EXHIBIT B

AUTHORIZED FACILITIES AND SERVICES

CITY OF UNION CITY
COMMUNITY FACILITIES DISTRICT NO. 2026-1
(STATION EAST FACILITIES AND SERVICES)

AUTHORIZED FACILITIES
The City of Union City Community Facilities District No. 2026-1 (Station East Facilities and Services), Improvement Area No. 1, and any Future Improvement Area (collectively, the “CFD”) is authorized to finance all or a portion of the costs of the facilities permitted under the Mello-Roos Community Facilities Act of 1982 (“Act”) and that are provided in connection with the development of the property located in the CFD, including, but not limited to, those described below.

The CFD is authorized to finance the purchase, construction, expansion, improvement, or rehabilitation of any real or other tangible property with an estimated useful life of five years or longer, together with the planning and design work that is directly related to the purchase, construction, expansion, or rehabilitation of any real or tangible property (collectively, the “Facilities”), including, but not be limited to, roadway and transportation facilities, water, sewer and storm drain facilities, parks, landscape, and open space, and school facilities. Examples of Facilities are described below.

Authorized Facilities include any facilities authorized by the Act that are financed in whole or in part by development impact fees and/or mitigation payments levied or collected in connection with development of the property, whether by the City or any other local agency. By way of example and not limitation, authorized facilities include, but are not limited to, facilities authorized by the Act to be funded by the following:
• City of Union City
• Union Sanitary Sewer District
• Alameda County Water District
• New Haven Unified School District
Roadway and Transportation Improvements
Authorized facilities include any and all on-site and off-site publicly-owned roadway and transportation facilities required to meet the needs of development within the CFD.

Eligible costs of these facilities include, but are not limited to, the following to the extent that they are capital costs of the facilities: Acquisition of land and easements; design; project management; payment and performance bond premiums; clearing, grubbing, and demolition; grading, soil import/export; paving (including slurry seal), and decorative/enhanced pavement concrete and/or pavers; bridge crossings and culverts; joint trenches, underground utilities and undergrounding of existing utilities; dry utilities and appurtenances; curbs, gutters, sidewalks, bike trails (including onsite and off-site); enhanced fencing, and access ramps; street lights; roundabouts; intersections, signalization, and traffic signal control systems; bus turnouts; signs and striping; winterization and erosion control; median and landscape corridor landscaping and irrigation; bus shelters; retaining walls; masonry walls; implementation and maintenance of Stormwater Pollution Prevention Plan (SWPPP) measures; traffic control and agency fees required as a condition of development within the boundaries of the CFD; and other improvements related thereto where required.

Parks, Landscaping and Open Space
Authorized facilities include any and all on-site and off-site parks, landscaping and open space designed to meet the needs of development within the CFD. Eligible costs of these facilities include, but are not limited to, the following to the extent that they are capital costs of the facilities: Acquisition of land and easements; design; project management; grading; implementation and maintenance of SWPPP measures; potable water storage, groundwater wells, storage tanks, distribution facilities including pipelines and appurtenances and irrigation facilities, gate valves, flow meters, booster pump pressurization system, hardscape improvements (pavement), fencing, lighting at water storage tank sites, booster pumping stations, and groundwater wells; and other improvements related thereto.

Drainage System Improvements
Authorized facilities include any and all on-site and off-site drainage facilities required to meet the storage and conveyance needs of development within the CFD. Eligible costs of these facilities include, but are not limited to, the following to the extent that they are capital costs of the facilities: Acquisition of land and easements; design; project management; grading; implementation and maintenance of SWPPP measures; mains, pipelines and appurtenances; outfalls and water quality measures; temporary drainage facilities; detention/retention basins and drainage pretreatment facilities; drainage ways/channels; pump stations; landscaping and irrigation; stormwater hydromodification (including grading & demolition); access roads, gates, and fencing; striping and signage; and other improvements related thereto where required.

Water System and Irrigation Improvements
Authorized facilities include any and all on-site and off-site potable water system facilities designed to meet the needs of development within the CFD. Eligible costs of these facilities include, but are not limited to, the following to the extent that they are capital costs of the facilities: Acquisition of land and easements; design; project management; grading; implementation and maintenance of SWPPP measures; potable water storage, groundwater wells, storage tanks, distribution facilities including pipelines and appurtenances and irrigation facilities, gate valves, flow meters, booster pump pressurization system, hardscape improvements (pavement), fencing, lighting at water storage tank sites, booster pumping stations, and groundwater wells; and other improvements related thereto.

Recycled Water System Improvements
Authorized facilities include any and all on-site and off-site recycled water system facilities designed to meet the needs of development within the CFD. Eligible costs of these facilities include, but are not limited to, the following to the extent that they are capital costs of the facilities: Acquisition of land and easements; design; project management; grading; implementation and maintenance of SWPPP measures; recycled water storage, treatment and distribution facilities including pipelines and appurtenances, gate valves, storage tanks, flow meters, booster pump pressurization system, hardscape improvements (pavement), fencing, lighting at water storage tank sites, booster pumping stations, and groundwater wells; and other improvements related thereto.

Wastewater System Improvements
Authorized facilities include any and all on-site and off-site publicly-owned facilities required to meet the wastewater conveyance needs of development within the CFD.

Eligible costs of these facilities include, but are not limited to, the following to the extent that they are capital costs of the facilities: Acquisition of land and easements; design; project management; grading; implementation and maintenance of SWPPP measures; pipelines and all appurtenances thereto; manholes; tie-in to existing main line; emergency storage for at lift station sites; force mains; lift stations; odor-control facilities; sewer treatment plant improvements; hardscape improvements (pavement), fencing, lighting at lift station sites; and other improvements related thereto where required.

Other
Any other facilities serving substantially the same purpose as the above-described facilities.

The foregoing description of the type of Facilities eligible to be financed is general in nature and includes any appurtenant work and incidental expenses related to the Facilities. The final nature and location of the facilities will be determined upon the preparation of final plans and specifications for such facilities.

AUTHORIZED SERVICES
The authorized services to be funded by the CFD are the services described in Section 53313 of the Act, including but not limited to performance by City employees or contractors of maintenance and operation activities. Maintenance as used herein includes replacement and the creation and funding of a reserve fund to pay for replacement of facilities. The CFD shall only fund authorized services to the extent that they are in addition to those provided to land within the CFD prior to the creation of the CFD.

Incidental Expenses
Also included as authorized expenditures for the CFD are: (1) CFD bond-related fees and costs, including but not limited to fees of the City, underwriters/placement agents, financial advisors, appraisals, reserve fund balance, capitalized interest, bond counsel, disclosure counsel, special tax consultant, bond and official statement printing and all other incidental expenses; and (2) CFD administrative fees, including fees of the City, the bond trustee/fiscal agent, and the special tax consultant, related to the CFD.