SERVICES AGREEMENT BETWEEN THE CITY OF VERNON AND CAMFIL POWER

SYSTEMS FOR ENGINEERING AND DESIGN SERVICES FOR GENERATOR

COOLING FILTER HOUSING MODIFICATION

COVER PAGE
Contractor: Camfil Power Systems
Responsible Principal of Contractor: Carl Larochelle, VP Americas Notice Information - Contractor: Camfil Power Systems
3025 Joseph-A. Bombardier
Laval, QC, Canada, H7P 6C5
Attention: Tom Carter, Retrofit & OEM Sales
Manager
Telephone: (450) 786-2532
Notice Information - City: City of Vernon
4305 Santa Fe Avenue
Vernon, CA 90058
Attention: Todd Dusenberry,
General Manager of Public Utilities

Telephone: (323) 583-8811 ext. 579
Commencement Date: May 16, 2023
Termination Date: May 15, 2024
Consideration: Total not to exceed $250,576 (includes all applicable sales tax); and more particularly
described in Exhibit B
Records Retention Period Three (3) years, pursuant to Section 11.20

Page 2 of 17 ends

SERVICES AGREEMENT BETWEEN THE CITY OF VERNON AND CAMFIL POWER

SYSTEMS FOR ENGINEERING AND DESIGN SERVICES FOR GENERATOR COOLING

FILTER HOUSING MODIFICATION
This Agreement is made between the City of Vernon, a California charter City and California municipal corporation (“City”), and Camfil Power Systems, a Quebec, Canada corporation (“Contractor”).

The City and Contractor agree as follows:

1.0 EMPLOYMENT OF CONTRACTOR. City agrees to engage Contractor to perform the services as hereinafter set forth as authorized by the City Council on May 16, 2023.

2.0 SCOPE OF SERVICES.

2.1 Contractor shall perform all work necessary to complete the services set forth in the City’s Request for Proposals issued on or about March 7, 2023, and titled Engineering and Design Services for Generator Cooling Filter Housing Modification, and Contractor's proposal to the City ("Proposal") dated April 3, 2023, Exhibit “A”, a copy which is attached to and incorporated into this Agreement by reference.

2.2 All services shall be performed to the satisfaction of City.

2.3 All services shall be performed in a competent, professional, and satisfactory manner in accordance with the prevailing industry standards for such services.

3.0 PERSONNEL.

3.1 Contractor represents that it employs, or will employ, at its own expense, all personnel required to perform the services under this Agreement.

3.2 Contractor shall not subcontract any services to be performed by it under this Agreement without prior written approval of City.

3.3 All of the services required hereunder will be performed by Contractor or by City approved subcontractors. Contractor, and all personnel engaged in the work, shall be fully qualified and authorized or permitted under State and local law to perform such services and shall be subject to approval by the City.

4.0 TERM. The term of this Agreement shall commence on May 16, 2023, and it shall continue until May 15, 2024, unless terminated at an earlier date pursuant to the provisions thereof.

5.0 COMPENSATION AND FEES.

5.1 Contractor has established rates for the City of Vernon which are comparable to and do not exceed the best rates offered to other governmental entities in and around Los Angeles County for the same services. For satisfactory and timely performance of

Page 3 of 17 ends

the services, the City will pay Contractor in accordance with the payment schedule set forth in Exhibit “B” attached hereto and incorporated herein by reference.

5.2 Contractor's grand total compensation for the entire term of this Agreement, shall not exceed $250,576 without the prior authorization of the City, as appropriate, and written amendment of this Agreement.

5.3 Contractor shall, at its sole cost and expense, furnish all necessary and incidental labor, material, supplies, facilities, equipment, and transportation which may be required for furnishing services pursuant to this Agreement. Materials shall be of the highest quality. The above Agreement fee shall include all staff time and all clerical, administrative, overhead, insurance, reproduction, telephone, air travel, auto rental, subsistence, and all related costs and expenses.

5.4 City shall reimburse Contractor only for those costs or expenses specifically approved in this Agreement, or specifically approved in writing in advance by City.

Unless otherwise approved, such costs shall be limited and include nothing more than the following costs incurred by Contractor:

5.4.1 The actual costs of subcontractors for performance of any of the services that Contractor agrees to render pursuant to this Agreement, which have been approved in advance by City and awarded in accordance with this Agreement.

5.4.2 Approved reproduction charges.

5.4.3 Actual costs and/or other costs and/or payments specifically authorized in advance in writing and incurred by Contractor in the performance of this Agreement.

5.5 Contractor shall not receive any compensation for extra work performed without the prior written authorization of City. As used herein, “extra work” means any work that is determined by City to be necessary for the proper completion of the Project, but which is not included within the Scope of Services and which the parties did not reasonably anticipate would be necessary at the time of execution of this Agreement. Compensation for any authorized extra work shall be paid in accordance with the payment schedule as set forth in Exhibit “B,” if the extra work has been approved by the City.

5.6 Licenses, Permits, Fees, and Assessments. Contractor shall obtain, at Contractor’s sole cost and expense, such licenses, permits, and approvals as may be required by law for the performance of the services required by this Agreement. Contractor shall have the sole obligation to pay for any fees, assessments, and taxes, plus applicable penalties and

Page 4 of 17 ends

interest, which may be imposed by law and which arise from or are necessary for the performance of the Services by this Agreement.

6.0 PAYMENT.

6.1 As scheduled services are completed, Contractor shall submit to the City an invoice for the services completed, authorized expenses, and authorized extra work actually performed or incurred according to said schedule.

6.2 Each such invoice shall state the basis for the amount invoiced, including a detailed description of the services completed, the number of hours spent, reimbursable expenses incurred and any extra work performed.

6.3 Contractor shall also submit a progress report with each invoice that describes in reasonable detail the services and the extra work, if any, performed in the immediately preceding calendar month.

6.4 Contractor understands and agrees that invoices which lack sufficient detail to measure performance will be returned and not processed for payment.

6.5 City will pay Contractor the amount invoiced within thirty (30) days after the City approves the invoice.

6.6 Payment of such invoices shall be payment in full for all services, authorized costs, and authorized extra work covered by that invoice.

7.0 CITY'S RESPONSIBILITY. City shall cooperate with Contractor as may be reasonably necessary for Contractor to perform its services; and will give any required decisions as promptly as practicable so as to avoid unreasonable delay in the progress of Contractor's services.

8.0 COORDINATION OF SERVICES. Contractor agrees to work closely with City staff in the performance of Services and shall be available to City’s staff, consultants, and other staff at all reasonable times.

9.0 INDEMNITY. Contractor agrees to indemnify City, its officers, elected officials, employees and agents against, and will hold and save each of them harmless from, any and all actions, suits, claims, damages to persons or property, losses, costs, penalties, obligations, errors, omissions or liabilities (herein “claims or liabilities”), including but not limited to professional negligence, that may be asserted or claimed by any person, firm or entity arising out of or in connection with the work, operations or activities of Contractor, its agents, employees, subcontractors, or invitees, provided for herein, or arising from the acts or omissions of Contractor hereunder, or arising from Contractor’s performance of or failure to perform any term, provision, covenant or condition of this Agreement, except to the extent such

Page 5 of 17 ends

claims or liabilities arise from the gross negligence or willful misconduct of City, its officers, elected officials, agents or employees.

