2441 Broadway Street
Vallejo, CA
FIRM
FOUNDATION
COMMUNITY
HOUSING
WHO ARE WE
Non-Profit Developer with the mission to solve
involuntary homelessness by building high quality,
service enriched housing.
Founded in 2020 with 4 completed projects and 2
projects in construction resulting in over 150 units
We partner with local jurisdictions, community
members and faith based organizations to develop
underutilized land into vital housing projects that save lives.
Fairmont Navigation Center Tiny Homes in Alameda County Since opening in 2021, over 200 individuals have been given the tools they need to heal, thrive and move on to secure, individual housing.
34 Micro Home Community with Wrap Around Services
Proven Approach
We have
a solution
2441 Broadway will provide:
Evidence-based housing intervention, Permanent Supportive Housing for 47 individuals
On-site staff team providing ongoing supportive services.
Long lasting community and safety.
Opportunity to establish stability and receive support needed to interrupt the cycle of homelessness.
Solano County currently has 1,179 people experiencing homelessness* *per HUD Point in Time Count 2022-
new PIT count for 2024 to be
published soon anticipates a higher
number
SUPPORTIVE COMMUNITY + ELEVATED DESIGN
ON-SITE
SUPPORTIVE
SERVICES
Community Members will have access to more than
housing. Supportive Services include:
Classes ranging from financial literacy, parenting
support, and job search strategies.
Housing navigation
Meals
Mental health support
Substance abuse recovery support services
Support with seeking medical care
LOCATION
2442
BROADWAY
DOG PARK VETERAN’S MEMORIAL
PARK & PLAYGROUNDMULTI-FAMILY
APARTMENTS
SINGLE FAMILY RESIDENTIAL
NEIGHBORHOOD
29 HWY - SONOMA BLVD
BUS
STOP
GASFAST FOOD
BUILDING DESIGN
F
27,406 SF Total building squire footage, including:
Primary Building - Four Story, 40 unit elevator bldg with Community Space, Laundry room, and office.
Additional units: 4 back to back “duet” living units alongside outdoor landscaped gathering space. 47 total living units + 1 manager unit.
Units are equiped with a full bathroom, kitchen and living space.
Factory built units, constructed locally at Factory OS with the Carpenters Local 180 on nearby Mare Island
INNOVATIVE CONSTRUCTION
Currently
the project
is 70%
complete
Roofing Complete
Water Resist. Barrier 95% Complete
Unit Windows Complete
Ground flr windows 80% Complete
Underground Utilities 90% Complete
Exterior + Site
Framing Complete in
Common Areas
MEP rough in, Drywall and
storefront installations in
progress
Community Room
Modular units are factory
built and complete on-site,
including finishes and
appliance installations.
Unit Interiors
Community
Asset
Improving quality of lIfe, especially
regarding our community’s health, safety
and stability.
Reducing Blight & Alleviating an
Attractive Nuisance at project
completion
Bringing local jobs: many of the
contractors working on this project are
local to Solano County and the Bay Area
Addressing homelessness
Benefits to the Community Aligned with the goals of Measure P Ready for
Move In
Design &
Entitlements
Begin
Project Milestones
Spring
2022
Sept. 19
2022
Construction
Begins
Modular Unit
Install
complete
Stalled at
70% due to
funding gap
July 6
2023
Sept
2023
Target
Funding
resolution &
Remobilization
June
2024
TCO
Sept
2024
Dec
2024