CITY OF VERNON

PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 14 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS PROJECT: Atlantic Blvd. Bridge over the Los Angeles River Contract No. CS-0099 FEDERAL PROJECT No. DBPL02-5139(010) Project No. 103001 REQUESTED BY: City of Vernon Supplemental No.

TO: CNS Engineers, Inc. CONTRACTOR
You are hereby directed to make the herein described changes to the plans and specifications or do the following described work not previously included in the plans and specifications of this contract. Except as specifically modified herein, all terms and conditions of the original contract remain in full force and effect, and apply to the additional work as if said work was originally included in the contract.

Per the Request for Contract Amendment No. 14 from Contractor dated December 6, 2023, this Change Order provides for the additional work described below.

1. Extend the contract for an additional one-year period from December 31, 2023 to December 31, 2024, and increase the total not-to-exceed amount by an additional $177,070.27.

The project involves complex and lengthy right-of-way acquisition in BNSF, LADWP, LACFCD, and private properties; therefore the project schedule must be extended to finalize Construction and Managements Agreements, utility relocation coordination, and completion of Right of Way Certification and easements.

2. Design team to perform extra work to incorporate the new 2023 Caltrans Construction Contract Standards into the plans and finalize various easements, construction agreements, and permits.

Contract Amount (Base Bid) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 1,155,284.38 Amount of This Change Order . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 177,070.27 Amount of Previous Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 1,124,393.56 Total Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 1,301,463.83 Modified Contract Amount . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 2,456,748.21 By reason of this change order the time of
completion will be adjusted as follows: 365 additional calendar days Approved: Date:

Carlos Fandino, City Administrator
Attest: Date:

Lisa Pope, City Clerk
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all labor, equipment and materials, including overhead, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above.

Accepted Date: Contractor:

By: Title:

Accepted Date: Contractor:

By: Title:
c: Project File/Contractor/Purchasing Rev. 01/13
12/7/2023 CNS Engineers, Inc.

Principal James J. Lu
12/7/2023 CNS Engineers, Inc.

Hui-Min Huang CFO
Civil and Structural Engineers
11870 Pierce Street, Suite 265, Riverside, CA 92505
Phone: (951) 687-1005 / Fax: (951) 667-3387 / Web: www.cnseng.com December 6, 2023
Mr. Daniel Wall, P.E.

Director of Public Works
City of Vernon
4305 Santa Fe Avenue
Vernon, CA 90058
Subject: Rehabilitation of Atlantic Blvd. Bridge over the Los Angeles River Request for Contract Amendment No. 14
Dear Mr. Wall:

To complete the proposed project, we request an amendment for extra work as follows:

1. Extend the Professional Service Agreement (PSA) from December 31, 2023, to December 31, 2024:

CNS’s PSA will expire on December 31, 2023. The project has completed the design; however, there are several pending items listed below to be continuously coordinated and completed before the project is certified by Caltrans and ready to be advertised for construction:
 Close acquisition escrow and record easements for the impacted LADWP properties (6304-007- 274 and 6314-033-271). The acquisition cost has been finalized.  Finalize acquisition for the easements in the Magellan Atlantic property (APN 6314-033 and 005). A temporary user agreement is in place for Caltrans right of way certification.  Execute the BNSF Railroad Construction and Management (C&M) Agreement that addresses all railroad-related costs.
 Obtain the CPUC GO 88B Construction Permit. CPUC comments have been addressed.  Coordinate with the City and SCE to obtain a design permit from BNSF for the temporary electrical overhead shoofly and the permanent electrical underground casings below the at-grade rail crossings, which are prepared by City’s Consultant (Petrelli Electric). The initial permitting application has been submitted to BNSF.
 Obtain an encroachment permit from Caltrans District 7 for traffic controls at the I-710/Bandini Interchange involving 4-day street closure to replace the rail crossings adjacent to the bridge.  Complete utility relocation coordination involving the City, SCE and Maywood Mutual Water Company #3.
 Obtain the Right of Way Certification from Caltrans.
 Assist the City in obtaining Construction Authorization from Caltrans including obtaining NEPA Revalidation, if required by Caltrans Local Assistance.  Provide additional project coordination and attend additional Teams meetings for one year.

2. Engineering Design Modification to Implement the 2023 Caltrans Construction Contract Standards Design History: The design of the project was completed prior to 2021 while right of way acquisition, utility relocation, and railroad coordination were being coordinated. The project design was based on Caltrans 2018 Construction Contract Standards. Caltrans periodically (usually every three to four years) updates the construction contract standards. Although the Caltrans 2022 Standards were published on August 1, 2022, the 2018 Standards can be continuously used for federally funded projects receiving construction authorization before May 1, 2023, in accordance with a notice issued by Caltrans Local Assistance on November 9, 2022. On April 21, 2023, Caltrans issued a Mr. Daniel Wall
December 5, 2023

Page 2 of 2 ends

memorandum stating that the 2022 Standards will be no longer supported after July 21, 2023, and the new 2023 Standards will be published on July 24, 2023. Caltrans Local Assistance currently requires local agencies to implement the 2023 Standards for the HBP-funded bridge projects since the construction of the Project has not been authorized.

Required Design Modifications: The Caltrans 2023 Construction Contract Standards include Standard Specifications, Standard Special Provisions, and Standard Plans. The Standard Plans implement new design criteria involving the Eight Edition of AASHTO LRFD Bridge Design Specifications, California Amendments with 2022 Errata, and Seismic Design Criteria (SDC) Version 2.0.

The Design Team will update the project plans, technical special specifications, quantities, and cost estimates per the Caltrans 2023 Construction Contract Standards. The design modification will involve project elements that reference the Caltrans design standards, which include the bridge, retaining walls, traffic signals, and striping. The geotechnical foundation report per SDC 2.0 shall be updated accordingly.

3. Project Schedule: This amendment is necessary due to the delay associated with the lengthy coordination with BNSF, LADWP, relocation of SCE Communication Line, and addition of an Electrical Overhead Shoofly. It is expected that all project components will be completed by June 2024 and the right of way can be certified by Caltrans by August 2024. The construction funds will be requested in the Caltrans HBP Annual Survey in September 2024.

The estimated cost for all additional efforts to extend the PSA is $177,070.27.

Current Amended Contract Amount: $2,279,677.94
Proposed New Amendment: $177,070.27
Total Proposed Amended Contract Amount: $2,456,748.21
We look forward to receiving City’s approval for this contract amendment. Should you have any questions about this proposal, please feel free to contact me at (951) 687-1005 ext.104 or by e-mail at [email protected].

Sincerely,
James Lu, P.E., S.E.

