MOU# MOU.

Southeast Los Angeles Transit Improvement Project (SELA TIP)

MEMORANDUM OF UNDERSTANDING
This Memorandum of Understanding (MOU) is entered into between the Los Angeles County Metropolitan Transportation Authority (“Metro” or “Grantee”) and City of Vernon (“Sub-Grantee”), as of this date of ___________, 2026, for the Metro Southeast Los Angeles Transit Improvements Project (“SELA TIP”) Metro and Sub-Grantee may each be referred to individually as a “Party” and collectively as the “Parties”.

WHEREAS, Metro applied for and secured grant funding under the 2022 Local Partnership Program (LLP) for transit improvements in Southeast Los Angeles; and WHEREAS, the SELA TIP will include procurement and installation of new bus shelters at 100 stops along high-frequency (NextGen Tiers 1 & 2) bus lines within various jurisdictions; and
WHEREAS, The Metro Board of Directors on April 25, 2024 approved the East Los Angeles – Long Beach Corridor Mobility Investment Plan, which identifies bus stop improvements as a component project, including the SELA TIP; and WHEREAS, on June 27, 2024 the California Transportation Commission (“CTC”) approved the project baseline agreement for the SELA TIP, the “Baseline Agreement”, which is attached as Attachment D.

WHEREAS, bus shelters will be procured and maintained by the jurisdiction in which the bus stop is located; and
WHEREAS, eligible expenditures consist of new bus stop shelters in locations that do not have an existing shelter, which include a shade structure, night-time lighting, realtime information boards, and typically include other amenities such as seating and trash receptacles; and
WHEREAS, the Parties desire to set forth the roles and responsibilities with respect to the implementation and funding of the SELA TIP.

NOW THEREFORE, the Parties hereby agree as follows:

1. CONDITIONS

1.1 The Sub-Grantee shall use the Funds, as described below, to complete the Project as described in the Scope of Work attached as Attachment A. The Funds, as granted under this MOU, can only be used towards the completion of this Scope of Work. Sub-Grantee shall not use the Funds to substitute for any other funds or projects not specified in this MOU. The Scope of Work shall include a list of selected bus stop locations as indicated by: street and cross street, LA Metro bus stop identification MEMORANDUM OF UNDERSTANDING (MOU) – MOU

METRO SOUTH EAST LA TRANSIT IMPROVEMENTS PROJECT (SELA TIP) LA Metro MOU with City of Vernon
2 number, direction of travel, and near or far side of intersection; a description and illustration of shelter(s) to be used (where more than one shelter type is employed, the list of locations shall indicate which type is selected for each location); a project schedule that must be adhered to and that includes milestones consistent with purchase and installation of the new shelters and any site preparation work; and a breakdown of costs by activity.

1.2 The Sub-Grantee shall use the Funds in accordance with the Financial Plan attached to this MOU as Attachment B. The Financial Plan shows the Project’s cash flow and includes the Project’s entire financial commitment as well as the fiscal year that the funds will be expended.

1.3 The Sub-Grantee must demonstrate timely use of Funds by: (I) executing this MOU by August 1, 2026, and by (II) expending the Funds granted under this MOU by no later than September 1, 2027, which is the construction contract acceptance milestone date for the LPP grant.

1.4 During the term of this MOU, the Sub-Grantee shall submit Quarterly Progress Reports in the form attached as Attachment C. These reports shall include quarterly and inception to date actual expenditures, tasks completed during the reporting period, projected activities for the next quarter and any information that describes the progress of the Scope of Work. The Quarterly Reports are due to the Metro Project Manager on or before the thirtieth day (30th) of the first month following the close of the OctoberDecember, January-March, April-June, and July-September quarters.

1.5 Quarterly Reports, notices, and draft invoices shall be submitted as PDF documents via email to:

Joseph Forgiarini, Sr. Executive Officer, Service Development [email protected]
with CC to Monica Waggoner, Service Planning Manager, Gateway Cities [email protected]

1.6 The Sub-Grantee is responsible for reviewing and approving the design plans for the Project. The Sub-Grantee must obtain all necessary permits and approvals from the appropriate agencies.

1.7 The Sub-Grantee must ensure the design of the Project fully complies with the Americans with Disabilities Act (ADA).

1.8 This MOU shall terminate on 2/28/2028.

1.9 In the event that the Sub-Grantee notifies Metro it is unable to provide the realtime information boards, Metro is responsible for acquiring and installing real-time MEMORANDUM OF UNDERSTANDING (MOU) – MOU

METRO SOUTH EAST LA TRANSIT IMPROVEMENTS PROJECT (SELA TIP) LA Metro MOU with City of Vernon
3 information boards, including hardware, software and power connections, onto the new bus shelters at no expense to the Sub-Grantee. The real-time information boards remain the property of Metro after installation. Metro’s expenses for these real-time information boards will reduce the amount of funding available to the Sub-Grantee per shelter.

1.10 The Sub-Grantee is responsible for all maintenance and repair costs for bus shelters and appurtenances, excluding real-time information boards installed by Metro, incurred during the Project asset anticipated normal life span. Metro is responsible for technical supports (including software updates), maintenance, fees, operation and necessary repairs or replacements of real-time information boards installed by Metro, while Sub-Grantee is responsible for general cleaning, graffiti removal, and maintenance of lighting equipment. This requirement shall survive the termination of this agreement.

1.11 This is a one-time only grant subject to the terms and conditions agreed to herein. This grant does not imply nor obligate any future funding commitment on the part of Metro.

1.12 The Sub-Grantee shall carry out the Project in accordance with the terms of this MOU and all applicable laws, regulations, and rules.

2. TRANSFER OF FUNDS

2.1 To the extent that funds are available, Metro shall make a one-time grant of the funds in the amount of $520,000 for the Project subject to the terms of the Baseline Agreement and any additional terms and conditions contained herein. These Funds are programmed during the project span, from execution of agreement to September 1, 2027, and are allocated among the Scope of Work as specified in the Financial Plan.

2.2 The Funds will be transferred to the Sub-Grantee on reimbursement basis only and no advance of Funds shall be granted. The Sub-Grantee shall submit invoices to Metro upon completion of construction and installation of shelters (including any site preparation work), for the total grant-funded portion of the share of the Project expended by the Sub-Grantee. Sub-Grantee may submit invoices as individual shelters are completed, or after completion of all installations included in attachments A and A-1.

2.3 The invoice submitted to Metro should only relate to approved goods or services provided in accordance with this MOU. The invoice should clearly identify the charges, copies of the invoices, number of the MOU, and the period covered.

2.4 Metro shall reimburse the Sub-Grantee the full amount of the invoice less a tenpercent (10%) retainage. The retainage will be paid to the Sub-Grantee upon the successful completion of the Project’s closeout audit to be conducted by Metro.

MEMORANDUM OF UNDERSTANDING (MOU) – MOU

METRO SOUTH EAST LA TRANSIT IMPROVEMENTS PROJECT (SELA TIP) LA Metro MOU with City of Vernon
4 2.5 The Sub-Grantee is responsible for all cost overruns incurred as a result of this Project. Under no circumstance will the total amount of money that Metro reimburses the Sub-Grantee exceed the amount of the Funds allocated in the project’s Financial Plan.

2.6 If any amounts paid to Sub-Grantee are disallowed or not reimbursed by the CTC for any reason, Sub-Grantee shall remit to LACMTA the disallowed or non-reimbursed amount(s) within 30 days from receipt of LACMTA’s notice. All payments made by LACMTA hereunder are subject to the audit provisions contained herein and within the Baseline Agreement.

2.7 Sub-Grantee shall comply with and ensure that work performed under this Agreement is done in compliance with all applicable provisions of federal, state and local laws, statutes, ordinances, rules, regulations and procedural requirements, and the applicable requirements and regulations of LACMTA. Sub-Grantee acknowledges responsibility for obtaining copies of and complying with the terms of the most recent Federal, State or local laws and regulations and LACMTA requirements, including any amendments thereto.

2.8 Following Metro Operations staff approval, invoices shall be addressed to [email protected], sent as a PDF attachment.

2.9 Payments and notices shall be addressed to:
4305 S. Santa Fe Ave, Vernon, CA 90058
Attention: Daniel S. Wall – Director of Public Works
[email protected]

3. PENALTIES
Metro reserves the right to terminate this MOU and withhold all payments of Funds in the event of Sub-Grantee’s breach or defaults of any term or condition contained in this MOU, if such breach or default has not been cured by Sub-Grantee within fourteen (14) days of written demand by Metro.

4. MISCELLANEOUS

4.1 California law shall govern this MOU. If any provision of this MOU is held by a court of competent jurisdiction to be invalid, void, or unenforceable, the remaining provisions shall nevertheless continue in full force without being impaired or invalidated in any way.

4.2 The Sub-Grantee shall not assign this MOU, or any part thereof, without written consent and prior approval of Metro’s Chief Executive Officer or designee, and any assignment without said consent shall be void and unenforceable.

MEMORANDUM OF UNDERSTANDING (MOU) – MOU

METRO SOUTH EAST LA TRANSIT IMPROVEMENTS PROJECT (SELA TIP) LA Metro MOU with City of Vernon
5 4.3 This MOU constitutes the entire understanding between Parties, with respect to subject matter herein. This MOU shall not be amended, nor any provision or breach hereof waived except in writing signed by the Parties.

4.4 The covenants and agreements of this MOU shall inure to the benefit of, and shall be binding upon, each of the Parties and their respective successors and assigns.

4.5 Metro shall have the right to conduct a financial and compliance audit(s) of the Project. Sub-Grantee agrees to establish and maintain proper accounting procedures and cash management records and documents in accordance with generally accepted accounting principles. The Sub-Grantee shall reimburse Metro for any expenditure not in compliance with the Scope of Work and/or not in compliance with other terms and conditions of this MOU and Guidelines.

4.6 Metro shall indemnify, defend and hold harmless Sub-Grantee, its trustees, officers, agents, and employees from and against any and all liability, loss, expense, including reasonable attorney's fees, or claims for injury or damages arising out of the performance of this Agreement, but only in proportion to and to the extent such liability, loss, expense, attorney's fees, or claims for injury or damages are caused by or result from the negligent or intentional acts or omissions of Metro, its trustees, officers, agents or employees.

Sub-Grantee shall indemnify, defend and hold harmless Metro, its trustees, officers, agents, and employees from and against any and all liability, loss, expense, including reasonable attorney's fees, or claims for injury or damages arising out of the performance of this Agreement, but only in proportion to and to the extent such liability, loss, expense, attorney's fees, or claims for injury or damages are caused by or result from the negligent or intentional acts or omissions of Sub-Grantee, its trustees, officers, agents or employees.

Any entity hired by either Party shall be required to indemnify, defend and hold harmless the other Party, its Special Districts, elected and appointed officers, employees, agents and volunteers ("Indemnitees") from and against any and all liability including but not limited to demands, claims, actions, fees, costs, and expenses, including attorney fees, arising from or relating to this agreement, except for such loss or damage arising from the sole negligence or willful misconduct of the Indemnitees.

4.7 Sub-Grantee in the performance of the work required by this MOU is not an agent or employee of Metro. Sub-Grantee shall not represent itself as an agent or employee of Metro and shall have no powers to bind Metro in contract or otherwise.

MEMORANDUM OF UNDERSTANDING (MOU) – MOU

METRO SOUTH EAST LA TRANSIT IMPROVEMENTS PROJECT (SELA TIP) LA Metro MOU with City of Vernon
6 IN WITNESS WHEREOF, the Parties have caused this MOU to be executed by their duly authorized representatives as of the dates indicated below:

SUB-GRANTEE:

CITY OF VERNON

LOS ANGELES COUNTY

METROPOLITAN

TRANSPORTATION AUTHORITY
By: By:

Brian Saeki,
City Administrator
APPROVED AS TO FORM:
_________________________
Zaynah Moussa-Milward
City Attorney
Attest
_________________________
Genoveva Rocha,
City Clerk
Date
____
Date
___
Date
Stephanie Wiggins
Chief Executive Officer

APPROVED AS TO
FORM:
____________________
Dawyn R. Harrison
County Counsel
By:
___________________
Deputy
Date
____
Date
____
Date
5/14/2026
Attachment A: Scope of Work
Project Title: Vernon Bus Shelter Installation Project
Sub-Grantee: City of Vernon

1. Project Overview
This Scope of Work (“SOW”) delineates the obligations of the City of Vernon (“Sub-Grantee” or “City”) for the execution of the Vernon Bus Shelter Installation Project (“Project”). The Project is designed to enhance public transit amenities by installing standardized bus shelters at ten (10) high-priority designated Metro bus stop locations that currently lack such infrastructure. The installation of these shelters shall improve rider safety, comfort, and accessibility while ensuring compliance with all applicable federal, state, and local statutes, including the Americans with Disabilities Act (ADA), California Public Contract Code, and Los Angeles County Metropolitan Transportation Authority (“Metro”) guidelines.

2. Project Scope and Deliverables
The City shall be responsible for the procurement, delivery, and installation of the bus shelters, as well as the necessary site preparation, according to the following components:
a. Procurement and Delivery of Shelters
b. Site Preparation (if applicable)
• Execution of any necessary minor demolition, grading, and right-of-way clearance to accommodate the installation of shelters and digital real-time information systems; • Coordination with Metro to secure bus stop approvals, adjustment or removal of existing street elements (e.g., newspaper racks, signage, poles) as required to comply with ADA and pedestrian flow standards.
c. Shelter Installation
• Installation of the shelters and the integration of the digital real-time information boards; • Final inspection and certification to ensure compliance with all safety, structural, lighting, and ADA requirements.
d. Reporting and Closeout
• Submittal of photographic documentation, invoices, inspection records, and any required progress or final reports to the funding agency or grant administrator.

