City Council Agenda Report
Meeting Date: April 16, 2024
From: Daniel S. Wall, P.E., Director of Public Works
Department: Public Works
Submitted by: Gerard Garcia, Assistant Engineer
Subject
Notice of Completion for Contract No. 20240122 Gifford Avenue, 48th, 49th, & 50th Street Improvements
Recommendation
A. Find that the proposed action is categorically exempt from California Environmental Quality Act (CEQA) review, in accordance with CEQA Guidelines Section 15301, because the project consists of the maintenance, repair or minor alteration of existing streets and involves negligible or no expansion of an existing use;
B. Accept the work of Hardy & Harper, Inc. as related to City Contract No. 20240122; and C. Authorize the Director of Public Works to execute and submit the Notice of Completion for the project to the Los Angeles County Recorder’s Office.
Background
On January 16, 2024, the City Council awarded City Contract No. 20240122 Gifford Avenue, 48th, 49th, & 50th Street Improvements in the amount of $792,000, including a 10% contingency.
The final construction cost was $755,845.38. This project involved installing thick asphalt concrete in one lift along Gifford Avenue, 48th, 49th, and 50th Street. In addition, the project included the construction of ADA ramps, a new curb and gutter, and the construction of tree wells.
City Contract No. 20240122 was completed and accepted on March 4, 2024, in accordance with the project specifications and City Staff expectations.
The Notice of Completion was approved as to form by the City Attorney’s office.
Fiscal Impact
There is no fiscal impact associated with this report.
Attachments
1. Notice of Completion – Contract No. 20240122