applicant shall indicate the type of finish on the revised plans and materials and colors sample board.

28.Building Wall Treatment – The building walls shall incorporate architectural treatment to create a visually interesting appearance as viewed from the surrounding properties and scenic corridors. The treatment shall include, but is not limited to, incorporating decorative finish materials, vertical and horizontal variation and decorative window trim. The design shall comply with the building elevation plans as shown in the exhibits labeled “Project Plan Set,” date stamped February 27, 2023.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 15 ends

3 0
4 6
2 8
5 8

29.Building Height – Average building height shall comply with the 50-foot maximum average height specified by Specific Plan 20. In this case, the plans dated February 27, 2023, show a maximum average height of 34 feet.

30.Downspouts – The downspouts on the exterior of the buildings, within public view, shall be concealed within the building walls subject to the review and approval of the Community Development Department.

31.Roof-Mounted Mechanical Equipment – All roof-mounted mechanical equipment, including air conditioning, roof fans and any similar equipment, shall be located within the mechanical equipment enclosures or obscured by roofing elements as depicted on “Project Plan Set,” date stamped February 27, 2023. Said equipment shall be screened from public view perspectives, including Thousand Oaks Boulevard, Moody Court, Long Court, and the 101 Freeway. In the event such equipment cannot be entirely screened from public view, the applicant shall work with the Community Development Department to provide alternative methods, including painting equipment and providing individual screens around specific equipment areas, to screen the equipment. Roof screening treatment shall be designed in a manner that is integrated with the building design. Prior to the issuance of a building permit, final detailed building section drawings and details including mechanical equipment manufacturer's catalogue cuts, brochures, specifications as well as roof equipment locations shall be submitted for the review and approval by the Community Development Department.

32.Surface-Mounted Mechanical Equipment – All surface-mounted mechanical equipment, including transformers, terminal boxes or meter cabinets, shall be screened by landscaping or decorative enclosure to match the materials and colors of the new building.

33.Certified As-Built Grading – Prior to issuance of a building permit, a rough grading completion certification on the City standard form shall be prepared and signed by the applicant’s Civil Engineer and submitted to the Public Works Department. Said certificate shall state that the graded pad design and pad elevations are consistent with the pad elevation and grading details shown on the grading plan, as shown in the grading plan/attachments labeled “Preliminary Grading Plan,” date stamped February 27, 2023, to the Planning Commission staff report dated March27, 2023.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 16 ends

3 0
4 6
2 8
5 8

34.Exporting/Importing Earth Materials – Any exporting or importing of earth material and debris shall be authorized by permit issued by the Public Works Department. The builder shall comply with an approved haul route to and from the project site and shall coordinate the hauling of this material with the Public Works and Community Development Departments to minimize traffic disruptions and disturbances to the project area. The exporting and importing of any earth materials to new sites within the jurisdiction of the City of Thousand Oaks shall be subject to the review and approval by the Planning Commission unless such sites have previously been approved for development with an active entitlement, and said grading is in accordance with Public Works Department approved plan for the project.

35.Backflow Device – Any proposed backflow device shall be screened from public view, subject to review and approval by the Community Development and Public Works Departments.

36.APCD Permit – The applicant shall obtain all necessary clearances from the Ventura County Air Pollution Control District (APCD) prior to beginning any construction activity.

37.Final Detailed Grading, Paving and Drainage Plan Submittal – Prior to issuance of a grading permit, a final detailed grading, paving and drainage plan demonstrating compliance with all imposed conditions of this Development Permit shall be submitted for review and approval by the Community Development and Public Works Departments.

38.City's Recycling Program – The project's owner shall participate in the City of Thousand Oaks recycling program, which collects cardboard, plastics, glass and mixed paper and shall attempt to use post-consumer building materials (recycled products) whenever possible in the construction of the project.

PARKING, ACCESS, AND DRIVEWAY

39.Required Parking – A minimum of 113 parking spaces shall be provided as shown on site within “Project Plan Set,” date stamped February 27, 2023.

The number of required parking spaces is based upon the parking requirements for multi-family residential, as set forth by SP 20. All parking spaces and driveway aisles shall be designed in accordance with Section

9.4-2404 of the Municipal Code. On-site Electric Vehicle charging parking spaces can be included in the required parking count of the project. Minor changes to the parking may be permitted so long as the project complies with the parking standards contained in the Specific Plan. Any minor change to parking or future development on the subject property shall be reviewed and approved by the Community Development Department. Any substantial change may require the filing of a modification application to be considered by the Planning Commission.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 17 ends

3 0
4 6
2 8
5 8

40.Compact Parking – Maximum permitted compact parking spaces shall not exceed twenty-five percent (25%) parking spaces based on the total parking requirements as indicated under Section 9-4.2404(d)(3). No overhang compact parking space shall be permitted within five feet (5-feet) of any vertical obstruction.

41.Parking Stall Dimensions – The dimensions and design of all parking stall shall be installed as required by the Thousand Oaks Municipal Code.

42.Driveway – The design of the driveway and transitions are subject to review and approval of Community Development and Public Works Departments.

43.On-Site Traffic Control and Calming – Prior to issuance of any Building Permit, the applicant shall submit a Traffic Control and Traffic Calming plan demonstrating measures within onsite drive aisles and circulation areas.

Measures shall include, but not limited to, signs, striping, and speed bumps.

Said measures shall be designed and shown on a signing and striping plan.

The location and type of device(s) shall be designed and installed to the satisfaction of the Community Development and Public Works Directors.

44.Parking Management Program – Prior to occupancy of the project, a Parking Management Program shall be designed and submitted to ensure that proper parking assignments for tenants, guests, and employees are established within the parking structure and designated exterior spaces, as well as address timing and procedures for moving activities and moving- related vehicles/vans for all residential, commercial tenants and live/work units. As part of the Parking Management Program, the applicant shall provide appropriate signage and develop an action plan to prevent parking from spilling off-site onto adjacent locations. Said program shall be subject to the review and approval by the Community Development, Public Works and Police Departments.

LANDSCAPING, FENCES, AND WALLS

45.Walls and Fencing – Fences and walls shall have a maximum height of six feet. Where a solid fence or wall is provided, it shall be designed with both sides articulated, and with similar or complementary materials and colors to those used on the existing or proposed buildings. Chain link fencing is prohibited. The gate for the transformer enclosure shall be solid to conceal the interior area from public view. Said gate shall be decorative material and is subject to review and approval by the Planning Division of the Community Development Department.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 18 ends

3 0
4 6
2 8
5 8

46.Landscape Design Compliance/Approval – All landscaping and irrigation improvements, including those in the Residential Landscaping License Area, shall be designed and installed in accordance with the City’s Guidelines and Standards for Landscape Planting and Irrigation Resolution No. 2007-116). All landscape plans shall demonstrate compliance with the State of California Model Water Efficiency Landscape Ordinance (MWELO).

Prior to the issuance of a grading permit, complete landscape and irrigation plans reflecting compliance with all imposed conditions of project entitlements shall be submitted under separate permit for review and approval. Said plans shall be subject to review and approval by the Community Development and Public Works Departments. The location of light fixtures shall be shown on the landscape plans to ensure no conflict occurs between placement of trees/shrubs and light fixtures and to avoid plant growth interference with the level of illumination.

47.Manufactured Slope Landscaping – In accordance with the City’s Grading Ordinance (TOMC Section 7-3.24), all manufactured slopes shall be landscaped with drought resistant native plants materials including tree clusters and ground cover and provided with a permanent irrigation system throughout. Landscaping and an irrigation system shall be installed six (6) months following the completion of grading for the project. Prior to the issuance of a grading permit, landscaping and irrigation plans shall be submitted under separate permit for review and approval by the Community Development and Public Works Departments.