3. Project Locations
No. Street and Cross Street Metro Stop
ID
Direction
of Travel
Corner
Placement

1. Santa Fe / 27th 5531 N SE

2. Soto / 26th 5558 N NE

3. Soto / 46th 5560 N SE

4. Soto / 54th 5562 N SE

5. Slauson / Boyle 10200 W NE

6. Pacific / Leonis 12708 S SE

7. Santa Fe / 27th 13919 S NW

8. Soto / 26th 13947 S NW

9. Soto / 46th 13949 S NW

10. Santa Fe / 30th 5532 N SE

4. Shelter Design, Specifications
The key specifications are as follows:
• Amenities: Shade structure/bus shelters, seating or bench area, solar kit for night-time lighting, trash receptacle
• Vernon will opt to have Metro install real-time epaper display

5. Project Schedule
The Project shall be executed in accordance with the following schedule. The City shall notify the funding agency in writing upon the completion of each phase and submit the requisite documentation in a timely manner:

Project Phase Target Completion Date
(Month/Year)
Site Assessments/Design February 2026
Shelter Procurement (excluding digital boards) June 2026 Site Preparation August 2026
Shelter Installation November 2026
Project Closeout and Final Reporting February 2027

FRONT VIEW
SCALE 1/2" = 1'-0"

SIDE VIEW
SCALE 1/2" = 1'-0"

SIDE VIEW
SCALE 1/2" = 1'-0"

TOP VIEW
SCALE 1/2" = 1'-0"

SECTION A-A
SCALE 1/2" = 1'-0"

DETAIL A
SCALE 2" = 1'-0"

DETAIL B
SCALE 2" = 1'-0"
A A
A
B
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
A A
B B
C C
D D

DESCRIPTION

CUSTOMER/VENDOR
MATL.

SCALE
SIZE
DATE DRAWN BY:

DWG NO.

TOLAR MANUFACTURING COMPANY, INC
258 Mariah Circle, Corona CA. 92879
REV
16NASIGPMFASCIA

CITY OF VERNON, CA
D
VARIES
56714-00 -
AS NOTED 11/21/2025 RFarr
T:\Inventor\Shelters\Non-Ad Custom Dome\56714-00.idw

THE DESIGN AND DRAWINGS REMAIN THE
INTELLECTUAL PROPERTY OF TOLAR MFG.

AND ARE PROTECTED BY LAW. THEY MAY

NOT BE ALTERED, REPRODUCED OR USED

FOR FABRICATION WITHOUT EXPRESSED
WRITTEN CONSENT FROM TOLAR MFG.

ALL DOCUMENTS TO BE RETURNED TO
TOLAR MFG.. AT COMPLETION OF WORK.

CONTRACTOR TO SITE VERIFY ALL DETAILS

AND DIMENSIONS AND REPORT ANY AND
ALL DISCREPANCIES TO TOLAR MFG..

BEFORE COMMENCING WITH THAT RELATED
PORTION OF THE WORK.

PAGE:
1 OF 2
GENERAL NOTES:

1. ALL STRUCTURAL STEEL, UNLESS OTHERWISE NOTED, SHALL BE ASTM A-36, MINIMUM YIELD STRENGTH 36,000 PSI.

2. ALL STRUCTURAL ALUMINUM MEMBERS, UNLESS OTHERWISE NOTED, SHALL BE OF ALLOY 6063-T5 OR GREATER.

3. ALL HOLES TO BE DRILLED OR PUNCHED.

4. STEEL WELDING SHALL CONFORM TO AMERICAN WELDING SOCIETY STANDARD D1. 1-10.

ELECTRODES SHALL CONFORM TO AWS 5.1, CLASS E70S-5.

5. ALUMINUM WELDING SHALL CONFORM TO AMERICAN WELDING SOCIETY STANDARD D1. 2-08. ELECTRODES SHALL CONFORM TO AWS/SFA 5.10 CLASS ER4043.

6. ALL WELDING TO BE DONE AT TOLAR MANUFACTURING COMPANY, INC. FACILITY.

7. ALL CORPORATE PROCEDURES, INCLUDING FABRICATION, MUST BE IN COMPLIANCE WITH TOLAR MANUFACTURING CO. INC'S QUALITY CONTROL MANUAL

8. THE CONCRETE PAD SIZES SHOWN ARE STANDARD MINIMUM REQUIREMENTS FOR THE STRUCTURE AND ARE FOR REFERENCE ONLY. THE PAD MAY NEED TO BE REINFORCED

OR ENLARGED DEPENDING ON LOCAL CODES AND LOADING CONDITIONS AND DOES NOT INCLUDE ADA CLEAR PATH REQUIREMENTS.
6"
3" MIN. EMBED.
#4 REBAR @ 12" OCEW

REAR WALL TUBING WELDMENT,
2-1/2 ROUND ALUMINUM TUBE ENCAPSULATING
1/8 THK ALUMINUM PERF.

USC RMS100 SOLAR SYSTEM
W/ 8W LED LIGHT STRIP ROOF

ILLUMINATION
Ø8 1/2" LOGO PLAQUE W/ VINYL DECAL
(APPLIED TO BOTH SIDES)

ARTWORK PROVIDED BY CUSTOMER

ON UPSTREAM/ DOWNSTREAM

ROOF PANELS,
1/8" THICK ALUMINUM SHEET
8'-5"
8'-9 7/8"
5'-9 3/16"
15'-2 1/2"
6'-8" CLEARANCE
6" MIN. FROM EDGE OF

CONCRETE TO EDGE
OF SHOE FLANGE TYP.

ALL DIRECTIONS
15'- 1/2"
15'-10"
16'-10" MIN. CONCRETE SLAB
3'-1 1/8" 2'-3 11/16"
6'-0" MIN. CONCRETE SLAB
1'-6"
36 X 48 ADA
5' MESA BENCH WITH ENHANCED SEAT DELINEATORS
AND BLACK PLASTIC SLATS X2

TRASH RECEPTACLE,
32 GAL. W/ HARD RUBBER LINER

AND DOOR W/ DOME LID

FRONT BANNER,
1/8" ALUM. SHEET
8"
5"
5" n9 1/2" x 1/2" THICK ALUMINUM PLATE

ANCHORS,
HILTI KWIK BOLT TZ2
Ø1/2 X 4-1/2 SS304
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
A A
B B
C C
D D

DESCRIPTION

CUSTOMER/VENDOR
MATL.

SCALE
SIZE
DATE DRAWN BY:

DWG NO.

TOLAR MANUFACTURING COMPANY, INC
258 Mariah Circle, Corona CA. 92879
REV

CITY OF VERNON, CA
D
VARIES
AS NOTED 11/21/2025 RFarr
T:\Inventor\Shelters\Non-Ad Custom Dome\56714-00.idw

THE DESIGN AND DRAWINGS REMAIN THE
INTELLECTUAL PROPERTY OF TOLAR MFG.

AND ARE PROTECTED BY LAW. THEY MAY

NOT BE ALTERED, REPRODUCED OR USED

FOR FABRICATION WITHOUT EXPRESSED
WRITTEN CONSENT FROM TOLAR MFG.

ALL DOCUMENTS TO BE RETURNED TO
TOLAR MFG.. AT COMPLETION OF WORK.

CONTRACTOR TO SITE VERIFY ALL DETAILS

AND DIMENSIONS AND REPORT ANY AND
ALL DISCREPANCIES TO TOLAR MFG..

BEFORE COMMENCING WITH THAT RELATED
PORTION OF THE WORK.

PAGE:
2 OF 2
Attachment B: Financial Plan

1. Financial Commitment
The City of Vernon (“Sub-Grantee”) hereby commits to implementing the Vernon Bus Shelter Installation Project (“Project”) in accordance with this Financial Plan. The total funding allocation shall be used exclusively for eligible expenditures directly related to the scope of work outlined in Attachment A. Under no circumstances shall Project funds be used to supplant other budgeted expenditures or projects not specifically identified within this agreement.

All expenditures shall be incurred, documented, and reported in accordance with generally accepted accounting principles, applicable grant compliance requirements, and relevant provisions of the California Government Code. The City shall maintain detailed records of all expenditures for audit and reporting purposes.

2. Project Budget and Cost Allocation
Activity Estimated Cost Fiscal Year
Expended
Bus Shelter Procurement (10 units) $119,311.50 FY26-27
Site Preparation $21,000.00 FY 26-27
Installation and Labor $220,0000.00 FY27-28
Project Management $30,000.00 FY27-28
Contingency 10% $52,000.00 FY27-28
Total Project Cost $519,311.50 FY 27-28
The City shall submit quarterly expenditure reports and payment requests in accordance with the funding agency’s prescribed schedule and shall promptly notify the Metro (“agency”) of any material changes in project cost, scope, or delivery timelines.

ATTACHMENT C: Please use this template to craft your quarterly reports on your bus shelter progress for the SELA TIP.

Southeast Los Angeles Transit Improvement Program (SELA TIP) Quarterly Report
Agency:_____________________________________ Reporting period end date: ___________________ Stop No. Intersection Direction/Corner Status
Expenditures
Budget amount: $
Expenditures this period: $
Prior expenditures: $
Budget remaining: $
Narrative
ATTACHMENT C: Please use this template to craft your quarterly reports on your bus shelter progress for the SELA TIP.

Instructions
Add more rows to or delete rows from the stop table as required, based on the number of stops approved for inclusion.

Stop Number and Intersection: These should match the lists provided for Attachment A.

Direction/Corner:

Direction is northbound, southbound, eastbound, or westbound. Corner is nearside (before the intersection), farside (after the intersection), or midblock.

Abbreviate direction as NB, SB, EB, or WB, for the direction of travel of the street (not necessarily the bus line).

Abbreviate corner as NS, FS, or M.

Final should look like this: EB/NS is a nearside bus stop on the eastbound side of the street.

Status -- record as one of the following:
• Not Started
• Planning
• Construction
• Installed
Expenditures: please provide copies of invoices/receipts for Expenditures this period.

Narrative: Provide here a description of successes, challenges, lessons learned, upcoming milestones, or anything else that you would like to share with Metro about this project. These comments may be used in our reporting to the Metro Board or State of California on grant progress.

They will also inform our processes for similar projects in the future.

LPP-P-2324-14B
6/28/2024

LPP-P-2324-14B
07/08/2024
Tanisha Taylor
7 B. Fact Sheet
Southeast Los Angeles Transit Improvements Project
SB1 LPP-Competitive Cycle 3 Project
SB1 Project Baseline Agreement – Scope, Schedule, Costs, Benefits PPNOs (5 segments) :-- LP011A, LP011B, LP011C, LP011D, LP011E Project Location :-- Multiple Metro NextGen Tier One and Tier two bus line corridors throughout southeast Los Angeles County along the I-710 corridor Total Project Cost = $31,130,000 ; LPP-Competitive Funding = $14,500,000 LA Metro website – Projects :-- https://www.metro.net/projects/

LP011A - Scope, Schedule, Costs, Benefits
Scope :-- The purchase, design, and installation of cloud-based transit signal priority in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities. The project will be delivered via the design-build method.

Schedule :--
PA&ED (Environmental) Begin = 06/01/2023 End = 07/01/2023 PS&E (Design) Begin = 12/01/2024 End = 06/01/2026
ROW-Certification Begin = 11/01/2024 End = 11/30/2024
Construction (Contract) Begin = 07/01/2026 End = 12/01/2027 Costs (Funding) :-- Total = $6.63M (Local) – FY 24/25 ; LPP-C = $0 Benefits/Outputs :-- TMS – Transit Signal Priority (TSP) = 114 each Southeast Los Angeles Transit Improvements Project
SB1 LPP-Competitive Cycle 3 Project
SB1 Project Baseline Agreement – Scope, Schedule, Costs, Benefits LP011B - Scope, Schedule, Costs, Benefits
Scope :-- The purchase and installation of bus shelters with real-time display and security lighting in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Schedule :--
PA&ED (Environmental) Begin = 06/01/2023 End = 07/01/2023 PS&E (Design) Begin = 07/02/2023 End = 01/31/2025
ROW-Certification Begin = 07/02/2023 End = 01/31/2025
Construction (Contract) Begin = 04/01/2025 End = 09/01/2027 Costs (Funding) :-- Total = $6M – FY 24/25 ; LPP-C = $3M Benefits/Outputs :-- Rail/Multi-Modal – Station Improvements = 100 each LP011C - Scope, Schedule, Costs, Benefits
Scope :-- The purchase and installation of solar-powered lighting upgrades in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Schedule :--
PA&ED (Environmental) Begin = 06/01/2023 End = 07/01/2023 PS&E (Design) Begin = 07/02/2023 End = 08/02/2024
ROW-Certification Begin = 07/02/2023 End = 08/02/2024
Construction (Contract) Begin = 12/01/2024 End = 06/30/2026 Costs (Funding) :-- Total = $500K – FY 24/25 ; LPP-C = $250K Benefits/Outputs :-- Rail/Multi-Modal – Station Improvements = 100 each STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
Amendment (Existing Project) YES NO Date 05/13/2024 17:27:50 Programs LPP-C LPP-F SCCP TCEP STIP Other
07 District EA Project ID
LP011A
PPNO
Los Angeles County Metropolitan Transportation Authority Nominating Agency
Co-Nominating Agency
SCAG
MPO
Mass Transit (MT)
Element

TYRONE CRUMP
Project Manager/Contact
213-547-4377
Phone
[email protected]
Email Address
Southeast Los Angeles Transit Improvements Project (Transit Signal Priority) Project Title
County Route PM Back PM Ahead
Los Angeles County
The purchase, design, and installation of cloud-based transit signal priority in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities. The project will be delivered via the design-build method.

Location (Project Limits), Description (Scope of Work)
Component Implementing Agency
PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Los Angeles County Metropolitan Transportation Authority Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts
Assembly: 64,51,53,58,63 Senate: 32,33,35,24 Congressional: 34,38,40,44 Project Milestone Existing Proposed
Project Study Report Approved
Begin Environmental (PA&ED) Phase 06/01/2023
Circulate Draft Environmental Document Document Type CE 06/01/2023 Draft Project Report 06/01/2023
End Environmental Phase (PA&ED Milestone) 07/01/2023
Begin Design (PS&E) Phase 12/01/2024
End Design Phase (Ready to List for Advertisement Milestone) 06/01/2026 Begin Right of Way Phase 11/01/2024
End Right of Way Phase (Right of Way Certification Milestone) 11/30/2024 Begin Construction Phase (Contract Award Milestone) 07/01/2026 End Construction Phase (Construction Contract Acceptance Milestone) 12/01/2027 Begin Closeout Phase 01/01/2028
End Closeout Phase (Closeout Report) 06/01/2028
X
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
Date 05/13/2024 17:27:50
The Project is part of Metro’s commitment to creating an equitable, shared I-710 South Corridor transportation system that provides safe, quality multimodal options for moving people that will foster clean air and sustainable communities for all residents, communities, and users in the corridor who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. The Project’s improvements implement several of Metro’s programs and plans for transforming the speed and reliability, customer experience, and zero emission operations of bus service.