Project Manager / Principal
CNS Engineers, Inc.

Attachment: Cost proposal backup details
Local Assistance Procedures Manual
Date:

DIRECT LABOR Hourly Rate
Range Hours Total
68 @ 103.00 $ 7,004.00 $
40 @ 79.00 $ 3,160.00 $
24 @ 53.00 $ 1,272.00 $
64 @ 75.20 $ 4,812.80 $
24 @ 48.20 $ 1,156.80 $
0 @ - $ - $
0 @ - $ - $
Total Direct Labor Costs (DLC)
Rate Total
* %
Total Fringe Benefits (FB)
INDIRECT COSTS Total
Overhead (OH) * % *
General and Administrative (G&A) * % *
Total (* Combined FB, OH and G&A) 137.07 % 23,857.86 $
Total Indirect Costs (IC)
FEE (PROFIT) Rate Total
10 % 4,126.35 $
Fee (DLC+FB+IC)

ESTIMATED OTHER DIRECT COSTS (ODC)
(ODC is actual cost to be reimbursed with supporting documentation.)

1. Reproduction and Binding - $

2. Conference Calls - $

3. Transportation / Travel (Mileage will be IRS standard rate.) - $

4. Overnight Deliveries - $
Total Other Direct Costs
$ 45,389.80

SUBCONTRACTOR COSTS
KOA Corporation (Traffic) 19,655.23 $
Overland , Pacific & Cutler (Right of Way Appraisal and Acquisition) 18,366.90 $ Stantec (Roadway, Right of Way Easements, Regulatory Permits) 15,485.82 $ RailPros (Railroad) 68,171.95 $
Converse (Geotechnical) 10,000.57 $
GPA (Environmental) - $
Total Subcontractor Costs

TOTAL CONTRACT COST
Senior Bridge Engineer
Bridge Project Engineer
Senior CADD Designer
Project Manager (PM) / Principal
Bridge Engineer James Lu
Senior Roadway Engineer / Deputy
PM
Project Name:

Consultant:

Hourly Rate
Classification Name (2024)
Rehabilitation of Atlantic Blvd. Bridge over the Los Angeles River CNS Engineers, Inc. (Prime Consultant)
EXHIBIT 10-H

CITY OF VERNON

COST PROPOSAL
Federal Project No. 5139 (010)
Caltrans EA No. 0793210L 12/5/2023
Subtotal Direct Labor Costs 17,405.60 $
Anticipated Salary Increases (0.0%) (Escalation) - $
$ 131,680.47
$ 177,070.27
$ 17,405.60

FRINGE BENEFITS
$ -
$ 23,857.86
$ 4,126.35
$ -
Prime Consultant (CNS) Cost:

Project Name:

Consultant: CNS Engineers, Inc. (Prime Consultant) Date: 8/3/20 Task No. Task Description
Project Manager
(PM) / Principal
Bridge Engineer
Senior Bridge
Engineer
Bridge Project
Engineer
Senior Roadway
Engineer / Deputy
PM
Senior CADD
Designer Total Hours Labor Cost
(loaded billing rates) $ 268.60 $ 206.01 $ 138.21 $ 196.10 $ 125.69

1.0 1.01 Meetings and Coordination 24 8 8 40 9,663.35 $

1.02 Project Administration and Project Controls 16 16 4,297.60 $

1.03 Quality Control and Quality Assurance 8 16 24 5,286.47 $

1.04 Caltrans Local Assistance Funding Supports 16 16 32 7,435.27 $

2.0 2.01 Data Collection 0 - $

2.02 Field Review and Site Assessment 0 - $

2.03 Design Surveys and Orthophoto 0 - $

2.04 Right-of-Way Research and Base Mapping 0 - $

2.05 Utility Notification and Identification including
Potholing 0 - $

2.06 Geotechnical Investigations 0 - $

2.07 Limited Phase II Soil Sampling (RR Contamination) 0 - $

2.08 Diurnal and Nocturnal Bat/Nesting Bird Surveys 0 - $

2.09 Bridge Aesthetic Analysis and Historic Preservation Report 0 - $

2.10 Roadway Drainage Report 0 - $

2.11 Storm Water Quality Documentation 0 - $

2.12 Railroad Phasing and Signal Requirements 0 - $

2.13 Channel Hydraulics and Modification Requirements 0 - $

3.0 3.01 Resource Agency Permits (CDFG 1601, RWCB 401
and ACOE 404 and 408) 0 - $

3.02 CPUC General Order 88B Application 0 - $

3.03 Railroad C&M Agreement Assistance 0 - $

3.04 Utility Relocation Supports 0 - $

3.05 Right-of-Way Plats and Legal Description 0 - $

3.06 Right-of-Way Easement/Acquisition Supports 0 - $

4.0 4.01 Roadway Plans 0 - $

4.02 Stage Constructing Plans 0 - $

4.03 Utility Plans 0 - $

4.04 Drainage Plans 0 - $

4.05 Traffic Signal Plans 0 - $

4.06 Work Area Traffic Control Plans 0 - $

4.07 Signing and Striping Plans 0 - $

4.08 Street Lighting Plans and Sign Illumination Plans 0 - $

4.09 Channel Modification Plans 0 - $

4.10 Bridge Unchecked Plans 0 - $

4.11 Grade Crossing Plans 0 - $

5.0 5.01 Roadway Plans 0 - $

5.02 Stage Constructing Plans 0 - $

5.03 Utility Plans 0 - $

5.04 Drainage Plans 0 - $

5.05 Traffic Signal Plans 0 - $

5.06 Work Area Traffic Control Plans 0 - $

5.07 Signing and Striping Plans 0 - $

5.08 Street Lighting Plans and Sign Illumination Plans 0 - $

5.09 Channel Modification Plans 0 - $

5.10 Bridge Checked Plans 0 - $

5.11 Grade Crossing Plans 0 - $

5.12 Special Provisions and Workday Schedule 0 - $

5.13 Quantities and Cost Estimates 0 - $

5.14 Supplemental Cultural Study 0 - $
Design Coordination
65% Design Submittal
95% PS&E Submittal
PS&E Initiation

CITY OF VERNON
Cost Proposal - Man Hour Worksheet
Atlantic Blvd. Bridge over the Los Angeles River
Phase I: Development of Plans, Specifications and Estimates (PS&E) Project Management

Page 2 of 3 ends

Project Name:

Consultant: CNS Engineers, Inc. (Prime Consultant) Date: 8/3/20 Task No. Task Description
Project Manager
(PM) / Principal
Bridge Engineer
Senior Bridge
Engineer
Bridge Project
Engineer
Senior Roadway
Engineer / Deputy
PM
Senior CADD
Designer Total Hours Labor Cost
(loaded billing rates) $ 268.60 $ 206.01 $ 138.21 $ 196.10 $ 125.69

