1 10/21/2025
Conejo Summit Appeal
Generally located at the intersection of
Conejo Center Drive and Rancho Conejo Boulevard
2022-70771-EIR, 2019-70439-DP , 2019-70440-VTTM, 2019-70441-VTTM, 2021-71158-PTP, 2019-70442-USP , 2019-70443-LPC
City Council
October 21, 2025
• Appellant 1 (SAFER) 15 Minutes
• Appellant 2 (CARE CA) 15 Minutes
• Applicant 30 Minutes
• Appellant 1 5 Minute Rebuttal
• Appellant 2 5 Minute Rebuttal
• Applicant 10 Minute Rebuttal
• Public Comment 2-5 Minutes each, depending on number of speakers Public Hearing Outline
2 1
2 Item 10.A.
(Staff's Presentation)
2 10/21/2025
Adopt resolution •Denying the two appeals, thereby •Upholding the Planning Commission’s certification of the Final Environmental Impact Report (EIR), adoption of the Mitigation Monitoring and Reporting Program (MMRP), and project approvals for the Conejo Summit Project.Recommendation 3 Maps4
3 4
3 10/21/2025
Building Design 5
Protected Trees 6
RemoveEncroachIdentifiedType102132Oaks12719Toyons
5 6
4 10/21/2025
Signage7
1983 Rancho Conejo Specific Plan (SP 7) adopted1,862-acre area 1,893 residential units152-acre employment park with light manufacturing and office uses 23 acres of commercial development1983 – 2015SP 7 Amended 16 times1,324 residential units, 100-acre employment park with light manufacturing and office uses 33-acre public facility No commercial developmentProject Background8 7 8
5 10/21/2025
SP 7’s Employment Park Development Potential 100 acresGeneral Plan 1.0 FAR = ~4.4 million square feetM-1 50% building coverage = ~2.2 million square feet0.35 FAR = ~ 1.5 million square feetSP 7’s Employment Park Development Realized~50 acres ~260,000 square feet 30 residential unit navigation center (emergency shelter)Backbone infrastructureConejo Summit~50 acres~755,000 square feetSP 7’s Cumulative Development100 acres ~1.01 million square feet 30 residential unit navigation center (emergency shelter)Project Background9 Enhance the City’s high-value economic sectors Diversify the City's job base Contribute to the City's long-term economic vitalityDevelop a critical mass of buildings in a large-format business park for uses authorized in the Specific PlanExpand economic development opportunitiesFoster growth and attract new industriesPromote and expand existing job centersBe competitive with other similar facilities in the regionEnhance and improve infrastructure and circulationCreate adequate parkingSummary of Applicant’s Goals & Objectives109 10 6
10/21/2025
EIR Prepared in conformance with CEQANotice of Preparation review period: February 17 – March 20, 2023Scoping Meeting: March 1, 2023Notice of Availability review period: November 26, 2024 – January 10, 2025Response to Comments preparedFinal EIR identifies impact levelsPlanning Commission found all potentially significant impacts are mitigated to levels that are less than significantCalifornia Environmental Quality Act11 Two appeals were filedAppeal #1 – SAFERAppeal #2 – CARE CABoth appeals allege the DEIR fails to comply with CEQACARE CA appeal also alleges approvals of the Vesting Tentative Tract Maps, Development Permit, and Uniform Sign Program were unsupported by the recordThe substance of both appeals and responses were previously provided to the Planning CommissionThe Planning Commission did not find merit in the comments that were provided by the now appellantsThe EIR analysis and project findings are supported by substantial evidenceStaff concludes neither appeal has merit, and staff recommends City Council reject the appeals and uphold the Planning Commission’s prior approvalAppeals1211 12 7
10/21/2025
Appeal alleges the DEIR fails to comply with CEQABiological ResourcesUnderestimated species diversityBiological baseline was faultyFailed to assess or mitigate impactsMitigation measures do not reduce project impacts to less-than-significant levelsStaff ResponseThe EIR’s wildlife diversity was more extensive than in the appellant’s commentsBiological baseline was thoroughly establishedBiological impacts accurately assessedMitigation measures reduce project impacts to less-than-significant levelsCalifornia Department of Fish & Wildlife did not identify deficiencies on the EIR’s approachAppeal #1 – SAFER13 Appeal alleges the DEIR fails to comply with CEQAEnergyEnergy impacts were not properly analyzedStaff ResponseAdequately analyzed construction and operational energy usageThe project will not result in wasteful or inefficient energy useThe project will incorporate solar-ready roofs and EV infrastructure consistent with Building CodeStaff concludes Appeal #1 has no merit, and staff recommends City Council reject the appeal and uphold the Planning Commission’s prior approvalAppeal #1 – SAFER1413 14 8
10/21/2025