48.Landscaping and Irrigation – All landscaping shall be designed using xeriscaping techniques, i.e. drought-tolerant low water-using plants. The use of lawn, grasses, and turf shall be minimized. Landscape irrigation systems shall likewise be designed using low output sprinklers and/or drip automatic timed controls. All landscaping and irrigation plans shall demonstrate compliance with the State of California Model Water Efficiency Landscape Ordinance (MWELO), with all applicable calculations provided on the cover sheet.

49.Landscape Planters – All landscape planters and fingers shall be planted with shrubs, trees and flowers subject to the review and approval of the Community Development Department.

50.Retaining Walls – All retaining walls shall be constructed of a decorative masonry material with a decorative cap or a concrete material to match the buildings subject to cut sheet detail designs submitted for the review and approval of the Planning Division. All retaining walls shall be limited to a maximum exposed height of six (6) feet and softened by landscaping.

Where such walls are exposed to public view, horizontal articulation of varying depths shall be provided to break up a linear wall appearance.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 19 ends

3 0
4 6
2 8
5 8

51.Construction/Security Fencing – Prior to the issuance of a grading/building permit, the applicant shall install a temporary five (5) foot high chain-link fence within the limits of the proposed development area.

Said fencing shall be provided for purposes of maintaining security, as well as containing trash and debris on-site. The fence shall remain in place during all phases of construction and shall be maintained until no longer needed for trash and debris control as determined by the Community Development Department. The applicant shall be responsible for pick-up of trash and debris on a weekly basis during building construction operations.

LIGHTING

52.Restriction of Light Poles – Light poles are prohibited at the ends of landscape fingers.

53.Parking Lot Lighting – All parking lot illumination shall comply with the City’s parking lot standards as identified in the City’s Security Ordinance utilizing decorative light fixtures with heights not to exceed fourteen (14) feet in height. Special design features within the light fixture, including lens and shielding devices, shall be provided to avoid an over intensity of illumination and to direct illumination in a downward direction. All lighting utilized shall be located within landscaped areas, at least three (3) feet from parking surfaces. All pedestals shall be painted the same color which shall complement one of the main wall colors of the buildings, subject to the review and approval of the Community Development Department. Where pedestrian walkways occur, the height of these fixtures may be reduced in proportion to human scale. Use of bollard type lighting for safety adjacent to driveways is also encouraged for pedestrian traffic circulation. All lighting attached to these features shall be decorative, oriented in a downward direction, and downward shielded. Prior to issuance of a parking lot electrical permit, a photometric analysis and light fixture catalogue cuts and specifications shall be submitted to the Planning and Building Divisions for review and approval.

54.Decorative Lighting Above Public Area – Low intensity lighting may be provided above and across the public exterior space.

55.Lighting on Roof Top Terrace – No roof illumination shall be permitted except as otherwise needed to comply with building security requirements.

The design and location of such fixtures shall be subject to review and approval of the Community Development Department prior to the issuance of a building permit. The rooftop areas shall be illuminated with wall sconces and shall not extend beyond the height of the parapet. Additionally, the rooftop areas may be illuminated subject to the following:
•Cut-off shields shall be installed/maintained on each side of the light fixtures visible from the parapet wall perspectives;

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 20 ends

3 0
4 6
2 8
5 8
•Motion sensors shall be installed to limit operation of the lighting to times activity is detected on the rooftop areas. Lighting shall be off when no activity is on the rooftop; and
•Stand-alone light standards shall not exceed 10’-0” in height.

56.Wall Lighting – Wall-lighting fixtures at building entrance doors, loading areas, and outdoor areas within public view area are permitted. Lighting may be provided by decorative downward shielded light fixtures, recessed in a downward direction from projecting canopies, recessed doorways, and window openings. Decorative architectural light fixtures shall be installed on the building walls. Light fixture cut sheets shall be submitted for review and approval by the Planning Division. Architecturally designed fixed pendant and bracket light fixtures are permitted. The use of such lighting shall be designed to create a uniform illumination generally in a downward direction and not create illumination hot spots on adjacent surfaces.

57.On-building Light Fixtures – The applicant shall submit catalogue cut sheets and specifications for any new exterior light fixtures to the Community Development Department for review and approval prior to installation.

58.Light Source – Use of bright white, high intensity LED or metal halide lighting is prohibited.

SIGNS

59.All Signs – All site and building signage shall comply with Specific Plan 20 and shall be designed to meet the Precise Plan of Design Guidelines (Res.

No. 2006-108), and as specified in the Thousand Oaks Municipal Code. The design, color and location of all site and building signs as well as address numbers shall be processed under separate permits. A sign permit application shall be submitted to the Community Development Department for review and approval.
2022-70535-PTP CONDITIONS

60.Scope of Permit Approval – The Protected Tree Permit is granted to allow the following:
•Removal of one (1) coast live oak (Quercus agrifolia) and three (3) California sycamore (Platanus racemosa) trees;
•Encroachment into the protected zones of twenty-two (22) Oak trees; and
•Encroachment into the protected zone of two (2) California sycamore trees.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 21 ends

3 0
4 6
2 8
5 8

61.Oak Tree Replacement – The applicant shall provide two 24-inch box and one 36-inch oak replacement tree for each Coast Live Oak (Quercus agrifolia) tree removed. Total of three replacement trees are required.

62.Landmark Tree Replacement – Each landmark tree that is removed shall be replaced with two 24-inch box sycamore trees and one 36-inch oak sycamore tree. For those trees unable to be located on site the applicant shall provide the dollar value per the formula below to compensate for the removal of the tree as a cash donation to Conejo Open Space Conservation Fund to be used toward open space land acquisition.

Description Amount
24” Box Sycamore Tree
Provide healthy nursery stock tree with installation
(fertilizer tables, tree stakes/ties, bubbler equipment) $ 575
Irrigation Lateral (75LF x $3) and Valve ($50) $ 316
Water (5 years) 30 gallons a week $ 12
Maintenance Warranty (5 Years) $ 575
Total $ 1,478
24” Box Sycamore Tree
Provide healthy nursery stock tree with installation
(fertilizer tables, tree stakes/ties, bubbler equipment) $ 575
Irrigation Lateral (75LF x $3) and Valve ($50) $ 316
Water (5 years) 30 gallons a week $ 12
Maintenance Warranty (5 Years) $ 575
Total $ 1,478
36’” Box Sycamore Tree
Provide healthy nursery stock tree with installation
(fertilizer tables, tree stakes/ties, bubbler equipment) $ 863
Irrigation Lateral (75LF x $3) and Valve ($50) $ 316
Water (5 years) 30 gallons a week $ 12
Maintenance Warranty (5 Years) $ 863
Total $ 2,054
Grand Total x Per to be removed $ 5,010
*Prepared 3/2023 – Total price to increase three percent (3%) annually

63.Mitigation Oak and Landmark Tree Location Map – Prior to issuance of a grading permit, the applicant shall submit a mitigation tree location map demonstrating the location of the replacement trees.

64.Oak Tree Removal and Encroachment – The removal and encroachment into the protected zones of oak trees for the construction of the new multi- family residential building, utilities, and associated development is hereby approved.

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 22 ends

3 0
4 6
2 8
5 8

65.Preservation of Existing Oak and Landmark Trees – The preservation of two (2) coast live oak trees, identified as trees numbered 19 and 2 in the Oak & Landmark Tree Report, is authorized under this permit. These oak and landmark trees will require pruning to accommodate the construction activities and for the overall long-term health of the trees which is also approved under this permit. Appropriate work methods and monitoring are required as described in the Protected Tree Report dated November 3, 2022, prepared by Richard Ibarra, I.S.L.A.