10.0 INSURANCE. Contractor shall, at its own expense, procure and maintain policies of insurance of the types and in the amounts set forth below, for the duration of the Agreement, including any extensions thereto. The policies shall state that they afford primary coverage.
i. Automobile Liability with minimum limits of at least $1,000,000 combined single limit, including owned, hired, and non-owned liability coverage. ii. Contractor agrees to subrogate automobile liability resulting from performance under this Agreement by agreeing to defend, indemnify and hold harmless, the City, and its respective employees, agents, and City Council from and against all claims, liabilities, suits, losses, damages, injuries and expenses, including all costs and reasonable attorney’s fees (“Claims”), which are attributable to any act or omission by the City under the performance of the services. The city of Vernon, its directors, commissioners, officers, employees, agents, and volunteers must be endorsed on the policy as additional insureds and under the Contractors’ policy shall be primary and non-contributory and will not seek contribution from the City’s insurance or self-insurance.
iii. General Liability with minimum limits of at least $1,000,000 per occurrence and $2,000,000 aggregate written on an Insurance Services Office (ISO) Comprehensive General Liability "occurrence" form or its equivalent for coverage on an occurrence basis.

Premises/Operations and Personal Injury coverage is required. The City of Vernon, its directors, commissioners, officers, employees, agents, and volunteers must be endorsed on the policy as additional insureds as respects liability arising out of the Contractor's performance of this Agreement. The additional insured coverage under the Contractor’s policy shall be primary and non-contributory and will not seek contribution from the City’s insurance or self-insurance. (1) If Contractor employs other contractors as part of the services rendered, Contractor's Protective Coverage is required. Contractor may include all subcontractors as insureds under its own policy or shall furnish separate insurance for each subcontractor, meeting the requirements set forth herein.
(2) Contractor agrees to subrogate General Liability resulting from performance under this Agreement by agreeing to defend, indemnify and hold harmless, the City, and its respective employees, agents, and City Council from and against all claims, liabilities, suits, losses, damages,

Page 6 of 17 ends

injuries and expenses, including all costs and reasonable attorney’s fees (“Claims”), which are attributable to any act or omission by the City under the performance of the services.
iv. Professional Errors and Omissions coverage in a sum of at least $2,000,000, where such risk is applicable. Applicable aggregates must be identified and claims history provided to determine amounts remaining under the aggregate. Contractor shall maintain such coverage for at least one (1) year after the termination of this Agreement. v. Contractor shall comply with the applicable sections of the California Labor Code concerning workers' compensation for injuries on the job. In addition, Contractor shall require each subcontractor to similarly maintain workers’ compensation insurance in accordance with the laws for California for all of the subcontractor’s employees. Compliance is accomplished in one of the following manners:
(1) Provide copy of permissive self-insurance certificate approved by the State of California; or
(2) Secure and maintain in force a policy of workers' compensation insurance with statutory limits and Employer's Liability Insurance with a minimal limit of $1,000,000 per accident. The policy shall be endorsed to waive all rights of subrogation against City, its directors, commissioners, officers, employees, and volunteers for losses arising from performance of this Agreement; or
(3) Provide a "waiver" form certifying that no employees subject to the Labor Code's Workers' Compensation provision will be used in performance of this Agreement.
vi. Each insurance policy included in this clause shall be endorsed to state that coverage shall not be cancelled except after thirty (30) days' prior written notice to City. vii. Insurance shall be placed with insurers with a Best's rating of no less than A-VIII. viii. Prior to commencement of performance, Contractor shall furnish City with a certificate of insurance for each policy. Each certificate is to be signed by a person authorized by that insurer to bind coverage on its behalf. The certificate(s) must be in a form approved by City. City may require complete, certified copies of any or all policies at any time. ix. Failure to maintain required insurance at all times shall constitute a default and material breach. In such event, Contractor shall immediately notify City and cease all performance under this Agreement until further directed by the City. In the absence of satisfactory insurance coverage, City may, at its option: (a) procure insurance with collection

Page 7 of 17 ends

rights for premiums, attorney's fees and costs against Contractor by way of set-off or recoupment from sums due to Contractor, at City's option; (b) immediately terminate this Agreement and seek damages from the Agreement resulting from said breach; or (c) self-insure the risk, with all damages and costs incurred, by judgment, settlement or otherwise, including attorney's fees and costs, being collectible from Contractor, by way of set-off or recoupment from any sums due to Contractor.

11.0 GENERAL TERMS AND CONDITIONS.

11.1 INDEPENDENT CONTRACTOR.

11.1.1 It is understood that in the performance of the services herein provided for, Contractor shall be, and is, an independent contractor, and is not an agent, officer or employee of City and shall furnish such services in its own manner and method except as required by this Agreement, or any applicable statute, rule, or regulation. Further, Contractor has and shall retain the right to exercise full control over the employment, direction, compensation and discharge of all persons employed by Contractor in the performance of the services hereunder. City assumes no liability for Contractor’s actions and performance, nor assumes responsibility for taxes, bonds, payments, or other commitments, implied or explicit, by or for Contractor. Contractor shall be solely responsible for, and shall indemnify, defend and save City harmless from all matters relating to the payment of its employees, subcontractors and independent contractors, including compliance with social security, withholding and all other wages, salaries, benefits, taxes, exactions, and regulations of any nature whatsoever.

11.1.2 Contractor acknowledges that Contractor and any subcontractors, agents or employees employed by Contractor shall not, under any circumstances, be considered employees of the City, and that they shall not be entitled to any of the benefits or rights afforded employees of City, including, but not limited to, sick leave, vacation leave, holiday pay, Public Employees Retirement System benefits, or health, life, dental, long-term disability or workers' compensation insurance benefits.

11.2 CONTRACTOR NOT AGENT. Except as the City may authorize in writing, Contractor and its subcontractors shall have no authority, express or implied, to act on behalf of or bind the City in any capacity whatsoever as agents or otherwise.

11.3 OWNERSHIP OF WORK. All documents and materials furnished by the City to Contractor shall remain the property of the City and shall be returned to the City upon termination of this Agreement. All reports, drawings, plans, specifications, computer tapes, floppy disks and printouts, studies, memoranda, computation sheets, and other documents prepared by Contractor in furtherance of the work shall be the sole property of City and shall be

Page 8 of 17 ends

delivered to City whenever requested at no additional cost to the City. Contractor shall keep such documents and materials on file and available for audit by the City for at least three (3) years after completion or earlier termination of this Agreement. Contractor may make duplicate copies of such materials and documents for its own files or for such other purposes as may be authorized in writing by the City.

11.4 CORRECTION OF WORK. Contractor shall promptly correct any defective, inaccurate or incomplete tasks, deliverables, goods, services and other work, without additional cost to the City. The performance or acceptance of services furnished by Contractor shall not relieve the Contractor from the obligation to correct subsequently discovered defects, inaccuracy, or incompleteness.

11.5 RESPONSIBILITY FOR ERRORS. Contractor shall be responsible for its work and results under this Agreement. Contractor, when requested, shall furnish clarification and/or explanation as may be required by the City, regarding any services rendered under this Agreement at no additional cost to City. In the event that an error or omission attributable to Contractor occurs, then Contractor shall, at no cost to City, provide all necessary design drawings, estimates and other Contractor professional services necessary to rectify and correct the matter to the sole satisfaction of City and to participate in any meeting required with regard to the correction.