The FEIR does not meet CEQA’s requirements and must be recirculatedAir QualitySignificant impacts remain unmitigatedAll feasible onsite mitigation measures have not been implementedThe impact fee would not result in emissions reductionsStaff ResponseImpacts are reduced to less-than-significant through Transportation Demand Management FeeThe City has a history of emission reduction projectsThe City’s adopted Capital Improvement Program includes qualifying programs for these feesThe City’s Climate & Environmental Action Plan will result in additional qualifying programsProject conditions reduce emissions beyond code requirementsAppeal #2 – CARE CA15 The FEIR does not meet CEQA’s requirements and must be recirculatedElectric Vehicle SpacesProject fails to meet EV capable spaces code requirementsAdditional EV capable spaces are necessary to reduce air quality impactsStaff ResponseProject must comply with code requirementsMitigation Measure TRAF-5 includes language to install EV chargers exceeding 2022 code requirementsTruck Trip Lengths and EmissionsThe FEIR underestimated emissions from truck tripsStaff ResponseThe FEIR conservatively analyzed emissions from truck trips. Emissions were not underestimated.Appeal #2 – CARE CA1615 16 9
10/21/2025
The FEIR does not meet CEQA’s requirements and must be recirculatedBackup GeneratorsFEIR discounted emissions from future use of backup generatorsStaff ResponseGenerators are not proposed and not requiredIt is speculative to assume future tenants will have generators and the energy source (diesel, solar)Traffic NoiseFEIR fails to validate the traffic noise modelStaff ResponseNoise analysis was validated and based on site-specific dataMeasured ambient air, Traffic data, Model adjusted for time-of-day sensitive periodsAppeal #2 – CARE CA17 The FEIR does not meet CEQA’s requirements and must be recirculatedFire FlowFEIR failed to conduct a quantitative fire flow analysisStaff ResponseCity & Fire staff found adequate flowFire flow compliance verified at plan-check and construction inspectionsRecirculationRecirculation of the EIR is requiredStaff ResponseRecirculation of the EIR is not required No new significant informationNo new or substantially significant impactNo considerable changes to mitigation measures or alternativesEIR had substantial evidence and was not conclusoryAppeal #2 – CARE CA1817 18 10
10/21/2025
The FEIR does not meet CEQA’s requirements and must be recirculatedProject Findings: Maps, Development Permit, Uniform Sign ProgramPlanning Commission lacked substantial evidence to make the FindingsStaff ResponseSubstantial evidence and Findings are in the recordEIR & AppendicesPlanning Commission staff report & attachmentsPlanning Commission ResolutionStaff concludes Appeal #2 has no merit, and staff recommends City Council reject the appeal and uphold the Planning Commission’s prior approvalAppeal #2 – CARE CA19 CityNotice of ApplicationCEQAPublic HearingGeneral inquiriesApplicantOutreachPublic Correspondence 2019 20 11
10/21/2025
Adopt resolution •Denying the two appeals, thereby •Upholding the Planning Commission’s certification of the Final Environmental Impact Report (EIR), adoption of the Mitigation Monitoring and Reporting Program (MMRP), and project approvals for the Conejo Summit Project.Recommendation 21 2221
22 10/13/2025
1 CONEJO SUMMIT
T h o u s a n d O a k s
15 16
Item 10.A.
(Applicant's Presentation)
10/13/2025
2 HISTORY IN RANCHO CONEJO AREA•Purchased former MGM Ranch property in late 1970’s•Entitled master plan for area in 1980’s, originally included over 100 acres of industrial land•Constructed over 1,000 homes•Developed & still own Arroyo Villas apartments (354 units) Aerial viewSite17
18 10/13/2025
3 Master Site Plan
IllustrativeLandscape Plan
19 20
10/13/2025
4 Buildings 1A-1D-1E-2
Elevations Buildings 1A-1D-1E-2
21 22
10/13/2025
5 Buildings 1B-1C-4A-4B
Elevations Buildings 1B-1C-4A-4B
23 24
10/13/2025
6 Buildings 1F-1G
Elevations Buildings 1F-1G
25 26
10/13/2025
7 Building 3
Elevations Building 3
27 28
10/13/2025
8 Building 5A
Elevations Building 5A
29 30
10/13/2025
9 Building 5B-6A
Elevations Building 5B-6A
31 32
10/13/2025
10 Building 6B
Elevations Building 6B
33 34
10/13/2025
11 CONEJO SUMMITT h o u s a n d O a k s35
1 10/21/2025
City Council Meeting
October 21, 2025
Amgen Concurrent
Processing Request
• Concurrent Processing for a Specific Plan
Amendment and Development Entitlements
Request
1 2
Item 12.A.
2 10/21/2025
Background3
•Amgen Specific Plan (SP-16) serves aslong-term development plan guidingexpansion of the biopharmaceuticalcompany’s headquarters.•Functions as an implementation tool forthe General Plan.•Includes height districts ranging from 35to 75 feet.•Recent announcement to invest in anew center for science and innovation.
General Plan Land Use Designations4A
3 4
3 10/21/2025
Area SpecificGuidance5
Concurrent Processing 6A•Specific Plan Amendment•Development Permit•Landscape Plan Check5 6 4
10/21/2025
Specific Plan Amendment and Concurrent Processing
Application Submittal/ Review
Environmental Analysis
Planning Commission Hearing
City Council HearingNext Steps7
1.Adopt resolution authorizing the concurrent processing of the Specific Plan Amendment and projectentitlements for the proposed development of new research and development, laboratories, andsupporting facilities for the Amgen campus.2.Find that such declaration does not constitute a project as defined under the California EnvironmentalQuality Act (CEQA) pursuant to Section 15378 of the CEQA Guidelines; however, even if the actionscontemplated herein constituted a project, the actions are exempt under Section 15061(b)(3).Recommendations7 8 5
10/21/2025
9