66.Mitigation Tree Maintenance and Monitoring – The required mitigation trees shall be monitored for a period of five (5) years. An irrigation system designed for “dryscape” planting shall be installed for successful oak establishment, which generally involves a drip-system irrigation for managing water distribution near the oak trees and does not include watering during summer months when natural rainfall would not be abundant. Maintenance shall include leaving the leaf-litter build-up or a 3- inch layer of mulch under the canopies of the oak trees to promote healthy tree growth and root development.

Monitoring shall be performed by the applicant’s oak tree consultant and monitoring shall entail visits at quarterly intervals for the first two (2) years and biannually for the next three (3) years. The applicant’s oak tree consultant shall submit to the Community Development Department a semi- annual report regarding the conditions of the oak trees.

67.Oak Tree and Landmark Tree Preservation and Protection Guidelines Compliance – Unless otherwise approved by the Community Development Department, all construction activities to or near an oak or landmark tree shall conform and abide by the City of Thousand Oaks, Preservation and Protection requirements as specified in Articles 42 and 43 of Chapter 4 of Title 9 of the Thousand Oaks Municipal Code.

68.Oak Tree and Landmark Tree Protection – Every effort shall be made to protect all oak and landmark trees in near proximity affected by the proposed improvements.

69.Site Monitoring – Unless otherwise modified herein, all authorized pruning and encroachment activities shall be conducted in accordance with the conditions contained herein. All work shall be monitored by the applicant’s oak tree consultant and follow the recommendations contained in the applicant’s oak tree report labeled Oak & Landmark Tree Report dated November 3, 2022, prepared by Richard Ibarra, I.S.L.A.

70.Required Temporary Fencing – Prior to commencing construction, a five- foot (5’) high chain-link fence shall be installed and maintained around the protected zone, or other location as approved by the Community

COMMUNITY DEVELOPMENT DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 23 ends

3 0
4 6
2 8
5 8
Development Department, of all onsite and offsite oak trees and landmark trees. Installation of said fence shall be reviewed and approved by the Planning Division of the Community Development Department. It shall be the responsibility of the applicant to maintain all protective fencing in a good condition throughout the development period. The fence shall be removed upon completion of construction and upon authorization from the Community Development Department, Planning Division.

71.Root Preservation – If “saved roots” must stay exposed for longer than one day then they shall be wrapped in burlap (or similar) and kept moist. During excavation for construction improvements, if an oak tree root over two inches (2") in diameter is encountered, the Planning Division of the Community Development Department shall be immediately contacted to conduct a field inspection to determine if it is appropriate to cut the root(s) or whether the improvements need to be redesigned and/or relocated to avoid root damage to ensure preservation of the trees.

72.Excavation in Protected Zones – Unless otherwise waived by the Community Development Director, all excavation and construction activity within the protected zone of the existing oak and landmark trees shall be performed with the use of hand tools only, in accordance with the Oak Tree Preservation and Protection Guidelines Resolution, No. 2010-14, and observed in progress by the applicant’s oak tree consultant.

73.Herbicides – No herbicides shall be used within one hundred feet (100') of the dripline of any oak and landmark tree.

74.Storage of Materials – No storage of materials is permitted within the protected zones of any oak tree.

75.Irrigation/Lighting – No spray irrigation or lighting system shall be installed within the protected zone of any oak tree except as otherwise authorized by the Community Development Department.

76.Billing by City Oak Tree Consultant – The applicant shall be billed on a real time basis for any work performed by the City’s oak tree consultant in conjunction with this oak tree permit.

77.Written Certification – The applicant’s oak tree consultant shall certify in writing that all conditions of this Oak Tree Permit have been met and that protective measures, to ensure the preservation of the subject oak trees, have been properly implemented. A final inspection by the City’s Oak Tree Consultant, paid for by the applicant, shall be performed upon receipt of certification and prior to final inspection for building occupancy.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 24 ends

3 0
4 6
2 8
5 8

PUBLIC WORKS DEPARTMENT

GENERAL

78.Plan Format – All plans submitted to the Public Works Department shall be formatted to 24 inch by 36-inch sheet size, using city standard title block, and as-built/record plans shall be submitted as part of the closure and acceptance of the project.

79.Standard Plates – The City of Thousand Oaks Public Works Road Design and Construction Standards and Standard Plates, adopted May 15, 2018, in Resolution No. 2018-024 shall be used as the principal criteria for the design of development plans. It shall be the responsibility of the applicant to maintain a copy of the latest edition of said Plates available to all parties utilizing said Plates for construction purposes. The Standards establish uniform criteria, polices, standard and procedures for the design and construction of City roads, drainage facilities and appurtenances. The design engineer shall review the methods and procedures contained in the Road Standards, where not considered applicable, the design engineer shall request an exception from these standards in writing to be approved by the City Engineer. Said Road Standards are available for download at www.toaks.org/roadstandards.

80.Updating of Existing Improvement Drawings – All existing improvement drawings in the Department’s possession for water and wastewater which are affected by the subject project will be updated by the City to reflect the new improvements associated with this project. This work shall be considered as part of the project final process, and subject to a change order fee.

81.Base Topography Map – The grading plan for this project must be prepared using topography which has been plotted by photogrammetric methods or survey data compiled no longer than two years prior to the date of submittal of the grading plan, and must be on current City datum. The name of the firm which prepared the topography and the date(s) on which the data was compiled or obtained must be shown on the plan. Topography must be presented in 1” = 40’ or larger (closer) scale and must extend a minimum of 100 feet outside the limits of the property proposed for development. Any deviation from this condition must be approved by the City Engineer.

82.Title Report – A copy of the applicant’s preliminary title report for the subject property, dated within 1 year of the entitlement application, shall be submitted to the Public Works Department for review prior to grading plancheck or the issuance of any Building or Grading Permits.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 25 ends

3 0
4 6
2 8
5 8

83.Inspection Hours – The applicant is advised that City Hall is closed on alternating Fridays, and as such, inspection services are not available on those particular dates. The applicant shall schedule any and all grading, stormwater, encroachment, paving and utility work requiring City inspection accordingly. A schedule of City Hall hours may be obtained from City Hall or at the City’s website www.toaks.org.

84.Survey Monuments – The Applicant shall be fully responsible for the preservation of all survey monuments to the satisfaction of the City Engineer. Prior to the start of construction and prior to the disturbance or destruction of any existing survey monument, all monuments shall be located and referenced with minimum of four (4) ties by the Applicant’s Land Surveyor. A corner record or record of survey shall be filed with and approved by the County Surveyor showing monuments that will be disturbed or destroyed, along with the reference monuments or marks and bearings or azimuth and distances to the location of the monument to be disturbed or destroyed. Documentation shall be provided to the City that the surveying has been completed.

WATER AND WASTEWATER

85.Water Service – In order to obtain water service, the applicant shall pay for the Cost of the Water Meter Deposit plus the City’s Water Plant Investment Fee, at the rates in effect at the time of payment, prior to issuance of a building permit. Additional fees for special facilities zones and fire flow surcharges may also apply. The applicant shall also pay the established change order fee for updating the plans for this new lateral.

86.Water Mainline Extension – As necessary for the project and to the satisfaction of the City Engineer, the Applicant shall design and construct an 8-inch watermain between the existing 8-inch watermains in Long Court and Moody Court and shall be located in the proposed driveway at the south end of the project. A 15-foot easement shall be dedicated to the City of Thousand Oaks for waterline maintenance purposes.

87.Location of Water Meter Boxes - Water meter boxes may not be located within driveways. It is the responsibility of the applicant and his engineer to properly coordinate and locate all water service lateral locations such that there is a single, unbroken/unrepaired service line between the main in the street and the meter box to each residence or building. In the event the configuration of the proposed house or building is revised and the meter box is then situated in a driveway, the applicant shall abandon the existing service by excavating the service at the main, closing the corporation stop, severing the service lateral approximately 12 inches beyond the corporation stop, folding and crimping this remaining portion of the service lateral and PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 26 ends

3 0
4 6
2 8
5 8
soldering the crimped pipe together. The remainder of the lateral may be abandoned in place, but the meter box must be removed and the area returned to a condition acceptable to the water purveyor. If service laterals are relocated, the applicant’s engineer shall process a change order and pay any applicable charges for said change order.