11.6 WAIVER. The City's waiver of any term, condition, breach, or default of this Agreement shall not be considered to be a waiver of any other term, condition, default or breach, nor of a subsequent breach of the one waived. The delay or failure of either party at any time to require performance or compliance by the other of any of its obligations or agreements shall in no way be deemed a waiver of those rights to require such performance or compliance.

No waiver of any provision of this Agreement shall be effective unless in writing and executed by a duly authorized representative of the party against whom enforcement of a waiver is sought.

11.7 SUCCESSORS. This Agreement shall inure to the benefit of, and shall be binding upon, the parties hereto and their respective heirs, successors, and/or assigns.

11.8 NO ASSIGNMENT. Contractor shall not assign or transfer this Agreement or any rights hereunder without the prior written consent of the City and approval by the City Attorney, which may be withheld in the City's sole discretion. Any unauthorized assignment or transfer shall be null and void and shall constitute a material breach by the Contractor of its obligations under this Agreement. No assignment shall release the original parties from their obligations or otherwise constitute a novation.

Page 9 of 17 ends

11.9 COMPLIANCE WITH LAWS. Contractor shall comply with all Federal, State, County and City laws, ordinances, rules and regulations, which are, as amended from time to time, incorporated herein and applicable to the performance hereof. Violation of any law material to performance of this Agreement shall entitle the City to terminate the Agreement and otherwise pursue its remedies. Further, if the Contractor performs any work knowing it to be contrary to such laws, rules, and regulations Contractor shall be solely responsible for all costs arising therefrom.

11.10 ATTORNEY'S FEES. If any action at law or in equity is brought to enforce or interpret the terms of this Agreement, the prevailing party shall be entitled to reasonable attorney's fees, costs, and necessary disbursements in addition to any other relief to which such party may be entitled.

11.11 INTERPRETATION.

11.11.1 Applicable Law. This Agreement shall be deemed an agreement and shall be governed by and construed in accordance with the laws of the State of California. Contractor agrees that the State and Federal courts which sit in the State of California shall have exclusive jurisdiction over all controversies and disputes arising hereunder, and submits to the jurisdiction thereof.

11.11.2 Entire Agreement. This Agreement, including any exhibits attached hereto, constitutes the entire agreement and understanding between the parties regarding its subject matter and supersedes all prior or contemporaneous negotiations, representations, understandings, correspondence, documentation, and agreements (written or oral).

11.11.3 Written Amendment. This Agreement may only be changed by written amendment executed by Contractor and the City Administrator or other authorized representative of the City, subject to any requisite authorization by the City Council. Any oral representations or modifications concerning this Agreement shall be of no force or effect.

11.11.4 Severability. If any provision in this Agreement is held by any court of competent jurisdiction to be invalid, illegal, void, or unenforceable, such portion shall be deemed severed from this Agreement, and the remaining provisions shall nevertheless continue in full force and effect as fully as though such invalid, illegal, or unenforceable portion had never been part of this Agreement.

11.11.5 Order of Precedence. In case of conflict between the terms of this Agreement and the terms contained in any document attached as an Exhibit or otherwise

Page 10 of 17 ends

incorporated by reference, the terms of this Agreement shall strictly prevail. The terms of the City’s Request for Proposals shall control over the Contractor’s Proposal.

11.11.6 Construction. In the event an ambiguity or question of intent or interpretation arises with respect to this Agreement, this Agreement shall be construed as if drafted jointly by the parties and in accordance with its fair meaning. There shall be no presumption or burden of proof favoring or disfavoring any party by virtue of the authorship of any of the provisions of this Agreement.

11.12 TIME OF ESSENCE. Time is strictly of the essence of this agreement and each and every covenant, term, and provision hereof.

11.13 AUTHORITY OF CONTRACTOR. The Contractor hereby represents and warrants to the City that the Contractor has the right, power, legal capacity, and authority to enter into and perform its obligations under this Agreement, and its execution of this Agreement has been duly authorized.

11.14 ARBITRATION OF DISPUTES. Any dispute for under $25,000 arising out of or relating to the negotiation, construction, performance, non-performance, breach, or any other aspect of this Agreement, shall be settled by binding arbitration in accordance with the Commercial Rules of the American Arbitration Association at Los Angeles, California and judgment upon the award rendered by the Arbitrators may be entered in any court having jurisdiction thereof. The City does not waive its right to object to the timeliness or sufficiency of any claim filed or required to be filed against the City and reserves the right to conduct full discovery.

11.15 NOTICES. Any notice or demand to be given by one party to the other must be given in writing and by personal delivery or prepaid first-class, registered or certified mail, addressed as follows. Notice simply to the City of Vernon or any other City department is not adequate notice.

If to the City:

City of Vernon
Attention: Todd Dusenberry, General Manager of Public Utilities 4305 Santa Fe Avenue
Vernon, CA 90058
If to the Contractor:

Camfil Power Systems
Tom Carter, Retrofit & OEM Sales Manager
3025 Joseph-A. Bombardier
Laval, QC, Canada, H7P 6C5

Page 11 of 17 ends

Any such notice shall be deemed to have been given upon delivery, if personally delivered, or, if mailed, upon receipt, or upon expiration of three (3) business days from the date of posting, whichever is earlier. Either party may change the address at which it desires to receive notice upon giving written notice of such request to the other party.

11.16 NO THIRD PARTY RIGHTS. This Agreement is entered into for the sole benefit of City and Contractor and no other parties are intended to be direct or incidental beneficiaries of this Agreement and no third party shall have any right or remedy in, under, or to this Agreement.

11.17 TERMINATION FOR CONVENIENCE (Without Cause). City may terminate this Agreement in whole or in part at any time, for any cause or without cause, upon fifteen (15) calendar days' written notice to Contractor. If the Agreement is thus terminated by City for reasons other than Contractor's failure to perform its obligations, City shall pay Contractor a prorated amount based on the services satisfactorily completed and accepted prior to the effective date of termination. Such payment shall be Contractor's exclusive remedy for termination without cause.

11.18 DEFAULT. In the event either party materially defaults in its obligations hereunder, the other party may declare a default and terminate this Agreement by written notice to the defaulting party. The notice shall specify the basis for the default. The Agreement shall terminate unless such default is cured before the effective date of termination stated in such notice, which date shall be no sooner than ten (10) days after the date of the notice. In case of default by Contractor, the City reserves the right to procure the goods or services from other sources and to hold the Contractor responsible for any excess costs occasioned to the City thereby. Contractor shall not be held accountable for additional costs incurred due to delay or default as a result of Force Majeure. Contractor must notify the City immediately upon knowing that non-performance or delay will apply to this Agreement as a result of Force Majeure. At that time Contractor is to submit in writing a Recovery Plan for this Agreement. If the Recovery Plan is not acceptable to the City or not received within 10 days of the necessary notification of Force Majeure default, then the City may cancel this order in its entirety at no cost to the City, owing only for goods and services completed to that point.

11.19 TERMINATION FOR CAUSE. Termination for cause shall relieve the terminating party of further liability or responsibility under this Agreement, including the payment of money, except for payment for services satisfactorily and timely performed prior to the service of the notice of termination, and except for reimbursement of (1) any payments made by the City for service not subsequently performed in a timely and satisfactory manner, and (2) costs

Page 12 of 17 ends

incurred by the City in obtaining substitute performance. If this Agreement is terminated as provided herein, City may require, at no additional cost to City, that Contractor provide all finished or unfinished documents, data, and other information of any kind prepared by Contractor in connection with the performance of Services under this Agreement. Contractor shall be required to provide such document and other information within fifteen (15) days of the request.

