TO: Andrew P. Powers, City Manager
FROM: Nader Heydari, Public Works Director
DATE: October 27, 2026
SUBJECT: Water Mainline Replacement Project (CI 5642)
RECOMMENDATION:
1. Approve the Third Amendment to the Professional Services Agreement with MNS Engineers, Inc. (Santa Barbara, CA), Contract No. 14134-2025 for the Water Mainline Replacement Project (CI 5642), in the amount of $84,945, for a revised not-to-exceed amount of $359,685 and extend the agreement term to December 31, 2027.
2. Authorize expense in the amount of $84,945 from A/C# 613-8030-682-8300 (Water Capital Fund – Improvements Other Than Buildings, CI 5642).
LEVINE ACT ITEM: Yes
FINANCIAL IMPACT:
No Additional Funding Requested. $2,100,000 is included in the Adopted FY 2026-27 Water Fund Capital Budget, and $1,829,000 in additional carryover budget is available, for a total available project budget of $3,929,000. The total estimated cost of the project is $3,278,445.
BACKGROUND:
The City provides water service to over 17,000 customers. The City’s existing water distribution system includes 11 turnouts from Calleguas Municipal Water District (CMWD), 16 pump stations, 16 reservoirs, and approximately 232 miles of transmission and distribution pipelines.
Water Mainline Replacement Project (CI 5642)
October 27, 2026
The City is actively working on replacing its aging water mainlines throughout its water distribution system to improve water system supply reliability and water quality. The average age of the City’s water infrastructure is 40 years with 1/3 of the system being 50-60 years old. Therefore, targeted replacement of these pipelines is critical to maintain the health of the system.
The Water Mainline Replacement Project (CI 5642) aims to rehabilitate a 16-inch water main by lining the existing mainline, and to replace other 12-inch and 16- inch water lines (Attachment #1). The 16-inch mainline from Meadows Reservoir to Avenida De Las Flores, which was installed in 1972, has experienced leaks and failures. The portion of the line between El Monte Drive and Avenida De Las Flores through Conejo Creek North Park was replaced by a previous project. This project will replace and rehabilitate portions from Meadows Reservoir to El Monte Drive.
This project also includes relocating a 12-inch water mainline located within Caltrans’ right-of-way. The existing line, constructed in 1967, currently crosses beneath California State Route 23 (SR-23). The new alignment will reroute the mainline through an existing bridge cavity along the Avenida De Las Flores overpass. This improvement will eliminate the risks associated with positioning critical City infrastructure beneath the freeway, which could otherwise require a freeway closure to repair a leak or line break at that location.
On December 2, 2025, City Council approved a Professional Services Agreement with MNS Engineers, Inc. (MNS) in a not-to-exceed amount of $262,205 and authorized $26,295 in extra services. The First Amendment, executed March 17, 2026, in the amount of $8,511, added scope to inspect and video the interior cavity of the Avenida De Las Flores bridge to confirm the location and size of the existing utility opening. The Second Amendment, executed July 6, 2026, in the amount of $4,024, added scope to prepare easement documentation for the relocation of an existing line within Conejo Recreation and Park District property. These amendments increased the not-to-exceed amount to $274,740, leaving $13,760 in extra services available for additional tasks that may be required.
DISCUSSION/ANALYSIS:
Relocating the 12-inch water mainline from beneath SR-23 to the bridge cavity at the Avenida De Las Flores overpass requires a Caltrans encroachment permit.
During the permit review process, Caltrans identified additional engineering analysis and design requirements that were not included in the original scope of work.
Water Mainline Replacement Project (CI 5642)
October 27, 2026
To address these requirements and obtain Caltrans approval, MNS will provide the following additional engineering services:
• Task 3.3.4 – Grate Flow Calculations
• Task 3.3.5 – Deck and Soffit Load Rating Calculations • Task 3.3.6 – Lateral Pipe Restraint Design
• Task 3.3.7 – Deflection Calculations
• Task 3.4.3 – Additional Traffic Control plans on SR-23 The additional services will evaluate the proposed pipeline installation within the bridge structure and address Caltrans requirements related to structural loading, pipe restraint, drainage, and traffic control. Staff reviewed and negotiated the proposed fees and determined them to be reasonable.