88.Fire-Flow Verification - The applicant shall pay the Department a fee for calculation and verification of the existing water system to deliver required fire flows. In the event the fire flow, as determined by the Ventura County Fire Protection District, cannot be met utilizing the existing system, the applicant shall design and install new water main(s) of sufficient size and length, as determined by the Department, to provide said fire flow. A completed copy of the above-mentioned fire flow calculation must be provided to the Department before, or at the same time as, the submittal of the first plan check for the water system. Plans will not be checked or processed unless these calculations, along with a copy of the plan showing locations for proposed fire hydrants approved by the Fire Department, are submitted.

89.Fire Hydrant Upgrade - Applicant/Owner shall coordinate replacement of the existing fire hydrant located on Long Court near the proposed southerly driveway of the project. The existing 2½"x 4" two-way hydrant shall be replaced with a 2½"x 2½"x 4" 3-way hydrant at no cost to the water purveyor.

90.Concrete Pads Around Fire Hydrants - Regardless of whether a fire hydrant is located within the parkway between the curb and sidewalk (where detached sidewalks are required), or behind the sidewalk (where monolithic sidewalks are required), or within commercial areas, the applicant shall install a 4-inch (minimum) thickness concrete pad around each fire hydrant which extends a minimum of 18 inches beyond the barrel of the fire hydrant in all directions. Where detached sidewalks are installed, the pad shall be rectangular, extend from the back of the curb to the sidewalk and be 48 inches wide. A detail for said concrete pad shall be shown on all water plans for all water purveyors within the City of Thousand Oaks. The hydrant and concrete pad must be located within a specific easement, right-of-way, or public service easement shown on the tract map or dedicated by separate instrument dedicated to or usable by the respective water purveyor and the Ventura County Fire Protection District, or by other means acceptable to the Public Works Department.

91.Separate Irrigation Meter - This project shall require a fully separate water meter for irrigation and landscaping. Said irrigation meter will require all water permit fees to be paid, each service lateral and meter box installed and approved by the City Public Works Inspector, and the appropriate backflow device(s) installed, tested and certified (by an approved PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 27 ends

3 0
4 6
2 8
5 8
independent testing firm hired by the applicant) prior to the installation of the irrigation meters by the Department. The City may lock off the angle meter stop at the meter until the applicant has accomplished all of the above. Any taking of irrigation water without being metered through a water meter is a violation of the Municipal Code Section 10-2.514, punishable in fines up to $1,000 per day for each day of illegal taking.

92.Cross Connection Device - The applicant shall design and construct new backflow connection devices for the project’s irrigation water as well as fire sprinkler systems. Prior to the issuance of clearance for occupancy by the Department, all cross-connection control devices must be inspected and approved by the Cross Connection Control Specialist of the County of Ventura, telephone 805.654.2436 (MC 10-2.600). Full right of access and entry to the cross-connection device shall be granted to the Public Works Department.

93.Usefulness of Existing Water Laterals – Where there are existing water laterals serving the subject property and it is the desire of the applicant to reuse these laterals as part of the proposed project, the applicant must demonstrate to the satisfaction of the Department that the lateral(s) are in acceptable condition (no broken pipe, no root intrusion, etc.). These laterals must be made of copper; all poly services must be abandoned at the main under Department inspection and the meter boxes removed.

94.Procedure for Determination of Wastewater Fees - Prior to issuance of a building permit for this project, applicant shall submit a plumbing plan and a listing of proposed fixture units for the subject project to the Public Works Department for determination of a "preliminary" wastewater connection fee estimate. The plan and listing will be reviewed for apparent correctness only and the applicant shall pay the wastewater connection fee based on this "preliminary" estimate at the time a building permit is issued. The final fee amount to be paid by the applicant will be based on the actual numbers and types of plumbing fixture units installed as determined by City staff from a field count made of the project building(s) before certificate of occupancy is granted. Any difference between the actual/field verified fixture unit count and the total amount paid will be reimbursed to the applicant. If additional connection fees are due, these shall be paid by the applicant to the City upon request. Any existing fixture units for which fees have been previously paid on the parcel will act as a credit against the amount to be paid.

95.Usefulness of Existing Wastewater Laterals – Where there is an existing wastewater lateral(s) serving the subject property and it is the desire of the applicant to reuse these laterals as part of the proposed project, the applicant must demonstrate to the satisfaction of the Department that the lateral(s) are in acceptable condition (no broken pipe, no root intrusion, etc.). This can best be done by utilization of a television video from a point PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 28 ends

3 0
4 6
2 8
5 8
on the subject property to the main, or by excavating the lateral at the property line and making a visual inspection of the lateral. Other methods may be utilized but are subject to Department approval. If the lateral is acceptable to the Department, it may be reused; where it is not acceptable, a replacement lateral must be constructed or the existing lateral renovated (such as by use of pipe bursting technology). Laterals that are not appropriate for re-use must be abandoned at the main under Department inspection.

DEVELOPMENT ENGINEERING

96.Encroachment Permit - Where any construction occurs within public right- of-way, an encroachment permit shall be obtained, plan check and inspection fees paid, an approved traffic control submitted, and bond/security posted (if required) prior to initiating construction of any improvements.

97.Annexation to Lighting and Landscape District - In order to mitigate the impacts of this project and to have this project pay its fair share of maintenance costs for existing and future street lighting and landscape improvements that provide a benefit to the property, the applicant is hereby notified, consents to and agrees that the real property subject to this entitlement will be annexed into the City’s Lighting and Landscape Assessment District No. 79-2 at the next annual renewal of the District (typically June of each year). Said annexation will occur only if the City has given final approval to this entitlement. Prior to recording the final map or the issuance of any subsequent City permit needed for this project, whichever event occurs first, the applicant shall sign an annexation pre- submittal form, as provided by the City, agreeing to the unconditional annexation of the real property to said District. Applicant shall also post with the City a cash deposit or other security, as approved by the City, that could equal up to 2 years of maintenance costs for the property, based on City’s estimate of all expenses associated with the improvements for the period City deems appropriate, in order to guarantee funding for maintenance by City of lighting and landscape improvements that provide a benefit to the property. Said deposit or security shall remain in a separate City fund until such time as the property is annexed into said District. Until said annexation is complete, City shall draw on a yearly basis those amounts necessary for maintenance of said improvements. The balance of funds remaining at the time of annexation, not including any accrued interest, shall be refunded to the applicant, If annexation is not accomplished, said funds shall be used at City’s discretion to pay for maintenance of said improvements. Upon receipt of ballot(s) transmitted by the City in accordance with annexation proceedings, the applicant shall not oppose the assessment or the assessment formula for the subject property (as calculated in accordance with Article XIIID of the California PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 29 ends

3 0
4 6
2 8
5 8
Constitution), said ballot(s) shall be signed and returned to the City prior to the scheduled public hearing, per the instructions outlined on the ballot(s).

An annual assessment may be placed on the tax rolls by the City. The applicant, and/or applicant’s successor in interest, heirs or assigns shall be responsible to pay all applicable charges for annexation of said property to said District.

98.Permission for Offsite Construction - Prior to the issuance of a grading permit, written permission for all proposed offsite construction along with any required easements from the owners of the affected property shall be submitted to the City Engineer.