11.19.1 Additional Services. In the event this Agreement is terminated in whole or in part as provided herein, City may procure, upon such terms and in such manner as it may determine appropriate, services similar to those terminated.

11.20 MAINTENANCE AND INSPECTION OF RECORDS.

The City, or its authorized auditors or representatives, shall have access to and the right to audit and reproduce any of the Contractor's records to the extent the City deems necessary to insure it is receiving all money to which it is entitled under the Agreement and/or is paying only the amounts to which Contractor is properly entitled under the Agreement or for other purposes relating to the Agreement.

The Contractor shall maintain and preserve all such records for a period of at least three (3) years after termination of the Agreement.

The Contractor shall maintain all such records in the City of Vernon. If not, the Contractor shall, upon request, promptly deliver the records to the City of Vernon or reimburse the City for all reasonable and extra costs incurred in conducting the audit at a location other than the City of Vernon, including, but not limited to, such additional (out of the City) expenses for personnel, salaries, private auditors, travel, lodging, meals, and overhead.

11.21 CONFLICT. Contractor hereby represents, warrants, and certifies that no member, officer, or employee of the Contractor is a director, officer, or employee of the City of Vernon, or a member of any of its boards, commissions, or committees, except to the extent permitted by law.

11.22 HEADINGS. Paragraphs and subparagraph headings contained in this Agreement are included solely for convenience and are not intended to modify, explain or to be a full or accurate description of the content thereof and shall not in any way affect the meaning or interpretation of this Agreement.

11.23 ENFORCEMENT OF WAGE AND HOUR LAWS. Eight hours labor constitutes a legal day's work. The Contractor, or subcontractor, if any, shall forfeit twenty-five dollars ($25) for each worker employed in the execution of this Agreement by the respective Contractor or subcontractor for each calendar day during which the worker is required or

Page 13 of 17 ends

permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Sections 1810 through 1815 of the California Labor Code as a penalty paid to the City; provided, however, work performed by employees of contractors in excess of 8 hours per day, and 40 hours during any one week, shall be permitted upon compensation for all hours worked in excess of 8 hours per day at not less than 1½ times the basic rate of pay.

11.24 EQUAL EMPLOYMENT OPPORTUNITY PRACTICES. Contractor certifies and represents that, during the performance of this Agreement, it and any other parties with whom it may subcontract shall adhere to equal employment opportunity practices to assure that applicants, employees and recipients of service are treated equally and are not discriminated against because of their race, religion, color, national origin, ancestry, disability, sex, age, medical condition, sexual orientation or marital status. Contractor further certifies that it will not maintain any segregated facilities. Contractor further agrees to comply with The Equal Employment Opportunity Practices provisions as set forth in Exhibit “C”. [Signatures Begin on Next Page].

Page 14 of 17 ends

IN WITNESS WHEREOF, the Parties have executed this Agreement as of the Commencement Date stated on the cover page.

City of Vernon, a California charter City
and California municipal corporation
By: ____________________________
Carlos Fandino, City Administrator

Camfil Power Systems, a Quebec, Canada
corporation
By:

Name:

Title:

ATTEST:
_______________________________
Lisa Pope, City Clerk
By:

Name:

Title:

APPROVED AS TO FORM:
_______________________________
Zaynah N. Moussa,
City Attorney

Page 15 of 17 ends

EXHIBIT A

CONTRACTOR'S PROPOSAL

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 1 of 13 ends

RFP for Engineering and Design Services for
Generator Cooling Filter Housing Modification
Supplier: Camfil Power Systems
Address: 3025 Joseph-A. Bombardier,
Laval, QC, Canada
Phone No: 450-786-2532
Fax No: 450-629-5847

Contact: Tom Carter
Retrofit & OEM Sales Manager
Address: 3025 Joseph-A. Bombardier,
Laval, QC, Canada
Phone No: (803)-280-7034
Email: [email protected]

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 3 of 13 ends

Item 1 - Introduction
As one of the leading providers of air inlet systems for turbomachinery, we understand the critical role of effective filtration solutions in maximizing the output and efficiency of gas turbines. Camfil’s air filtration solutions for gas turbines provide reliable and effective protection against harmful airborne contaminants, resulting in improved performance and longevity of the turbines. By ensuring clean and efficient operation, our solutions ultimately help reduce downtime and maintenance costs, while increasing the overall efficiency and sustainability of operations.

Our proposal aims to upgrade the existing generator filter houses to increase filter efficiency in removing harmful hydrocarbon particulates and allow for extended operating usage of the filters. Our scope of work includes the design, manufacturing, and delivery of a new air inlet filter house for each of the two units at the station. Reliable, highperforming air filtration is essential for the success of your operations, and we are committed to providing a solution that meets your needs.

We are confident that our experience, expertise, and commitment to quality will ensure that the Malburg Generating Station’s air inlet filter house upgrade is a success. By partnering with Camfil, the City of Vernon will benefit from our expertise, experience, and commitment to delivering the best possible filtration solutions.

Item 2 - Scope of Work (SoW)
The project will involve the design, manufacturing, and delivery of a new air inlet filter house for each of the two units at the Malburg Generating Station. Camfil’s scope of work includes the following deliverables:

1. Engineering site survey report: This report will summarize the findings of the site survey and identify any outstanding questions about the scope which need to be addressed prior to the start of engineering design.

2. Structural analysis: This analysis will determine reaction loads of the existing structure any identify necessary structural modifications (vertical supports) that must be implemented in order to support Camfil’s proposed solution.

3. Design and manufacturing: Camfil will design and manufacture the new air inlet filter house with the support of our subcontractors. In addition, sets of highefficiency final filters will be supplied for each of the two new units.

4. Shipment: The units and filters will be shipped to the Malburg Generating Station.

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 4 of 13 ends

Item 3 - Work Plan
The following activities will be required to achieve the deliverables outlined in the SoW:

1. Engineering site survey: Our engineering team will perform an engineering site survey to perform a dimensional check of the existing unit to sign off on dimensions to define the scope for engineering of the new units.

2. Structural analysis: Our engineering team will perform a structural analysis of the existing support structure to determine reaction loads and identify any necessary structural modifications that must be implemented for the integration of the new air inlet filter houses.

3. Site survey report: Our engineering team will put together a site survey report to summarize our findings, present the design concept based on the survey and structural analysis, and identify any outstanding design considerations to be discussed with the City of Vernon.

4. Design: Following the results of the site survey and structural analysis, our dedicated project engineer will work with our highly experienced design team to design the 3D models and drawings for the new air inlet filter houses. A General Assembly drawing will be provided for approval prior to manufacturing.

5. Manufacturing: Partnering with our subcontractors, we will manufacture the new air inlet filter houses.

6. Quality Control: Thorough quality control checks will be conducted throughout the design and manufacturing process to ensure that the final products meet the project specifications.

7. Shipment: The manufactured units and full sets of high-efficiency final filters will be shipped to the Malburg Generating Station.

8. Project management: Throughout the project, a dedicated project manager will oversee all aspects of the project and ensure that all deliverables are completed on time and within budget.