Purpose and Need
NHS Improvements YES NO Roadway Class NA Reversible Lane Analysis YES NO Inc. Sustainable Communities Strategy Goals YES NO Reduce Greenhouse Gas Emissions YES NO Project Outputs
Category Outputs Unit Total
TMS (Traffic Management Systems) Transit Signal Priority (TSP) EA 114 STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
Date 05/13/2024 17:27:50
Categorical Exemption (CE) is shown as 'Document Type' under Project Milestones but the actual exempt status is Statutory Exemption (SE).

SE was not listed as an option in the drop-down list.

There is no Right-of-Way phase proposed, as all Right-of-Way is within LA Metro’s, Caltrans, or City jurisdictions existing Right-of-Way and no additional acquisition is required.

While the Project depends on all of the separate contracted components, LA Metro acknowledges the LPP-C funding will be applied to the bus shelters, solar lighting, terminal/layover, and zero emission bus charging infrastructure improvements only. No LPP-C funds are proposed for the transit signal priority component.

Additional Information
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Congestion
Reduction

LPPC, SCCP,
LPPF
Change in Daily Vehicle Miles
Travelled
Miles 0 0 0
VMT per Capita 0 0 0

LPPC, SCCP,
LPPF
Person Hours of Travel Time Saved
(Only ‘Change’ required)
Person Hours -192,064 0 -192,064
Hours per Capita 788,223 725,165 63,058
Throughput
(Freight) Optional Bicyclist/ Pedestrian Screen Line
Counts
# of Bikes 0 0 0
# of Pedestrians 0 0 0
System
Reliability
(Freight)

LPPC, SCCP,
LPPF
Peak Period Travel Time Reliability
Index (Only ‘No Build’ Required) Index 0 0 0

LPPC, SCCP,
LPPF Level of Transit Delay (if required) % "On-time" 0 0 0 Air Quality &
GHG (only
‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Particulate Matter PM 2.5 Tons 5.36 5.64 -0.28
PM 10 Tons 5.36 5.64 -0.28

LPPC, SCCP,
TCEP, LPPF Carbon Dioxide (CO2) Tons 4,113 71,030 -66,917

LPPC, SCCP,
TCEP, LPPF Volatile Organic Compounds (VOC) Tons 0 2.63 -2.63

LPPC, SCCP,
TCEP, LPPF Sulphur Dioxides (SOx) Tons 0 0.51 -0.51

LPPC, SCCP,
TCEP, LPPF Carbon Monoxide (CO) Tons 0 1,102 -1,102

LPPC, SCCP,
TCEP, LPPF Nitrogen Oxides (NOx) Tons 0 7.13 -7.13
Safety LPPC, SCCP,
TCEP, LPPF Number of Fatalities Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Fatalities per 100 Million VMT Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Number of Serious Injuries Number 0 0 0

LPPC, SCCP,

TCEP, LPPF
Number of Serious Injuries per 100
Million VMT Number 0 0 0
Accessibility Optional Number of Jobs Accessible by Mode Number 0 0 0 Optional Number of Destinations Accessible by
Mode Number 0 0 0
Optional
Percent of Population Defined as Low
Income or Disadvantaged Within 1/2
Mile of Rail Station, Ferry Terminal, or
High-Frequency Bus Stop
% 0 0 0
Economic
Development

LPPC, SCCP,
TCEP, LPPF Jobs Created (Only ‘Build’ Required) Number 362.4 0 362.4 Cost
Effectiveness
(only ‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Cost Benefit Ratio
Ratio 4.36 0 4.36
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change System
Preservation
Pavement
Optional Pavement Condition Index Index 0 0 0
Rating NA NA
System
Preservation
Bridges
Optional Bridge Deck Rating Rating NA NA
Optional Bridge Superstructure Rating Rating NA NA
Optional Bridge Substructure Rating Rating NA NA
Noise Level
(Soundwalls
Only)
Optional Number of Receptors Number 0 0 0
Optional Properties Directly Benefited Number 0 0 0
Optional Number of Decibels Number 0 0 0
Vehicle
Volume

LPPC, LPPF,
SCCP
Existing Average Annual Vehicle
Volume on Project Segment Number 0 0 0

LPPC, LPPF,
SCCP
Estimated Year 20 Average Annual
Vehicle Volume on Project Segment
with Project
Number 0 0 0
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
07 District EA Project ID
LP011A
PPNO
Los Angeles County
County Route
Southeast Los Angeles Transit Improvements Project (Transit Signal Priority) Project Title
Existing Total Project Cost ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan Tra
PS&E Los Angeles County Metropolitan Tra
R/W SUP (CT) Los Angeles County Metropolitan Tra
CON SUP (CT) Los Angeles County Metropolitan Tra
R/W Los Angeles County Metropolitan Tra
CON Los Angeles County Metropolitan Tra
TOTAL
Proposed Total Project Cost ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 6,630 6,630
TOTAL 6,630 6,630
Fund #1: Local Funds - Local Measure (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 6,630 6,630
TOTAL 6,630 6,630
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0051 v0
PPR ID
Fund #2: State SB1 LPP - Local Partnership Program - Competitive program (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
LPP-C funds are not proposed for
this component.

Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
Amendment (Existing Project) YES NO Date 05/13/2024 17:22:40 Programs LPP-C LPP-F SCCP TCEP STIP Other
07 District EA Project ID
LP011B
PPNO
Los Angeles County Metropolitan Transportation Authority Nominating Agency
Co-Nominating Agency
SCAG
MPO
Mass Transit (MT)
Element

TYRONE CRUMP
Project Manager/Contact
213-547-4377
Phone
[email protected]
Email Address
Southeast Los Angeles Transit Improvements Project (Bus Shelters) Project Title
County Route PM Back PM Ahead
Los Angeles County
The purchase and installation of bus shelters with real-time display and security lighting in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Location (Project Limits), Description (Scope of Work)
Component Implementing Agency
PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Los Angeles County Metropolitan Transportation Authority Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts
Assembly: 64,51,53,58,63 Senate: 32,33,35,24 Congressional: 34,38,40,44 Project Milestone Existing Proposed
Project Study Report Approved
Begin Environmental (PA&ED) Phase 06/01/2023
Circulate Draft Environmental Document Document Type CE 06/01/2023 Draft Project Report 06/01/2023
End Environmental Phase (PA&ED Milestone) 07/01/2023
Begin Design (PS&E) Phase 07/02/2023
End Design Phase (Ready to List for Advertisement Milestone) 01/31/2025 Begin Right of Way Phase 07/02/2023
End Right of Way Phase (Right of Way Certification Milestone) 01/31/2025 Begin Construction Phase (Contract Award Milestone) 04/01/2025 End Construction Phase (Construction Contract Acceptance Milestone) 09/01/2027 Begin Closeout Phase 09/02/2027
End Closeout Phase (Closeout Report) 02/28/2028
X
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
Date 05/13/2024 17:22:40
The Project is part of Metro’s commitment to creating an equitable, shared I-710 South Corridor transportation system that provides safe, quality multimodal options for moving people that will foster clean air and sustainable communities for all residents, communities, and users in the corridor who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. The Project’s improvements implement several of Metro’s programs and plans for transforming the speed and reliability, customer experience, and zero emission operations of bus service.

Purpose and Need
NHS Improvements YES NO Roadway Class NA Reversible Lane Analysis YES NO Inc. Sustainable Communities Strategy Goals YES NO Reduce Greenhouse Gas Emissions YES NO Project Outputs
Category Outputs Unit Total
Rail/ Multi-Modal Station improvements EA 100
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
Date 05/13/2024 17:22:40
Categorical Exemption (CE) is shown as 'Document Type' under Project Milestones but the actual exempt status is Statutory Exemption (SE).

SE was not listed as an option in the drop-down list.

There is no Right-of-Way phase proposed, as all Right-of-Way is within LA Metro’s, Caltrans, or City jurisdictions existing Right-of-Way and no additional acquisition is required.

While the Project depends on all of the separate contracted components, LA Metro acknowledges the LPP-C funding will be applied to the bus shelters, solar lighting, terminal/layover, and zero emission bus charging infrastructure improvements only. No LPP-C funds are proposed for the transit signal priority component.

Additional Information
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Congestion
Reduction

LPPC, SCCP,
LPPF
Change in Daily Vehicle Miles
Travelled
Miles 0 0 0
VMT per Capita 0 0 0

LPPC, SCCP,
LPPF
Person Hours of Travel Time Saved
(Only ‘Change’ required)
Person Hours -192,064 0 -192,064
Hours per Capita 788,223 725,165 63,058
Throughput
(Freight) Optional Bicyclist/ Pedestrian Screen Line
Counts
# of Bikes 0 0 0
# of Pedestrians 0 0 0
System
Reliability
(Freight)

LPPC, SCCP,
LPPF
Peak Period Travel Time Reliability
Index (Only ‘No Build’ Required) Index 0 0 0

LPPC, SCCP,
LPPF Level of Transit Delay (if required) % "On-time" 0 0 0 Air Quality &
GHG (only
‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Particulate Matter PM 2.5 Tons 5.36 5.64 -0.28
PM 10 Tons 5.36 5.64 -0.28

LPPC, SCCP,
TCEP, LPPF Carbon Dioxide (CO2) Tons 4,113 71,030 -66,917

LPPC, SCCP,
TCEP, LPPF Volatile Organic Compounds (VOC) Tons 0 2.63 -2.63

LPPC, SCCP,
TCEP, LPPF Sulphur Dioxides (SOx) Tons 0 0.51 -0.51

LPPC, SCCP,
TCEP, LPPF Carbon Monoxide (CO) Tons 0 1,102 -1,102

LPPC, SCCP,
TCEP, LPPF Nitrogen Oxides (NOx) Tons 0 7.13 -7.13
Safety LPPC, SCCP,
TCEP, LPPF Number of Fatalities Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Fatalities per 100 Million VMT Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Number of Serious Injuries Number 0 0 0

LPPC, SCCP,

TCEP, LPPF
Number of Serious Injuries per 100
Million VMT Number 0 0 0
Accessibility Optional Number of Jobs Accessible by Mode Number 0 0 0 Optional Number of Destinations Accessible by
Mode Number 0 0 0
Optional
Percent of Population Defined as Low
Income or Disadvantaged Within 1/2
Mile of Rail Station, Ferry Terminal, or
High-Frequency Bus Stop
% 0 0 0
Economic
Development

LPPC, SCCP,
TCEP, LPPF Jobs Created (Only ‘Build’ Required) Number 362.4 0 362.4 Cost
Effectiveness
(only ‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Cost Benefit Ratio
Ratio 4.36 0 4.36
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change System
Preservation
Pavement
Optional Pavement Condition Index Index 0 0 0
Rating NA NA
System
Preservation
Bridges
Optional Bridge Deck Rating Rating NA NA
Optional Bridge Superstructure Rating Rating NA NA
Optional Bridge Substructure Rating Rating NA NA
Noise Level
(Soundwalls
Only)
Optional Number of Receptors Number 0 0 0
Optional Properties Directly Benefited Number 0 0 0
Optional Number of Decibels Number 0 0 0
Vehicle
Volume

LPPC, LPPF,
SCCP
Existing Average Annual Vehicle
Volume on Project Segment Number 0 0 0

LPPC, LPPF,
SCCP
Estimated Year 20 Average Annual
Vehicle Volume on Project Segment
with Project
Number 0 0 0
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
07 District EA Project ID
LP011B
PPNO
Los Angeles County
County Route
Southeast Los Angeles Transit Improvements Project (Bus Shelters) Project Title
Existing Total Project Cost ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan Tra
PS&E Los Angeles County Metropolitan Tra
R/W SUP (CT) Los Angeles County Metropolitan Tra
CON SUP (CT) Los Angeles County Metropolitan Tra
R/W Los Angeles County Metropolitan Tra
CON Los Angeles County Metropolitan Tra
TOTAL
Proposed Total Project Cost ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 6,000 6,000
TOTAL 6,000 6,000
Fund #1: State SB1 LPP - Local Partnership Program - Competitive program (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 3,000 3,000
TOTAL 3,000 3,000
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0056 v0
PPR ID
Fund #2: Local Funds - Local Transportation Funds (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 3,000 3,000
TOTAL 3,000 3,000
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
Amendment (Existing Project) YES NO Date 05/13/2024 17:25:29 Programs LPP-C LPP-F SCCP TCEP STIP Other
07 District EA Project ID
LP011C
PPNO
Los Angeles County Metropolitan Transportation Authority Nominating Agency
Co-Nominating Agency
SCAG
MPO
Mass Transit (MT)
Element

TYRONE CRUMP
Project Manager/Contact
213-547-4377
Phone
[email protected]
Email Address
Southeast Los Angeles Transit Improvements Project (Lighting) Project Title
County Route PM Back PM Ahead
Los Angeles County
The purchase and installation of solar-powered lighting upgrades in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Location (Project Limits), Description (Scope of Work)
Component Implementing Agency
PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Los Angeles County Metropolitan Transportation Authority Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts
Assembly: 64,51,53,58,63 Senate: 32,33,35,24 Congressional: 34,38,40,44 Project Milestone Existing Proposed
Project Study Report Approved
Begin Environmental (PA&ED) Phase 06/01/2023
Circulate Draft Environmental Document Document Type CE 06/01/2023 Draft Project Report 06/01/2023
End Environmental Phase (PA&ED Milestone) 07/01/2023
Begin Design (PS&E) Phase 07/02/2023
End Design Phase (Ready to List for Advertisement Milestone) 08/02/2024 Begin Right of Way Phase 07/02/2023
End Right of Way Phase (Right of Way Certification Milestone) 08/02/2024 Begin Construction Phase (Contract Award Milestone) 12/01/2024 End Construction Phase (Construction Contract Acceptance Milestone) 06/30/2026 Begin Closeout Phase 07/01/2026
End Closeout Phase (Closeout Report) 12/31/2026
X
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
Date 05/13/2024 17:25:29
The Project is part of Metro’s commitment to creating an equitable, shared I-710 South Corridor transportation system that provides safe, quality multimodal options for moving people that will foster clean air and sustainable communities for all residents, communities, and users in the corridor who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. The Project’s improvements implement several of Metro’s programs and plans for transforming the speed and reliability, customer experience, and zero emission operations of bus service.