CITY OF VERNON
Cost Proposal - Man Hour Worksheet
Atlantic Blvd. Bridge over the Los Angeles River

6.0 6.01 Roadway Plans 24 24 4,706.50 $

6.02 Stage Constructing Plans 0 - $

6.03 Utility Plans 0 - $

6.04 Drainage Plans 0 - $

6.05 Traffic Signal Plans 0 - $

6.06 Work Area Traffic Control Plans 0 - $

6.07 Signing and Striping Plans 0 - $

6.08 Street Lighting Plans and Sign Illumination Plans 0 - $

6.09 Channel Modification Plans 0 - $

6.10 Bridge Plans 4 32 24 24 84 14,000.60 $

6.11 Grade Crossing Plans 0 - $

6.12 Special Provisions and Suggested Workday Schedule 0 $ -

6.13 Quantities and Cost Estimates 0 - $

6.14 Resident Engineer's Pending Files 0 $ -
Total Hours 68 40 24 64 24 220 45,389.80 $
100% (Final) PS&E Submittal
2

Page 3 of 3 ends

Atlantic Blvd Bridge Replacement Page 1
CNS; City of Vernon JB73140 - Amendment #8
333 S. Anita Drive, Orange, CA 92868
T: 714.573.0317 | F: 714.573.9534 | www.koacorp.com

MONTEREY PARK ORANGE ONTARIO SAN DIEGO
December 5, 2023
Mr. James Lu
CNS Engineers, Inc.
11870 Pierce Street, Suite 265
Riverside, CA 92505
Subject: Atlantic Boulevard Bridge Reconstruction Project, Vernon, CA Amendment #8: Contract Extension for Final Approved Engineering Plans Dear Mr. Lu,
KOA Corporation (KOA) is submitting this amendment at the request of CNS for revisions to the latest engineering plans to update the plans, specifications and special provisions to comply with current local and State (Caltrans) 2023 Standards. Below is a summary of scope of services justifying the additional requested budget for the proposed contract extension.

SCOPE OF WORK
Management, Coordination, & Administration
KOA will provide availability to attend up to three (3) additional project team meetings (through December 2024) with the project team to discuss the development of the updated construction documents, including design-related issues, schedule, deliverables, etc. We will maintain lines of communication between CNS throughout the completion of this work. We will invoice in the same manner as the original contract, including summary of monthly progress using CNS’ standard form template.

Caltrans/Agency-Approved Traffic Control, Signing & Striping and Bridge Lighting Plans KOA’s latest plan set must be updated to current Caltrans standards, and has not yet been approved by the local agencies and/or Caltrans. The engineering plans to be updated and finalized as part of this task will incorporate the standards, guidelines and optional design directions established in (1) the latest California MUTCD (Revision 7 – March 10th, 2023); and (2) the Caltrans 2023 Standard Plans (July 24, 2023).

This amendment work also covers anticipated review and comment of the updated engineering plans by local agencies (Vernon, Maywood, Bell), LA Metro, CPUC and Caltrans, particularly in regards to traffic control and detouring impacts near the I-710/Atlantic/Bandini interchange. We will submit for review and revise the engineering plans as directed up to two (2) times for approval by local agencies and Metro, and up to two (2) times for approval by the CPUC and Caltrans. The engineering plan revisions will include the following sheets:
• Traffic Control Plans – Stages 1, 2A, 2B, 2C, 2D, D-A, 3A, 3A-B, 3B-A,B,C,D 11 sheets • Traffic Control and Detour Plans – 4-Day Bridge Closure 4 sheets • Signing and Striping Plan 2 sheets
• Street/Bridge Lighting Plan 1 sheet
Total 18 sheets

Atlantic Blvd Bridge Replacement Page 2
CNS; City of Vernon JB73140 - Amendment #8
333 S. Anita Drive, Orange, CA 92868
T: 714.573.0317 | F: 714.573.9534 | www.koacorp.com

MONTEREY PARK ORANGE ONTARIO SAN DIEGO
This scope of work does not include bid, pre-construction or construction phase support such as pre-bid meetings; bidding interpretations/addenda; review/evaluation of bids; pre-construction/site meetings; review and response to Contractor RFIs and/or submittals; preparation of design addenda; as-built plan preparation; or any other related project close-out tasks.

Revised Specifications and Estimates
KOA will provide updated technical specifications, special provisions, take-off quantities and cost estimates in compliance with Caltrans 2023 Standard Specifications and Contract Item Codes (July 24, 2023).

FEE
KOA will perform the above scope of work for a not-to-exceed fee of $19,655.23. Please see attached fee breakdown.

WORK SCHEDULE
KOA will coordinate with CNS to deliver the revised plans and construction documents in accordance with the Project’s master schedule. Upon receiving Notice To Proceed (NTP) and direction to commence the design revisions, KOA will accommodate completion of the first revised submittal for the Client’s review within six (6) weeks from said notice. Subsequent revisions will be competed approximately three (3) weeks after receiving comments from the Client and/or the reviewing agencies.

KOA is not responsible for delays caused by factors beyond KOA’s reasonable control, including but not limited to delays because of strikes, lockouts, work slowdowns or stoppages, accidents, acts of God, failure of any governmental or other regulatory authority to act in a timely manner, failure of the Client to furnish timely information or approve or disapprove of the KOA’s services or work product promptly, or delays caused by faulty performance by the Client or by contractors of any level. When such delays beyond KOA’s reasonable control occur, the Client agrees the KOA is not responsible for damages, nor shall KOA be deemed to be in default of this Agreement.

Atlantic Blvd Bridge Replacement Page 3
CNS; City of Vernon JB73140 - Amendment #8
333 S. Anita Drive, Orange, CA 92868
T: 714.573.0317 | F: 714.573.9534 | www.koacorp.com

MONTEREY PARK ORANGE ONTARIO SAN DIEGO

AUTHORIZATION
The signature below indicates acceptance of this proposal and authorization to proceed.

Sincerely,
KOA Corporation
Shirjeel Muhammad, MS, PE
Principal
The person signing and executing this contract for the Client represents and warrants that he or she is duly authorized and has legal capacity and actual authority to bind the Client to each and every term, condition and obligation of this Contract and that all requirements of the Client have been fulfilled to provide such actual authority. By signing below, Client agrees with the terms and conditions attached hereto and hereby made a part of this agreement.

