TO: Andrew P. Powers, City Manager
FROM: Nader Heydari, Public Works Director
DATE: November 10, 2026
SUBJECT: Westlake Boulevard Landscape Improvements (CI 5652) RECOMMENDATION:

1. Approve the project design, plans, specifications, and Addenda No. 1 through No. 3 for construction of the Westlake Boulevard Landscape Improvements (CI 5652).

2. Award construction contract for the Westlake Boulevard Landscape Improvements (CI 5652) to Marina Landscape, Inc. of Orange, CA, in the amount of $6,435,466.41, plus a contingency of $450,000.00.

3. Approve Second Amendment to Professional Services Contract No. 14069- 2025 with D&D Engineering, Inc. (D&D) of North Hollywood, CA, for Construction Support Services for the Westlake Boulevard Landscape Improvements (CI 5652) in the amount of $157,432.00, for a revised not-to-exceed amount of $655,787.00 and extend the term of the agreement to December 31, 2027.

4. Approve budget appropriation in FY 2026-27 in the amount of $3,722,181 from A/C #142-0000-311-1000 (Landscape Fund - Fund Balance) to A/C #142-5310- 632-8300 (Landscape Fund - Improvements Other Than Buildings, CI 5652).

5. Authorize expenditure in the amount of $7,042,898.41 ($6,435,466.41 construction contract, $450,000.00 construction contract contingency, and $157,432.00 construction support services), from A/C #142-5310-632-8300 (Landscape Fund - Improvements Other Than Buildings, CI 5652).

6. Delegate authority to the City Engineer to approve changes in the design, plans, specifications, and working details of the project on work directives and change orders up to the project-approved contingency amount.

7. Find that the Project is Categorically Exempt from the California Environmental Quality Act (CEQA) pursuant to 14 CCR 15301(a), 15301(h), and 15304.

Westlake Boulevard Landscape Improvements (CI 5652)
November 10, 2026

Page 2 ends

LEVINE ACT ITEM: Yes
FINANCIAL IMPACT:
$3,722,181 Increase to Adopted FY 2026-27 Landscape Fund Budget. $3,722,181 increase to the Adopted FY 2026-27 Landscape Fund Budget is requested. $3,375,718 is available in carryover in the Landscape Fund Budget for CI 5652, including $55,000 in previously approved consultant extra services and City-furnished supplies and services. Total project cost for CI 5652 is estimated to be $7,596,253.41.

BACKGROUND:

In 2017, the City adopted the Forestry Master Plan (FMP), which included comprehensive street tree and understory planting palettes focused on water conservation, sustainability, and community input. In 2019, the City constructed five demonstration sites to provide visual examples of the new plant palettes identified in the FMP and closely monitored and resolved the plants’ maintenance and establishment challenges in anticipation of citywide landscape improvement projects.

The proposed project will retrofit approximately 158,000 square feet of landscaping in the center medians along Westlake Boulevard between Thousand Oaks Boulevard and Allyson Street (Attachment #1), including the median island on Valley Springs at Westlake Boulevard. The medians within the project limit currently contain mostly dead and dying ornamental turf, non-native trees, and concrete curbs and gutters that do not meet current City standards. The existing turf is classified as non-functional turf and may no longer be irrigated under current state law.

On August 26, 2025, City Council approved a Professional Services Agreement with D&D for the Westlake Boulevard Landscape Improvements Project (CI 5652).

The agreement included engineering, landscape architecture design, and bid support services in a not-to-exceed amount of $498,355, plus $50,000 for extra services.

The project design, prepared by D&D, supports the City’s sustainability goals by incorporating low-water-use landscape infrastructure and plantings aligned with recommendations outlined in the FMP, including new high-efficiency irrigation systems and California-friendly, drought-resistant plant materials and trees. The project also provides for replacement of all existing curbs and gutters along significant portions of the medians in order to match City standards.