99.Hauling of Imported or Exported Materials - In the event this project will require either the importing or exporting of earth to or from the project site, prior to issuance of a grading permit the applicant shall submit a written plan to the Department for review and approval. Said plan shall detail the quantity of earth to be imported or exported, the location from which or to which the earth will be removed or taken, the proposed haul routes to be used, the size and numbers of the trucks to be used, the proposed hours of operation (times of day, days of the week, and estimated number of days), the estimated number of round trip truck movements, the proposed methods to be utilized to keep the haul route clear of any dirt dropped along the route, and any other information as may be required by the Department. 100.Grading Permit and Soils Certification - The applicant shall prepare and submit final grading plans, improvement plans, erosion control plans, BMP improvement plans, geotechnical soils reports, supporting hydrology and hydraulic calculation reports, title report, and other items as required by the City Engineer in order to obtain a grading permit in accordance with the requirements of the City’s Grading Ordinance. Applicant shall also prepare and submit detailed erosion control plans for both phases of land development; the pre-grading / site stabilization phase, as well as the post grading / building construction phase. The grading and improvement plans submitted to the City for plancheck shall at a minimum indicate all topography, proposed improvements, drainage features, water/wastewater connections and laterals, existing easements, interface with adjacent properties, storm drain and drainage systems, and street improvements.

All submittals shall include the completed public and private improvement cost estimate worksheets, the required plancheck and inspection fees, and the posting of the required grading bond prior to the start of any construction. After the grading is complete, the applicant shall submit a building pad compaction report and a rough grading certificate from the soils engineer prior to issuance of a building permit. Grading bonds shall be exonerated after satisfactory completion of the project punchlist items, which are generated after the applicant’s engineer provides a submittal of the final Record (as-built) Drawings.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 30 ends

3 0
4 6
2 8
5 8
101.On-site Run-off - On-site storm water shall be intercepted within the project boundaries in approved pick-up structures, treated and retained and/or conveyed to the nearest public street or existing storm drain system to the maximum extent practicable, as approved by the City Engineer (M.C. 7-3.09 and 7-3.21).
102.On-Site Drainage Design - Project design shall use the City of Thousand Oaks “Master Plan of Drainage” (2007) for the purpose of establishing on- site storm flows. The CFS-per-acre unit discharge in the Master Plan shall be used when preparing the Q10 (developed) discharge flows and for the detention calculations up through Q100.
103.On-Site Drainage - Project design and engineering plans shall show drainage flows to street and/or yard drains and elevations. 104.Drainage Study - The applicant’s engineer shall prepare a hydraulic/ hydrology analysis for the project. The study shall include, but is not limited to addressing offsite tributary flows, retention/detention, inlet hydraulics and storm drains and appurtenances intended to convey and treat project storm discharges. The focus of the study is to ensure the existing conveyances possess sufficient capacity to pass the Q10 (developed) and to demonstrate that no new flooding will occur adjacent to or upon the property during a Q100 event as a result of development. The study shall be subject to the review and approval of the City Engineer prior to grading permit issuance. 105.On-site Ribbon Gutters - The City prohibits the use of ribbon gutters and encourages the use of graded parking lots with perimeter curb and gutter to convey flow away from pedestrian pathways. Parking lot and drive drainage shall conform to this standard. The use of ribbon gutters will only be considered under special circumstances as determined by the Public Works and Community Development Directors (MC 9-4.2405).
106.Parking Structure Drainage – The City prohibits the discharge of pressure-washing effluent, antifreeze and motor oils into either the wastewater system or storm drain system. Inasmuch as these are the anticipated discharges from the interior of the parking structure, the applicant shall incorporate a blind sump containment area within the parking structure designed to capture and store such discharges. Provisions shall be provided for periodic pump-out of the blind sump via tanker truck with disposal in conformance with all local, state and federal regulations. The roof and other surfaces of the parking structure directly exposed to rainfall may be drained and discharged in accordance with NPDES design parameters for a normal, rainfall-exposed surface parking lot.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 31 ends

3 0
4 6
2 8
5 8
107.Building Pad Protection - The project engineer must provide analysis to demonstrate building pad protection from Q100 flows. On-site discharges (including roofs, etc) shall be detained behind a wall, graded barriers or curb, and metered through a weir or other controlling device, constraining discharge to the Q10 developed condition for the tributary area. Applicants’ engineer must prepare calculations to support this design. Said calculations must be approved by the City Engineer (M.C. 4-7.01).
108.Detention of Onsite Storm Flows - The applicant’s engineer shall prepare a hydraulic/hydrology analysis for the site and design onsite catch basin(s) and conveyances which will pass only the Q10 (developed) flows into the public storm drain system. All flows in excess of Q10 (developed) up to and including Q100 (developed) must be detained on-site. A simplified detention method is available for this site.
109.Existing Improvements - Existing improvements adjacent to the property, including but not limited to sidewalks and curb & gutter which are broken or uneven shall conform to City and ADA standards, and if deemed necessary by the City Engineer, shall be repaired or replaced.
110.Sidewalk Construction – The existing five-foot sidewalk on Moody Court shall be removed and replaced with an eight-foot-wide sidewalk per City Standard Plate 8.3. Additional right-of-way or easement shall be dedicated to the City to include the additional sidewalk width on Long Court. 111.Driveway Construction - The proposed driveway shall be constructed per Plate No. 6-1 and 6-4 of the Road Standards. The sidewalk must conform to the cross section as shown on Plate 6-4 and the applicant must grant an additional easement to the City covering the entire length of the sidewalk across the driveway. An encroachment permit shall be obtained, plan check and inspection fees paid, and security posted (if required) prior to initiating construction of said driveway improvements.
112.On-site Improvement / Paving Permit – The applicant shall submit for and obtain an on-site paving and improvement permit. An approved pavement section from the registered soils engineer of record shall accompany the permit application, along with payment of plan check and inspection fees, prior to initiating the construction of on-site parking, paving, and/or drainage improvements (M.C. 9-4.2405).

NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
113.NPDES Permit Compliance – NPDES Permit Compliance - Development shall be undertaken in accordance with conditions and requirements of the Ventura Countywide Stormwater Quality Management Program, National Pollutant Discharge Elimination System (NPDES) Permit No. CAS004002.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 32 ends

3 0
4 6
2 8
5 8
The project shall employ NPDES best management practices in accordance with the latest applicable version of the Countywide Stormwater Program “Technical Guidance Manual” and the California Stormwater Quality Association (CASQA) “BMP Handbooks” and/or other approved reference documents cited in Permit No. CAS004002 (M.C. 7-8.302). 114.BMP Sizing Requirements – Prior to issuance of a grading/paving permit, the project’s engineer shall prepare analyses to demonstrate that the proposed Best Management Practices (BMP’s) for stormwater treatment will mitigate pollutants of concern. The analyses shall include calculations demonstrating that the selected BMP’s must satisfy one of the following sizing criteria:

Treat the storm flow equivalent to ten percent (10%) of the 50-year peak flow; or
Treat the volume of annual runoff (based upon the unit storage water quality volume) to achieve 80 percent or more volume treatment by the method recommended in the “California Stormwater Best Management Practices Handbook – Industrial / Commercial (1993)” and the “Ventura Countywide Stormwater Quality Management Program Technical Guidance Manual for Stormwater Quality Control Measures (2002).”
115.Landscaped Areas / Roof Drains - Landscaped areas shall be designed with efficient irrigation to reduce runoff and promote surface filtration and minimize the use of fertilizers and pesticides which can contribute to urban runoff pollution. Unless otherwise recommended in the soils report, on-site stormwater discharges (including roof drains if applicable) shall be directed toward landscaped areas. Applicant may employ pervious landscaping design, rainfall capture pocket-planters, and other L.I.D. techniques and measures to the maximum extent practicable.
116.Deed Restriction Regarding Best Management Practices (BMPs) – Prior to issuance of occupancy, the applicant/owner shall record a Stormwater Covenant and Deed Restriction, requiring all property owners and their successors in interest to assume all duties and responsibilities for ongoing maintenance of all onsite permanent stormwater BMP’s, including, but not limited to, maintenance of all Best Management Practice and any and all equipment which is required for implementation of Best Management Practices. Contained within the Covenant and Deed Restriction must be a description of the BMP’s that are being provided as part of the project, a description of the inspection and maintenance requirements and procedures, and a site map indicating the location of the BMP’s to be maintained. The draft language and contents included in the Covenant and Deed Restriction shall be submitted to the City Attorney’s Office and Public PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 33 ends