The project timeline will be as follows:
 Within 4 weeks of PO receipt, Camfil will perform an engineering site survey and structural analysis
 4 weeks after survey, Camfil will provide a site survey report  4-6 weeks for engineering drawings after site survey report  24-26 weeks for manufacturing after engineering drawing approval  2-3 weeks for final shipment to site

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 5 of 13 ends

Item 4 - Fees and Costs
Price (USD)
Front Access Inlet Filtration System See Pricing Table
Scope for 1 Unit includes:

Air Intake Filter House 6Wx3H (Static) in 316L Stainless Steel  Weather louvers (hinged), frames in 316L Stainless Steel o Droplet separator profiles in UV-resistant polypropylene with 33mm spacing, allowing for inertial separation of water
 Single-stage filtration for a high efficiency final filter Inlet Transition in 316L Stainless Steel
 Plenum used to transition from the filter house static module to the existing on-site silencer
 Transition outlet: 118.2”W x 70.8”H
Hardware and Packaging
Note:
- Pricing does not include any electrical components
- Camfil to design the system to match the base-to-duct centerline and the retrofit flange dimensions exactly.

Price (USD)
Filters See Pricing Table
Scope for 1 Unit includes:
18 x CamGT 3V-600 E10
Price (USD)
Structural Analysis See Pricing Table
Camfil will perform a structural analysis of the existing filter house cantilever supports to determine the reaction loads at the enclosure structural connection shown below.

The proposed filter house retrofit will be designed such these loads are not exceeded, and include vertical supports to ground as shown in the sketch below to minimize the wall

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 6 of 13 ends

reaction loads if needed. Vertical support members will be removable to maintain clearance for generator maintenance.

The customer is responsible for the foundation design of the vertical supports.

Camfil will only evaluate and ensure the suitability of the structure up to (and including) the connecting point to the enclosure wall.

Review and certification by California licensed PE is excluded at the moment - Customer to confirm scope of review and stamping required. Structural analysis will be performed by a Professional Engineer.

Price (USD)
Freight (DDP Vernon, California) See Pricing Table
Includes:

Delivery of 2 units and filters to Malburg Generating Station in Vernon, California, USA.

Note: The customer is responsible for unloading the goods on-site at the time of delivery.

This is an estimate and the actual cost would be determined at the time of shipment.

The estimated lead time is between 2-3 weeks after the ready-to-ship date. Specifics for the logistics to be discussed during project execution.

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 7 of 13 ends

Price (USD)
Site Survey See Pricing Table
Includes:

Mobilization and de-mobilization (lodging, meals, air fare, transportation) Two personnel, up to two days on-site, 8-10 hours per day Deliverables:
 Site survey report
 Sign off on dimensions to define scope for engineering Note:
- This does not include any additional stand-by (waiting) time due to: mandatory site-specific trainings, security and safety clearance, and/or due to force majeure - This does not include any material or non-standard equipment and tools Estimated Initial Pressure Drop
The following table shows the estimate initial pressure drop at 2500 CFM per filter:

Item Initial (“ w.g.)
Weather louvers 0.16
CamGT 3V-600 E10 0.55
Total 0.71
*Above values are estimations only

QUOTATION
Vernon Malburg Generator
Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 8 of 13 ends

PRICING FOR FULL 2 UNIT SCOPE
Item Price (USD)
Full project scope:
 Front Access Inlet
Filtration System
 Filters
 Structural Analysis
 Freight (DDP Vernon,
California)
 Site Survey

REDACTED FOR
SEALED PRICE.

REFER TO PLANET
BIDS SUBMISSION.

Tax (10.25%) REDACTED
Total for project REDACTED
Note 1: Pricing excludes PE stamps, taxes (other than 10.25% sales tax for Vernon, California), testing, or third party certification.

Note 2: Camfil is offering a bid contingent on a Camfil engineering site survey.

Note 3: The above pricing is based on a scope of supply of two exactly identical units. Any changes may impact the pricing.

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 9 of 13 ends

Warranty: 12 months in commercial operation,
24 months from delivery, whichever comes first

Payment Terms: Net 30
Payment Schedule 10% after acceptance of PO
20% after drawings released for fabrication
60% upon ready to ship
10% upon delivery to site
Lead Time: Within 4 weeks of PO placement, Camfil will
conduct an engineering site survey and structural
analysis
4 weeks after site survey, Camfil will provide a site
survey report
4-6 weeks for engineering drawings after site
survey report
24-26 weeks for manufacturing after engineering
drawing approval
2-3 weeks for final shipment to site
Delivery Terms: DDP Vernon, California, USA
Quote Validity: 90 days, subject to currency and material fluctuations. If raw material varies more than 3%,
Camfil reserves the right to modify pricing.

Cancellation Terms:

Day 1+  Cancellation Fee = 20% of contract value
Drawing Submittal  Cancellation Fee = 40% of contract value Material Purchase  Cancellation Fee = 60% of contract Value 2 weeks before shipping  Cancellation Fee = 100% of contract Value

Day 1 will be the purchase order date

Sincerely,
Tatiana Mikus
Sales Application Engineering
CC: Michelle Bourbonnais-Spear, Key Account Manager
Tom Carter, OEM and Retrofits Sales Manager

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 10 of 13 ends

Item 5 - Camfil Power Systems Competences and Team:

CAMFIL POWER SYSTEMS AMERICAS
 Leading provider of air filtration solutions for the power systems industry, offering innovative and sustainable products and services to customers around the world, with a focus on developing advanced technologies that improve the efficiency and longevity of their filters.
 Aside from standard filtration solutions, Camfil Power Systems offers retrofit solutions for existing air filtration systems. These solutions help customers to reduce operating costs, extend the life of their equipment, and enhance the overall performance and efficiency of their air filtration systems.
 Company has a proven track record of delivering high-quality filtration solutions to customers in the power systems industry. The company's extensive experience and technical expertise enable them to provide solutions that are tailored to each customer's specific needs and requirements.

LIST OF REFERENCE & RELATED PROJECTS 2022-2023
CamGT 3V600 E10 Filtration Solution
 Shell Enchilada Platform (3 units) – Gulf of Mexico – Delivery November 2022 (2 units) & April 2023 (1 unit)
 Exxon Mobil Larut A Platform – 125 miles off Terengganu, Malaysia – Delivery October 2022
 CNOOC Yacheng (2 units) – Offshore Hong-Kong – Delivery November 2022  Bonga FPSO (5 units) – Offshore Nigeria – Delivery September 2022  Medco Energi Platform (5 units) – Offshore Indonesia – Delivery September 2022
 Beacon Offshore Energy BOE Shenandoah (5 units) – Gulf of Mexico – Delivery September 2022
 SGN Energia Plant (4 units) - Punta Caucedo, Dominican Republic – Delivery August 2022
 Texas Gas Transmission LLC – Slaughters, Kentucky – Delivery March 2023  Pazflor FPSO (7 units) – Offshore Angola – Delivery July 2022  Bacardi Plant – Puerto Rico – Delivery February 2022
 Vedanta Limited (Cairn Oil & Gas) – India - Delivery March 2023  Oxy Mukhaizna – Oman – Delivery in January 2022
 Proctor & Gamble Oxnard Plant – Oxnard California - Delivery October 2021

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 11 of 13 ends

Retrofit Solution to Existing Air Inlets
 Proctor & Gamble Oxnard Plant – Oxnard California - Delivery October 2021 o Site Survey & Engineering
o Manufacturing & Shipment
o Installation Kick-Off Meeting with Contractor & Support during Installation  ExxonMobil Beaumont Refinery – Beaumont, Texas – Delivery October o Site Survey & Engineering
o Manufacturing & Shipment
o Installation Kick-Off Meeting with Contractor & Support during Installation

QUOTATION
Vernon Malburg Generator

Our ref: S21099
Date: 2023-04-03
Prepared by: TMI

Page 12 of 13 ends

PROJECT TEAM – RETROFIT 2022-2023
Camfil Power Systems has a highly skilled engineering and project management team that works closely with customers to ensure that their air filtration solutions are designed and fabricated to the highest standards, delivering the best possible performance and value.