Purpose and Need
NHS Improvements YES NO Roadway Class NA Reversible Lane Analysis YES NO Inc. Sustainable Communities Strategy Goals YES NO Reduce Greenhouse Gas Emissions YES NO Project Outputs
Category Outputs Unit Total
Rail/ Multi-Modal Station improvements EA 100
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
Date 05/13/2024 17:25:29
Categorical Exemption (CE) is shown as 'Document Type' under Project Milestones but the actual exempt status is Statutory Exemption (SE).

SE was not listed as an option in the drop-down list.

There is no Right-of-Way phase proposed, as all Right-of-Way is within LA Metro’s, Caltrans, or City jurisdictions existing Right-of-Way and no additional acquisition is required.

While the Project depends on all of the separate contracted components, LA Metro acknowledges the LPP-C funding will be applied to the bus shelters, solar lighting, terminal/layover, and zero emission bus charging infrastructure improvements only. No LPP-C funds are proposed for the transit signal priority component.

Additional Information
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Congestion
Reduction

LPPC, SCCP,
LPPF
Change in Daily Vehicle Miles
Travelled
Miles 0 0 0
VMT per Capita 0 0 0

LPPC, SCCP,
LPPF
Person Hours of Travel Time Saved
(Only ‘Change’ required)
Person Hours 788,223 725,165 63,058
Hours per Capita -192,064 0 -192,064
Throughput
(Freight) Optional Bicyclist/ Pedestrian Screen Line
Counts
# of Bikes 0 0 0
# of Pedestrians 0 0 0
System
Reliability
(Freight)

LPPC, SCCP,
LPPF
Peak Period Travel Time Reliability
Index (Only ‘No Build’ Required) Index 0 0 0

LPPC, SCCP,
LPPF Level of Transit Delay (if required) % "On-time" 0 0 0 Air Quality &
GHG (only
‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Particulate Matter PM 2.5 Tons 5.36 5.64 -0.28
PM 10 Tons 5.36 5.64 -0.28

LPPC, SCCP,
TCEP, LPPF Carbon Dioxide (CO2) Tons 4,113 71,030 -66,917

LPPC, SCCP,
TCEP, LPPF Volatile Organic Compounds (VOC) Tons 0 2.63 -2.63

LPPC, SCCP,
TCEP, LPPF Sulphur Dioxides (SOx) Tons 0 0.51 -0.51

LPPC, SCCP,
TCEP, LPPF Carbon Monoxide (CO) Tons 0 1,102 -1,102

LPPC, SCCP,
TCEP, LPPF Nitrogen Oxides (NOx) Tons 0 7.13 -7.13
Safety LPPC, SCCP,
TCEP, LPPF Number of Fatalities Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Fatalities per 100 Million VMT Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Number of Serious Injuries Number 0 0 0

LPPC, SCCP,

TCEP, LPPF
Number of Serious Injuries per 100
Million VMT Number 0 0 0
Accessibility Optional Number of Jobs Accessible by Mode Number 0 0 0 Optional Number of Destinations Accessible by
Mode Number 0 0 0
Optional
Percent of Population Defined as Low
Income or Disadvantaged Within 1/2
Mile of Rail Station, Ferry Terminal, or
High-Frequency Bus Stop
% 0 0 0
Economic
Development

LPPC, SCCP,
TCEP, LPPF Jobs Created (Only ‘Build’ Required) Number 362.4 0 362.4 Cost
Effectiveness
(only ‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Cost Benefit Ratio
Ratio 4.36 0 4.36
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change System
Preservation
Pavement
Optional Pavement Condition Index Index 0 0 0
Rating NA NA
System
Preservation
Bridges
Optional Bridge Deck Rating Rating NA NA
Optional Bridge Superstructure Rating Rating NA NA
Optional Bridge Substructure Rating Rating NA NA
Noise Level
(Soundwalls
Only)
Optional Number of Receptors Number 0 0 0
Optional Properties Directly Benefited Number 0 0 0
Optional Number of Decibels Number 0 0 0
Vehicle
Volume

LPPC, LPPF,
SCCP
Existing Average Annual Vehicle
Volume on Project Segment Number 0 0 0

LPPC, LPPF,
SCCP
Estimated Year 20 Average Annual
Vehicle Volume on Project Segment
with Project
Number 0 0 0
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
07 District EA Project ID
LP011C
PPNO
Los Angeles County
County Route
Southeast Los Angeles Transit Improvements Project (Lighting) Project Title
Existing Total Project Cost ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan Tra
PS&E Los Angeles County Metropolitan Tra
R/W SUP (CT) Los Angeles County Metropolitan Tra
CON SUP (CT) Los Angeles County Metropolitan Tra
R/W Los Angeles County Metropolitan Tra
CON Los Angeles County Metropolitan Tra
TOTAL
Proposed Total Project Cost ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 500 500
TOTAL 500 500
Fund #1: State SB1 LPP - Local Partnership Program - Competitive program (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 250 250
TOTAL 250 250
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0055 v0
PPR ID
Fund #2: Local Funds - Local Transportation Funds (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 250 250
TOTAL 250 250
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
Amendment (Existing Project) YES NO Date 05/13/2024 17:20:08 Programs LPP-C LPP-F SCCP TCEP STIP Other
07 District EA Project ID
LP011D
PPNO
Los Angeles County Metropolitan Transportation Authority Nominating Agency
Co-Nominating Agency
SCAG
MPO
Mass Transit (MT)
Element

TYRONE CRUMP
Project Manager/Contact
213-547-4377
Phone
[email protected]
Email Address
Southeast Los Angeles Transit Improvements Project (Termini/Layover) Project Title
County Route PM Back PM Ahead
Los Angeles County
The construction of civil works at bus termini/layovers at Norwalk, Artesia, and Compton Stations in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Location (Project Limits), Description (Scope of Work)
Component Implementing Agency
PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Los Angeles County Metropolitan Transportation Authority Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts
Assembly: 64,51,53,58,63 Senate: 32,33,35,24 Congressional: 34,38,40,44 Project Milestone Existing Proposed
Project Study Report Approved
Begin Environmental (PA&ED) Phase 06/01/2023
Circulate Draft Environmental Document Document Type CE 06/01/2023 Draft Project Report 06/01/2023
End Environmental Phase (PA&ED Milestone) 12/01/2023
Begin Design (PS&E) Phase 01/01/2024
End Design Phase (Ready to List for Advertisement Milestone) 01/01/2025 Begin Right of Way Phase 01/01/2024
End Right of Way Phase (Right of Way Certification Milestone) 01/01/2025 Begin Construction Phase (Contract Award Milestone) 06/30/2025 End Construction Phase (Construction Contract Acceptance Milestone) 12/30/2026 Begin Closeout Phase 01/01/2027
End Closeout Phase (Closeout Report) 06/01/2027
X
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
Date 05/13/2024 17:20:08
The Project is part of Metro’s commitment to creating an equitable, shared I-710 South Corridor transportation system that provides safe, quality multimodal options for moving people that will foster clean air and sustainable communities for all residents, communities, and users in the corridor who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. The Project’s improvements implement several of Metro’s programs and plans for transforming the speed and reliability, customer experience, and zero emission operations of bus service.

Purpose and Need
NHS Improvements YES NO Roadway Class NA Reversible Lane Analysis YES NO Inc. Sustainable Communities Strategy Goals YES NO Reduce Greenhouse Gas Emissions YES NO Project Outputs
Category Outputs Unit Total
Rail/ Multi-Modal Station improvements EA 3
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
Date 05/13/2024 17:20:08
Categorical Exemption (CE) is shown as 'Document Type' under Project Milestones but the actual exempt status is Statutory Exemption (SE).

SE was not listed as an option in the drop-down list.

There is no Right-of-Way phase proposed, as all Right-of-Way is within LA Metro’s, Caltrans, or City jurisdictions existing Right-of-Way and no additional acquisition is required.

While the Project depends on all of the separate contracted components, LA Metro acknowledges the LPP-C funding will be applied to the bus shelters, solar lighting, terminal/layover, and zero emission bus charging infrastructure improvements only. No LPP-C funds are proposed for the transit signal priority component.

Additional Information
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Congestion
Reduction

LPPC, SCCP,
LPPF
Change in Daily Vehicle Miles
Travelled
Miles 0 0 0
VMT per Capita 0 0 0

LPPC, SCCP,
LPPF
Person Hours of Travel Time Saved
(Only ‘Change’ required)
Person Hours -192,064 0 -192,064
Hours per Capita 788,223 725,165 63,058
Throughput
(Freight) Optional Bicyclist/ Pedestrian Screen Line
Counts
# of Bikes 0 0 0
# of Pedestrians 0 0 0
System
Reliability
(Freight)

LPPC, SCCP,
LPPF
Peak Period Travel Time Reliability
Index (Only ‘No Build’ Required) Index 0 0 0

LPPC, SCCP,
LPPF Level of Transit Delay (if required) % "On-time" 0 0 0 Air Quality &
GHG (only
‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Particulate Matter PM 2.5 Tons 5.36 5.64 -0.28
PM 10 Tons 5.36 5.64 -0.28

LPPC, SCCP,
TCEP, LPPF Carbon Dioxide (CO2) Tons 4,113 71,030 -66,917

LPPC, SCCP,
TCEP, LPPF Volatile Organic Compounds (VOC) Tons 0 2.63 -2.63

LPPC, SCCP,
TCEP, LPPF Sulphur Dioxides (SOx) Tons 0 0.51 -0.51

LPPC, SCCP,
TCEP, LPPF Carbon Monoxide (CO) Tons 0 1,102 -1,102

LPPC, SCCP,
TCEP, LPPF Nitrogen Oxides (NOx) Tons 0 7.13 -7.13
Safety LPPC, SCCP,
TCEP, LPPF Number of Fatalities Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Fatalities per 100 Million VMT Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Number of Serious Injuries Number 0 0 0

LPPC, SCCP,

TCEP, LPPF
Number of Serious Injuries per 100
Million VMT Number 0 0 0
Accessibility Optional Number of Jobs Accessible by Mode Number 0 0 0 Optional Number of Destinations Accessible by
Mode Number 0 0 0
Optional
Percent of Population Defined as Low
Income or Disadvantaged Within 1/2
Mile of Rail Station, Ferry Terminal, or
High-Frequency Bus Stop
% 0 0 0
Economic
Development

LPPC, SCCP,
TCEP, LPPF Jobs Created (Only ‘Build’ Required) Number 362.4 0 362.4 Cost
Effectiveness
(only ‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Cost Benefit Ratio
Ratio 4.36 0 4.36
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change System
Preservation
Pavement
Optional Pavement Condition Index Index 0 0 0
Rating NA NA
System
Preservation
Bridges
Optional Bridge Deck Rating Rating NA NA
Optional Bridge Superstructure Rating Rating NA NA
Optional Bridge Substructure Rating Rating NA NA
Noise Level
(Soundwalls
Only)
Optional Number of Receptors Number 0 0 0
Optional Properties Directly Benefited Number 0 0 0
Optional Number of Decibels Number 0 0 0
Vehicle
Volume

LPPC, LPPF,
SCCP
Existing Average Annual Vehicle
Volume on Project Segment Number 0 0 0

LPPC, LPPF,
SCCP
Estimated Year 20 Average Annual
Vehicle Volume on Project Segment
with Project
Number 0 0 0
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
07 District EA Project ID
LP011D
PPNO
Los Angeles County
County Route
Southeast Los Angeles Transit Improvements Project (Termini/Layover) Project Title
Existing Total Project Cost ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan Tra
PS&E Los Angeles County Metropolitan Tra
R/W SUP (CT) Los Angeles County Metropolitan Tra
CON SUP (CT) Los Angeles County Metropolitan Tra
R/W Los Angeles County Metropolitan Tra
CON Los Angeles County Metropolitan Tra
TOTAL
Proposed Total Project Cost ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 8,000 8,000
TOTAL 8,000 8,000
Fund #1: State SB1 LPP - Local Partnership Program - Competitive program (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 4,000 4,000
TOTAL 4,000 4,000
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0057 v0
PPR ID
Fund #2: Local Funds - Local Transportation Funds (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 4,000 4,000
TOTAL 4,000 4,000
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
Amendment (Existing Project) YES NO Date 05/13/2024 17:17:52 Programs LPP-C LPP-F SCCP TCEP STIP Other
07 District EA Project ID
LP011E
PPNO
Los Angeles County Metropolitan Transportation Authority Nominating Agency
Co-Nominating Agency
SCAG
MPO
Mass Transit (MT)
Element

TYRONE CRUMP
Project Manager/Contact
213-547-4377
Phone
[email protected]
Email Address
Southeast Los Angeles Transit Improvements Project (ZEB Charging) Project Title
County Route PM Back PM Ahead
Los Angeles County
The purchase and installation of zero emission bus (ZEB) charging masts in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Location (Project Limits), Description (Scope of Work)
Component Implementing Agency
PA&ED Los Angeles County Metropolitan Transportation Authority PS&E Los Angeles County Metropolitan Transportation Authority Right of Way Los Angeles County Metropolitan Transportation Authority Construction Los Angeles County Metropolitan Transportation Authority Legislative Districts
Assembly: 64,51,53,58,63 Senate: 32,33,35,24 Congressional: 34,38,40,44 Project Milestone Existing Proposed
Project Study Report Approved
Begin Environmental (PA&ED) Phase 06/01/2023
Circulate Draft Environmental Document Document Type CE 06/01/2023 Draft Project Report 06/01/2023
End Environmental Phase (PA&ED Milestone) 12/01/2023
Begin Design (PS&E) Phase 01/01/2024
End Design Phase (Ready to List for Advertisement Milestone) 01/01/2025 Begin Right of Way Phase 01/01/2024
End Right of Way Phase (Right of Way Certification Milestone) 01/01/2025 Begin Construction Phase (Contract Award Milestone) 06/30/2025 End Construction Phase (Construction Contract Acceptance Milestone) 12/30/2026 Begin Closeout Phase 01/01/2027
End Closeout Phase (Closeout Report) 06/01/2027
X
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
Date 05/13/2024 17:17:52
The Project is part of Metro’s commitment to creating an equitable, shared I-710 South Corridor transportation system that provides safe, quality multimodal options for moving people that will foster clean air and sustainable communities for all residents, communities, and users in the corridor who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. The Project’s improvements implement several of Metro’s programs and plans for transforming the speed and reliability, customer experience, and zero emission operations of bus service.