3 0
4 6
2 8
5 8
Works Department for review and approval prior to issuance of building/ paving/grading permits (MC 7-8.401(c)).
117.Stormwater Pollution Prevention Plan and Notice of Intent (SWPPP) – Prior to the issuance of any grading permit and/or the commencement of any clearing, grading or excavation for all projects that disturb over 1 acre, the applicant/owner shall submit a Notice of Intent (NOI) to the California State Water Resources Control Board, Storm Water Permit Unit, in accordance with the NPDES Construction General Permit (No. 2009-009- DWQ including amendments). The applicant/owner shall provide the City with a WDID number or proof of the NOI submittal. The applicant/owner shall comply with all additional requirements of this General Permit including preparation of a Stormwater Pollution Prevention Plan (SWPPP). The SWPPP shall be prepared by a certified QSD, fully comply with RWQCB requirements and contain specific BMPs to be implemented during project construction to reduce erosion and sedimentation to the maximum extent practicable. A copy of the adopted SWPPP shall be maintained in the construction site office at all times during construction and the site superintendent shall use the plan to train all construction site contractors in site Best Management Practices prior to starting work on the site. At a minimum, the following BMPs and requirements shall be included:

A. Pollutant Escape: Deterrence
B. Pollutant Containment Areas
C. Pollutant Detainment Methods
D. Sediment control and capture
E. Erosion Control / Dust Control
F. Recycling/Disposal
G. Hazardous Materials Identification and Response

TRAFFIC
118.Traffic Mitigation Fees – The applicant acknowledges that the subject development will impact traffic and agrees to provide for the mitigation by depositing with the City of Thousand Oaks the appropriate non-refundable fees no later than prior to the issuance of building permits. 119.Gated Entrance – The design of any gated entrance shall comply with the City standards subject to review and approval of the Traffic Engineer, Ventura Fire Department and the Department of Community Development.

Any use of decorative pavers as paving material and located around a central planter shall be subject to review and approval by the Department of Public Works. No pavers shall be located in the path of travel for the physically challenged. Should the gate interfere with traffic safety on the public street they will be removed at the property owner’s expense.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 34 ends

3 0
4 6
2 8
5 8

SUSTAINABILITY

Solid Waste Collection and Diversion Requirements
120.Trash Hauler Approval – Required: Prior to issuance of a trash enclosure building permit, the applicant shall provide a letter from Athens Services, the City’s trash hauler, indicating they have reviewed the project plans and that the enclosure locations and orientation as shown are acceptable to their company for purposes of trash and recyclables pick up. Contact Athens Services at (805) 852-5264, or visit their Sustainability Center at 2251 E.

Thousand Oaks Blvd.
121.Construction/Demolition Debris Recycling Plan – Required: Prior to the issuance of a demolition permit (where the site contains existing structures or facilities) or of a grading/building permit, the applicant shall submit a Construction and Demolition (C&D) Debris Recycling Plan to the Department for review and approval. The applicant must divert a minimum sixty-five percent (65%) of all C&D waste materials generated from the project. The C&D Debris Recycling Plan shall indicate the proposed means of disposition of all C&D waste materials, including but not limited to, asphalt, concrete, wood, drywall, brush and vegetation, landscaping materials, lights, piping, concrete block, metal, and the like, which will be recycled, reused, salvaged, and /or delivered to a landfill. The Recycling Plan must also include estimated weights of the materials, list of proposed recycling/disposal facilities, and authorized hauling companies to be used.

For a list of authorized waste haulers and/or to complete and submit a C&D Debris Recycling Plan go to ThousandOaks.WasteTracking.com. 122.Trash Enclosures - Solid Waste, Recycling and Organics Collection – Required: American with Disabilities (ADA) accessible, covered 3-bin enclosures with a ramp are required for the collection of solid waste, recycling, and organics (food waste). The design of the enclosure must be large enough to accommodate collection containers for source-separated solid waste, organic waste, and recyclable materials.

Refer to the City’s revised waste ordinance (November 16, 2021) governing the enclosures’ locations, specific sizing, configuration, and clearances.

Resident access to Waste Enclosures serving MFD-C or MXD developments via walk-up shall be located no further than 150 feet from the front door of the furthest residential unit served as measured along the accessible path of travel.
123.Bulky Item Collection – A covered location shall be provided for occupants to place bulky items for collection by the authorized hauler. 124.Required - Operational recycling plans are required before occupancy.

PUBLIC WORKS DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 35 ends

3 0
4 6
2 8
5 8
Water and Irrigation
125.Water – Thousand Oaks is a State Water Dependent Area and we are currently at a level 4 drought restriction which has a maximum of one day per week outside irrigation and requires the use of drip/low flow irrigation. If the drought continues, all outside irrigation could be eliminated. Please visit www.toakswater.org for more information on restrictions. Note that our water conservation ordinance has restrictions that exceed MWELO requirements and the developer should design their palette to thrive on once a week low- flow irrigation only. Trees should be on separate zones so they can be operated separately in the event that additional restrictions are added. 126.Low-flow/low volume Irrigation – Sprinklers including rotators are prohibited within the City please review the specific requirements on our irrigation page. https://www.toakswater.org/sprinklersandirrigation. 127.Plantings during the drought – The drip/low flow irrigation system should be installed, and trees planted. However, installing the smaller shrubs and plants should be deferred until either the drought is over, or the City determines we have sufficient water to establish new plantings. 128.Turf/Grass – State law now prohibits the watering of non-functional turf in commercial developments. A waiver from the Sustainability Division is required to use potable water for turf. The waiver must include an explanation of why it is "functional turf". Include a description of the subsurface irrigation system or mechanism to irrigate. In planning for the future, turf areas should be minimized and established on separate valves for easier shutoff during droughts.
129.Dust control – Refer to Ventura County Air Pollution Control District methods of dust control for eligible methods, for the duration of the water restrictions. Alternatives to the use of use of potable water during construction should be the primary methods employed. If potable water is needed a hardship waiver is required and must explain when potable water will be used in the different construction stages and when other methods will be used. The hardship waiver is available from the Sustainability Division.
130.Electric Vehicles – 5% of the total 126 parking spaces (7 spaces) will be equipped with EV chargers on the first day the apartments are approved to be occupied. 20% of the parking spaces will be EV Capable (25 spaces). 35% of the parking spaces (44 spaces) will be EV Ready.

131.General – Owner will install all electric appliances for all 73 residential units.

