Quarry Lakes Parkway Update
Discussion of 1986 Measure B
Allocation Request and
Programming-Allocation of RM3
Dumbarton Funds
Alameda CTC QLP Funding Update and MTC RM3 Request
Tuesday, August 12,2025 at 2:00 PM (Alameda CTC) and
Thursday, September 4, 2025 at 4:30 PM (MTC)
2 PMO-Union City QLP: AGENDA
1) Introductions & Purpose
2) Segment 1 Design – Allocation, PFA and Usable Segment 3) Segment 2 Design – Design Status Update and Usable
Segment
4) RM3 Actions- Status and Scope
5) Next Steps- Commission Actions
• Request for Allocation of 1986MB for Final Design of Phase 1 (Usable Segment) • Request for Programming and Allocation of RM3 Dumbarton Funds 3 PMO-Union City QLP – Intro and Purpose
PURPOSE OF MEETING:
• Request for Allocation of 1986MB for Final Design of
Phase 1 (Usable Segment)
• Request for Programming and Allocation of RM3
Dumbarton Funds (Mitigation, Ph 1 and Ph 2
Construction)
4 Quarry Lakes Parkway Update
3 5
PMO-Union City QLP – Segment 1 Design
2.01-Allocation Request of 1986 MB Funds (July 2025)
Request for $2,578,000 for Final PS&E and Other Misc for bid package Final PS&E
PFA #2 included
$2.373 M
Amendment
request
$2.578 M
TOTAL
$4.951 M
6 PMO-Union City QLP – Segment 1 Design
2.02 Scope of Initial Usable Segment for Construction
7 PMO-Union City QLP – Segment 1 Design
2.02 Scope of Initial Usable Segment for Construction
▪ Construct QLP four-lane road from 7th St – Mission Blvd ▪ Realign 7th Street at Corp Yard to align with Chesapeake ▪ Create new QLP/7th and QLP/Mission Blvd (SR 238)
▪ Implement Complete Streets (Multi-Use Trail and Bike Lanes ▪ Modify lighting and landscaping
▪ Create new Corp Yard parking & modify dog park access ▪ Realign existing Line M Open Channel and Box
▪ Relocate existing Utilities and roadway drainage
▪ Relocate & Reconstruct Corp Yard Security Wall
8 PMO-Union City QLP – Segment 1 Design
2.02 Scope of Initial Usable Segment for Construction
Major Corp Yard Impacts (Maintain 24-hour Operations)
Need to Temporary
Relocate all Transit Fleet:
1) UC Transit Fleet (Exist
Fixed Route Buses
(CNG), Paratransit and
FLEA buses
2) Dumbarton Express
Fleet
3) New 14 Fixed Route
BEB Fleet to arrive
Dec. 2025
4) Construct UC Fleet
Electrification Project
(by mid-2026)
9 PMO-Union City QLP – Segment 1 Design
2.02 Scope of Initial Usable Segment for Construction
Proposed Line M Open Channel Realignment
Right of Way Impacts
• Need to trade
property Alameda
County
• Need PG&E
approval for work
within Transmission
Easement
10 PMO-Union City QLP – Segment 1 Design
2.02 Scope of Initial Usable Segment for Construction
▪ Construct Line M Overflow Pipe from Line M Channel-ANR 11 PMO-Union City QLP – Segment 2 Design
3.02 Design Status
▪ City Council to approve Consultant AM#4 for QLP, Ph 2 (PS&E) ▪ Reviewing 65% Review Comments
▪ Prepared Tentative Parcel Map and Map Approval in Sept 2025 ▪ Met with PG&E
▪ Meeting with Developer
▪ Enter into Initial CSA with Oberling Environmental
▪ Coordinated with RWQCB from March – Aug 2025 (6 months) 12 PMO-Union City QLP – Segment 2 Design
3.02 Design Status – Environmental Mitigation Update
• RWQCB defined the
existing Line M Detention
Basin as Seasonal Pond
(“Waters of the State)
• Requires 3:1 Mitigation
Ratio
• Option 2 Mitigation - $30
million
• Union City did not agree
• RM3 Request, $20 million
13 PMO-Union City QLP – Segment 2 Design
3.02 Design Status – Environmental Mitigation Update
• City constructed the Line M
Detention Basin in 2006 and
expected Route 84 construction
by 2009
• Discussed Line M Overflow will
add stormwater to OAC
(Relocating basin to OAC)
• Provided RWQCB with Project
History and Maintenance Memo
• RWQCB concurred on Option 1
Mitigation - $13.0 million on Aug.