Purpose and Need
NHS Improvements YES NO Roadway Class NA Reversible Lane Analysis YES NO Inc. Sustainable Communities Strategy Goals YES NO Reduce Greenhouse Gas Emissions YES NO Project Outputs
Category Outputs Unit Total
Rail/ Multi-Modal Rail/Transit Equipment EA 10
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
Date 05/13/2024 17:17:52
Categorical Exemption (CE) is shown as 'Document Type' under Project Milestones but the actual exempt status is Statutory Exemption (SE).

SE was not listed as an option in the drop-down list.

There is no Right-of-Way phase proposed, as all Right-of-Way is within LA Metro’s, Caltrans, or City jurisdictions existing Right-of-Way and no additional acquisition is required.

While the Project depends on all of the separate contracted components, LA Metro acknowledges the LPP-C funding will be applied to the bus shelters, solar lighting, terminal/layover, and zero emission bus charging infrastructure improvements only. No LPP-C funds are proposed for the transit signal priority component.

Additional Information
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change Congestion
Reduction

LPPC, SCCP,
LPPF
Change in Daily Vehicle Miles
Travelled
Miles 0 0 0
VMT per Capita 0 0 0

LPPC, SCCP,
LPPF
Person Hours of Travel Time Saved
(Only ‘Change’ required)
Person Hours 788,223 725,165 63,058
Hours per Capita -192,064 0 -192,064
Throughput
(Freight) Optional Bicyclist/ Pedestrian Screen Line
Counts
# of Bikes 0 0 0
# of Pedestrians 0 0 0
System
Reliability
(Freight)

LPPC, SCCP,
LPPF
Peak Period Travel Time Reliability
Index (Only ‘No Build’ Required) Index 0 0 0

LPPC, SCCP,
LPPF Level of Transit Delay (if required) % "On-time" 0 0 0 Air Quality &
GHG (only
‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Particulate Matter PM 2.5 Tons 5.36 5.64 -0.28
PM 10 Tons 5.36 5.64 -0.28

LPPC, SCCP,
TCEP, LPPF Carbon Dioxide (CO2) Tons 4,113 71,030 -66,917

LPPC, SCCP,
TCEP, LPPF Volatile Organic Compounds (VOC) Tons 0 2.63 -2.63

LPPC, SCCP,
TCEP, LPPF Sulphur Dioxides (SOx) Tons 0 0.51 -0.51

LPPC, SCCP,
TCEP, LPPF Carbon Monoxide (CO) Tons 0 1,102 -1,102

LPPC, SCCP,
TCEP, LPPF Nitrogen Oxides (NOx) Tons 0 7.13 -7.13
Safety LPPC, SCCP,
TCEP, LPPF Number of Fatalities Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Fatalities per 100 Million VMT Number 0 0 0

LPPC, SCCP,
TCEP, LPPF Number of Serious Injuries Number 0 0 0

LPPC, SCCP,

TCEP, LPPF
Number of Serious Injuries per 100
Million VMT Number 0 0 0
Accessibility Optional Number of Jobs Accessible by Mode Number 0 0 0 Optional Number of Destinations Accessible by
Mode Number 0 0 0
Optional
Percent of Population Defined as Low
Income or Disadvantaged Within 1/2
Mile of Rail Station, Ferry Terminal, or
High-Frequency Bus Stop
% 0 0 0
Economic
Development

LPPC, SCCP,
TCEP, LPPF Jobs Created (Only ‘Build’ Required) Number 362.4 0 362.4 Cost
Effectiveness
(only ‘Change’
required)

LPPC, SCCP,

TCEP, LPPF
Cost Benefit Ratio
Ratio 4.36 0 4.36
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
Performance Indicators and Measures
Measure Required For Indicator/Measure Unit Build Future No Build Change System
Preservation
Pavement
Optional Pavement Condition Index Index 0 0 0
Rating NA NA
System
Preservation
Bridges
Optional Bridge Deck Rating Rating NA NA
Optional Bridge Superstructure Rating Rating NA NA
Optional Bridge Substructure Rating Rating NA NA
Noise Level
(Soundwalls
Only)
Optional Number of Receptors Number 0 0 0
Optional Properties Directly Benefited Number 0 0 0
Optional Number of Decibels Number 0 0 0
Vehicle
Volume

LPPC, LPPF,
SCCP
Existing Average Annual Vehicle
Volume on Project Segment Number 0 0 0

LPPC, LPPF,
SCCP
Estimated Year 20 Average Annual
Vehicle Volume on Project Segment
with Project
Number 0 0 0
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
07 District EA Project ID
LP011E
PPNO
Los Angeles County
County Route
Southeast Los Angeles Transit Improvements Project (ZEB Charging) Project Title
Existing Total Project Cost ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total Implementing Agency E&P (PA&ED) Los Angeles County Metropolitan Tra
PS&E Los Angeles County Metropolitan Tra
R/W SUP (CT) Los Angeles County Metropolitan Tra
CON SUP (CT) Los Angeles County Metropolitan Tra
R/W Los Angeles County Metropolitan Tra
CON Los Angeles County Metropolitan Tra
TOTAL
Proposed Total Project Cost ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 10,000 10,000
TOTAL 10,000 10,000
Fund #1: Local Funds - Local Measure (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 2,750 2,750
TOTAL 2,750 2,750
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION

PROJECT PROGRAMMING REQUEST (PPR)
PRG-0010 (REV 08/2020)
ePPR-6065-2023-0058 v0
PPR ID
Fund #2: State SB1 LPP - Local Partnership Program - Competitive program (Committed) Program Code Existing Funding ($1,000s)
Component Prior 23-24 24-25 25-26 26-27 27-28 28-29+ Total

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON
TOTAL
Los Angeles County Metropolitan Tra
Funding Agency
Non-proportional spending allowed
for this component.

Proposed Funding ($1,000s) Notes

E&P (PA&ED)
PS&E

R/W SUP (CT)

CON SUP (CT)
R/W
CON 7,250 7,250
TOTAL 7,250 7,250
Southeast Los Angeles Transit Improvements Project
SB1 LPP-Competitive Cycle 3 Project
SB1 Project Baseline Agreement – Scope, Schedule, Costs, Benefits LP011D - Scope, Schedule, Costs, Benefits
Scope :-- The construction of civil works at bus termini/layovers at Norwalk, Artesia, and Compton Stations in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Schedule :--
PA&ED (Environmental) Begin = 06/01/2023 End = 12/01/2023 PS&E (Design) Begin = 01/01/2024 End = 01/01/2025
ROW-Certification Begin = 01/01/2024 End = 01/01/2025
Construction (Contract) Begin = 06/30/2025 End = 12/30/2026 Costs (Funding) :-- Total = $8M – FY 24/25 ; LPP-C = $4M Benefits/Outputs :-- Rail/Multi-Modal – Station Improvements = 3 each LP011E - Scope, Schedule, Costs, Benefits
Scope :-- The purchase and installation of zero emission bus (ZEB) charging masts in NextGen Tier 1 and 2 high frequency corridors throughout the I-710 South communities in southeast Los Angeles County to improve bus service with speed and reliability infrastructure and enhanced customer amenities.

Schedule :--
PA&ED (Environmental) Begin = 06/01/2023 End = 12/01/2023 PS&E (Design) Begin = 01/01/2024 End = 01/01/2025
ROW-Certification Begin = 01/01/2024 End = 01/01/2025
Construction (Contract) Begin = 06/30/2025 End = 12/30/2026 Costs (Funding) :-- Total = $10M (Local) – FY 24/25 ; LPP-C = $7.25M { non-proportional spending allowed }
Benefits/Outputs :-- Rail/Multi-Modal – Rail/Transit Equipment = 10 each District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024

PROJECT REPORT EQUIVALENT
Project Title: Southeast Los Angeles Transit Improvements Project Project Location Description (include route, postmiles, rail mile posts, address, intersections, etc.):

The Los Angeles County Metropolitan Transportation Authority (LA Metro) Southeast Los Angeles Transit Improvements Project (SELA TIP) area stretches across multiple high frequency LA Metro NextGen Tier 1 and 2 bus line corridors throughout southeast Los Angeles County along the I-710 corridor (see Figure 1), a critical goods movement corridor that sustains the state’s and nation’s economies to the detriment of the corridor communities who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. The exact locations of the waiting environment improvements will be determined in coordination with the Southeast Los Angeles cities where the corridors are located, based on bus stop existing conditions and needs.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Figure 1: Project Location
 


























!


"#
$
#%
$

#&
&'

()

#*
)
#





"%
%
+"







*
#

)
#



"

##"#
,(+""
+



-
-


-
"#

"
+.

/-
-+
-(
-
-"
-#


.

"%
""+

/

+


+

-
++-,

00000000000000000000000000000000000000000   000000000000000000 )

#
*
)
#






)





*
#

)
#



"






("%%/-"
+





-
"#

-+
-"-
-
+





#

-,

 
!%*


1*


 
2 3


1*







*
#

)
#



"


 


:;<=>?@<ABC 456758789 DEFEGHII;JEF>?KL;:;<=>?@<ABC DHG?M8789N74N676OM9PMQ9R7ST77T
DEFEGHII;JEF>?KL;MUVHW==>
DXM@XYUVHW==>?BHEIYCH>B==>?ZB?G<=N
>?G@Y[\
UVHW==>DHG?M8789N74N6Q66M9PM98R7]T77T
^=J?C_`=<FEH<E>E
DEFEGHII;JEF>?KL;^=J?C_
`=<FEH<E>E
DHG?M8789N74N6Q67MQ4M86R7ST77T
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Table of Contents

1. Introduction

2. Background

3. Purpose and Need

4. Environmental Clearance Description

5. Considerations Requiring Discussion

6. Funding, Programming and Estimate

7. Delivery Schedule

8. Risks

9. External Agency Coordination

10. Additional Information

11. Attachments
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024

1. INTRODUCTION
The Southeast Los Angeles Transit Improvements Project (SELA TIP) is comprised of transit improvements along multiple NextGen Tier 1 and 2 high frequency bus lines in key corridors serving Southeast Los Angeles County. These lines provide 10 minute or 15-minute bus service all day weekday throughout the I-710 South communities in southeast Los Angeles County. The I-710 South is a critical goods movement corridor that sustains the State of California and nation’s economies to the detriment of the corridor communities who have long suffered from health and mobility issues caused by growing congestion along and near the freeway. This proposed project will bring immediate and tangible benefits to corridor residents by improving bus service with bus speed and reliability infrastructure and enhanced customer amenities at bus stops on these key corridors.

Major project elements are as follows:
• PPNO LP011A: Expansion of Transit Signal Priority (TSP) to cover 114 intersections • PPNO LP011B: New shelters plus electronic real time arrival solar-powered displays at 100 of the busiest bus stops that currently lack shelters in the project area • PPNO LP011C: Bus stop solar light kits to upgrade 100 other bus stops that do not have shelters to improve lighting
• PPNO LP011D: Bus terminal/layover operational capacity and passenger amenity and improvements at Norwalk, Artesia, and Compton Station mobility hubs • PPNO LP011E: 10 ZEB charging masts to support implementation of ZEB operations on Southeast LA area bus lines serving key terminals.

The corridor improvements will be available for shared use by other transit agencies. This Project makes a large investment in the reduction of GHG emissions through equipping transit terminals with ZEB charging equipment to help allow multiple transit lines to transition to zero emission battery electric bus operation on corridors that connect to the Metro A Line (Blue) and C Line (Green) light rail lines. This investment supports Metro’s comprehensive program for serving clean, safe, and sustainable communities with world-class zero emission service by 2030, supporting those many residents of Southeast Los Angeles who rely on transit for their daily mobility.

The Project is part of Metro’s commitment to creating an equitable, shared I-710 South Corridor transportation system that provides safe, quality multimodal options for moving people that will foster clean air and sustainable communities for all residents, communities, and users in the corridor. It was prioritized for application for LPP-C funds by a task force of corridor residents, public health advocates, community-based organizations, subregional agencies, and elected offices. The Project’s improvements implement several of Metro’s programs and plans for transforming the speed and reliability, customer experience, and zero emission operations of bus service in Los Angeles County.

Project Limit/Footprint

District 7-Los Angeles County
The Los Angeles County Metropolitan
Transportation Authority (LA Metro) Southeast
Los Angeles Transit Improvements Project (SELA
TIP) area stretches across multiple high
frequency LA Metro NextGen Tier 1 and 2 bus
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
line corridors throughout southeast Los Angeles
County along the I-710 corridor (see Figure 1), a
critical goods movement corridor that sustains
the state’s and nation’s economies to the
detriment of the corridor communities who have
long suffered from health and mobility issues
caused by growing congestion along and near the
freeway. The exact locations of the waiting
environment improvements will be determined in
coordination with the Southeast Los Angeles
cities where the corridors are located, based on
bus stop existing conditions and needs.

Total Project Cost $31,130,000
Outputs PPNO LP011A: Transit Signal Priority (TSP) at
114 intersections
PPNO LP011B: 100 station improvements
PPNO LP011C: 100 station improvements
PPNO LP011D: 3 station improvements
PPNO LP011E: 10 rail/transit equipment
Outcomes See Attachment C
Environmental Determination or
Document
Statutory Exemption (SE)

2. BACKGROUND
The I-710 South Corridor is a 19-mile stretch of the I-710 Freeway, from East Los Angeles in the north to the Ports of Long Beach and Los Angeles in the south (see Figure 2). Connecting the ports with shipping and warehousing facilities in Southern California, this corridor is a goods movement corridor of national significance, as 40% of all waterborne or containerized imports into the United States come through the Ports of Long Beach and Los Angeles, which have become California’s and America’s loading docks. Metro has been studying ways to relieve congestion and improve safety along the I-710 South Corridor for more than two decades.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Figure 2: Accessibility
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Today, challenges along the I-710 South Corridor not only remain but continue in many ways to further deteriorate. The Ports are seeing record imports, and many of these products are being trucked out, on the I-710 Freeway, creating even more congestion along and near the freeway, further exacerbating safety issues and worsening air quality for communities throughout the corridor.