FIRE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269- DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 36 ends

3 0
4 6
2 8
5 8

VENTURA COUNTY FIRE PROTECTION DISTRICT

132.Fire Department Clearance - Applicant shall submit VCFD Form #610, Fire Permit Application, prior to obtaining a building permit for any new structures.
133.Fire-Flow (Commercial, Industrial, Multi-family buildings) - The minimum fire-flow required shall be determined as specified by the current adopted edition of the California Fire Code Appendix B with adopted Amendments and the City of Thousand Oaks Public Works Water Works (whichever is more restrictive). The applicant shall verify that the water purveyor can provide the required volume and duration for the project prior to obtaining a building permit by having them fill out VCFD Form #625, Fire- Flow Verification.
134.Building Plan Review - Building plans of all A, E, I, H, R-1, R-2, or R-4 occupancies shall be submitted, with payment for plan check, to the Fire District for review and approval prior to obtaining a building permit. 135.Emergency Planning and Preparedness - The owner/applicant and all occupants of buildings shall comply with the Fire Department requirements for Emergency Preparedness Requirements as indicated under the California Fire Code, Chapter 4 “Emergency Planning and Preparedness”, and CCR Title 19 Sec 3.09. All required records and documentation shall be available for review by the Fire Department upon request. 136.Access Point(s) on Roads - Roads shall be provided such that any portion of the exterior walls, at grade level, of a building or structure, is not more than 150 feet from a road as measured by an approved route around the exterior of the building. Exception: The distance shall be permitted to be extended to 250 feet when the building is protected by an automatic fire sprinkler system in accordance with NFPA 13 and provided with an approved access walkway leading from the road to the exterior openings around the structure.
137.Aerial Apparatus Access - Private roads shall comply with Public Road Standards. Multi-Family, Commercial, or Industrial Buildings or portions of buildings or facilities exceeding 30 feet in height above the lowest level of fire department access shall require an approved aerial ladder fire apparatus access road. The highest roof surface shall be determined by measurement to the eave of a pitched roof, the intersection of the roof to the exterior wall, or the top of parapet walls, whichever is greater. One aerial apparatus access road shall be provided per 50,000 square feet of building area. Aerial apparatus access roads shall have a minimum unobstructed width of 30 feet, exclusive of shoulders. Required aerial apparatus access roads shall be located within a minimum of 15 feet and a maximum of 30 FIRE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269- DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 37 ends

3 0
4 6
2 8
5 8
feet from the building. Aerial apparatus access roads shall be positioned such that they are parallel to the entire side of the building. The side of the building on which the aerial fire apparatus access road is positioned shall be along the longest side of the building, unless otherwise approved by the fire code official. Parking shall be prohibited along the required width of the access roads. Overhead utility and power lines shall not be located within the aerial ladder fire apparatus access roads. Landscaping and other improvements between the required access and the buildings shall not interfere with aerial ladder fire apparatus operations, as approved by the fire district.
138.Mitigation to Aerial Fire Apparatus Access Roads- The fire code official is authorized to reduce the required width to not less than 24 feet when all the following are provided.
•Automatic fire sprinklers are installed throughout the structure in accordance with NFPA 13.
•Fire sprinkler standpipes are provided on all floors and through to the roof.
•Two or more roof access points are provided through 2-hour fire rated stairs separated a distance not less than half of the diagonal of the structure.
139.Turning Radius - The access road shall be of sufficient width to allow for a 40-foot centerline turning radius at all turns in the road. 140.Road Surface Construction and Grade Limitations - Fire apparatus access roads serving commercial and industrial occupancies shall have a structural cross section and surface complying with the public road standards for the jurisdiction in which the project is located and grades shall not exceed 10%.
141.Vertical Curve - The vertical curve of a fire apparatus access roads serving commercial and industrial occupancies shall not allow for transitions between grades that exceed 6% elevation change along any 10-foot section. These transitions shall include angle of approach, angle of departure, and high centering of fire apparatus.
142.Vertical Clearance - All access roads/driveways shall have a minimum vertical clearance of 13 feet 6 inches (13' 6"). Clear of building to sky. 143.Construction Access Utilities - Prior to combustible construction, all utilities located within the access road and the first lift of the access road pavement shall be installed. A minimum 20-foot clear width shall remain free of obstruction during any construction activities within the development once combustible construction starts.

FIRE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269- DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 38 ends

3 0
4 6
2 8
5 8
144.Access Road Certification - The access road(s)/driveway(s) inclusive of bridges, culverts, and other appurtenant structures which supplement the roadway bed or shoulders, shall be certified by a registered civil engineer as having an all-weather surface in conformance with the City of Thousand Oaks Public Works and/or Fire District standards. This certification shall be submitted to the Fire District for review and approval prior to occupancy. 145.Fire Lanes - Prior to construction the applicant shall submit two (2) site plans to the Fire District for approval of the location of fire lanes. Prior to occupancy, all fire lanes shall be posted “NO PARKING-FIRE LANE-TOW AWAY” in accordance with California Vehicle Code, the California Fire Code and current VCFPD Fire Lane Standards. All signs and or Fire Lane markings shall be within recorded access easements.
146.Fire Hydrant(s) Required - Fire hydrant(s) shall be provided in accordance with current adopted edition of the California Fire Code, Appendix C and adopted amendments. On-site fire hydrants may be required as determined by the Fire District
147.Fire Hydrant Design (Commercial, Industrial, Multi-family buildings) – Fire hydrants shall be installed and in service prior to combustible construction and shall conform to the minimum standard of the City of Thousand Oaks Water Works Manual and the following.
•Each hydrant shall be a 6-inch wet barrel design and shall have one 4-inch and two 2 ½-inch outlets.
•The required fire flow shall be achieved at no less than 20-psi residual pressure.
•Fire hydrants shall be spaced 300 feet on center and so located that no structure will be farther than 150 feet from any one hydrant. •Fire hydrants shall be set back from the curb face 24 inches on center.
•No obstructions, including walls, trees, lights, signposts, and meters shall be placed within three feet of any hydrant.
•A concrete pad shall be installed extending 18 inches in all directions from the fire hydrant.
•Ground clearance to the lowest operating nut shall be between 18 to 24 inches.
148.Fire Sprinklers - All structures shall be provided with an automatic fire sprinkler system in accordance with current VCFPD Ordinance at time of building permit application.
149.Standpipe Systems - Standpipe systems shall be installed in accordance with California Building and Fire Code requirements.

FIRE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269- DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 39 ends

3 0
4 6
2 8
5 8
150.Water System Plans - Plans for water systems supplying fire hydrants and/or fire sprinkler systems and not located within a water purveyor’s easement, shall be submitted to the Fire District for review and approval prior to issuance of grading and/or building permits or signing of plans, whichever is first. Plans shall reflect only dedicated private fire service lines and associated appurtenances. Plan shall be design and submitted with the appropriate fees in accordance with VCFPD Standards.
151.Fire Alarm System - A fire alarm system shall be installed in all buildings in accordance with California Building and Fire Code requirements. 152.Fire Alarm/Sprinkler Monitoring Plans - Plans for any fire alarm system or sprinkler monitoring system shall be submitted, with payment for plan check, to the Fire District for review and approval prior to installation. 153.Emergency Lighting and Exit Signs - Emergency lighting and exit signage shall be installed in all buildings in accordance with California Building Code and California Fire Code requirements.
154.Fire Extinguishers - Fire extinguishers shall be installed in accordance with California Building Code and California Fire Code requirements. The placement of extinguishers shall be subject to review by the Fire District. 155.Panic Hardware - All exit doors shall be provided with panic hardware when serving A, E, I occupancies with an occupant load of 50 or more persons. 156.Walkways - Approved walkways shall be provided from all building openings to the public way or fire department access road/driveway. 157.Exterior Exit Stairway - Emergency escape and rescue openings shall be provided in Group R occupancies. Such openings shall discharge directly to the exterior of the building. The exit discharge shall be at grade or shall provide a direct path of egress travel to grade. The exit discharge shall not reenter a building. An exterior exit stairway is required to provide a path of egress from the podium deck to grade and ground ladder access to the podium deck.
158.Ground Ladder Access – Access around the building shall be provided to allow for laddering the building, at a maximum 75-degree angle, to reach emergency escape and rescue openings below the fourth story above the grade plane. A three (3) foot clear working space shall be provided around the ladder at ground level.
159.Walk and Pedestrian Gates - If gates are to be locked, a Knox system shall be installed. The method of gate control, including operation during power failure (battery back-up), shall be subject to review by the Fire FIRE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022-70269- DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 40 ends