Michelle Bourbonnais, P.Eng 13 years of experience in Air Inlet Filtration Industry Small Frame & Plant Optimization Director
 Business development & market analysis to identify opportunities for growth  Strategic planning & optimization of resources to ensure project deliveries  Customer relationship and customer service to build strategies that meet the requirements
Tom Carter 13 years of experience in Air Inlet Filtration Industry Retrofit & OEM Sales Manager
 Sales Strategy and Planning for the Americas
 Customer relationship management to ensure that needs are taken into account in the development of new products and services
Mary Beshay, PMP 6 years of experience in Air Inlet Filtration Industry Project Manager for Small Frame & Plant Optimization Projects  Project planning and execution by defining project deliverables and timeline  Communication and Reporting with the customer
 Internal team management to achieve project goals
 Quality Assurance to ensure project meet quality standards and customer requirements
Alexandre Gilbert, P. Eng 7 years of experience Air Inlet Filtration Industry Senior Project Engineer – Plant Optimization and Complex Systems  Design of air filtration solution of standard and complex systems to capture customer technical requirements and specifications
 Design review gates with customer per defined deliverables  Optimization of design to ensure high-quality manufacturability & ease of installation
 Collaboration with quality team to ensure project specifications are reflected in project documentation and control plan
Extended team members shown in attached Organizational Chart

QUOTATION
Vernon Malburg Generator
Our ref: S21099
Date: 2023-04-03 Prepared by: TMIPage 13 of 13
Camfil Canada Inc.
3025 Joseph A.Bombardier Laval, QC, H7P 6C5 www.camfil.com Addendum 1 - Organizational Chart

Manufacturer: Air Flow (CFM)
Product Name: Air Density (kg/m³)
Part Number: Air Temperature (o
C)
Nominal Dimensions: (inches) Relative Humidity (%)
Product Description: Barometric Pressure (kPa)
Test Operator: Type of Test Aerosol:

Client: Particle Counter:

Site name: Filter Condition:

Test Date:

Manufacturing Date of Filter:

Media Type:

Net Effective Media Area:

Procurement Method: Air 1 865 2 168 2 459 2 780 3 061

0.37 0.47 0.57 0.68 0.79
Contact Name
Email Address
Contact Number

99.6 %

99.3 %

0.160 um

95.9 %

96.4 %
Filter Resistance vs Air Flow
Efficiency95% min @ MPPS
Photo not taken
Efficiency Rating
2500 CFM
Additional Information >>>
Efficiency @ MPPS
Photo not taken
Photograph of Label/Markings
Customer Contact
N/A
Resistance (In. WG)
@
Efficiency @ 0.4 µm
Efficiency Class T11 @
Report No.

Air Filter Date:

Test Report
Page:

LVL-22023
03-May-22
1 of 2
[email protected]
3025 Joseph A Bombardier, Laval, Quebec, Canada H7P 6C5 Filter Description
ISO29461-1 Report, Efficiency Only
Test Conditions
Camfil 2500
Solar
ePM1min
MPPS

1.20 21.5

26.8 101.8
CamGT 3V-600 E10 STD
Welas 1200
ESM
N/A Initial Resistance:

N/A
13-April-2022 Test Results
855242003
24x24x24
Gas Turbine Filter
DEHS

0.58 IWG
2 500 CFM
Filter Resistance vs Air Flow
Photograph of Filter
New
N/A
Crystal Lake

0.37 0.47

0.57 0.68

0.79 0.00

0.10 0.20

0.30 0.40

0.50 0.60

0.70 0.80

0.90 500 1 000 1 500 2 000 2 500 3 000 3 500
Resistance - Inches WG
Air Flow - CFM
Manufacturer: Air Flow Capacity (CFM)
Product Name: Air Temperature (oC)
Part Number: Relative Humidity (%)
Nominal Dimensions: (inches) Barometric Pressure (kPa)
Product Description: Type of Test Aerosol:

Media Type: Particle Counter:

As Received Discharged
Range (µm) E (%) E95min (%) Min (µm) Max (µm) Mean (µm) Efficiency Efficiency

0.111 98.37% 97.06% 0.29 0.39 0.34 99.3% 99.2%

0.120 97.26% 96.37% 0.39 0.56 0.47 99.7% 99.6%

0.129 96.77% 96.05% 0.56 0.70 0.63 99.8% 99.9%

0.138 96.44% 95.83% 0.70 1.00 0.84 99.9% 99.9%

0.149 96.68% 96.19% ePM1: 99.6%

0.160 96.42% 95.88% ePM1min: 99.6%

0.172 96.53% 96.00%

0.184 96.83% 96.34% Min (µm) Max (µm) Mean (µm) As Received Discharged

0.198 97.07% 96.62% 1.00 1.33 1.15

0.213 97.29% 96.87% 1.33 1.65 1.49

0.229 97.60% 97.23% 1.65 2.21 1.91

0.246 97.89% 97.57% 2.21 2.94 2.55

0.264 98.27% 97.98% *ePM2.5:

0.284 98.70% 98.36% *ePM2.5min:

0.340 99.11% 98.93%

0.392 99.34% 99.19% Min (µm) Max (µm) Mean (µm) As Received Discharged

0.470 99.56% 99.45% 2.94 3.92 3.40

0.626 99.87% 99.76% 3.92 6.98 5.23

0.835 99.95% 99.88% 6.98 10.00 8.35

1.155 *ePM10:

1.485

1.911

2.548

3.398

5.233

8.354
*In the case of T6+ filters which are rated per ePM1min only, DEHS may be used as the only test aerosol in which case the ePM2.5min and ePM10 fields will remain blank. If KCl aerosol is used, ePM2.5min and ePM10 efficiency will be reported and lower ratings provided. **The results of this test relate only to the test devices in the condition stated herein. The performance results cannot by themselves be quantitatively applied to predict filtration performance in all "real life" environments.

T11 @ 2500
Report No.

