Bid Item No. Description Unit Quantity Unit Price Total Cost Unit Price Total Cost 1 MOBILIZATION LS 1 $5,000.00 $5,000.00 $30,000.00 $30,000.00 2 SITE CLEARING AND DEMOLITION LS 1 $30,000.00 $30,000.00 $1,500.00 $1,500.00 3 TEMPORARY FACILITIES AND CONTROLS LS 1 $3,000.00 $3,000.00 $1,500.00 $1,500.00 4 WATER POLLUTION CONTROL PLAN LS 1 $7,000.00 $7,000.00 $6,000.00 $6,000.00 5 PAINT PAVEMENT MARKING + STRIPING SF 112,700 $0.36 $40,572.00 $0.30 $33,810.00 6 CHAIN-LINK FENCE LF 930 $126.00 $117,180.00 $60.00 $55,800.00 7 PEDESTRIAN GATE EA 6 $1,800.00 $10,800.00 $400.00 $2,400.00 8 VEHICULAR GATE EA 2 $1,900.00 $3,800.00 $600.00 $1,200.00 9 RUBBER WHEEL STOPS EA 11 $180.00 $1,980.00 $220.00 $2,420.00 10 CONEX BOX EA 1 $8,000.00 $8,000.00 $10,000.00 $10,000.00 11 PORTABLE SOLAR-POWERED LIGHT EA 2 $26,850.00 $53,700.00 $35,000.00 $70,000.00 12 PORTABLE SOLAR-POWERED CAMERA EA 3 $58,450.00 $175,350.00 $35,000.00 $105,000.00 13 SIGNAGE LS 1 $2,000.00 $2,000.00 $2,500.00 $2,500.00 $458,382.00 $322,130.00
-50% -6%
Mark Lee and Yong Kay
Inc. DBA Bay
Silicon Valley Paving, Inc. Construction Co.
SUBTOTAL=
% Below the Engineer's Estimate of $305,000
Union City Corporation Yard
Block 6 Interim Transit Facility Project - Bid Summary
Project No. 26-19