Of the 1.2 million people who live along the I-710 South Corridor, nearly 1 million, or 83 percent, identify as Black or Hispanic. These residents face some of the worst air quality anywhere in the country, as the corridor accounts for 20% of all particulate emissions in Southern California. The I-710 South is known as the “diesel death zone” owing to very high levels of diesel pollutants within a quarter mile either side of the freeway. These high levels of pollutants have been linked to health challenges including decreased lung function, asthma, increased lung and heart disease symptoms, and chronic bronchitis in communities along the corridor, which also face longstanding disparities in health and access to healthcare. In addition, these communities are identified as disadvantaged and low-income under the state’s definitions and as Metro-defined Equity Focus Communities (EFCs) which are communities in Los Angeles County with the highest concentration of low-income households; Black, Indigenous, and other People of Color (BIPOC) residents; and households with no access to a car.

Beginning in mid-2021, Metro staff initiated a new process to reimagine the corridor, convening a Task Force comprised of stakeholders representing labor, the ports, local elected leadership, goods movement industry, and community-based organizations to ensure community-centered mobility options are developed for all who live, work, and visit the area. The Task Force includes a Community Leadership Committee (CLC) to help inform future project direction and decision making and an Equity Working Group (EWG), which includes Task Force and CLC members, that meets regularly to ensure that all aspects of the Task Force’s work and recommendations consider historical and current inequities and discuss solutions and decisions to maximize equitable outcomes.

Over the course of one year, Metro and the 710 Task Force met nearly monthly to establish a Vision Statement, Guiding Principles, and Goals and initiated the process to identify multimodal strategies, projects, and programs for the corridor, see Figure 3. With leadership and support from the Task Force, CLC, and EWG, Metro engaged community-based organizations and corridor residents to identify mobility needs. The types and number of engagement strategies are shown in Figure 4. This effort included an I-710 South Corridor mapping tool and survey between August 2 to October 31, 2022. The mapping and survey results showed strong community desire for transit improvements. Of the nearly 1,000 map comments collected through the mapping tool, 15% of comments were related to transit improvements including requests to increase bus frequency and reliability, see figure 5.

When asked what type of projects, programs, or improvements they would most like to see implemented in the corridor, 54% of survey respondents chose transit improvements, see Figure 6.

Survey respondents further specified what types of transit improvements they desire. Improved frequencies to reduce waiting times at bus/rail stations and improved amenities such as lighting and shelters were the top two selections. The Project responds to the community identified needs just described. For this reason and to provide immediate benefits to the community while the work continues to identify longer term improvements for the corridor, Metro pursued LPP-C funds for the project.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Figure 3: Metro – Vision, Mission, and Goals
Figure 4: Community Engagement
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Figure 5: I-710 Corridor Public Engagement
Figure 6: Survey Responses
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
With the LPP-C funds, LA Metro will improve transit service in the I-710 communities in southeast Los Angeles County through the implementation of speed, reliability, and customer experience improvements identified in Metro’s NextGen Transit First Service Plan. These improvements include the following five elements:

PPNO LP011A: Transit Signal Priority
Metro will use a design-build contract for purchase, design, and installation of cloud-based transit signal priority (TSP) infrastructure on 114 intersections. TSP reduces trip time by shrinking dwell time at traffic signals for transit vehicles by extending green lights or shortening red lights, giving priority to transit vehicles approaching an intersection. The reduced dwell time contributes to faster and more reliable bus service, making travel times shorter and thereby making service more attractive to existing and potential new riders.

In LA County the coverage of TSP is incomplete, resulting in bus service that is more likely to be delayed in areas without TSP. Closing gaps in the TSP coverage network countywide contributes to more seamless operation of transit, speeding travel and offering more even distribution of transit benefits.

PPNO LP011B: Bus Shelters
Purchase and installation of 100 bus shelters plus real-time arrival electronic passenger information signs will be coordinated between Metro and various municipalities who are responsible for bus stops amenities within their jurisdiction. The same approach would apply for solar lighting at bus stops without shelters identified for this improvement due to lack of existing lighting. Multiple vendors may be involved in these purchases depending on existing arrangements Municipalities may have for provision of bus shelters. Shelters at the busiest bus stops will provide protection from the elements when waiting for the bus. Realtime passenger information will provide riders with more confidence when making their trip and supports equity by reducing the need for a smartphone to view real-time bus arrival and departure information.

PPNO LP011C: Solar Light Upgrades
Purchase and installation of 100 solar-powered lighting upgrades at bus stops without shelters.

Upgrades to solar lighting at other bus stops provide more reliable lighting during the evening to enhance the perception of safety.

PPNO LP011D: Terminal/Layover Improvements
Construction of civil works at the bus termini/layovers at the Norwalk, Artesia, and Compton Station mobility hubs to increase and improve bus boarding/alighting bays and layover areas and improve passenger amenities. The bus/terminal layover improvements will increase and improve bus boarding/alighting bays and layover areas and improve passenger amenities. These operational and customer experience enhancements will be made at three mobility hubs (at Norwalk, Compton, and Artesia Stations) that connect users to the Metro Bus and Rail network as well as to other transit systems serving the region. As buses run more frequently, there is greater demand at these mobility hubs for bus boarding and alighting bays, as well as layover areas for buses beginning or terminating routes. When layover areas reach capacity, buses may need to layover in areas intended for passenger drop off, forcing passengers to alight farther from their desired transfer point to other bus or Metro Rail service. The proposed operational improvements and passenger amenities at these mobility hubs will improve access to multimodal transportation. Waiting environment improvements will increase the attractiveness of transit by making the experience of riding the bus more comfortable, more convenient, and safer.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
PPNO LP011E: Zero Emission Bus Charging Infrastructure
Purchase and installation of 10 ZEB charging masts to be installed at bus termini/layover areas at Norwalk, Artesia, or Compton Station mobility hubs. Metro would provide initial design concepts for these facilities. This Project makes a large investment in the reduction of GHG emissions through equipping transit terminals with ZEB charging equipment to help allow multiple transit lines to transition to zero emission battery electric bus operation on corridors that connect to the Metro A Line (Blue) and C Line (Green) light rail lines. This investment supports Metro’s comprehensive program for serving clean, safe, and sustainable communities with world-class zero emission service by 2030, supporting those many residents of Southeast Los Angeles who rely on transit for their daily mobility.

Altogether, these improvements ensure that transit riders in the Project area have access to fast, reliable, and comfortable bus service with ease to make multimodal connections.

3. Purpose and NEED
As identified through community engagement efforts during the I-710 public engagement process, the current accessibility issues and concerns in the project area focus on transit service, including bus speed, reliability, and customer experience including improved bus frequency and amenities. The Project will address these issues by improving access to fast, reliable, and comfortable bus stations and service.

In recent years, the primary contributor to slow bus speeds and poor schedule reliability has been growing traffic congestion on city streets. This congestion reduces the quality of bus service and disproportionately impacts low-income people who depend on the bus to access jobs, healthcare, and other important destinations. During the development of the NextGen Bus Plan, the public clearly told Metro that speeding up buses and improving reliability is the single most important step Metro can take to retain and grow ridership, increase the carrying capacity of local roadways, and shift regional travel patterns toward more efficient modes. The resulting NextGen Bus Plan was adopted by the Metro Board in October 2020. The Plan includes improvements that would speed up buses, double the number of frequent Metro bus lines; provide more than 80% of current bus riders with 15-minute or better frequency (compared with 48% of riders previously); create an all-day, everyday frequent service; ensure a one-quarter mile walk to a bus stop for 99% of current riders; and create a more comfortable and safer waiting environment. Key components of the Plan have been implemented between December 2020 and December 2021, including establishing a set of bus service higher frequency tiers. Additional bus speed and reliability and passenger amenity improvements remain to be implemented, including TSP, as proposed in this project, to ensure that Southeast Los Angeles residents can reliably and comfortably access the Tier 1 and Tier 2 bus services they need to get to key destinations within and beyond the project area.

Access to Multimodal Choices. Also identified during community engagement efforts, were the issues and concerns in the project area call for improving the customer experience with improved bus frequency and amenities. The Project will provide access to higher-frequency and more reliable service, allowing more modal choices through: Transit Signal Priority (TSP), bus/terminal layover improvements, and waiting environment improvements. TSP reduces trip time by shrinking dwell time at traffic signals for transit vehicles by extending green lights giving priority to transit vehicles approaching a signalized intersection. The reduced dwell time contributes to faster and more reliable bus service, making travel times shorter and thereby making service more attractive to existing and potential new riders. The bus/terminal layover improvements will increase and improve bus boarding/alighting bays and layover areas and improve passenger amenities. These operational and District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
customer experience enhancements will be made at three mobility hubs (at Norwalk, Compton, and Artesia Stations) that connect users to the Metro Bus and Rail network as well as to other transit systems serving the region. As buses run more frequently, there is greater demand at these mobility hubs for bus boarding and alighting bays, as well as layover areas for buses beginning or terminating routes. When layover areas reach capacity, buses may need to layover in areas intended for passenger drop off, forcing passengers to alight farther from their desired transfer point to other bus or Metro Rail service. The proposed operational improvements and passenger amenities at these mobility hubs will improve access to multimodal transportation. Waiting environment improvements will increase the attractiveness of transit by making the experience of riding the bus more comfortable, more convenient, and safer. Shelters at the busiest bus stops will provide protection from the elements when waiting for the bus. Realtime passenger information will provide riders with more confidence when making their trip and supports equity by reducing the need for a smartphone to view real-time bus arrival and departure information. Upgrades to solar lighting at other bus stops provides more reliable lighting during the evening to enhance the perception of safety. Altogether, these improvements ensure that transit riders in the Project area have access to fast, reliable, and comfortable bus service with ease to make multimodal connections.

Gap Closure. In LA County the coverage of TSP is incomplete, resulting in bus service that is more likely to be delayed in areas without TSP. Closing gaps in the TSP coverage network countywide contributes to more seamless operation of transit, speeding travel and offering more even distribution of transit benefits.

Connectivity. By improving the speed, reliability, and customer experience of the bus network, the Project will enhance the connection experience at three key transit centers and improve the ability to connect to numerous employment centers, education, retail, medical, and residential locations throughout the project corridor and Los Angeles metropolitan area.

Air Quality and GHGs. The Project bus speed and reliability and passenger amenity improvements are expected to reduce greenhouse gas and vehicle emissions through investments in electric charging infrastructure to support the transition from conventional CNG vehicles to battery electric buses (BEB). Emissions reductions support state and regional climate goals of the Southern California Association of Governments (SCAG) 2020-2045 Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) and state regulations including the September 2019 State Executive Order N-19-19.

The reduced emissions resulting from the shift from CNG to BEBs are specific to the on-route charging period assumed to be 15 minutes per bus per layover. With the project improvements the energy used to charge the buses is assumed to be sourced from the grid and will offset the equivalent requirements for CNG to support the same number of operating miles. As a result of transitioning from CNG to BEB, the carbon dioxide, nitrogen oxide, oxides, particulate matter, and volatile organic compounds emissions related to those equivalent miles of operation Safety. Apart from roadway safety, Metro customers indicate that safety and security, including perceived safety, are crucial to the experience of using the bus and choosing to ride the bus among other travel options. Metro’s study on How Women Travel indicates that women can feel less safe waiting for the bus than they do onboard. Through TSP, the Project will decrease wait times due to faster and more reliable transit service thereby limiting any unsafe experiences. In addition, the proposed customer experience passenger amenities will enhance passenger safety and security by providing new shelters and lighting at up to 100 locations each. This investment enhances safety and District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
security for those riders who travel in early morning and evening/late night hours throughout the Southeast Los Angeles region, and during periods of inclement weather conditions.

Due to lack of data availability for safety incidents at individual stops to be improved through this project, the safety benefits have not been quantified for this application. As such, no safety performance measures are proposed.

System Preservation. The Project will improve the operations of existing street infrastructure by increasing person throughput. Additionally, the speed improvements resulting from the TSP element of the Project will allow Metro and other transit operators to serve as many or more passengers with the same number of buses, increasing operational efficiency and improving utilization of existing resources. Current conditions on the transportation system will improve through the implementation of transit- preferential infrastructure. TSP will increase bus line average operating speeds, reducing travel times for users of all modes on the corridor but most importantly for bus riders. The resulting system will benefit from increased throughput of bus riders, as the increased operating speeds will make buses a more appealing mobility choice.

Transportation, Land Use, and Housing Goals. SCAG’s RTP/SCS, Connect SoCal, includes several goals including:

1. Improve mobility, accessibility, reliability, and travel safety for people and goods

2. Enhance the preservation, security, and resilience of the regional transportation system

3. Increase person and goods movement and travel choices within the transportation system

4. Reduce greenhouse gas emissions and improve air quality

5. Leverage new transportation technologies and data-driven solutions that result in more efficient travel
The Project advances these Connect SoCal goals by implementing the plan’s recommended Sustainable Communities Strategies and Transportation Strategies and does so in Priority Growth Areas which the plan identifies as locations where the plan’s proposed strategies can be fully realized to accelerate progress towards regional goals.

One of the Sustainable Communities Strategies from Connect SoCal is to Focus Growth Near Destinations and Mobility Options. The Project implements this strategy by making speed, reliability, and customer experience improvements that will encourage the use of transportation options that reduce the reliance on and number of solo car trips. Improving the bus network in the Southeast Los Angeles region will provide a high-quality mobility option that is able to serve growth. Another strategy is to Leverage Technology Innovations. The Project implements this strategy with the ZEB charging masts and cloud-based TSP. The ZEB charging masts supports eventual full fleet transition to ZEBs by ensuring reliable on-route fueling opportunities. TSP is transit infrastructure that enables priority for low emission modes such as bus.

One of the Transportation Strategies from Connect SoCal is to Preserve and Optimize Our Current System. The Project implements this strategy by improving bus speed and reliability through TSP.

Without adding additional revenue service hours, Metro will be able to serve more riders faster due to reduced bus dwell times enabled by TSP.

The Project implements these strategies in Priority Growth Areas which are typically the dense mixed residential and commercial uses along the Tier 1 and 2 network in Southeast Los Angeles where Project improvements are proposed. The dense and intense development patterns of Priority Growth District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Areas are made viable by the availability of high-quality transit such as Metro’s bus system. They also offer a high proportion of affordable housing and employment opportunities that demand equitable access. Priority Growth Areas include Livable Corridors and High-Quality Transit Areas.