3 0
4 6
2 8
5 8
Prevention Division. Gate plan details shall be submitted to the Fire District for approval prior to installation. A final acceptance inspection by the Fire District is required prior to placing any gate into service. 160.Address Numbers (Commercial, Industrial, Multi-family buildings) - Building address numbers, a minimum of ten inches (10") high, shall be installed prior to occupancy, shall be of contrasting color to the background, and shall be readily visible at night. Brass or gold-plated numbers shall not be used. Individual unit numbers shall be a minimum of 4 inches in height and shall be posted at the front and rear entrance to each unit. Additional address directional signs may be required at common building entrances and stairways.
161.Address Directory - An address directory shall be provided at all entrances to the project at locations approved by the Fire District. Design shall be in accordance with Fire District Addressing Standards. Directory plans shall be submitted to the Fire Prevention Division for review and approval prior to installation.
162.Address Number Plan - A plan shall be submitted to the Fire District for review indicating the method in which buildings are to be identified by address numbers.
163.Accessory Room Door Labeling - All accessory room doors shall be labeled on the doors indicating use of the room (i.e., Electrical Room, Riser Room, Fire Alarm Panel Inside, Storage Room, Janitor, Roof Access, etc.). 164.Knox Device - Exterior access leading to fire sprinkler riser rooms and alarm control panels shall be provided with a Knox Box for emergency access.

POLICE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022- 70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 41 ends

3 0
4 6
2 8
5 8

POLICE DEPARTMENT
165.POOL ACCESS – Pool access will be controlled by key-fob or similar device to reduce trespasser access. The pool will be surrounded by a decorative fence of no less than 6 feet in height, with the same CPTED “2 foot / 6 foot” rules of landscaping to apply.
166.UTILITY ROOMS AND ENCLOSURES – All exterior utility rooms and enclosures containing electrical and telephone equipment shall be kept locked at all times.
167.LANDSCAPING – Landscaping shall not cover, nor partially cover any exterior door or window. Landscaping, including trees, will not be placed directly under any overhead lighting that could cause loss of light at ground level. All landscaping will be kept trimmed in order to provide an unobstructed view of the parking areas and building from adjacent streets.

The standard CPTED (Crime Prevention Through Environmental Design) landscaping rules of “two foot / six foot” shall apply to the property (No shrubbery shall be higher than 2 feet and lower the tree canopy shall not grow below 6 feet). This will reduce concealment areas and keep the area well-lit during darkness hours.
168.DOOR SECURITY HARDWARE – Exterior double doors shall have an astragal constructed of steel or aluminum a minimum of .125” thick, which will cover the opening between the doors. The attachment of the astragal shall comply with all applicable provisions of the Fire Code. Exterior, outward opening single doors shall have the appropriate type of latch guard installed so as to prevent the violation of the latch and strike. The latch guard shall be a minimum of .125” thick and extend a minimum of six inches above and below the door latch or deadbolt. Doors utilizing rim and cylinder locks shall have heavy-duty cylinder guards installed. All outward opening exterior doors shall have hinges equipped with non-removable hinge pins or a mechanical interlock (set screws) to prevent removal of the door from the outside by removing the hinge pins.
169.ADDRESS NUMBERS – Wall mounted address numbers shall be a minimum of ten inches in height, be of a highly contrasting color to the background on which they are attached, and shall be illuminated from dusk to dawn by a permanent, dedicated light source.
170.ELEVATORS – Elevator interiors shall be equipped with mirrors or highly reflective surfaces to allow surveillance of the interior prior to entry, and shall have a minimum interior dimension of 6’ 8” wide x 4’9” deep in order to accommodate a standard sized medical gurney and emergency response personnel.

POLICE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022- 70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 42 ends

3 0
4 6
2 8
5 8
171.STAIRWELLS - Stairwells leading to additional floors in the enclosed areas will either have (1) mirrors, (2) an open stairs concept, (3) half-wall concept or (4) any combination of the aforementioned, to allow the traveler to view up or down to the next floor for the purposes of an increased field of view and reduced blind spots.

Additionally, any stairwell or doors leading from the public area to any residential area is to be accessed by key-fob, key, punch code or other control device as to restrict access from the general, non-residing public.

This includes all exterior doors on the perimeter of the residential portion of the project. The doors will have emergency access via a “Knox Box” or similar security device. A generic code for door access will also be provided to Sheriff’s Dispatch at 805-654-9511 if coded. Any code changes need to be provided to Sheriff’s Dispatch ASAP
172.TRASH ENCLOSURES – Exterior trash enclosures shall be kept closed and locked during non-business hours to discourage, loitering, illegal dumping and theft. Trash encloses will be constructed to have outside visibly to reduce the possibility of camping or sleeping in the area. 173.UNDERGROUND PARKING – For the residents, will have a motorized gate to limit free and unrestricted access from persons not having business at the location. The garage area will have emergency access to the gate via a “Knox Box” or similar security device. A generic code for gate access will also be provided to Sheriff’s Dispatch at 805-654-9511. Any code changes need to be provided to Sheriff’s Dispatch immediately.
174.PARKING STRUCTURES – Install a digital, color, CCTV security camera system on each level of the parking structures. Cameras shall cover the parking areas as well as the pedestrian and vehicular egress and ingress points. Cameras shall provide good image quality during all hours of operation. It shall be a requirement that a minimum of the past 72 hours of recorded activity be retained by staff and be available upon request by the Police Department. The interior staircases shall be of the open construction variety in order to minimize blind spots and areas of concealment. Security mirrors shall be placed in the stairwells and parking structure interior.

All exterior openings in the structure's walls shall be secured with decorative metal grids to minimize unauthorized pedestrian entry. The concrete flooring of the structure shall be rough swirled to prevent skateboarding, rollerblading, etc.

For the safe movement of vehicles and pedestrians, lighting levels should be evenly distributed to provide uniform illumination of the entire parking area. Care should be given to prevent the casting of glare and spillover POLICE DEPARTMENT CONDITIONS OF APPROVAL FOR 2021-70182-LU; 2022- 70269-DP; 2022-70535-PTP; and 2022-70822-DAGR
cdd:420-46\jk\H:COMMON\City Council\CC Agenda Items\2023\04252023\Long Ct\Attach42.docx\pz [FILE ID: 2022- 70822-DAGR)

Page 43 ends

3 0
4 6
2 8
5 8
lighting outside of the structure. The applicant shall comply with the following lighting requirements in the proposed parking structure:
• A minimum five-foot candles at the floor level shall be provided on interior driving aisles, at all times.
• The roof parking area shall have a minimum maintained one-foot candle at floor level during hours of darkness.
• Interior parking spaces at barrier and railings shall have a minimum maintained one-foot candle at floor level at all times. • Stairways, ramps and exits shall have a minimum maintained ten- foot candle at floor level at all times.

The lighting for the parking structure shall be controlled by photocell and shall remain on during hours of darkness and diminished lighting.

It is recommended that the interior walls and ceiling of the parking structure be painted with a light, reflective color to maximize lighting efficiency.

All entrances to the parking structure shall be posted with signs indicating the structure is under 24 hour video surveillance. All driveway entrances shall be posted with appropriate signs per 22658(a) of the California Vehicle Code to assist in removing abandoned vehicles on the property. 175.PARKING – In order to facilitate parking concerns, the developer shall post signs at each entrance to the parking lot indicating the California Vehicle Code will be enforced. To discourage theft and vandalism, the parking lot shall be fenced. The use of chain link is discouraged. Access shall be through a gate equipped with key card reader. Entry logs shall be retrievable and presented to the Thousand Oaks Police Department when necessary.
176.OTHER SECURITY CONCERNS - The business will correct any safety or security concerns upon written notice by the Thousand Oaks Police Department.
*****

← All documents from this meeting