NON-DISCRIMINATION
POLICY STATEMENT
The California Department of Transportation, under Title VI of the Civil Rights Act of 1964, ensures “No person in the United States shall, on the ground of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be subjected to discrimination under any program or activity receiving federal financial assistance.”
Caltrans will make every effort to ensure nondiscrimination in all of its services, programs and activities, whether they are federally funded or not, and that services and benefits are fairly distributed to all people, regardless of race, color, or national origin. In addition, Caltrans will facilitate meaningful participation in the transportation planning process in a nondiscriminatory manner.
Related federal statutes, remedies, and state law further those protections to include sex, disability, religion, sexual orientation, and age.
For information or guidance on how to file a complaint, or obtain more information regarding Title VI, please contact the Title VI Branch Manager at (916) 324-8379 or visit the following web page:
https://dot.ca.gov/programs/civil-rights/title-vi .
DECLARACIÓN DE POLÍTICA
DE NO DISCRIMINACIÓN
El Departamento de Transporte de California, bajo el Título VI de la Ley de Derechos Civiles de 1964, asegura que “Ninguna persona en los Estados Unidos, debido a su raza, color u origen nacional, será excluída de participar, ni se le negarán los beneficios, o será objeto de discriminación, en ningún programa o actividad que reciba ayuda financiera federal.” Caltrans hará todos los esfuerzos para asegurar que no exista discriminación en ninguno de sus servicios, programas y actividades, ya sea que reciban fondos del gobierno federal o no, y que los servicios y beneficios sean justamente distribuidos a todas las personas sin importar su raza, color, u origen nacional. Adicionalmente, Caltrans facilitará la participación significativa en el proceso de planeación de los programas de transporte de manera no discriminatoria.
Los estatutos federales relacionados, los remedios, y la ley estatal refuerzan estas protecciones para incluir el sexo, la discapacidad, la religión, la orientación sexual y la edad.
Para información u orientación sobre cómo presentar una queja o para obtener más información relacionada con el Título VI, por favor comuníquese con el Gerente del Título VI al teléfono (916) 324-8379 o visite la siguiente página de Internet: https://dot.ca.gov/programs/civil- rights/title-vi.
I-80 SIX BRIDGES PROJECT VALLEJO
VERTICAL CLEARANCE
Magazine Street Overcrossing to Redwood Street Overcrossing
RE-OPENING OF DUAL BRIDGES
• Georgia Street overcrossing re-
opening this Friday, May 6.
• Tennessee Street overcrossing re-
opening, Friday, May 13.
• Redwood St. overcrossing set to
close on Monday, May 16.
• Both bridges will be open to the
traveling public before the
Redwood St. closure.
INVESTMENTS IN VALLEJO
• Clean CA events to address trash
and beautification projects.
• I-80/SR-29 Bridge Replacement
Project (Completion Spring 2023)
• Caltrans working with city staff on
the improvements of the
approaches.
PROJECT
LOCATION
CONSTRUCTION SEQUENCE
1. Springs Road Overcrossing(Completed
April 2021)
2. Magazine Street Overcrossing
(Completed August 2021)
3. Benicia Road Overcrossing
(Competed Jan. 2022)
4. Georgia Street Overcrossing
(Opening this week)
5. Tennessee Street Overcrossing
(Opening by the end of next week)
6. Redwood Street Overcrossing (Closing
May 16, 2022)
PURPOSE & NEED
PURPOSE
To increase the vertical clearance to the current standard height of 16.5 feet.
NEED
Existing minimum vertical clearance ranges between 14.9 feet to 15.3 feet. This needs to be increased to the current standard height to avoid the bridges from being hit by high load trucks travelling through the I-80 freight corridor.
GEORGIA STREET
OVERCROSSING
TENNESSEE STREET OVERCROSSING
REDWOOD STREET OVERCROSSING
REDWOOD STREET OVERCROSSING
Aerial Photo of Existing Facility
TENTATIVE PROJECT SCHEDULE
Begin Construction May 16, 2022
End Construction October 16, 2022
WORK DESCRIPTION
The steps in elevating the bridges include the following:
• Install temporary supports
• Jack up the superstructure
• Set it to its new permanent supports
• Modify the abutments/bridge approaches to conform to the new height
TEMPORARY
SUPPORTS
Typical Falsework on Either Side of
Span Being Elevated
Erect Temporary Supports Under I-
80 Night-time Lane Closures
JACKING
OPERATION
Typical Falsework on Either Side of
Span Being Elevated
Elevate Span Under Full WB or EB I-
80 Closure (5-hr window)
MODIFY
APPROACH
ROADWAY
Roadway to be
Reconstructed after Bridge
Raising
TRAFFIC MANAGEMENT
Lane Reductions on I-80
One to two lanes of I-80 will be closed in each direction for construction at night as needed to prepare for the elevation of each bridge.
Full Closure (one direction only) on I-80
- I-80 will be completely closed in one direction at a time on consecutive nights to elevate the bridge and then repeated to set the bridge down on the new extended supports.
- Each night’s complete closure will be limited to a 5-hour window between 11 PM to 4 AM.
TRAFFIC MANAGEMENT
Closure of bridge to local traffic
• Redwood Street will be closed on May 16, 2022.
• Detours will be provided, and extensive public outreach will take place in order to advise the public about the project, the schedule, and the detours.
• Shuttle service on a 24/7 basis will also be provided for both pedestrians and bicyclists to navigate the bridge closure.
DETOUR PLAN EB
REDWOOD ST.
• EB Redwood St. shuttle stop
located across from the Shell
Gas Station on Admiral Callahan
Lane near the intersection of
Admiral Callahan Lane and
Redwood Parkway.
• 24-hr shuttle service will be
available for pedestrians and
bicyclists.
• Call: (415) 263-4000
DETOUR PLAN WB
REDWOOD ST.
• WB Redwood St. shuttle
stop next to the Chevron
Gas Station on
Fairgrounds Drive.
• 24-hr shuttle service will
be available for
pedestrians and
bicyclists.
• Call: (415) 263-4000
DETOUR PLAN
I-80 WB/EB
FULL CLOSURE
I-80 SIX BRIDGES
PROJECT OUTREACH
CAMPAIGN
• Redwood Street Overcrossing
mailers sent to businesses and
residents near the project site.
• I-80 Six Bridges Project Informational
Meeting on Wednesday, May 4,
2022, starting at 6:30 PM
• For more information on the I-80 Six
Bridges Project, please visit our
project website:
i80sixbridgesvallejo.com
ASK YOUR QUESTIONS LIVE
Q & A
• Contact:
• Pedro Quintana, Public Information Officer, (510) 867-6028, [email protected]
• Vince Jacala, Public Affairs Branch Chief,
(510) 385-7069, [email protected]
• Bart Ney, Public Affairs Branch Chief, (510) 715-7212
THANK YOU
THIS CONCLUDES OUR PRESENTATION