From: Alvin Papa, Public Works Director
By: Brenda Moun, Engineering Manager | [email protected] Subject: Public Works – Award a Consulting Services Agreement for the Design of Miscellaneous Water Main Replacement, I-153 (Del Amo Blvd and Crenshaw Blvd).
Expenditure: $379,000 (Non-General Fund).
RECOMMENDATION
Recommendation of the Public Works Director that City Council award a consulting services agreement to Tetra Tech, Inc. of Irvine, CA (RFP B2026-04), in the amount of $379,000, for engineering design services for the Miscellaneous Water Main Replacement, I-153 (Del Amo Blvd and Crenshaw Blvd), for a two-year (2) period beginning September 15, 2026 and ending September 14, 2028.
FUNDING
Funding is available from the Miscellaneous Water Main Replacement, I-153, Water Capital Project Fund.
DISCUSSION
Miscellaneous Water Main Replacement, I-153 (“I-153 Project”) is an annual project to replace aging cast iron water mains with ductile iron water mains. Project locations are selected based on water main break frequency. This project would replace the existing cast iron water mains and increase the size of the mains to meet current demands on Crenshaw Blvd from 190th Street to Del Amo Boulevard, and on Del Amo Boulevard from Crenshaw Boulevard to Western Avenue.
On April 1, 2026, a Request for Proposals (RFP) for engineering design services for the I-153 Project was issued. Five proposals were received by May 15, 2026. The RFP included defined, weighted evaluation criteria. Each proposal was independently reviewed and evaluated by three staff members. The individual scores were averaged to determine the final rankings, which were posted on the PlanetBids website at least two weeks prior to tonight’s Council meeting. All participating vendors were notified of the results.
1 City Council
September 15, 2026
SCORING
AVERAGE SCORE
CRITERIA MAX
POINTS Ardurra BKF CWE SA
Associates
Tetra
Tech
Understanding of the
project and scope of
work; completeness of
RFP
25 25 25 23 25 25
Qualifications of
proposed project team 20 19 19 19 13 18
Relevant projects of
proposed project team
members
15 13 13 14 13 15
Firm's qualifications and
experience with similar
projects
10 8 6 8 8 9
Project Schedule 10 8 9 9 8 9
Cost and Cost
Effectiveness 20 6 0 13 20 12
Total Points 100 79 72 86 87 88
The table below summarizes the final ranking of each vendor, including their location, evaluation score, and proposed fee:
RANKING
RANK VENDOR NAME CITY STATE SCORE PROPOSED FEE
1 Tetra Tech, Inc. Irvine CA 88 $379,000.00
2 SA Associates Arcadia CA 87 $359,000.00
3 CWE Fullerton CA 86 $369,263.63
4 Ardurra Group, Inc. Torrance CA 79 $500,265.00
5 BKF Engineers Newport Beach CA 72 $736,844.00
Upon completion of the proposal review process, it was determined that Tetra Tech, Inc. of Irvine, CA was the most qualified for the project. Their firm's qualifications and extensive experience with similar projects, combined with an efficient project schedule and an appropriate level of staff effort, demonstrate their ability to provide engineering design services that meet the requirements of the RFP and the City's standards. Accordingly, the Public Works Director recommends approval of a 2 City Council
September 15, 2026
consulting services agreement with Tetra Tech, Inc. in the amount of $379,000. Design is expected to be completed in fall 2028.
ATTACHMENTS
1. Location Map
2. Consulting Services Agreement
3 190TH ST
DEL AMO BLVD
CRENSHAW BLVD
WESTERN AVE
VAN NESS AVE
VAN NESS AVE
SAN DIEGO FWY
´
MISCELLANEOUS WATER MAIN REPLACEMENT, I-153
Crenshaw Blvd from 190th St to Del Amo Blvd and
Del Amo Blvd from Crenshaw Blvd to Western Ave
ATTACHMENT 1
4 ATTACHMENT 1
ATTACHMENT 2
5 ATTACHMENT 2
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
28 29
30 31
32 33
34 35
36 37
38 39
40 41
42 43
44 45
46 47
48 49
50 51
52 53
54 55
56 57
58 59
60 61
62 63
64 65
66 67
68 69
70 71
72 73
74 75
76 77
78 79
80 81
82 83