TO:Andrew P. Powers, City Manager
FROM:Clifford G. Finley, Public Works Director
DATE:July 2, 2024
SUBJECT: Improvements at Lone Oak (CI 5673), Erbes Road (CI 5738), and Ventu (CI 5739) Pump Stations
RECOMMENDATION:

1. Authorize staff to advertise the Improvements at Lone Oak (CI 5673), Erbes Road (CI 5738), and Ventu (CI 5739) Pump Stations Projects for construction bids.

2. Find that the projects are Categorically Exempt from the California Environmental Quality Act (CEQA) pursuant to 14 CCR 15301.

LEVINE ACT ITEM: No
FINANCIAL IMPACT:

No Additional Funding Requested. $2,000,000 is available in the Adopted FY 2024-25 Water Capital Fund Budget for CI 5673 with an additional $200,000 in carryover budget, $1,500,000 in carryover budget is available in the Adopted FY 2024-25 Water Capital Fund Budget for CI 5738, and $1,440,102 in carryover budget is available in the Adopted FY 2024-25 Water Capital Fund Budget for CI 5739. The estimated cost for the three improvement projects is $5,385,000.

Additional appropriation may be required at the time of construction award depending on the actual bid amount.

BACKGROUND:

The City’s Public Works Department manages the City’s water storage and distribution facilities consisting of 11 Calleguas turnouts (connections to the Calleguas Municipal Water District Supply), four hydropneumatic pump stations, 16 pump stations, 16 reservoirs, and two booster stations. Many of these sites need certain improvements to better address wildfire resiliency, site drainage, accidental tank overflow containment, pump and electrical equipment enclosures,

Improvements at Pump Stations
July 2, 2024

Page 2 ends

1 0
3 0
fencing to enhance site security, and the addition of emergency generators. These improvements are necessary to maintain these crucial infrastructure components and ensure proper protection of neighboring slopes from erosion and damage (Attachment #1).

The proposed improvements at the pump stations will address the following scope of work:
•Lone Oak Pump Station (CI 5673)
oFire hardening at this site will include rebuilding the existing roofing structures to enhance protection against wildfires.
oNew emergency power backup generator will be installed at this location and will be housed in a noise-suppressing enclosure. oDrainage improvements will be constructed at this location to address onsite drainage deficiencies to prevent erosion and water damage, as well as reduce ongoing maintenance upkeep.
oSite security enhancements will be provided with the replacement of the existing access gates and fencing, as well as site lighting. •Erbes Road Pump Station (CI 5738)
oFire Hardening will require rebuilding a portion of the existing pump station to implement a new roofing structure with fire-hardening measures to reduce wildfire risks.
oNew emergency power backup generator will be installed to maintain operations during power outages.
oSite security enhancements will include updated site lighting, and new access gates and fencing.
•Ventu Pump Station (CI 5739)
oFire hardening enhancements will include replacing the existing roof with fire-resistant roofing material.
oElectrical improvements to the site will include replacement of all existing Motor Control Centers (MCCs) as well as provide for overall system enhancements that meet current standards and will improve system reliability.
oSite security enhancements will be provided with the replacement of the existing access gates and fencing, as well as site lighting.

DISCUSSION/ANALYSIS:

The installation of generators at Lone Oak and Erbes Road Pump Stations provides power to critical pump station infrastructures during power outages and ensures water service availability during wildfire events and other emergencies.

The electrical improvement of Ventu Pump Station will improve system reliability and bring the pump station up to the current standards.

Improvements at Pump Stations
July 2, 2024

Page 3 ends

1 0
3 0
The titles and scope of the three capital improvement projects (CI 5673, CI 5738, and CI 5739) as included in the Approved FY 2023-25 Capital Improvement Budget have been revised to more accurately cover the proposed improvements at each site under an individual CI number. This will better serve to capture the full costs of the improvements at each location, helping better capitalize the proposed improvements from a bookkeeping perspective.

On June 20, 2023, City Council awarded a Professional Services Agreement in the amount of $399,055 to AECOM Technical Services Inc. (AECOM) for feasibility study, design, and preparation of the contract documents. Subsequently, Amendments No. 1 and No. 2, increasing AECOM’s total contract amount to $538,464, were approved for additional design and bid phase services.

The project plans and specifications have been completed and are available for review upon request to the Public Works Department by e-mail at [email protected] or by phone at (805) 449-2400.

Staff is recommending that the projects be advertised for bid. Once bids are received, staff will seek City Council’s approval at a future City Council meeting to award the construction contract.

The estimated construction costs are as follows:

Lone Oak Pump Station (CI 5673) $ 1,690,000
Erbes Road Pump Station (CI 5738) $ 1,520,000
Ventu Pump Station (CI 5739) $ 1,350,000
Construction Contingency $ 450,000 Engineering Support Services During Construction $ 365,000 City Furnished Materials/Supplies $ 10,000
Total Estimated Cost for all Projects $ 5,385,000
$5,140,100 is included in the Adopted FY 2023-25 Water Fund Budget. The total project cost (including contingencies) is estimated at $5,385,000. Additional appropriation at the time of construction award may be required depending on the actual bids received.

The timeline is as follows for all projects:

Bid Opening August 2024
Start of Construction Fall 2024
Project Completion Spring 2026
Improvements at Pump Stations
July 2, 2024

Page 4 ends

1 0
3 0
The improvements at Lone Oak, Erbes Road, and Ventu Pump Stations are categorically exempt from CEQA per Section 15301 (repair/maintenance of an existing facility).

These projects meet City Council’s Top Ten Priorities #7, “Public Works + Infrastructure Investments across the community.”
Community Outreach: A public outreach plan has been established, with a focus on residents located adjacent to the project as well as the general public. Project website updates will be utilized to inform the public and receive feedback. Additionally, before the start of the construction, construction notices will be mailed to all property owners in the project area and intermediate special notices will be delivered to individual properties impacted by specific issues.

CIP PROJECT PRIORITY (as outlined in FY 2023-24 and FY 2024-25 CIP Program Budget)
Priority One – Addresses Health & Safety, legal and regulatory requirements, or a top City Council Priority.

COUNCIL GOAL COMPLIANCE:

Meets the following City Council goals:

C. Operate City government in a fiscally and managerially responsible and prudent manner to ensure that the City of Thousand Oaks remains one of California's most desirable places to live, work, visit, recreate, and raise a family.

F. Provide and enhance essential infrastructure to ensure that the goals and policies of the Thousand Oaks General Plan are carried out and the City retains its role and reputation as a leader in protecting the environment and preserving limited natural resources.

PREPARED BY: Roner DelCastillo, Associate Engineer
Attachments:

Attachment #1 – Vicinity and Location Maps
DPW: 850-20\ev\Council\CI 5673 CI 5738 CI5739\ Improvements to Pump Stations staff report.docx