4, 2025 (last Monday)
• $17.0 million SAVINGS
14 PMO-Union City QLP – Segment 2 Design
3.02 Scope of Initial Usable Segment for Construction
▪ Construct QLP four-lane road from OAC - ANR
▪ Reconstruct Quarry Lakes Drive (OLD) from Isherwood- QLP ▪ Create new QLP/QLD and QLP/ANR intersections
▪ Modify ANR from Niles Bridge to existing Osprey
▪ Implement Complete Streets (Multi-Use Trail and Bike Lanes) ▪ Modify lighting and landscaping
▪ Create water quality treatment basin for roadway drainage ▪ Relocate existing Utilities and add roadway drainage
▪ Modify access to Arroyo Park
15 PMO-Union City QLP – Segment 2 Design
3.02 Scope of Initial Usable Segment for Construction
▪ Construct Line M Overflow Pipe from ANR to OAC
16 PMO-Union City QLP – RM3 Actions
4.01 Status of RM3 Programming/Allocation
Submitted RM3 Request to MTC in July 2025
▪ Mitigation $20.0 million
▪ QLP, Segment (Phase) 1 CON $ 1.5 million
▪ QLP, Segment (Phase) 2 CON $ 3.5 million
$25.0 Million
Schedule MTC Meeting next week
17 PMO-Union City QLP – Next Steps
Request for Programming of RM3 Funds Options
Modify RM3 Request to MTC (Resubmitted late Aug 2025)
▪ Mitigation (Per RWQCB concur) $13.000 million
▪ QLP, Segment (Phase) 1 PS&E $ 2.578 million
▪ QLP, Segment (Phase) 1A CON $ 1.000 million
▪ QLP, Segment (Phase) 2 CON $ 8.422 million
$25.000 Million
Commission Action- Program RM3 Funds Only for Mitigation, CON Phase of Segment 1A (Temp Bus Area) and CON Phase of Segment
2. Hope to expedite LATIP deposit. No 1986MB approval action now. 18 PMO-Union City QLP – RM3 Actions
4.02 Scope for Improvements for Usable Segments
Mitigation (Spring 2026)
Off Site Mitigation (Oberling Environmental Site)
QLP, Segment (Phase) 1 Final PS&E (Nov. 2025- Jan 2027) Modify the 65% PS&E and coordinate realignment and right of way exchange of the AC Flood Control Line M Channel Line accommodate QLP, Segment (Phase) 1A CON (Spring 2026)
Construct Off-Site Location to relocate all transit fleet (UC and DBX) to accommodate QLP, Phase 1 Construction
QLP, Segment (Phase) 2 CON (Summer 2026)
Construct Line M Overflow Pipe and Other Utilities
19 PMO-Union City QLP – Next Step to check with MTC
1) AlaCTC Commission Action- Approve and concur
Union City’s RM3 DB Allocation Request $25 million
for Quarry Lakes Parkway (October 6th PPC Monday &
October 23rd Commission Meetings)
2) MTC Commission Action- Approve and concur
Union City’s RM3 DB Allocation Request $25 million
for Quarry Lakes Parkway (November Meetings)
20 Quarry Lakes Parkway –Transportation Funds
Dedicated Transportation Funds Regional
Sources
Amount
AlaCTC 1986 Measure B Funds County $65,500,000
AlaCTC 2005 CMA-TIP County $14,300,000
Caltrans Route 84 LATIP Funds
(QLP, Phase 2 Development Site)
State $41,814,000
AlaCTC 2014 Measure BB (TEP 21-
Dumbarton)
County $40,000,000
AlaCTC 2014 Measure BB (TEP 22-
Intermodal Station)
County $75,000,000
MTC RM3, Dumbarton Corridor
Funds
Bay Area $25,000,000
Total Funds $261,614,000
21 Quarry Lakes Parkway, Phase 2
Caltrans Property (LATIP Revenue $86 million)
Quarry Lakes Drive
Caltrans
Parcel
Caltrans Parcel
Approximate ROW Quarry Lakes Parkway / New Quarry Lakes Drive 22 PMO-Union City QLP – Next Steps
23 Open Discussion