Item No. Bid Item Quantity Unit Unit Price Total
ABB Chargers/Dispensers
1 150kW ABB Chargers 8 EA $255,000 $2,040,000
2 Level 3 PCS/Dispensers 16 LS $120,000 $1,920,000
3 Charging Dispenser Foundation (18-inc diameter x 3 feet deep) 16 EA $15,000 $240,000 4 3/4-Inch Conduit for 120V Power Cable (LDP3 -Dispensers 1-18) 1,705 LF $84 $143,220 5 Combined Charger Foundation (7 ft x 24 ft x 1.5ft) 1 LS $23,000 $23,000 $4,366,220
Misc Civil Work
6 Extend Concrete Bus Parking 1 LS $50,000 $50,000
7 Median Island (Electrical Equipment & Transformer) 1 LS $400,000 $400,000 8 Median Island Charging Stations 1 LS $100,000 $100,000 9 BEB Lighting 2 EA $50,000 $100,000
$650,000
$5,016,220
Contingency @10% $501,622
TOTAL with Contingency $5,518,000
25% Local
Match $1,379,500
TOTAL 2026 CIP REQUEST $4,138,500
The Engineer has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known.
City of Union City
Union City Transit Battery Electic Bus (BEB) Charging Infrastructure, City Project No. 22-11 Engineer's Opinion of Probable Construction Costs for AlaCTC 2026 CIP Prepared October 16, 2024
SUBTOTAL
Preliminary Design
No Design Completed
Preliminary Design Final Design