Westlake Boulevard Landscape Improvements (CI 5652)
November 10, 2026

Page 3 ends

The project includes planting 71 new oak trees and approximately 9,000 new shrubs of varying sizes within the medians along project limits on Westlake Boulevard. Based on the project arborist’s evaluation, 88 oak trees will be protected in place while three oak trees that are exhibiting extensive disease are proposed for removal. This project will retain 123 non-native trees but remove 129 non-native trees of undesirable species that are not suitable for long-term placement in medians and/or not approved trees in the City’s FMP such as American Sweetgum, Eucalyptus, and Callery Pear.

DISCUSSION/ANALYSIS:

On August 25, 2026, City Council authorized staff to advertise the Westlake Boulevard Landscape Improvements Project (CI 5652) for construction bids. On September 4, 2026, the Notice Inviting Bids was published in the Acorn newspaper and was posted on the City’s OpenGov procurement site. Five bids were received and publicly opened on October 14, 2026. The bid results are as follows:

Bidder Bid as
Submitted
*Revised Bid

1. Marina Landscape, Inc. Orange, CA $ 6,435,866.41 $ 6,435,466.41

2. American Landscape, Inc. Canoga
Park, CA
$ 6,637,174.90 $ 6,637,174.90

3. Toro Enterprises, Inc. Oxnard, CA $ 7,138,794.85 $ 6,967,100.26

4. Environmental Construction Inc.,
Woodland Hills, CA
$ 8,441,679.52 $ 8,522,683.12

5. Ardalan Construction Company, Inc.,
Thousand Oaks, CA
$ 9,961,251.52 $ 9,965,903.46
*All bids submitted, with the exception of American Landscape’s, contained mathematical errors. The bids were revised based on the submitted unit prices.

The bid package submitted by Marina Landscape, Inc., the apparent lowest bidder, in the amount of $6,435,866.41 has been reviewed and found to be in order with the exception of a mathematical error, which has been corrected to a new total of $6,435,466.41. The bid is approximately 14 percent lower than the engineer’s estimate of $7,500,000.

A bid protest was filed with the City by American Landscape on October 23, 2026; however, after review by staff, the protest was found to be immaterial and was therefore rejected on October 26, 2026, pursuant to Thousand Oaks Municipal Code Section 3-10.310(d). Staff recommends the award of the construction contract to the lowest responsive bidder, Marina Landscape, Inc., for the bid amount of $6,435,466.41.

Westlake Boulevard Landscape Improvements (CI 5652)
November 10, 2026

Page 4 ends

Engineering Support During Construction
D&D is the project engineer of record and will provide design support services during the construction of the project. These support services will include responding to requests for information, reviewing material submittals, reviewing irrigation layout, arborist and bird nesting services, audit of completed irrigation system, preparation of final project punch list, and preparation of record drawings upon completion. The services will also include Storm Water Pollution Prevention Plan (SWPPP) inspection and field observations throughout the construction period. Providing engineering support services during construction was part of the qualification-based selection process outlined in the original Request For Proposals/Qualifications (RFP/Q). Staff recommends approval of the Second Amendment to Contract No. 14069-2025 with D&D in the amount of $157,432.00 (Attachment #2) for a revised not-to-exceed amount of $655,787.00, and an agreement term extension to December 31, 2027.

The estimated overall project cost breakdown is as follows:

Design & Engineering (previous action) $498,355.00
Design Extra Services (previous action) $50,000.00
City Furnished Supplies and Services (previous action) $5,000.00 Engineering Support Services During Construction (this action) $157,432.00 Construction Cost (this action) $6,435,466.41
Construction Contingency (this action) $450,000.00
Total Estimated Costs $ 7,596,253.41
The current estimated project cost exceeds the original amount included in the 2025–27 CIP Program Budget primarily due to the addition of curb and gutter replacement along the medians, as well as recent increases in labor and material costs. SoCal Water Smart offers a Turf Replacement Program that provides a rebate of $3 per square foot for replacing existing turf with drought-tolerant landscaping. This project will replace approximately 158,000 square feet of turf with drought-tolerant landscaping, including bioswales, making the project eligible for an estimated rebate of $474,000. The program requires the project to be constructed within 180 days of application approval. Due to this time limitation, staff plans to apply for the rebate closer to the anticipated construction date.

