SUMMARY OF CITY COUNCIL ACTIONS FOR FUNDING (2018-2025) RESO # DATE RESOLUTION ACTION
5374-18 8/14/2018
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY TO APPROVE
FUNDING AGREEMENT BETWEEN ALAMEDA COUNTY TRANSPORTATION COMISSION AND THE CITY OF UNION CITY FOR I-880 TO SR 238 (MISSION BLVD) EAST WEST CONNECTOR; APPROVE TWO AGREEMENTS FOR PRELIMINARY ENGINEERING
SERVICES WITH UNION PACIFIC RAILROAD IN CONJUNCTION WITH SEGMENT C OF THE EAST WEST CONNECTOR IN THE AMOUNT NOT TO EXCEED $100,000 EACH;
APPROVE DESIGN AGREEMENT BETWEEN CITY OF UNION CITY AND SAN FANCISCO
BAY AREA RAPID TRANSIT FOR THE CONSTRUCTION OF SEGMENT C OF THE EAST WEST CONNECTOR PROJECT IN THE AMOUNT NOT TO EXCEED $605,000; APPROVE
CONSULTING AGREEMENT BETWEEN THE CITY OF UNION CITY AND TYLIN FOR VALUE ENGINNERING SERVICES FOR THE QUA CITY PROJECT 18-04, IN THE AMOUNT OF $30,000; AND APPROPRIATE $2,500,000 FROM THE CAPITAL PROJECTS FUND 4100 TO CITY PROJECT 18-04
5504-19 7/9/2019
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY
DECLARING A PUBLIC PURPOSE AND AUTHORIZING THE CITY MANAGER TO
NEGOTIATE AND EXECUTE A PURCHASE AND SALE AGREEMENT WITH THE
CALIFORNIA DEPARTMENT OF TRANSPORTATION FOR THE PURCHASE OF CERTAIN EXCESS ROUTE 84 PROPERTIES
5720-21 3/9/2021
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY AUTHORIZING THE
EXECUTION OF A PROJECT FUNDING AGREEMENT AND THE COMMITMENT OF FUNDING FROM THE 2014 MEASURE BB TRANSPORTATION EXPENDITURE PLAN FOR
THE DUMBARTON CORRIDOR AREA TRANSPORTATION IMPROVEMENT PROJECT TO THE QUARRY LAKES PARKWAY PROJECT, CITY PROJECT NO. 18-04 5721-21 3/9/2021
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY AUTHORIZING THE
EXECUTION OF A PROJECT FUNDING AGREEMENT AND THE COMMITMENT OF FUNDING FROM THE 2014 MEASURE BB TRANSPORTATION EXPENDITURE PLAN FOR
THE UNION CITY INTERMODAL STATION PROJECT TO THE QUARRY LAKES PARKWAY PROJECT, CITY PROJECT NO. 18-04
5841-21 10/12/2021
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY ACCEPTING $4.2
MILLION GRANT FROM ALAMEDA COUNTY TRANSPORATION COMMMISSION (ALAMEDA CTC), PROJECT FUNDING AGREEMENT NO. A22-0053 FOR FINAL DESIGN OF PHASES (SEGMENTS) 1 AND 2 FOR QUARRY LAKES PARKWAY (EAST WEST CONNNECTOR) PROJECT, CITY PROJECT NO. 18-04
2025-006 1/14/2025
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 2 TO THE ALAMEDA COUNTY
TRANSPORATION COMMISSION (ALAMEDA CTC) PROJECT FUNDING AGREEMENT (PFA) NO. A22-0053, TO ACCEPT AN ADDITIONAL $801,191, FOR A TOTAL PFA OF $5,001,191, FOR THE FINAL DESIGN OF PHASES (SEGMENTS) 1 AND 2 FOR THE QUARRY LAKES PARKWAY (EAST WEST CONNECTOR) PROJECT, CITY PROJECT NO. 18- 04, AND AMENDING THEFY 2024-2025 CAPITAL PROJECTS FUND BUDGET 2025-007 1/14/2025
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY AUTHORIZING THE
CITY MANAGER TO SUBMIT AN ALLOCATION REQUEST TO THE METROPOLITAN TRANSPORTATION COMMISSION (MTC) FROM THE REGIONAL MEASURE 3
DUMBARTON CORRIDOR IMPROVEMENTS PROGRAM, IN THE AMOUNT OF $3,507,000, AND ACCEPTING ALAMEDA COUNTY TRANSPORTATION COMMISSION’S
DESIGNATION OF THE CITY OF UNION CITY AS IMPLEMENTING AGENCY FOR THE UNION CITY QUARRY LAKES PARKWAY PROJECT, CITY PROJECT NO. 18-04 2025-087 6/24/2025
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 3 TO THE ALAMEDA COUNTY TRANSPORATION COMMMISSION PROJECT FUNDING AGREEMENT NO. A22-0053 TO ACCEPT AN ADDITIONAL $3,995,000, FOR A TOTAL AMOUNT OF $8,996,191, FOR THE FINAL DESIGN OF PHASE (SEGMENT) 2 FOR THE QUARRY LAKES PARKWAY (EAST WEST CONNNECTOR) PROJECT, CITY PROJECT NO. 18-04
2025-097 7/8/2025
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY AUTHORIZING THE
CITY MANAGER TO SUBMIT AN ALLOCATION REQUEST TO THE METROPOLITAN TRANSPORTATION COMMISSION FROM THE REGIONAL MEASURE 3 DUMBARTON
CORRIDOR IMPROVEMENTS PROGRAM AND ACCEPTING ALAMEDA COUNTY TRANSPORTATION COMMISSION’S DESIGNATION OF THE CITY OF UNION CITY AS
IMPLEMENTING AGENCY FOR THE UNION CITY QUARRY LAKES PARKWAY PROJECT, CITY PROJECT NO. 18-04