ATTACHMENT #2
Project Name: Conejo Canyons Bridge at Hill
Canyon Treatment Plant (Cl 5527)
SIXTH AMENDMENT TO
AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN THE CITY OF THOUSAND OAKS
AND
STANTEC CONSULTING SERVICES
Contract No. 11855-2018
THIS SIXTH AMENDMENT to the Agreement for Professional Services entered into between the CITY OF THOUSAND OAKS, a municipal corporation, (hereafter “City”) and STANTEC CONSULTING SERVICES (“Consultant”), entitled Conejo Canyons Bridge at Hill Canyon Treatment Plant (CI 5527), and dated September 25, 2018 and amended on May 23, 2019; December 6, 2019; December 24, 2020; February 22, 2022; and July 5, 2022 (herein “Contract”) is made this 11th day of July 2023.
RECITALS
A. Section 3 of Contract, currently, and as may have been previously amended, provides for a “not-to-exceed” total payment as consideration to Consultant of $358,607 for services generally and briefly described as Consultant’s services in connection with the preparation of the contract documents for the project’s post- construction habitat restoration including planting and irrigation.
B. Section 5 of Contract, currently, and as may have been previously amended, provides for a termination date of December 31, 2023.
C. City and Consultant desire to extend the date of the Contract.
D. City is in need of expanding the Scope of Services to be performed under the present Contract, and Consultant is desirous of performing such and receiving additional compensation for said extra services.
AGREEMENT TO AMEND
NOW, THEREFORE, the undersigned parties to Contract agree to amend Contract as described below:
DPW: 850-20\Council\2022\022222\CI 5527 Conejo Canyons Bridge Att 2.docx
3 3
9 1
Part 1. The following services to be performed by Consultant are added to the Scope of Services listed in Section 2 of Contract, such section is hereby amended to add and also include the following services, and Exhibit A-6 is hereby added to the Contract:
Additional design and engineering services related to preparation of contract documents for planting and irrigation systems, and engineering support during the bid and construction phases in connection with Conejo Canyons Bridge at Hill Canyon Treatment Plant post construction mitigation, as more fully described in Exhibit A-6 attached hereto and incorporated herein.
Part 2. The sum of $37,853 is added as compensation to Consultant under the present Contract for the above-described additional services, and Subsection 3 (a) of Contract is hereby amended to read in its entirety as follows. Exhibit B is hereby replaced in its entirety by Exhibit B-6, attached hereto and incorporated herein by reference.
(a)Maximum and Rate. The total compensation payable to Consultant by City for the services under this Agreement SHALL NOT EXCEED the sum of $396,460, and shall be earned as the work progresses on the following basis:
Hourly at the hourly rates and with reimbursement to Consultant for those expenses set forth in Consultant's Schedule of Fees marked Exhibit "B-6", attached and incorporated herein. The rates and expenses set forth in that exhibit shall be binding upon Consultant until December 31, 2023, after which any change in said rates and expenses must be approved in writing by City's Project Manager (City is to be given 60 days’ notice of any rate increase request), provided the not to exceed amount is the total compensation due Consultant for all work described under this Agreement.
Part 3. The Contract is extended for a period of 6 months and Section 5 is hereby amended in part to read as follows:
The term of this Agreement is from the date first written above to June 30, 2024, unless the term of this Agreement is extended or the Agreement is terminated as provided for herein.
DPW: 850-20\Council\2022\022222\CI 5527 Conejo Canyons Bridge Att 2.docx
3 3
9 1
Part 4. All terms used in Parts 1, 2, and 3 above shall have the meanings ascribed thereto in Contract. Except as amended in Parts 1, 2, and 3 above, all other sections, terms, obligations, duties, clauses, and provisions of Contract shall remain the same.
IN WITNESS WHEREOF, the parties execute this Sixth Amendment to Contract as of the date set forth above.
STANTEC CONSULTING SERVICES
_____________________________
Hady Izadpanah, Senior Principal
_____________________________
Derek Rapp, Principal
CITY OF THOUSAND OAKS
_____________________________
Kevin McNamee, Mayor
ATTEST:
Laura B. Maguire City Clerk
APPROVED AS TO ADMINISTRATION:
________________________________
Andrew P. Powers, City Manager
APPROVED BY DEPARTMENT HEAD:
Clifford G. Finley, Public Works Director
APPROVED AS TO FORM:
Office of the City Attorney
Tracy Friedl, Assistant City Attorney
DPW: 850-20\Council\2022\022222\CI 5527 Conejo Canyons Bridge Att 2.docx
3 3
9 1
EXHIBIT A-6
SIXTH AMENDMENT
CI 5527- Conejo Canyons Bridge at HCTP
SCOPE OF WORK
Consultant shall provide services as listed under the following Tasks:
Task 1: Project Coordination & Meetings
1.1 Take the lead in coordinating all project activities, including project meetings and coordination with staff, deliverables, submissions, and similar coordination efforts consistent with the scope of work.
Task 2: Review Project Data
2.1 Review documentation provided by the City and other discipline leads of the project including preliminary review comments, Biologist Habitat Restoration Plan, assessment reports, photos, and documentation provided by outside sources.
Task 3: Planting & Irrigation Plans
3.1 Based on information gathered from Task 2, design a 20-scale planting plan for areas 1 and 3. The plan shall identify the various plants (scientific and common names), the sizes and the amount to be planted per area.
3.2 Based on the information gathered in Task 2, and the planting described in Task
3.1, design a temporary above-grade irrigation system. The irrigation system shall include above-grade irrigation application using bubbler heads to the trees and above-grade drip tubing and/or emitters to container plants installed at Site 1 and bubblers to the trees installed at Site 3 as identified in the Biologist’s Habitat Restoration Plan.
3.3 Include Installation details for the planting and irrigation elements in the plan sheets.
3.4 Provide irrigation calculations including pressure and flow calculations. The pressure critical analysis for each area shall be posted on the irrigation sheets.
3.5 Provide general planting and irrigation specifications/notes on the plans.
3.6 Provide notes on the plans to direct the Contractor to the Biologist’s Habitat Restoration Plan for planting and irrigation performance criteria. Notes on the plan shall also state that bidder must show proof of similar work (habitat restoration).
3.7 Prepare an opinion of probable construction cost (OPCC) based on the final plan set. The OPCC shall include construction elements, the establishment and monitoring will be excluded.
DPW: 850-20\Council\2022\022222\CI 5527 Conejo Canyons Bridge Att 2.docx
3 3
9 1
Task 4: Bid and Construction Support
4.1 Review and respond to requests for information (RFI) during the bid and the construction phases of the project.
OPTIONAL Task 5: Inclusion of Area 2 in Planting and Irrigation Plans
5.1 Site 2, the riparian area, is specified to receive cuttings rather than container stock. The Biologist’s Habitat Restoration Plan identifies this area not to receive supplemental water. However, if the City determines that supplemental irrigation is preferred, this area shall be added to the plan set. Irrigation of this area will require an overhead sprinkler application rather than the drip and bubblers used on the other areas. The water source will be a water truck. Details, specifications/notes and an OPCC will be included with the other areas.