CERTIFICATE OF COMPLETION
(Sec. 4005 Government Code)
TITLE: CITYWIDE FULL TRASH CAPTURE DEVICE INSTALLATION
PROJECT, CITY PROJECT NO. 25-11
I, MARILOU AYUPAN, Public Works Director of the City of Union City, County of Alameda, State of California, do hereby certify as follows:
a. That the project consisted of the manufacture and installation of Full Trash Capture Devices (FTCDs) within the public right-of-way, consisting of 80 connector pipe screen (CPS) and 7 hanging basket units, to advance the City’s compliance with the 100% trash reduction requirement, as well as other related work indicated and required by the plans and standard specifications. A total of 87 FTCDs were installed, providing full trash capture coverage for applicable public catch basins; and
b. That the contract agreement was awarded by staff on May 30, 2025, in the amount of $133,641; and
c. That the adopted and approved plans and specifications have been changed in the following respects:
CCO # CONTRACT CHANGE DESCRIPTION AMOUNT
Project Total Invoiced $ 114,960.00
1 Fabricate and Install Hanging Basket Units $ 31,584.00 Total Construction Contract Cost to City $ 146,544.00
d. That the work performed has been done in accordance with such plans and specifications.
e. That United Storm Water, Inc., performed the work at a total cost of $146,544, including the above noted contract change description.
f. That the Final retention amount of $7,327.20 will be released after 35 days from the project’s acceptance.
Dated: ___________________________________
MARILOU AYUPAN, P.E.
PUBLIC WORKS DIRECTOR