Livable Corridors are major roads that feature a mix of housing and commercial development. The proposed set of speed and reliability improvements to Metro’s and other bus systems similarly support the Livable Corridors strategy, which encourages local jurisdictions to plan and zone for increased density at nodes along key corridors. A key component of the Livable Corridors strategy is Transit Improvements on “corridors that have been identified as candidates for onstreet, dedicated lane Bus Rapid Transit (BRT) or semi-dedicated “BRT-lite” transit. Other corridors have the potential to support features that improve the user experience and bus performance, including enhanced bus shelters, real-time travel information, off-bus ticketing, alldoor boarding and longer distances between stops to increase speeds.” All elements of the Project advance the Livable Corridors Strategy.

High Quality Transit Areas (HQTAs) are corridor-focused Priority Growth Areas within one half mile of an existing or planned fixed guideway transit stop or a bus transit corridor where buses pick up passengers at a frequency of every 15 minutes (or less) during peak commuting hours. HQTAs are places where vibrant Transit Oriented Development can be realized and are a cornerstone of land use planning best practice in the SCAG region.

HQTAs represent under 3 percent of the region’s acreage but are projected to be home to over 51 percent of new households between 2016 and 2045. Infrastructure investments such as this Project that support walkable, compact communities that integrate land use and transportation planning for a better functioning-built environment are essential within HQTAs. SCAG also calls for investment in Transit Backbones - major corridors at the center of transit-oriented communities. Transit oriented communities concentrate on housing density and intensity, putting people closer to jobs and to transit, thereby diminishing reliance on the car. The Project will make such communities more viable.

Vehicle-Miles Traveled. The improvements in bus service travel time and improvements to waiting areas are expected to help attract new riders by being more time competitive, safe, and comfortable.

These improvements will encourage riders to choose transit thereby reducing vehicle miles traveled.

However, this application did not monetize any VMT reduction, and is not proposing a VMT performance measure.

4. ENVIRONMENTAL CLEARANCE DESCRIPTION (attach full environmental documents. See Section 12. Attachments)
The environmental document is a Statutory Exemption (SE) and was completed on December 28, 2023. The Notice of Exemption (NOE) is included as Attachment A.

5. CONSIDERATIONS REQUIRING DISCUSSION (if not appliable, state N/A and justification) 5A. Hazardous Waste
There are no known or recorded uses that would lead to knowledge of hazardous waste being encountered.
5B. Value Analysis
No formal value analysis was completed for this project. 5C. Resource Conservation
There are no plans.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
5D. Right-of-Way Issues
There is no Right-of-Way phase proposed, as all Right-of-Way is within Metro’s, Caltrans, or City jurisdictions existing Right-of-Way and no additional acquisition is required. 5E. Environmental Compliance
As noted above, the project has been determined to be exempt. Below are the reasons why the project is exempt:

The Project falls within the provisions of Senate Bill [SB] 922 Exemption-added January 1, 2023) which establishes statutory exemptions (SEs) from its provisions for certain types of projects. The Project improvements fall within the exemptions described in Public Resources Code Section 21080.25(a)(11) "Transit prioritization projects". A Notice of Exemption for the project has been filed with the Los Angeles County Registrar’s Office.
5F. Air Quality Conformity
No. The project is exempt.
5G. Title VI Considerations
The implementing agency adheres to Title VI in its procurement practices. 5H. Noise Abatement Decision Report
No. No noise impacts are anticipated as a result of this project.

6. FUNDING, PROGRAMMING AND ESTIMATE
Funding
The table below presents the overall project’s funding for all phases in year of expenditure. For the TSP element of the project which will be delivered using the design-build method, the cost for design and construction (PSE and CON) are combined in construction.

The Project will leverage above the required 1:1 match by providing $16,630,000 in local funds – a

53.4% match. Specifically, Metro will allocate the funding as follows:

Phase
Fiscal Year of
Allocation Amount ($000s) Funding Source
Committed or
Uncommitted
PAED n/a $ - n/a n/a
PSE FY 25 Included in CON n/a n/a
ROW n/a $ - n/a n/a
CON FY 25 $ 16,630 Local (Match) Committed
FY 25 $ 14,500 LPP-C Committed
TOTAL $ 31,130
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Cost Overruns. Metro has a long history of successful delivery of State-funded Projects. We have a breadth of experience in handling major infrastructure Projects of this scale, and larger. We have the resources and expertise to deliver this Project using the awarded state funds. We are committed to using our own resources if necessary to address any cost overruns in accordance with LPP Guidelines.

Contracts. The project will be delivered across five contracts, one per functional element, requiring separate allocations of construction funds. One exception is the TSP element which will not be delivered using any of the requested LPP-C funds so will not require a construction allocation.

Federal Discretionary Grant Funds. There has been no commitment of nor application for federal discretionary grant funds at the time of this baseline agreement.

Project Project Description
Total Project
Cost LPP-C
Local
(Match) Comment
LP011A Transit Signal Priority $ 6,630 $ - $ 6,630 No LPP-C LP011B Bus Shelters $ 6,000 $ 3,000 $ 3,000 1:1 match
LP011C Solar Light Upgrades $ 500 $ 250 $ 250 1:1 match LP011D Terminal/Layover Improvements $ 8,000 $ 4,000 $ 4,000 1:1 match LP011E Zero Emission Bus Charging Infrastructure $ 10,000 $ 7,250 $ 2,750 Non-Proportional Spending Totals ($) $ 31,130 $ 14,500 $ 16,630
Totals (%) 100.0% 46.6% 53.4%
Amounts above are in 000s
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Programming
Total Project

PPNO LP011A: Transit Signal Priority

Fund #1 Local Funds - Local Transportation Funds
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 16,630,000 - - - - $ 16,630,000
Total $ - $ - $16,630,000 $ - $ - $ - $ - $ 16,630,000
Fund #2 LPP-C
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 14,500,000 - - - - $ 14,500,000
Total $ - $ - $14,500,000 $ - $ - $ - $ - $ 14,500,000
Total Project $ 31,130,000
Fund #1 Local Funds - Local Transportation Funds
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 6,630,000 - - - - $ 6,630,000
Total $ - $ - $ 6,630,000 $ - $ - $ - $ - $ 6,630,000
Fund #2 LPP-C
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - - - - - - $ -
Total $ - $ - $ - $ - $ - $ - $ - $ -
Project Component Total $ 6,630,000
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
PPNO LP011B: Bus Shelters

PPNO LP011C: Solar Light Upgrades
Fund #1 Local Funds - Local Transportation Funds
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 3,000,000 - - - - $ 3,000,000
Total $ - $ - $ 3,000,000 $ - $ - $ - $ - $ 3,000,000
Fund #2 LPP-C
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 3,000,000 - - - - $ 3,000,000
Total $ - $ - $ 3,000,000 $ - $ - $ - $ - $ 3,000,000
Project Component Total $ 6,000,000
Fund #1 Local Funds - Local Transportation Funds
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 250,000 - - - - $ 250,000
Total $ - $ - $ 250,000 $ - $ - $ - $ - $ 250,000
Fund #2 LPP-C
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 250,000 - - - - $ 250,000
Total $ - $ - $ 250,000 $ - $ - $ - $ - $ 250,000
Project Component Total $ 500,000
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
PPNO LP011D: Termini/Layover Improvements

PPNO LP011E: Zero Emission Bus Charging Infrastructure

Fund #1 Local Funds - Local Transportation Funds
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 4,000,000 - - - - $ 4,000,000
Total $ - $ - $ 4,000,000 $ - $ - $ - $ - $ 4,000,000
Fund #2 LPP-C
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 4,000,000 - - - - $ 4,000,000
Total $ - $ - $ 4,000,000 $ - $ - $ - $ - $ 4,000,000
Project Component Total $ 8,000,000
Fund #1 Local Funds - Local Transportation Funds
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 2,750,000 - - - - $ 2,750,000
Total $ - $ - $ 2,750,000 $ - $ - $ - $ - $ 2,750,000
Fund #2 LPP-C
Phase Prior 23/24 24/25 25/26 26/27 27/28 28/29 Total
PAED - - - - - - - $ -
PS&E - - - - - - - $ -
ROW - - - - - - - $ -
CON - - 7,250,000 - - - - $ 7,250,000
Total $ - $ - $ 7,250,000 $ - $ - $ - $ - $ 7,250,000
Project Component Total $ 10,000,000
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024

7. DELIVERY SCHEDULE

PPNO LP011A: Transit Signal Priority

PPNO LP011B: Bus Shelters

Project Milestone Milestone Designation
(Target/Actual)
Approved (per
Application)
Project Study Report Approved
Begin Environmental (PA&ED) Phase Target 6/1/2023
Circulate Draft Environmental Document Target 6/1/2023
Draft Project Report Target 6/1/2023
End Environmental Phase (PA&ED Milestone) Target 7/1/2023 Begin Design (PS&E) Phase Target 12/1/2024
End Design Phase (Ready to List for Advertisement Milestone) Target 6/1/2026 Begin Right of Way Phase Target 11/1/2024
End Right of Way Phase (Right of Way Certification Milestone) Target 11/30/2024 Begin Construction Phase (Contract Award Milestone) Target 7/1/2026 End Construction Phase (Construction Contract Acceptance Milestone) Target 12/1/2027 Begin Closeout Phase Target 1/1/2028
End Closeout Phase (Closeout Report) Target 6/1/2028
Project Milestone Milestone Designation
(Target/Actual)
Approved (per
Application)
Project Study Report Approved
Begin Environmental (PA&ED) Phase Target 6/1/2023
Circulate Draft Environmental Document Target 6/1/2023
Draft Project Report Target 6/1/2023
End Environmental Phase (PA&ED Milestone) Target 7/1/2023 Begin Design (PS&E) Phase Target 7/2/2023
End Design Phase (Ready to List for Advertisement Milestone) Target 1/31/2025 Begin Right of Way Phase Target 7/2/2023
End Right of Way Phase (Right of Way Certification Milestone) Target 1/31/2025 Begin Construction Phase (Contract Award Milestone) Target 4/1/2025 End Construction Phase (Construction Contract Acceptance Milestone) Target 9/1/2027 Begin Closeout Phase Target 9/2/2027
End Closeout Phase (Closeout Report) Target 2/28/2028
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
PPNO LP011C: Solar Light Upgrades
PPNO LP011D: Termini/Layover Improvements

Project Milestone Milestone Designation
(Target/Actual)
Approved (per
Application)
Project Study Report Approved
Begin Environmental (PA&ED) Phase Target 6/1/2023
Circulate Draft Environmental Document Target 6/1/2023
Draft Project Report Target 6/1/2023
End Environmental Phase (PA&ED Milestone) Target 7/1/2023 Begin Design (PS&E) Phase Target 7/2/2023
End Design Phase (Ready to List for Advertisement Milestone) Target 8/2/2024 Begin Right of Way Phase Target 7/2/2023
End Right of Way Phase (Right of Way Certification Milestone) Target 8/2/2024 Begin Construction Phase (Contract Award Milestone) Target 12/1/2024 End Construction Phase (Construction Contract Acceptance Milestone) Target 6/30/2026 Begin Closeout Phase Target 7/1/2026
End Closeout Phase (Closeout Report) Target 12/31/2026
Project Milestone Milestone Designation
(Target/Actual)
Approved (per
Application)
Project Study Report Approved
Begin Environmental (PA&ED) Phase Target 6/1/2023
Circulate Draft Environmental Document Target 6/1/2023
Draft Project Report Target 6/1/2023
End Environmental Phase (PA&ED Milestone) Target 12/1/2023 Begin Design (PS&E) Phase Target 1/1/2024
End Design Phase (Ready to List for Advertisement Milestone) Target 1/1/2025 Begin Right of Way Phase Target 1/1/2024
End Right of Way Phase (Right of Way Certification Milestone) Target 1/1/2025 Begin Construction Phase (Contract Award Milestone) Target 6/30/2025 End Construction Phase (Construction Contract Acceptance Milestone) Target 12/30/2026 Begin Closeout Phase Target 1/1/2027
End Closeout Phase (Closeout Report) Target 6/1/2027
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
PPNO LP011E: Zero Emission Bus Charging Infrastructure

8. RISKS
Schedule/Schedule Risks
The Project is ready to move forward. Metro understands that all major transportation capital projects include a level of risk and takes pride in fully assessing and addressing any potential risks associated with its projects before it begins construction. Metro also understands the reporting requirements and financial best practices associated with state grant funding. Furthermore, Metro has its own significant financial stake in the Project and has taken necessary precautions to ensure that it is completed on time and within budget.

There are no risks delivering the Project associated with right-of-way, as no acquisitions are required for the Project. There is potential for schedule delay if coordination with municipalities on the location of bus shelter and amenity improvements is prolonged. There is also potential for schedule delay if coordination with Caltrans is prolonged for the terminal/layover improvements at Norwalk Station mobility hub (which resides on Caltrans property). However, these risks can be mitigated as Metro has extensive experience delivering these kinds of projects and has a good working relationship with the various municipalities that will be involved in the implementation of all aspects of the Project involving infrastructure on Southeast Los Angeles streets, as well as Caltrans.

Other Potential Risks
Metro has a long history of successful delivery of State-funded Projects. The agency has a breadth of experience in handling major infrastructure projects of this scale, and larger. We have the resources and expertise to deliver this Project using the awarded state funds.

9. EXTERNAL AGENCY COORDINATION (anticipated agreements) The exact locations of the waiting environment improvements will be determined in coordination with the Southeast Los Angeles cities where the corridors are located, based on bus stop existing conditions and needs.

The terminal/layover at Norwalk Station mobility hub is on Caltrans right-of-way. Metro will cooperate with Caltrans on implementation of this element of the project.

Project Milestone Milestone Designation
(Target/Actual)
Approved (per
Application)
Project Study Report Approved
Begin Environmental (PA&ED) Phase Target 6/1/2023
Circulate Draft Environmental Document Target 6/1/2023
Draft Project Report Target 6/1/2023
End Environmental Phase (PA&ED Milestone) Target 12/1/2023 Begin Design (PS&E) Phase Target 1/1/2024
End Design Phase (Ready to List for Advertisement Milestone) Target 1/1/2025 Begin Right of Way Phase Target 1/1/2024
End Right of Way Phase (Right of Way Certification Milestone) Target 1/1/2025 Begin Construction Phase (Contract Award Milestone) Target 6/30/2025 End Construction Phase (Construction Contract Acceptance Milestone) Target 12/30/2026 Begin Closeout Phase Target 1/1/2027
End Closeout Phase (Closeout Report) Target 6/1/2027
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024

10. ADDITIONAL INFORMATION
No additional project specific information has been identified.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024

11. ATTACHMENTS (Number of Pages)
List attachments with the number of pages, such as:

A. Approved Environmental Document (54)
B. Engineers Estimate (1)
C. Outcomes (1)
D. Programming Document (9)
E. Performance Metrics (3)
n Prl~tForm
Notice of Exemption Appendix E
From: (Public Agency): Los Angeles County
Metropolitan Transportation Authority
To: Office of Planning and Research
P.O. Box 3044, Room 113
Sacramento, CA 95612-3044
County Clerk
One Gateway Plaza, Los Angeles, CA 90012
County of: Los Angeles
124001mper1al HiQllway
Noiwalk. CA 90650
{Address)
Project Title: Southeast Los Angeles Transit Improvements Project (SELA TIP) Project Applicant: Los Angeles County Metropolitan Transportation Authority (Metro) Project Location - Specific: Along the 710 South Corridor, within the Cities of Norwalk, Artesia, and Compton.

