UNION CITY TRANSIT BATTERY ELECTRIC BUS (BEB) CHARGING INFRASTRUCTURE, CITY PROJECT NO. 22-11
PROPOSED CONSTRUCTION SCHEDULE
October 2024
EQUIPMENT SITE CONSTRUCTION
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB BEBs on Production
Line
Charger Lead Time up to 36 weeks
Switchboard Lead Time up to 52 weeks
Transformer Lead Time up to 52 weeks
2025 2026
BEB
Commissioning
BEB Training
Target Operational Dates:
BEB Delivery 11/17 + 11/24
CONDUIT FROM CHARGER
ISLAND TO DISPENSERS
TRENCHING
ISLAND CONDUIT
SET SWITCHBOARD + PANELS
+ STEPDOWN TRANSFORMER
POUR CONCRETE FOR ISLAND
+ DISPENSERS
PG&E TO THE METER
SET CHARGERS + DISPENSERS
LIGHT POLES
CONNECT EQUIPMENT + PULL
CABLE
BOLLARDS
COMMISSION
CHARGERS
CLOSE-OUT
ARRIVAL OF EV FLEET