Signature

Name (Please Print) Date

Title (Please Print) Client Purchase Order or Project Number Local Assistance Procedures Manual
Date:

KOA Corporation
DIRECT LABOR Hourly Rate
Range Hours Total
- 2 @ 102.85 $ 205.70 $
- 24 @ 83.99 $ 2,015.88 $
- 8 @ 80.57 $ 644.53 $
- 50 @ 49.71 $ 2,485.56 $
- 4 @ 52.28 $ 209.13 $
@ - $
@ - $
@ - $
@ - $
@ - $
@ - $
@ - $
@ - $
Total Direct Labor Costs (DLC)
Rate Total

54.79 % 3,122.94 $
Total Fringe Benefits (FB)
INDIRECT COSTS Total
Overhead (OH) 44.75 % 2,550.67 $
General and Administrative (G&A) 59.16 % 3,372.02 $
Total (* Combined FB, OH and G&A) 158.7 % 9,045.63 $
Total Indirect Costs (IC)
FEE (PROFIT) Rate Total
10 % 1,786.84 $
Fee (DLC+FB+IC)

ESTIMATED OTHER DIRECT COSTS (ODC)
(ODC is actual cost to be reimbursed with supporting documentation.)

1. Reproduction and Binding $ -

2. Plotting $ -

3. Transportation / Travel (Mileage will be IRS standard rate.) $ -

4. Overnight Deliveries $ -
$ -
Total Other Direct Costs

SUBCONTRACTOR COSTS

TOTAL COST
$ -
$ -
$ 19,655.23
$ 3,122.94
$ 9,045.63
$ 1,786.84
$ -
$ -
$ -
Subtotal Direct Labor Costs 5,560.81 $
Anticipated Salary Increases (2.5%) (Escalation) 139 $ .02 $ 5,699.83

FRINGE BENEFITS
Engineer Associate Various
Designer Various
Principal Various
Project Manager Various
Engineer Various
Project Name:

Consultant:

Initial Hourly
Classification Name Rate
Addendum #8 Contract Extension for Final Approved Engineering Plans EXHIBIT 10-H

CITY OF VERNON

COST PROPOSAL
Federal Project No.:

Caltrans EA No.: 12/5/2022
www.OPCservices.com | 5000 Airport Plaza Drive, Suite 250, Long Beach, CA 90815 ph 562.304.2000 | fx 562.304.2020
November 17, 2022
Mr. James Lu, PE, SE
Senior Manager/Principal
CNS Engineers, Inc.
11870 Pierce Street, Suite 265
Riverside, CA 92505
Sent Via Email: [email protected]
RE: Rehabilitation of Atlantic Blvd. Bridge over the Los Angeles River Contract Amendment No. 9
Dear Mr. Lu:

As discussed, an amendment to our contract is necessary for work associated with the coordination of utilities and continued acquisition activities for the subject City of Vernon (City) bridge rehabilitation project (Project).

Our acquisition services will continue as follows:

1. Continue to be the primary point of contact for all acquisition activities, escrow coordination, including certification, through the December 2023 extension of the contract.

2. OPC will continue acquisition efforts obtaining licenses and acquisition documents for 6304-007-274, 6314- 033-271 LADWP, 6314-003-010 Amazon, 6314-003-900 & 901 BNSF, 6314-033-002-Magellan and 6314- 003-001 Krystal Enterprises and Clear Channel.

Utility Coordination will be led by David Moore, Senior Utility Manager, who will be the day-to-day coordinator on the Project. Utility coordination support work as follows:

1. Act as the primary point of contact with conflicting utility owners.

2. Actively participate in Project Development Team to update the City and Team on the progression of utility work (estimated eight meetings).

3. Issue updated Notice to Relocate Claim Letters using City provided templates (two conflicting utility owners).

4. Work with the design team to develop and update a utility conflict matrix.

5. Determine liability for the utility conflicts that are impacted by the Project (SCE and Maywood Mutual Water).

6. Coordinate and plan with the utility owners and their designers as needed to discuss Project design, conflicts, relocation alternatives, and resolution to conflicts (estimated two utility owners and five conflicts for a total of 12 meetings including face to face, field and teleconference).

7. Obtain detailed scopes of work from the utility owners for relocation, estimated start and completion dates and proposed cost to perform and complete the relocation activity.

8. Issue Notice to Owner to relocate using City provided letterhead.

9. Prepare and execute Utility Agreements (UA) for utility owners who have prior rights and conflict with the Project (estimated two UA).

10. Prepare Caltrans required Reports of Investigation for each utility owner.

11. Work with the City and utility owner to ensure the relocation plan is compatible with permit requirements.

12. Prepare and execute through Caltrans, the FHWA Specific Authorizations for utility relocations and utility agreements.

13. Prepare the utility section of the Right of Way Certification.

Rehabilitation of Atlantic Blvd. Bridge over the Los Angeles River Contract Amendment No. 9 Page | 2
Accepted, Authorization to Proceed:

Additional Fees of $18,366.90

Signature/Title:
_______
Date:

Assumptions/Exclusions

1. All conflicts will be determined by the Design team. The above estimates are based on information provided by the Design team. Changes in these items may result in increased/decreased scope.

2. All City owned facilities including utility service-related items (water meters, traffic signals and City owned streetlights) are not considered part of this scope. These items will be identified by Design, but actual noticing and detailed coordination is not necessary and relocation work will be conducted by the awarded road contractor.

3. Scope does not include any fees or work associated with the actual relocation of the utility facilities and/or construction management/inspection.

The amendment is necessary due to design changes and delays to the Project. The additional fees are for utility coordination work as indicated above.

Additional costs to complete the identified services as described will be $18,366.90, comprised of $6,444.52 and $11,922.38 for utility coordination. Back up documentation for our fees are included in Exhibit 10-H1 attached.

Based on this additional work, our revised contract amount would be as follows:

Original Contract Amount $ 57,764.65
Amendment No. 1 $ 6,300.00
Amendment No. 2 $ 40,086.70
Amendment No. 3 $ 90,912.04
Amendment No. 4 $ 47,410.00
Amendment No. 5 $ 800.00
Amendment No. 6 $ 6,061.00
Amendment No. 7 $ 24,450.00
Amendment No. 8 $ 24,108.76
Amendment No. 9 (this amendment) $18,366.90
Total New Contract Amount: $316,260.05
If the proposed Contract Amendment No. 9 meets your approval, please sign below and return it to me and/or provide a contract change order authorization in a form acceptable to you. Should you have any questions or need additional information, please contact me at 562.304.2028 or [email protected].