Welas 1200

21.5 26.8
ISO29461-1 Report, Efficiency Only
Date:

Page:

Test Conditions
2500
24x24x24
2 of 2
3-May-22
LVL-22023
Air Filter
Test Report
3025 Joseph A Bombardier, Laval, Quebec, Canada H7P 6C5 Efficiency Class
Filter Description
Camfil
Gas Turbine Filter
N/A
855242003
CamGT 3V-600 E10 STD
CFM
DEHS
101.8
[email protected]

80.0%

82.0%

84.0%

86.0%

88.0%

90.0%

92.0%

94.0%

96.0%

98.0%
100.0%

0.1 1.0 10.0
DEHS Particle Removal Efficiency - %
Particle Size - Microns
Particle Size Removal Efficiency
aaaaaaaaaaa
1 Clean Air Solutions

1. Filter Summary
Manufacturer Camfil
Product Name CamGT 3V-600 E10 STD
Part Number 855242003
Nominal Dimensions (inches) 24 x 24 x 24
Product Description Gas Turbine Filter
Procurement Method Internal
Test Date 28-April-2022
aaaaaaaaaaa
2 Clean Air Solutions

2. Deluge Test Results – CamGT 3V-600 E10
Unit CamGT 3V-600 E10
Water Sprayed L 75
Water Upstream L 49
Water Spray Rate L/min 0.415
Water Efficiency % 100
Total Test Run Time Minutes 180
First Penetration Time Minutes N/A
Filter Water Retention L 1
Water Downstream L N/A
Pressure drop end of
Test
IWG 0.60
Rating PASS
Date: Sep 19th, 2022
Prepared for: Gautam Marwaha
Report Name: Burst test CamGT 3V-600-T9-Std
Prepared by: Ezhil Murugesan
1 Clean Air Solutions
CamGT 3V-600 -T10-Std Crystal
Lake
Burst Test Report
LVL-22042
Date: Sep 19th, 2022
Prepared for: Gautam Marwaha
Report Name: Burst test CamGT 3V-600-T9-Std
Prepared by: Ezhil Murugesan
2 Clean Air Solutions

ABSTRACT
A CamGT is designed for operating in severe and harsh environments but it must also resist the most extreme conditions to ensure the performance and guarantee to protect the gas turbine throughout its life. High-stress burst test was performed on a CamGT 3V 600-T10-Std filter produced in Crystal Lake, USA. Filter was loaded with dust at an airflow of 7645 m³/h to gradually reach the final pressure drop to verify filter integrity.

This test should not be mixed up with a traditional blast wave test, where the filter is exposed to a sudden pressure impact, a blast wave.

RESULTS AND CONCLUSION
The filter element resisted up to a pressure drop of 5000 Pa without visible break or damage. All pleat tips were still in good condition after the test was ended.

The results of this test relate only to the test device in the condition stated herein.

RESULTS OF THE TEST
dP filter (Pa) Observations Status
1000 Pa No bending on any media
packs.

No damage to filter media.

Filter structure is sound.

Ok
2000 Pa No bending on any media
packs.

No damage to filter media.

Filter structure is sound.

Ok
3000 Pa Minor bending noticed in centre
of media packs.

No damage to filter media.

Filter structure is sound
Ok
5000 Pa Test is ended. All 6 media
packs are still intact.

Pass
Power Systems

CASE STUDY
www.camfil.com/ps
PLANT UPGRADES TO THE CAMGT 3V-600 FOR A 6-YEAR LIFECYCLE & TO PREVENT ENGINE DEGRADATION COMPARISON TEST INDICATES A POTENTIAL OF $937,000 USD SAVINGS OVER A SIX-YEAR TIMEFRAME BY UPGRADING TO EPA A new combined cycle plant on Louisiana’s Gulf
Coast has been operating commercially since
2014. The plant has two GE 7F.04 gas turbines,
producing 171 MW each, and a steam turbine
that produces 218 MW, totaling 560 MW of
power.

In early 2016, a small team of fleet turbine
managers took proactive measures to prevent
compressor corrosion and fouling that had
impacted other 7FA turbines’ power output
across their fleet. Corrosion, if unchecked,
could potentially cost the organization millions
of US dollars due to engine refurbishment and
loss of revenue. Further, the team understood
how fouling could lead to power and engine
degradation. Although degradation caused by
fouling can be mitigated somewhat by offline
washes, some non-recoverable degradation will
remain.

Another initiative of the plant is to change their
major outage schedule from three to six years,
therefore requiring final filters with a six year
lifecycle. In order to select the appropriate
filters that will prevent corrosion and fouling
at this new plant, they decided to test various
filter configurations with Camfil’s on-site testing
trailer. The CamLab, a 28-foot mobile test lab,
consists of four separate ducts that can be
fitted with pre-filters and final filters in order to
monitor and analyze the performance of each
configuration‘s capability of handling a site’s
contaminants before purchasing filters.

The trailer is a tool that provides critical insight
into what filtration configuration will withstand the
harsh conditions of the surrounding environment,
prevent the need for water washing, and
eliminate corrosion-related maintenance.

THE SITE
The plant is located less than 20 miles from
the Gulf Coast, along the Mississippi River in
South Louisiana. This particular site has annual
temperatures averaging 70°F, with temperatures
between May and September often exceeding
90°F, with relative humidity over 90%1. During
summer, afternoon thunderstorms produce
heavy rainfall over short periods of time.

Situated in an industrial area, the turbines are
exposed to heavy dust concentrations of various
particulate matter such as gypsum and airborne
grain from neighboring production plants.

The combination of humidity and heavy dust load
makes this site a challenging environment.

CURRENT FILTER CONFIGURATION
The filter configuration in 2016 was a two-stage,
12” bag pre-filter, rated at an M5 efficiency and a
17” compact final filter, rated at an F92 efficiency.

Heat rate increases, caused by fouling, required
water washes for recovery. The team performed
daily online washes and two offline washes per
year; this resulted in a 2% improvement in the
heat rate each time they water washed offline.

THE TEST
The CamLab was commissioned at the site for
2200 hours (3 months) with three different,
2-stage configurations outlined in Table 1.

The table shows that the CamGT 3V-600 24”
E103 filter, while offering a better efficiency,
clearly outperformed the competitor’s 17”,
F9 filter in terms of pressure drop. The Camfil
CamGT 4V-300 12” E10 filter had a similar
pressure drop performance to the competitor
initially, even with its higher efficiency. This
highlights that filter depth is only one part of
the design - aerodynamics, media performance,
media surface area, as well as construction, are
equally important in designing a well-performing
filter.

The 3V-600 configuration performed well in
terms of pressure drop and efficiency due to its
24” deep frame (twice the depth of the 4V-300),
aerodynamic configuration, and optimized media
area. This deep frame allows for unparalleled
media area and low velocity, providing the
lowest pressure drop and longest available life.

In similar environments, the 3V-600 has lasted
over 5 years without change-out, resulting in
high engine availability.
1Philip Grigsby, Forecaster for the National Oceanic and Atmospheric Administration, U.S. Department of Commerce 2F9 per EN779:2012 : European filter rating system : Average Efficiency ≥ 95% on 0.4μm 3E10 per EN1822 : European filter rating system : E10: Initial Efficiency ≥ 85 on MPPS (most penetrating particle size), typically between 0.1-0.2μm CamGT 3V-600
Optimum water drainage capabilities
Plant Upgrades to the CamGT 3V-600
Over a 6-Year Lifecycle:

No Final Filter Change-Out
Prevent Engine Degradation
Cut Water Washes by Half
Potential of $937,000 USD Savings / Engine

LIFE CYCLE COST (LCC) ANALYSIS
An LCC, total cost of ownership analysis, was
performed to determine the most cost efficient
set-up.

Figure 1 indicates that the lowest total cost of
ownership over a six-year timeframe is predicted
for the 3V-600 configuration. Due to the higher
E10 efficiency class, the plant would encounter
minimal fouling effects. The majority of savings,
therefore, are a result of lesser fouling leading
to higher power output, with savings up to 88%
percent. By minimizing the fouling effect in this
case, Table 2 shows that the plant could reduce
maintenance needs by requiring half as many
offline washes.

Table 2 further shows that the 3V-600
configuration requires final filter change-out
after 48,000 hours. This would allow the plant
to meet their initiative of operating continuously
for six years without shutdown for final filter
replacement.

The plant is expected to potentially save a
total of approximately 29% as compared to
the competitor configuration, or an estimated
$937,000 USD over a six-year period4.

