RESOLUTION NO. 2026-XXX
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UNION CITY
AUTHORIZING THE CITY MANAGER TO EXECUTE A CONSULTING
SERVICES AGREEMENT WITH CONSOR NORTH AMERICA, INC., IN
THE AMOUNT OF $260,000, FOR THE CONSTRUCTABILITY REVIEW
AS PART OF THE CONSTRUCTION MANAGEMENT SERVICES FOR
PHASE 2 OF THE QUARRY LAKES PARKWAY PROJECT, CITY
PROJECT NO. 18-04
WHEREAS, the Quarry Lakes Parkway project connecting Fremont and Union City from Mission Boulevard to I-880 was previously sponsored and managed for decades by Caltrans (where it was known as the Route 84 Corridor) and various Alameda County transportation agencies (where it was known as the East West Connector Project), most recently by Alameda County Transportation Commission (Alameda CTC); and WHEREAS, on March 22, 2018, Alameda CTC approved the request from the City of Union City to be the project sponsor of the former East West Connector Project, assuming responsibility for the design, right-of-way certification, and construction, and on February 12, 2019, the City Council adopted Resolution No. 5444-19, which authorized renaming the East West Connector Project to the Quarry Lakes Parkway Project (to reflect the roadway’s updated purpose as a local, multimodal corridor); and WHEREAS, to better manage the Project, the City divided the Project into usable segments or phases that included Phase (Segment) 1: 7th Street Connection (7th Street to Mission Boulevard), Phase (Segment) 2: Gateway Connection (Old Alameda Creek to Alvarado-Niles Road), Phase (Segment) 3: 11th Street Connection (11th Street to 7th Street), Phase (Segment) 4: Alvarado-Niles Connection & Grade Separations (BART and Oakland Subdivision) and Phase (Segment) 5: Paseo Padre Parkway & Bike Trail Connection (Paseo Padre Parkway in Fremont to Old Alameda Creek in Union City); and WHEREAS, the Quarry Lakes Parkway Project, City Project No. 18-04, is funded with 1986 Measure B funds, 2014 Measure BB funds, and other transportation funds administered by Alameda CTC, and most recently with Regional Measure 3 (RM3) Dumbarton Corridor Improvement Program funds administered by the Metropolitan Transportation Commission (MTC), and;
WHEREAS, the City of Union City has accepted over $9.0 million from the Alameda CTC Project Funding Agreement (PFA) No. A22-0053 for the Final Design of the Quarry Lakes Parkway Project, City Project No. 18-04, and over $16.0 million from MTC (see Exhibit A for List of QLP AlaCTC-MTC Funding Actions); and WHEREAS, in early 2022, Mark Thomas & Company, Inc., was selected as the civil engineering firm to lead the Final Design of Quarry Lakes Parkway, Phase 1 and Phase 2, City Project No. 18-04 and has managed the redesign effort of the former East West Connector project with a local multimodal four-lane roadway to better adapt to the planned residential land-use, and to meet local “Complete Street” design criterial for this complex transportation project for the past years (see Exhibit B for List of MTCo Agreements Actions); and
Resolution No. 2026-XXX
Approve CSA with Consor North America for QLP, Phase 2
WHEREAS, on December 22, 2025, the City of Union City released a Request for Proposal (RFP) for Constructability Review (Initial Scope of Work) and Construction Management Services (Future Work) for the Quarry Lakes Parkway, Phase 2 (Old Alameda Creek to Alvarado-Niles Road) Project followed by the issuance of Addendum No. 1, dated January 6, 2026, and Addendum No. 2, dated January 26, 2026 (see Exhibit C); and
WHEREAS, a Pre-Proposal Meeting for interested construction management firms was held on January 15, 2026, at Studio 11 (see Exhibit D); and WHEREAS, on January 29, 2026, the City of Union City received four (4) proposals from Consor North America, Inc., Ghirardelli Associates, CSG Consultants, Inc., and GFT Infrastructure, Inc. Interviews were held on February 26, 2026, with a selection panel consisting of staff from Public Works and the City Manager’s Office and the panel selected Consor North American, Inc. because of the firm’s highly experienced Project Manager/Resident Engineer and inspectors, their thorough project understanding and local knowledge, recently completed similar roadway projects in Union City and Fremont, and favorable reference checks; and
WHEREAS, Consor North America, Inc. will initially perform the constructability review of the Quarry Lakes Parkway, Phase 2, 95% PS&E (Plans, Specifications and Estimate), 100% PS&E Package and Final PS&E Package ready for advertisement as well as assistance with the contract bid package during advertisement period and, upon satisfactory performance, the City may exercise the option to extend the contract for Construction Management Services; and.
WHEREAS, Mark Thomas & Company, Inc., is scheduled to submit the completed 95% PS&E (Plans, Specifications, and Estimate) in late March 2025 for review and comments; and
WHEREAS, the construction of the Quarry Lakes Parkway, Phase 2, is currently estimated at $33.0 million, with the completion of the Final PS&E Package scheduled for August 2026 and advertisement beginning in September 2026, followed by bid opening in late October 2026; and
WHEREAS, the Consulting Services Agreement with Consor North America, Inc., for Construction Management Services for the Constructability Review, in the amount of $260,000, will be funded with $250,000 from the Alameda CTC Project Funding Agreement No. A22-0053 in the Capital Projects Fund (Account Number 410-91804- 54115) and $10,000 from the SB-1 Road Maintenance and Rehabilitation Account (RMRA) Fund (Account Number 251-91804-57115), which were budgeted in the approved Five-Year Capital Improvement Plan (CIP) for Fiscal Year 2025-2026 to Fiscal Year 2029-2030 for the Quarry Lakes Parkway Project, City Project No. 18-04.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Union City hereby authorizes the City Manager to execute a Consulting Services Agreement with Consor North America, Inc., in the amount of $260,000, for the Constructability Review as part of the Construction Management Services for the Quarry Lakes Parkway Project, City Project No. 18-04.
Resolution No. 2026-XXX
Approve CSA with Consor North America for QLP, Phase 2
PASSED, APPROVED, AND ADOPTED by the City Council of the City of Union City at a regular meeting held on March 24, 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
APPROVED:
GARY SINGH
Mayor
ATTESTED: APPROVED AS TO FORM:
THAI NAM N. PHAM
City Clerk
KRISTOPHER J. KOKOTAYLO
City Attorney
Attachments:
1. Exhibit A – List of QLP AlaCTC-MTC Funding Actions
2. Exhibit B – List of MTCo Agreements Actions
3. Exhibit C – CM RFP and Addendums 1 and 2
4. Exhibit D – Pre-Proposal Meeting Attendance Sheet and Presentation