Sincerely,
Roy Guinaldo, RWA
Senior Project Manager
OPC
Roy Guinaldo
Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal
Prime Consultant Subconsultant 2nd Tier Subconsultant
Consultant:

Project No. Contract: Date 11/17/2022
Hours Actual Hourly Rate Total

60.0 $ 4,326.76

35.0 $ 1,380.12

10.0 $ 360.60
Mia Garcia 1.0 $ 39.43

20.0 $ 558.63
$ 6,665.54
$ -
$ -
$ -

LABOR COSTS
$ 6,665.54
$ -
$ 99.98
d) TOTAL DIRECT LABOR COSTS [(a) + (b)+(c)] $ 6,765.52

INDIRECT COSTS

0.00% ) i) Total Fringe Benefits [(d) x (e)] 0.00

0.00% j) Overhead [(b) x (f)] 0.00
g) Overhead Office (Rate: 149.00% ) k) Overhead [(a) x (g)] 9,931.65

0.00% ) l) Gen & Admin [(d) x (h)] 0.00
m) TOTAL INDIRECT COSTS [(i) + (j) + (k)+(l)] $ 9,931.65 FIXED FEE n) TOTAL FIXED FEE [(d) + (j) + (k)] x fixed fee 10.00% ] 1,669.72 o) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary) Quantity Unit Total
$ -
p) TOTAL OTHER DIRECT COSTS $ -
q) SUBCONSULTANTS' COSTS (Add additional pages if necessary) $ -
r) TOTAL SUBCONSULTANTS' COSTS $ -
s) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(p) + (r)] $ - TOTAL COST [(d) + (m) + (n) + (s)] $ 18,366.89
NOTES:

1. 2.

3.

Page 1 of 3 ends

January 2020
$ 27.93
Senior Agent $ 36.06
Project Control Manager $ 39.43
Maria Martinez/Inez Garcia
$ 39.43
f) Overhead Field (Rate:

Description of Item
Field Personnel
Total Office Direct Labor
a) Subtotal Direct Labor Costs - Office
Unit Cost
Total Field Direct Labor $ -
h) General & Admin (Rate:

Project Coordinator
c) Anticipated Salary Increases (see page 2 for calculation) David Moore $ 72.11
Senior Project Manager Roy Guinaldo
Anticipated salary increases calculation (page 2) must accompany.

Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.

The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the consultant's annual accounting period and established by a cognizant agency or accepted by Caltrans. e) Fringe Benefits (Rate:
b) Subtotal Direct Labor Costs - Field
EXHIBIT 10-H1 COST PROPOSAL Page 1 of 3
Note: Mark-ups are Not Allowed
Name
Overland, Pacific & Cutler, LLC

DIRECT LABOR
Classification/Title
City of Vernon Rehabilitation of Atlantic Blvd. Bridge over the Los Angeles River

ACTUAL COST-PLUS-FIXED FEE OR LUMP SUM (FIRM FIXED PRICE) CONTRACTS Office Personnel
Senior Utility Manager
Stantec Consulting Services Inc.
38 Technology Drive, Irvine CA 92618-5312
November 30, 2023
File: 2073013430
Attention: James Lu
CNS Engineers, Inc.
11870 Pierce Street, Suite 265
Riverside, CA 92505
Dear Mr. Lu,
Reference: Cost Proposal for 2024 Contract Extension with Miscellaneous Tasks The contract is to be extended from 12/31/2023 to 12/31/2024. Stantec Consulting Services Inc. (Stantec) is requesting a contract amendment for additional services, which includes additional project management and coordination, completion of PS&E documents to current standards.

Services will be provided on a time-and-materials, not-to-exceed basis based upon the employee’s current year hourly rate plus fringe benefits, indirect costs, and fee (profit) as calculated in the fee summary attached.

The attached proposal includes the following information:
• Scope of Services
• Fee Summary
Please feel free to respond with any questions or comments.

Regards,
Stantec Consulting Services Inc.

Susan Reid P.E.

Project Manager
Phone: 949 923 6223
[email protected]
Sherry Weinmeier
Principal, Transportation Planning & Traffic
Engineering
Phone: 949 923 6265
[email protected]
November 30, 2023
James Lu

Page 2 of 2 ends

Reference: Cost Proposal for 2024 Contract Extension with Miscellaneous Tasks Scope of Services
• Extension of contract from 12/31/2023 to 12/31/2024. This one-year project extension requires additional project management and additional project coordination with CNS, the City of Vernon, various agencies, and other project consultants and parties to the project. Miscellaneous minor exhibits and details are also included, as well as minor finalization of the PS&E documents to current Caltrans 2023 standards. Additional oversight, quality control, contract review and administration are also required. This task includes 2 hours for Stantec Team Leader, 60 hours for the Roadway Design Lead, 2 hours for Survey Project Manager and 2 hours for Administrative Services.

Fee Summary
See attached spreadsheet.

TOTAL : $15,485.82
Local Assistance Procedures Manual
Date:

Stantec Consulting, Inc.

DIRECT LABOR Hourly Rate
Range Hours Total
2 @ $ 103.98 $ 207.96
60 @ $ 67.78 $ 4,066.80
2 @ $ 79.33 $ 158.66
2 @ $ 44.55 $ 89.10
Total Direct Labor Costs (DLC)
Rate Total
52% % $ 2,343.12
Total Fringe Benefits (FB)
INDIRECT COSTS Total
Overhead (OH) 107.67% % $ 4,869.26
General and Administrative (G&A) * % *
Total (* Combined OH and G&A) 159% % *
Total Indirect Costs (IC)
FEE (PROFIT) Rate Total
10 % $ 1,407.80
Fee (DLC+FB+IC)

ESTIMATED OTHER DIRECT COSTS (ODC)
(ODC is actual cost to be reimbursed with supporting documentation.)