The project plans are approximately 95 percent complete. Completion of the additional engineering analyses is necessary to obtain Caltrans approval and proceed with the proposed pipeline relocation. The additional work will require several months to complete.
Staff recommends approval of the Third Amendment to the agreement with MNS (Attachment #2) in the amount of $84,945, increasing the total not-to-exceed amount to $359,685, and extending the agreement term by one year to December 31, 2027.
The construction cost estimate increase is due to the refinement of the estimate at the 95 percent stage and will be requested at time of bids. Below is a breakdown of the project costs:
ESTIMATED PROJECT COST SUMMARY
Design $ 262,205
Design – Amendment No. 1 $ 8,511
Design – Amendment No. 2 $ 4,024
Design – Amendment No. 3 (this action) $ 84,945
Remaining Extra Services $ 13,760
City Furnished Materials/Supplies $ 5,000
Construction Estimate (Future Action) $ 2,900,000
Total Estimated Project Cost $ 3,278,445
PROJECT TIMELINE
Design Winter 2026 – Spring 2027
Bid and Award Process Spring 2027
Construction Summer 2027 – Spring 2028
Water Mainline Replacement Project (CI 5642)
October 27, 2026
Community Outreach: The design phase of this project is not expected to adversely impact any neighboring residences. Public Outreach will be performed during subsequent phases of the project, before and during construction activities.
This project meets City Council's Top Ten Priority #9, “Public Works Infrastructure & Sustainability.”
CIP PROJECT PRIORITY (as outlined in FY 2025-2026 and FY 2026-2027 CIP Program Budget)
Priority Two – Necessary, but not essential, and there could be consequences if deferred.
LEVINE ACT (California Government Code § 84308):
This item is subject to the Levine Act. City Councilmembers who have received a campaign contribution of more than $500 (aggregated) within the preceding 12 months from a party or their agent/representative, or a financially-interested participant involved in this proceeding may do either of the following: (1) disclose the contribution on the record and recuse themselves from this proceeding; or if applicable (2) return the portion of the contribution that exceeds $500 within 30 days from the time the official knew or should have known about the contribution, and participate in the proceeding.
All parties and their agents/representatives must disclose on the record of this proceeding any aggregated contribution of more than $500 made to any Councilmember within the preceding 12 months. Councilmembers are prohibited from accepting, soliciting, or directing a campaign contribution of more than $500 (aggregated) from a party, their agent/representative, or a financially-interested participant during a proceeding and for 12 months following the date a final decision is made. In addition, a party, their agent/representative, or a financially-interested participant is prohibited from contributing more than $500 (aggregated) to a Councilmember during a proceeding and for 12 months following the date a final decision is made. The completed Levine Act documents for MNS are included as Exhibit C-3 in Attachment #2.
COUNCIL GOAL COMPLIANCE:
Meets the following City Council goals:
C. Operate City government in a fiscally and managerially responsible and prudent manner to ensure that the City of Thousand Oaks remains one of California's most desirable places to live, work, visit, recreate, and raise a family.
Water Mainline Replacement Project (CI 5642)
October 27, 2026
F. Provide and enhance essential infrastructure to ensure that the goals and policies of the Thousand Oaks General Plan are carried out and the City retains its role and reputation as a leader in protecting the environment and preserving limited natural resources.
PREPARED BY: Clark Stanphill, Associate Engineer
Attachments:
Attachment #1 – Vicinity and Location Maps
Attachment #2 – Third Amendment to Contract No. 14134-2025 with MNS DPW: 850-20\ev\Council\2026\10272026\CI 5642\Water Mainline Replacement Project staff report.docx