UPGRADE
As a result of the CamLab results and LCC
analysis, Camfil was awarded with the project of
installing the CamFlo prefilters as a first stage
and CamGT filters as a final stage.

ADVANTAGES OF THE CAMGTs5
A common phenomenon in ordinary inlet air
filters is bypass and leakage, which allows salt,
water, as well as coarse and submicron particles
to pass through filters. Controlling bypass and
leakage will prevent fouling and corrosion,
wearing down of turbine components, as well as
unnecessary and expensive downtime.

Gasket
The CamGT has a one-piece, poured in place
endless gasket as compared to four-pieces.

Since there are no openings with a one-piece
gasket, it prevents any water penetration.

Glue
The CamGTs solid, airtight frame is designed to
prevent any bypass due to Camfil‘s patented new
glue technique, the double sealing design. Media
is typically glued to the filter header with 2-4 glue
steps, however, the double sealing design is a
6-step glue technique that fixes the media to the
frame, which ensures leakage prevention.

Resistant to Humidity
The CamGT not only offers large media surface
area, it also features vertical pleating and
patented interrupted hot melt separators for
optimum water handling.

Its construction allows trapped water to drain
freely from the filter during operation, thus
avoiding re-entrainment of dissolved impurities
(i.e. salt) and maintaining low pressure drop
under high humidity conditions.
www.camfil.com/ps
Power Systems

CASE STUDY
Chart 1: Pressure Drop Over 3 Months Table 1: Filter Class and Pressure Drop Table 2: 6 Year Life Cycle Cost Analysis
0 0.2

0.4 0.6

0.8 1

1.2 1.4

1.6 1.8
4/20/2016 5/10/2016 5/30/2016 6/19/2016 7/9/2016 7/29/2016 8/18/2016 9/7/2016 Pressure Drop (inch wg)
Pressure Drop Over Time
SN5 + F9MH XMGT F7 + 4V300 E10 XMGT F7 + 3V600 E10
.77” in wg

1.23” in wg

1.06” in wg
CamGT Key Features:
• High filtration efficiency
• Low pressure drop also in wet
conditions
• Long filter life
• Resistance to turbulence
CamGT User Benefits:
• Increased turbine availability
• Lower fuel consumption
• Higher power output
• Extended turbine life
• Reduced life cycle costs (LCC)
Filter Filter
Class
Average
Efficiency

0.4μm
dP
”w.g.

Competitor 12” bag + 17” final M5 / F9 78.30% 1.06”
Camfil CamFlo 25” bag +
CamGT 4V-300, 12” F7 / E10 97.86% 1.23”
Camfil CamFlo 25” bag +
CamGT 3V-600, 24” F7 / E10 99.48% 0.77”
4 The LCC was calculated using site-specific data and cannot be used as a prediction for every site. Request a personalized LCC for your site: http://www.camfil.com/ps/Contact 5The CamGT 3V-600 and 4V-300 have the same media and filter frame. Due to the redesigned shape and increased amount of media in the 3V-600 versus the 4V-300, a much lower and stable pressure drop can be achieved.

Filter
Offline
Water
Wash
Expected
Final Filter
Life
Competitor 12” bag +
17” final
Twice /
Year 24,000 hrs
Camfil CamFlo F7 bag +
CamGT 4V-300, 12”
Once /
Year 16,000 hrs
Camfil CamFlo F7 bag +
CamGT 3V-600, 24”
Once /
Year 48,000 hrs
Figure 1: 6 Year Life Cycle Cost Analysis 1833000 1301000 54000 3188000
2168000
151000
63000
2382000
2055000
151000
45000
2251000

PRESSURE DROP IM PACT FOULING IM PACT INSTALLATION &

DISPOSAL COST OF

FILTERS
TOTAL
6YRS LCC TIME LINE OPEX
Current Solution: M5 + F9
Camfil Solution: F7 + E10 4V-300
Camfil Solution: F7 + E10 3V-600
29% SAVINGS!
88% SAVINGS!
Competitor 12” bag
Final 17”
Camfil CamFlo XMGT 25” Bag
Camfil 4V-300,12” Final
Camfil CamFlo XMGT 25” Bag
Camfil 3V-600 24” Final
Americas:

[email protected]
613-299-5691
Europe:

[email protected]
+4942147886180
Asia:

[email protected]
+918800504103
[email protected]
+8618602184677
Middle East:

[email protected]
+97148865882
D
E
A C
B
E
C
A
B
D
A Front view
B Upper view
C Left view
D Right view
E Bottom view
ISO VIEW's
No Revision Date Drawn Appr
A First release. KAS

GENERAL TOLERANCES
Machining ISO 2768-c
Welding:

General EN-ISO 13920-BH
Flanges EN-ISO 13920-F
Sheet / No of sh
Order No
Quotation
Total Surface Area (m²)
NB! Tube internal
surfaces included
Weight (kg)
Rev.

Drawn by Approved by Date Scale Projection method
Drawing No
www.camfil.com
E-mail: [email protected]
Sh format
State
/
120700303 A

1 KAS 1:20

1 General Arrangement and Assembly Drawing

CHECKED_IN
A1 Filterhouse 6W x 3H Front Access

93.9 2385
157.81
4008.4
167.97
4266.5
Skid Weather louver LH Weather louver RH

44.35 1126.5

9.45 240
10 254
.28
7 37.6
955
.08
2 A
A
Transition
Filter module 6W x 3H
Weather louver 3W x 3H (2x)
skid
CL

90.4 2296.1

90.4 2296.1
90°
90°
127.683243.1
126.7
3218.1
Weather louver LH
Weather louver RH
Transition CamGT 3V-600 E10 (18x)
View with louvers open
118.2
3002.3 (ins.)

70.8 1798.3 (ins.)
A-A
Outlet flange detail
Note: This is a proposal drawing, NOT to be used for manufacturing Note:
- Dimensions inside [ ] are imperial units.
- The approximate weight of the overall assembly without filters is 1500 kg.

Camfil Power Systems reserves all rights in respect of this document. Unautthorized use of this document or its contents is prohibeted.

Page 16 of 17 ends

EXHIBIT B

SCHEDULE

Page 17 of 17 ends

EXHIBIT C

EQUAL EMPLOYMENT OPPORTUNITY

PRACTICES PROVISIONS
A. Contractor certifies and represents that, during the performance of this Agreement, the contractor and each subcontractor shall adhere to equal opportunity employment practices to assure that applicants and employees are treated equally and are not discriminated against because of their race, religious creed, color, national origin, ancestry, handicap, sex, or age. Contractor further certifies that it will not maintain any segregated facilities.

B. Contractor agrees that it shall, in all solicitations or advertisements for applicants for employment placed by or on behalf of Contractor, state that it is an "Equal Opportunity Employer" or that all qualified applicants will receive consideration for employment without regard to their race, religious creed, color, national origin, ancestry, handicap, sex or age.

C. Contractor agrees that it shall, if requested to do so by the City, certify that it has not, in the performance of this Agreement, discriminated against applicants or employees because of their membership in a protected class.

D. Contractor agrees to provide the City with access to, and, if requested to do so by City, through its awarding authority, provide copies of all of its records pertaining or relating to its employment practices, except to the extent such records or portions of such records are confidential or privileged under state or federal law.

E. Nothing contained in this Agreement shall be construed in any manner as to require or permit any act which is prohibited by law.