1. Reproduction and Binding $ -

2. Plotting $ -

3. Transportation / Travel (Mileage will be IRS standard rate.) $ -

4. Overnight Deliveries $ -

5. 2-man Field Survey Truck and Equipment $ -
Total Other Direct Costs

SUBCONTRACTOR COSTS
Potholing
Aerial Mapping
TOTAL COST $ 15,485.82
Anticipated Salary Increases (3.35 %) (Escalation) $ -
$ 4,522.52

FRINGE BENEFITS
$ 2,343.12
$ 7,212.38
$ 1,407.80
$ -
$ -
$ -
$ 4,522.52
Survey Project Manager Jim Steines
Administrative Services Connie Woodward
Subtotal Direct Labor Costs
Stantec Team Leader Sherry Weinmeier
Roadway Design Lead Susan Reid
Project Name: Atlantic Blvd. Bridge over the Los Angeles River Consultant:

Hourly Rate
Classification Name (2024)
EXHIBIT 10-H

CITY OF VERNON
COST PROPOSAL FOR 2024 CONTRACT EXTENSION, MISC
Federal Project No.:

Caltrans EA No.: 11/30/2023

Page 1 of 5 ends

250 Commerce, Suite 200
Irvine, CA 92602
P: (714) 734 - 8765 F: (714) 734 - 8755
w w w . r a i l p r o s . c o m
Atlantic Boulevard Bridge Widening
Contract Amendment No. 9
Scope of Work Amendment
December 4, 2023
A scope amendment is required to obtain permits from BNSF/LAJ for the proposed electrical underground utility casings at three locations under the North and South Atlantic Blvd at-grade railroad crossings and one temporary electrical overhead utility shoofly over the Temporary Construction Easement (TCE) areas at two locations over the North and South Atlantic Blvd atgrade railroad crossings. Also, the previous contract is soon to expire on December 31, 2023, and a scope amendment is required to extend the contract from December 31, 2023, to December 31, 2024. The extended contract length of one year generates the need for additional general project management, meetings, and coordination with stakeholders, which is captured in this contract amendment.

The Amendment No. 9 tasks outlined below are in addition to the tasks currently authorized on the project:
• Utility design review and permitting services for the proposed electrical underground utility casings and temporary electrical overhead utility shoofly crossings at the BNSF/LAJ Atlantic Blvd at-grade railroad crossings.
• Contract time extension for one year. Project Management, Railroad Design Coordination, and PS&E services extended from December 31, 2023, through December 31, 2024.
• Additional general project management, meetings, bid support, design reviews and support and permitting, and coordination services due to contract time extension and anticipated stakeholder feedback and requirements.

The attached cost proposal details our expected costs and staff to complete this additional work. RailPros is requesting $68,171.95 in additional authorization.

We look forward to continuing to work with CNS and the City towards the successful completion of this project. Please feel free to contact us if you have any questions regarding this.

Robert Williams, PE
Project Manager
250 Commerce | Suite 200 | Irvine | California | 92602
Direct 949.383.2331 | Office 714.734.8765 | Mobile 714.797.7809 [email protected] | www.railpros.com

Page 2 of 5 ends

250 Commerce, Suite 200
Irvine, CA 92602
P: (714) 734 - 8765 F: (714) 734 - 8755
w w w . r a i l p r o s . c o m

1.0 PROJECT MANAGEMENT

1.01 Meetings and Coordination
Addition of the following scope to this task:

Task Objective
RailPros shall participate in project meetings as specified below and perform general project coordination efforts with respective to the City, BNSF/LAJ, and design team staff.

RailPros Activities
• General project coordination efforts to deliver a quality product through time extension (December 2023 – December 2024).
• Meetings: Participate in up to 6 meetings via conference call:
o Up to 6 PDT meetings via conference call
o Ongoing coordination for all stakeholders
o Follow-up calls
o Emails

3.0 RAILROAD DESIGN COORDINATION

3.02 Final CPUC GO88B Applications
Task Objective
RailPros has been providing ongoing coordination and support services for the development of the draft CPUC GO 88-B construction permit applications for each of the two BNSF/LAJ railroad crossings. Additional reviews and revisions are anticipated before the construction permit applications are approved.

RailPros Activities
• Development and coordination of stakeholder review and revisions for the two GO 88-B construction permit applications (one for each crossing).

Task Deliverables
• Revised CPUC GO 88-B (one for each crossing)
• Final CPUC GO 88-B Documents for stakeholder signatures (one for each crossing)

3.07 Review Stage Construction and Work Area Traffic Control Plans Task Objective
RailPros has been providing ongoing design, coordination and support services for the project development. Due to the duration of the project, changes in stakeholder staffing, standards, and other requirements, additional, unanticipated design, and support services were previously provided, such as additional CPUC, BNSF, and other stakeholder design comments and plan revisions, CPUC GO 88-B construction permit application reviews, traffic signal design and

Page 3 of 5 ends

250 Commerce, Suite 200
Irvine, CA 92602
P: (714) 734 - 8765 F: (714) 734 - 8755
w w w . r a i l p r o s . c o m
interconnect revisions, temporary traffic control, and temporary grade crossing modification reviews and revisions, among other services. under his amendment RailPros will continue to provide these additional and other ongoing design support and coordination services. We also anticipate that additional review comments and design iterations may be required based upon stakeholder feedback. In addition, the design documents will need to be revised to reflect newly issued standard plans, specifications, and guidelines.

RailPros Activities
• Development and coordination of stakeholder review and revisions (up to 2 iterations) for the following:
o Traffic Signal and Interconnect Design Plans
o Temporary Grade Crossing Modification Design Plans
o Grade Crossing Modification Design Plans
o Railroad Crossing Preemption Calculations, Preemption Exhibits, and Preemption Request Forms
Task Deliverables
• Final Traffic Signal and Interconnect Design Plans
• Final Temporary Grade Crossing Modification Design Plans • Final Grade Crossing Modification Design Plans
• Final Railroad Crossing Preemption Calculations, Preemption Exhibits, and Preemption Request Forms

3.09 Railroad Utility Design Review and Permitting Services Task Objective
RailPros has provided and will continue to provide ongoing and as needed utility design review and permitting services to obtain permits from BNSF/LAJ for the proposed electrical underground utility casings at three locations under the North and South Atlantic Blvd at-grade railroad crossings and one temporary electrical overhead utility shoofly over the Temporary Construction Easement (TCE) areas at two locations over the North and South Atlantic Blvd at-grade railroad crossings.

RailPros will utilize an online application project management system to enable communication and document distribution between RailPros and the City. The RailPros Real Estate Specialist oversees the entire application and engineering review process. A designated representative(s) of the City will have 24-hour access to online project management system.

When a railroad permit is needed, the City will upload the request to the RailPros permitting management system, including complete project detail and agreed upon form of design/sketch.

The RailPros Real Estate Specialist will oversee the internal and railroad review process. Upon City submittal, RailPros will acknowledge receipt within one (1) business day. RailPros will review and respond to City within five (5) business days with questions, requests for clarifications, or

Page 4 of 5 ends

250 Commerce, Suite 200
Irvine, CA 92602
P: (714) 734 - 8765 F: (714) 734 - 8755
w w w . r a i l p r o s . c o m
comments noting design issues or safety concerns based upon the specific railroad criterium for each submittal or resubmittal of the design. The City will inform the RailPros Real Estate Specialist of interruptions to the permit schedule after the initial RailPros review.