The estimated project timeline is as follows:

Construction Start December 2026
Construction Completion July 2027
Completion of 90-day Plant Establishment Period October 2027 Westlake Boulevard Landscape Improvements (CI 5652)
November 10, 2026

Page 5 ends

The project design, specifications, and Addenda No.1 through No. 3 are available for review by request to the Public Works Department by e-mail at [email protected] or by phone at (805) 449-2400.

This project is categorically exempt from the CEQA pursuant to 14 CCR Section 15304 (minor alteration of existing topographic features for grading within the landscaped median along Westlake Boulevard), as well as Section 15301(a) (alteration of existing plumbing and electrical for the irrigation system), and Section 15301(h) (maintenance of existing landscaping within the median area).

Community Outreach: Staff has established a public outreach plan for the project, with a particular focus on the residents located adjacent to the project as well as the general public. An initial communication letter has already been sent to all local Homeowners Associations (HOAs), and direct mailers will be sent to nearby residents soon. A dedicated project website has been created at www.toaks.gov/wlblvdlandscape where updated project information and public outreach will continue to be provided throughout the design and construction phases of the project. Various communication tools and strategies, including press releases, website updates, and social media posts, will continue to be utilized to inform the public and receive feedback.

This project meets City Council’s Top Ten Priority #9 “Public Works Infrastructure & Sustainability”.

CIP PROJECT PRIORITY (as outlined in FY 2025-26 and FY 2026-27 CIP Program Budget)
Priority Two – Necessary, but not essential, and there could be consequences if deferred.

LEVINE ACT (California Government Code § 84308):

This item is subject to the Levine Act. City Councilmembers who have received a campaign contribution of more than $500 (aggregated) within the preceding 12 months from a party or their agent/representative, or a financially-interested participant involved in this proceeding may do either of the following: (1) disclose the contribution on the record and recuse themselves from this proceeding; or if applicable (2) return the portion of the contribution that exceeds $500 within 30 days from the time the official knew or should have known about the contribution, and participate in the proceeding.

Westlake Boulevard Landscape Improvements (CI 5652)
November 10, 2026

Page 6 ends

All parties and their agents/representatives must disclose on the record of this proceeding any aggregated contribution of more than $500 made to any Councilmember within the preceding 12 months. Councilmembers are prohibited from accepting, soliciting, or directing a campaign contribution of more than $500 (aggregated) from a party, their agent/representative, or a financially-interested participant during a proceeding and for 12 months following the date a final decision is made. In addition, a party, their agent/representative, or a financially-interested participant is prohibited from contributing more than $500 (aggregated) to a Councilmember during a proceeding and for 12 months following the date a final decision is made. The completed Levine Act form for D&D is included in the Agreement (Attachment #2).

COUNCIL GOAL COMPLIANCE:

Meets the following City Council goals:

C. Operate City government in a fiscally and managerially responsible and prudent manner to ensure that the City of Thousand Oaks remains one of California's most desirable places to live, work, visit, recreate, and raise a family.

F. Provide and enhance essential infrastructure to ensure that the goals and policies of the Thousand Oaks General Plan are carried out and the City retains its role and reputation as a leader in protecting the environment and preserving limited natural resources.

PREPARED BY: Mario Mazed, Engineering Assistant
Attachments:

Attachment #1 – Vicinity and Location Maps
Attachment #2 – Second Amendment to Contract No. 14069-2025 with D&D
Documents Provided Under Separate Cover:
#1 – Project Plans, Specifications and Addendum No. 1 thru No. 3 DPW: 850-20\ev\Council\2026\111026\CI5652\Westlake Blvd Landscape Improvements staff report.docx