Cities Index.
Attachment 3 - Cost Estimate, Union City, November 20, 2025

Legislation and Policy Committee
February 2, 2026

Document
Attachment 3 - Cost Estimate, Union City, November 20, 2025
Meeting
February 2, 2026
Body
Legislation and Policy Committee
Original file
71 KB
Text extracted from the city's file for reading and search. Open the original on unioncity.primegov.com. That file is the official record.

Teen Bike Workshop (Larry Orozco Teen Workshop)
Updated 11/20/25
For 25/26 For 26/27 For 27/28 Total
CIP Funding Approved $0 $0 $200,000 $200,000
Rough Order Magnitude (ROM)
Work Description Vendor
Purchase order
No.

Paid to Date Pending
Payments
Estimated Cost to
Complete
Total Cost
by item Notes
Construction
Abatement - Lead LCMs $20,000 $20,000 9/9/25: Eisen proposal + contingency.

Abatement - Asbestos ACMs $0 $0 9/9/25: Included in Eisen proposal.

Exterior Stucco Repair, after
abatement $10,000 $10,000
Exterior Paint, after abatement $20,000 $20,000
Allowane for solid color on the outside. In case it can be done by community or FAC. Cost for proffesional muralized is
ownknown.

Interior Paint $5,000 $5,000 Recommend painting wood ceiling in the garage.

Replace Roof Mastic $3,000 $3,000 Allowance.

ADA - Compliant Asphalt Paving +
Parking Space $50,000 $50,000
Grade site, prepare base, and pave site with asphaltic concrete.

Stripe for parking spaces and traffic control, including disabledaccess parking spaces; walkway from parking spaces to the building entrance. This cost is a
preliminary budget only, which should be validated by
additional
investigation and contractor bid[s].

ADA - Compliant (Walkway)
"Sidewalk" $12,000 $12,000
To Provide a complient walkway from the public way to the main building entrance. Ensure the existing main door meets
requirements for opening, width, threshold, and opening force.

ADA - Doors $7,000 $7,000
Adjust interior doors and frames. Replace if needed to meet width requirements.

ADA - Compliant Restroom $65,000 $65,000
Assuming we only need on restroom, occupancy will not
change. 11/20: ROM updated.

Demolish Lean To (Storage Unit) $30,000 $30,000
Replace All Windows $30,000 $30,000 (6) Windows - Old building, including additional work at frames.

Roof Access - Install Internal ladder $10,000 $10,000
Roof Replacement $75,000 $75,000 Based on Historical Museum Cost HVAC Replacement $9,000 $9,000 Replace gas area heaters.

Water Supply Piping $22,500 $22,500 Re-plumb galvanized piping.

Water Heater Replacement $5,000 $5,000
Electrical Testing - Allowance $15,000 $15,000
Test Main Switchgear, Ground-Fault Testing. Some minor
miniatous cost included. Replacement or upgrading of electrical switchgear not included
Construction OH&P $38,850 $38,850 Overhead and Profit
FF&E Furniture, Fixtures, and Equipment
ITS Infrastructure/Equipment $40,000 $40,000
6/4: Per UC IT, equipment alone could be $25K. Add extra to labor. 6/5: Added $5K for WAPs.

Security - Allowance $20,000 $20,000 6/5: Added line item. Cams Soft Cost
Property Condition Assessment (PCA LLC) NA $9,131 $0 $0 $9,131 7/15: Paid.

Haz Mat Survey
Ninyo &
Moore N/A $3,600 $1,350 $0 $4,950 10/7/25: Updated panding payments.

Haz Mat Monitoring $3,000 $3,000 In case needed.

Haz Mat Floor Sampling & Testing $3,000 $3,000 Scope TBD. Allowance added.

Telecom/Data Services - Allowance $15,000 $15,000
Allowance to get data, phone, and WIFI service to the building.

Electrical, Water, and Security Alarm Service is already in place.

Design/Engineering - Allowance $50,000 $50,000
UC Facilities Support - Allowance $5,000 $5,000
CM Services - Pre Construction FY
24/25
Cumming
Group $9,898 $3,053 $0 $12,951 8/17: Payments updated thru June 2025.

CM Services - Pre Construction FY
25/26 (Cumming Group) $15,000 $15,000 Need funding for 2025/26 efforts. Per Jose, can Joan help? CM Services - Construction
(Cumming Group) $25,000 $25,000
Assumes project will be bid as a single project and not broken out or phased.

Construction Contingency 10% $0 $0 $42,735.0 $42,735
Soft Cost Contingency 10% $0 $0 $11,600 $11,600
Total $22,629 $4,403 $657,685 $684,717
Notes

1. Assuming permit fees will be waived.

← All documents from this meeting