Once the design and application meet the specific railroad standards, RailPros will formally file the application on the City’s behalf. City will be responsible for paying all application and license fees to the railroad, unless specifically requested by City. RailPros will track the application process with the railroad and will notify the City of the progress on a regular basis. Should the City request RailPros to pay for any application fees, they will be billed to the City plus 5% handling charge and identified on the RailPros invoice. City will be invoiced monthly for the services rendered per the attached Fee Schedule.

RailPros Activities
• Additional review of railroad permit requirements (based on stakeholder feedback) • Engineering review of utility crossings (to assist in addressing stakeholder feedback) • Submittal/resubmittal of applications, details or revisions to railroads • Tracking and monitoring of the application status
Task Deliverables
• Review comments of railroad permit requirements
• Engineering review comments of utility crossings
• Utility application submittals (up to 1 additional submittal/iteration for each of the 2 crossings)

3.10 BNSF/LAJ Plan Review Coordination, Comment Resolution, and Plan Revisions RailPros will coordinate reviews of all design plan sets with BNSF, participate in and resolve all potential design plan set comment conflicts, and coordinate design plan set revisions. This task may involve the coordination with another Project Team consultant regarding the development of an additional Temporary Traffic Control Design plan sheet and/or an additional Temporary Grade Crossing Modification Design plan sheet.

RailPros Activities
• Coordination of initial and subsequent design plan set reviews with BNSF/LAJ • Participation and eventual resolution of any and all potential design comment conflicts • Coordination with the Project Team concerning all design plan set revisions.

Task Deliverables
• Up to two (2) revisions of all design plan sets including final stage design plan sets • Internal comments for up to two (2) revisions of all design plan sets including final stage design plan sets.
• Stakeholder resolution comment matrices for up to two (2) revisions of all design plan sets including final stage design plan sets.

Page 5 of 5 ends

250 Commerce, Suite 200
Irvine, CA 92602
P: (714) 734 - 8765 F: (714) 734 - 8755
w w w . r a i l p r o s . c o m
• Draft and final minutes for up to two (2) comment resolution meetings.

Assumptions
• Total meeting, coordination, project management, and participation hours are per the fee breakdown. If additional support is needed, a scope amendment may be necessary to complete services.
• All agreement and permit fees will be paid by the City of Vernon or by proxy and not by RailPros.
• Where possible, meetings will be via conference call to conserve costs • Where possible, documents or other deliverables will be provided electronically in PDF format to conserve costs.
• Meetings, coordination, project management, and other as-needed support services will be per the fee breakdown. If additional support is needed, a scope amendment may be necessary to complete services.
• All design specifications will be in accordance with CPUC and BNSF standards and requirements and may be subject to review by CPUC and BNSF. • CPUC and BNSF permits/plan approvals will follow standard procedures and will be based on or drafted from standard forms or boilerplate documents provided by the respective stakeholders. Information for completing the draft documents, including plans and other details, will be provided to RailPros by the project team or respective stakeholders. Final permits, license agreements or other documents may involve stakeholder legal or other internal reviews and comments that are outside of RailPros control and may require additional effort, scope, or fees to complete. Finalizing of these is contingent on concurrence or agreement between the stakeholders and may impact the associated schedule and scope for receiving final approvals.
• Bid support or design services during construction are excluded. • Stakeholder review and processing fees may vary and may exceed estimated costs included in this scope of work. Additional fees may be required to obtain final approvals. • RailPros’ efforts are limited to the hours and level of effort on the attached fee estimate, and Based on current design status and stakeholder coordination, additional design review submittals and comments may be required. No new design plan sheets or design elements are anticipated. Comments and revisions are assumed to be addressed on existing design sheets and design elements. This scope assumes up to 2 submittal iterations.
• Additional services may be provided by RailPros under a separate scope and fee amendment.

Local Assistance Procedures Manual
Date:

RailPros, Inc.

DIRECT LABOR Hourly Rate
Range Hours Total
44 @ $ 96.00 $ 4,224.00
142 @ $ 77.00 $ 10,934.00
68 @ $ 45.00 $ 3,060.00
4 @ $ 113.00 $ 452.00
8 @ $ 40.00 $ 320.00
@ $ -
@ $ -
Total Direct Labor Costs (DLC)
Rate Total
* %
Total Fringe Benefits (FB)
INDIRECT COSTS Total
Overhead (OH) * % *
General and Administrative (G&A) * % *
Total (* Combined FB, OH and G&A) 150 % $ 29,439.25
Total Indirect Costs (IC)
FEE (PROFIT) Rate Total
10 % $ 4,906.54
Fee (DLC+FB+IC)
UTILITY DESIGN REVIEW AND PERMITTING SERVICES Total Crossings $1,550 2
$1,550 2
$1,000 2
$1,000 2
$2,000 2

ESTIMATED OTHER DIRECT COSTS (ODC)
(ODC is actual cost to be reimbursed with supporting documentation.)

1. Reproduction and Binding $ -

2. Plotting $ -

3. Transportation / Travel (Mileage will be IRS standard rate.) 0 miles/trip; 0 trips $ -

4. Overnight Deliveries $ -

5. Video Survey $ -
Total Other Direct Costs

SUBCONTRACTOR COSTS
Total Cost

FRINGE BENEFITS
Anticipated Salary Increases (3.35%) (Escalation)
Per Crossing
$ 18,990.00
$ 636.17
$ 19,626.17
$ 68,171.95 ADDITIONAL AUTHORIZATION REQUESTED FOR TOTAL COST TO COMPLETE AND AMENDMENT No. 8:
$ -
$ 29,439.25
$ 4,906.54
$ -
$ 68,171.95
$ 3,100.00
$ 3,100.00
Total Cost $ 14,200.00
Filing and Tracking of Railroad Application for Utility Crossing Permit
Amendment / Modification of Utility Crossing Submittal
Per Crossing
$ 2,000.00
$ 2,000.00
Structures Engineer R. Casimere
Subtotal Direct Labor Costs
Project Manager R. Williams
Traffic Designer K. Ablan
Structures Specialist S. Naveed
Traffic Engineer W. Swindle
Hourly Rate
Classification Name (2024)
EXHIBIT 10-H

CITY OF VERNON

COST PROPOSAL
Federal Project No.:

Caltrans EA No.: 12/4/2023
Project Name: Atlantic Blvd. Bridge over the Los Angeles River Consultant:
$ 4,000.00
Per Crossing
Per Crossing
Per Crossing
Initial Engineering Review of Client's Print/Plan and Profile for Crossings
Non-Intrusive/Survey Permit Submittals not requiring a Right of Entry request
Secondary Engineering Reviews/Modification review of Client’s Print/Plan and Profiles

Page 1 of 1 ends

Project: Rehabilitation of Atlantic Blvd Bridge over the Los Angeles River Consultant: RailPros, Inc.

Project
Manager
Traffic
Engineer
Traffic
Designer
Structures
Specialist
Structures
Engineer
Robert
Williams
William
Swindle
Kyle
Ablan
Sarwar
Naveed
Reece
Casimere
$ 96.00 $ 77.00 $ 45.00 $ 113.00 $ 40.00

1.0 Project Management (Dec 2023 to Dec 2024 - 1 year)

1.01 Meetings and Coordination (Meetings via conference call, follow-up calls, emails) 20 30 50 $ 4,230.00

3.0 Railroad Design Coordination (Dec 2023 to Dec 2024 - 1 year)

3.02 Final CPUC GO88B Applications
(2 BNSF/LAJ at-grade crossings) 8 35 20 63 $ 4,363.00

3.07 Review Stage Construction and Work Area Traffic Control Plans 8 42 28 78 $ 5,262.00

3.09 Railroad Utility Design Review and Permitting Services (2 BNSF/LAJ at-grade crossings) 4 8 12 $ 772.00

3.10 Stakeholder Plan Review Coordination, Comment Resolution, and Plan Revisions
(2 BNSF/LAJ at-grade crossings)
8 35 20 63 $ 4,363.00
44 142 68 4 8 266 $ 18,990.00
$ 636.17
$ 29,439.25
$ 4,906.54
No. Utility Permitting Services Rate Schedule
1 $ 3,100.00
2 $ 3,100.00
3 $ 2,000.00
4 $ 2,000.00
5 $ 4,000.00
$ 14,200.00
$ 68,171.95
Task Total Hours / Subtotal Estimate to Complete Tasks
Anticipated Salary Increases (3.35%) (Escalation) =
Indirect Costs =
Profit =
Contract Amendment No. 9
(raw rate)
Task Description Task
No.

Total Hours Raw Labor Cost
Subtotal Other Direct Costs
Total Estimate to Complete
Filing and Tracking of Railroad Application for Utility Crossing Permit @ $1,550.00 per crossing (2 BNSF/LAJ at-grade crossings) Amendment / Modification of Utility Crossing Submittal @ $1,550.00 per crossing (2 BNSF/LAJ at-grade crossings) Initial Engineering Review of Client's Print/Plan and Profile for Crossings @ $1,000.00 per crossing (2 BNSF/LAJ at-grade crossings) Non-Intrusive/Survey Permit Submittals not requiring a Right of Entry request @ $1500.00 per crossing (2 BNSF/LAJ at-grade crossings) Secondary Engineering Reviews/Modification review of Client’s Print/Plan and Profiles @ $1000.00 per crossing (2 BNSF/LAJ at-grade crossings) 250 Commerce, Suite 200
Irvine, Ca 92602 12/4/2023
P: (714) 734 - 8765 F: (714) 734 - 8755
www.railpros.com
Converse Consultants
Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services 717 South Myrtle Avenue, Monrovia, California 91016
Telephone: (626) 930-1200 ♦ Facsimile: (626) 930-1212 ♦ www.converseconsultants.com November 30, 2023
Mr. James Lu, PE, SE
Principal
CNS Engineers, Inc.
10370 Hemet Street, Suite 340
Riverside, California 92503
Subject: PROPOSAL TO UPDATE THE DESIGN AND SPECIFICATIONS PER

NEW STANDARDS
Atlantic Boulevard Bridge Widening
Vernon, California
Converse Project No. 08-31-330-00 (03)
Dear Mr. Lu:

Converse Consultants (Converse) appreciates the opportunity to submit this proposal to update the project design and specifications per new Caltrans (or Greenbook) standards for the Atlantic Boulevard Bridge Widening project over Los Angeles River in Vernon, California

SCOPE OF SERVICES
Per your email dated November 27, 2023, we understand you would like us to provide the following:
 Update the design/specs/Foundation Report per new Caltrans (or Greenbook) standards.
 Extend the contract to December 31, 2024.

COST ESTIMATE AND FEES
Our services will be performed in accordance with our current Schedule of Fees and General Conditions, copies of which are attached and form a part of this proposal.

Our cost breakdown is included in the following table:

Title Unit Number Unit Rate Cost
of Units ($) ($)
Principal Hours 8 $261.33 $2,090.64
Senior Staff Professional Hours 36 $161.65 $5,819.40
Drafting Hours 20 $67.35 $1,347.00
Word Processing Hours 12 $61.96 $743.52
TOTAL $10,000.56
Proposal to Update the Design and Specifications per New Standards Atlantic Boulevard Bridge Widening
Vernon, California
November 30, 2023
Page ii
Converse Consultants
K:\31-Geotech\2008\08-31-330 Atlantic Boulevard CNS Engineering\03 Proposal 11-30-23 u12-1-23\08-31-330_upro(03) Atlantic Blvd Bridge Widening u12-1-23.doc

CLOSURE
Our review will be prepared in accordance with generally accepted professional geotechnical engineering and engineering geologic principles and practice in Southern California. Unless we hear differently, it will be assumed that these conditions are acceptable to you.

This proposal expires ninety (90) days from its issuance, if not accepted within that time. Converse’s billing rates are reviewed annually and are subject to adjustment at the beginning of each calendar year.

If the terms of this proposal are acceptable, please complete and sign the attached Acceptance of Agreement and Authorization to Proceed form and forward it to our office with one copy of this signed proposal to formally authorize our services.

Special billing instructions, including backup documentation requirements, should be mutually agreed upon and indicated in the authorization form. Subsequent additions or changes should likewise be mutually agreed upon and submitted in writing with the appropriate authorization.

Please do not hesitate to contact the undersigned at (626) 930-1275 if you have any questions or wish to discuss this proposal in greater detail. The opportunity to be of service is appreciated.

Sincerely,

CONVERSE CONSULTANTS
Siva K. Sivathasan, PhD, PE, GE, DGE, QSD, F. ASCE
Senior Vice President / Principal Engineer
Dist: 1/Addressee via Email
Encl: Schedule of Fees, General Conditions
SKS/PA:jjl
Title Quantity Hourly Rate Loaded Rate Amount
Principal Engineer 8 $ 97.00 $ 261.33 $ 2,090.64
Senior Staff Engineer 36 $ 60.00 $ 161.65 $ 5,819.30
Drafting 20 $ 25.00 $ 67.35 $ 1,347.06
Word Processing 12 $ 23.00 $ 61.96 $ 743.58
Total= $ 10,000.57