Project Location - City: Ncr.valk. Arte~ anc1 ec""'1on. Lo, "nae1" Project Location - County: Los Angeles Description of Nature, Purpose and Beneficiaries of Project:

Meire> is pn,poslng Ille Soulhaasl Los Angeles Transil lmi,rovements Project. (SaA TIP). Thia project wcuk! pnMdl !he 141Jowlng; ln.11allaUon of Cloud-based TSP lnlnlalluclW8. IJlslallall0n of bUs aMltfllS pus real-lime eletlronlc pas&engar lnformauon signs, 1ns11111suon or solar-powered Jlg)lllll9 upgrados at bus stops wl1hout slleJters, lnot.eVatian of mo-<1mlSSkln lnls ct,~g masts at blla to,mln{Jlayover •rea• et NotWSlk, Alfasla, and Canplon Station rnobllity hubs, an lnc:rMSe end lr!lpro.ed but boanllng/aliQhllng bays ana lay""8C areas anct Improved psuenger amenities Ill the Norwalk. Artesia, and compu,n Station, and ZIIIO Em!$Slon Bus (ZEB) cl,arg\ng llalions and lerml~rfmpravamonts.

Name of Public Agency Approving Project: Los Angeles County Metropolitan Transportation Authority Name of Person or Agency Carrying Out Project: Los Angeles County Metropolitan Transportation Authority Exempt Status: (check one):

Ministerial (Sec. 21080(b)(1); 15268);
D Declared Emergency (Sec. 21080(b)(3); 15269(a));
D Emergency Project (Sec. 21080(b)(4); 15269(b)(c)};
Categorical Exemption. State type and section number: _____________ _ ll!I Statutory Exemptions. State code number: Public Resources Code Sections 21oao.25{a)(11) Reasons why project is exempt:

The Project falls within the provisions of Senate Bill [SB] 922 Exemption-added January 1, 2023) which establishes statutory exemptions (SEs) from its provisions for certain types of projects. The Project improvements fall within the exemptions described in Public Resources Code Section 21080.25(a)(11) "Transit prioritization projects".

Lead Agency Contact Person: Tom Kefafas ----------- Area Codeffelephone/Extanslon: (213)418-3370 If flied by applicant:

1. Attach certified do ument of exemption finding.

2. ~f emption been flled by the public agency approving the project? Yes No Signature: ..;,-,:-~'-7---~,__ ____ Data///~ 7/~ Title: _,7i~d:.,.1-=f'~s2)~ _ _:.

Signed by Lead Agency Signed by Applicant
Authority cited: Sections 21083 and 21110, Public Resources Code.

Aelerence; Sections 21108, 21152, and 21152.1, Publfc Resources Code.

THIS NOTICE WAS POSTED
Date Received for filing at OPA: ____ _
ON November 28 2023
2023 254709
11111/f 1111111/lf llfllll!! l!llll!ffl llmlll!! 1111111!! 111! UNTIL December 28 2023

REGISTRAR-RECORDER/COUNTY CLERK
FILED
Nov 28 2023
llou C. LOG•, Rtlbl,.-RtcorMrl~tlllll Ckrk
f~<1ro11,n1r11, .. ~orHE101 vu.hERR•
Revised 2011
This is a true and certified copy of the rec
if it bears the seal, imprinted in purple ink,
of the Registrar-Recorder/County Clerk
NOV 2 8 2023
'Du:uu:,. /.-tr.;-1,1,.___ REGISTR,~-RECORDER/COUNTY ClE LOS·A~LES COUNTY, CALIFORNIA s ANGElf ,
.. ~u......-.--,ilPI,
 


    


 !" 
#
$% 

#
 &' &'  ( )

( ) *+, )
( -*+, )
(   )

 . )
. *+, )
( -*+, )
. '
/
3 012 '
'
/012 45674 89:
765;<=84>;<4 ?@
#
 
#
 #

ABCD ? 3#
%EF
#
G

? 3#
 %EF
#
G

 EH


 ?@
 I
  JE !KLM
;NOPQM

LRNST

UPVLWQXSYN
<V MWLVSYXLN
;RSZLVXT [ [ ?@

 :LRSZPYM
KL;NOPQM
<VYNMXS
7\WVL]P\PNSM
^VL_P`S
a:4K;
<7^b(<VYNMXS
:ONYQ
^VXLST
a<:^b
LNQT ?@
 URQSXWP
UPSVL
5PcS6N
<XVdN Ye<XPV fLgRMQXNP`LVXe M

SZLRO S
M ZPYM
KL;NOPQM

LRNST
YQLNO
SZP7(
`LVXe h 
C
 E
 
 F%
iE
I E
jD E
i
?kl3m j% 
#
 
nY\PM
:ZY \XVX  EH



 C#
ABCD  $%
?@
#
 
#

 3o
F
p

kj
Go%
Gm 
 Gk %
G
q <VYNMXS
:ONYQ
^VXLST
a<:^b 

o
F <VYNMXS
:ONYQ
^VXLST
a<:^b
rstu *r -
vw
xyz{|}~
yz€‚
ƒ~ „|

†‡|
yˆy
x|{‰
Š‹Œ ŠŽ
Ž‰Š 
‘‹’“
District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024
Environmental Benefits
The Project bus speed and reliability and passenger amenity improvements are expected to reduce greenhouse gas and vehicle emissions through investments in electric charging infrastructure to support the transition from conventional CNG vehicles to battery electric buses (BEB). Emissions reductions support state and regional climate goals of the Southern California Association of Governments (SCAG) 2020-2045 Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) and state regulations including the September 2019 State Executive Order N-19-19.

The reduced emissions resulting from the shift from CNG to BEBs are specific to the on-route charging period assumed to be 15 minutes per bus per layover. With the project improvements the energy used to charge the buses is assumed to be sourced from the grid and will offset the equivalent requirements for CNG to support the same number of operating miles. As a result of transitioning from CNG to BEB, the carbon dioxide, nitrogen oxide, oxides, particulate matter, and volatile organic compounds emissions related to those equivalent miles of operation (see table below).

Benefit Cost Analysis
The SELA TIP is expected to generate $184.0 M in undiscounted 2021-dollar benefits from 2026 through 2045,inclusive of the offsetting net increases in rehabilitation and replacement (R&R) costs. At a 4 percent real discount rate, these total benefits are $105.1 M. The key benefits of the SELA TIP Project are derived from transit signal prioritization, waiting environment improvements, including covered busstops and real-time arrival information, and supporting the transition of LA Metro’s bus fleet from CNG to zero-emissions BEBs through installation of ZEB charging masts. Primary benefits include travel time savings, improved quality of stations and direct user benefits and the reduction in vehicle fueling costs as well reductions in vehicle emissions and upstream greenhouse gas emissions with the transition to a cleaner fuel source. Overall, the project benefits are anticipated to exceed the project costs. This leads to an overall project discounted Net Present Value of $81.1 M and a Benefit Cost Ratio (BCR) of 4.37.

District 7 – Los Angeles County
Planning Program Number (PPNO): LP011A, LP011B, LP011C, LP011D, LP011E, Local Partnership Program - Competitive (LPP-C)
April 2024

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION Memorandum
To: CHAIR AND COMMISSIONERS CTC Meeting: June 28-29, 2023 From: TANISHA TAYLOR, Interim Executive Director
Reference Number: 4.6, Action
Prepared By: Leishara Ward
Associate Deputy Director
Published Date: June 16, 2023
Subject: 2022 Local Partnership Competitive Program Adoption – Program of Projects, Resolution G-23-47
Recommendation:

Staff recommends the California Transportation Commission (Commission) adopt the 2022 Local Partnership Competitive Program, as presented in Attachment B and consistent with the Resolution G-23-47 (Attachment A).

Issue:

The Commission established the 2022 Local Partnership Competitive Program as a two-year, $144 million program across fiscal years 2023-24 through 2024-25. The 2022 Local Partnership Competitive Program proposes 11 projects for a total of $142,453,000 in funding with a combined total project cost of approximately $610 million.

The 2020 Local Partnership Competitive Program was over-programmed by $25,800,000. It received redistributed set-aside Inventive funds totaling $12,000,000 for fiscal years 2020-21 and 2021-22, leaving a remaining over-programmed amount of $13,800,000. The 2020 Local Partnership Competitive Program over-programming amount will be deducted from the 2022 Local Partnership Competitive Program, leaving a balance of $130,200,000 for the 2022 Local Partnership Competitive Program. Staff anticipates that the redistribution of $6,000,000 from set-aside Incentive funds from fiscal year 2022-23 will be redistributed in August 2023 and increase the available funding capacity for the 2022 Local Partnership Competitive Program to the final amount of $136,200,000.

Therefore, the recommended 2022 Program of Projects includes an over-programmed amount of $6,253,000, to be funded with future unused Incentive funds that are set-aside each fiscal year, if available or project cost savings generated over the two-year program. The anticipated, unused Incentive funding available for fiscal year 2023-24 is $8,000,000, which could be redistributed to the 2022 Local Partnership Competitive Program in August 2024. Any remaining over-programmed amount by the end of fiscal year 2024-25 will be deducted from the Local Partnership Competitive Program in the subsequent programming cycle.

CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 2 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION The recommended Program of Projects includes a variety of project types that collectively will enhance and maintain roadways, including: the construction of a roundabout and replacement of a highway interchange; construction of active transportation and complete street improvements; construction of bridge improvements; improvements to bus and rail public transit; implementation of traffic management system enhancements; and rehabilitation of local road infrastructure.

The recommended Program of Projects was posted on the Commission’s website on June 8, 2023, and is included in the book item as Attachment B.

Development of Staff Recommendations
The Commission received 37 project nominations seeking a total of $560.3 million in 2022 Local Partnership Competitive Program funds.

Evaluation teams consisting of Commission and Caltrans staff reviewed project nominations based on the screening and evaluation criteria set forth in the Commission’s adopted 2022 Local Partnership Competitive Program Guidelines. In addition, applications were reviewed by the Department of Housing and Community Development staff for the Transportation, Land Use and Housing criteria, as well as members of the Interagency Equity Advisory Committee for the Community Engagement evaluation criteria. Due to the competitive nature of this program, staff evaluations were limited to documentation submitted with the application package including the required performance metrics outlined in the program guidelines.

The 11 projects recommended in the Program of Projects were determined to best address the criteria outlined in the guidelines and are anticipated to provide the following benefits:
• Reduce thousands of vehicle miles traveled
• Reduce thousands of tons of greenhouse gas emissions
• Save person-hours of travel time
• Create nearly 10,000 thousand jobs
The projects proposed for funding meet the following program requirements: the nominating agencies have established eligibility with either a voter-approved tax, toll or fee, or an imposed fee within their jurisdiction that solely dedicates revenue to transportation; the fund request is for construction in an eligible fiscal year; each project’s construction phase has a full funding commitment, including any potential cost increases. All applications were organized into eligibility types (voter-approved tax, toll, or fee or imposed fee) and population categories pursuant to the 2022 Local Partnership Competitive Guidelines. The recommended Program of Projects resembles a similar proportion of these types and categories when compared to all projects submitted.

Projects not recommended for funding were considered less competitive for a variety of reasons, including: the start of the construction phase was outside of the program cycle; inconsistent or ineligible funding plan; lack of local match; low community engagement; less benefit demonstrated when compared to cost; or project was fully funded from another state or federal discretionary program. Lastly, one project was deemed ineligible based on information provided in the application. The projects not recommended for funding are, by and large, worthy projects, though not as competitive for this program cycle.

CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 3 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION Project Highlights:

The recommended Program of Projects will deliver a variety of benefits that include reduction of vehicle miles traveled; safety improvements for motorized and non-motorized users; transition to electric bus fleets; increased mobility and accessibility; bridge improvements; improved pavement conditions; reduction of greenhouse gas emissions; and advance transportation and housing goals.

Five of the projects focus on local road improvements including a highway overcrossing, new and modified bridges, complete streets, traffic management system enhancements, and safety improvements.

Two of the projects involve highway improvements including the reconstruction of an existing interchange and replacement of a rural highway intersection with a modern roundabout.

Four of the projects improve public transportation for bus and rail services by reducing vehicle miles traveled and greenhouse gas emissions, and implementing operational improvements that will increase speed, safety, and reliability.

While most of the projects incorporate bicycle and pedestrian facilities, one project has made active transportation and complete streets its main purpose. These projects support the Climate Action Plan for Transportation Infrastructure and the state’s climate, housing, safety, equity, and economic vitality goals as they incorporate multimodal, transit, and active transportation solutions.

The following descriptions highlight a sample of projects contained in the staff recommendations:
• US 101/Hearn Avenue Regional Multimodal Interchange, $8,600,000 – in the City of Santa Rosa, Sonoma County, the project will replace the US 101/Hearn Avenue overcrossing to increase vertical clearance over US 101 and provide two vehicle lanes in each direction, a median, sidewalks, Class II bike lanes, and Class IV protected bikeways. It will also widen the US 101 off-ramp, add lanes at select intersections and add ADA elements and protected intersection facilities for bike crossings. • Oakland Alameda Access Project, $25,000,000 – in the Cities of Oakland and Alameda, Alameda County, the project is located on Interstate 880 and State Route 260 between 5th Avenue Overhead and 5th and 6th Street Viaduct. The project proposes to improve access along I-880 and in and around the Webster and Posey Tubes (SR-260 tunnels under the Oakland Estuary), downtown Oakland, and the City of Alameda by removing the I-880/Broadway northbound off-ramp, realigning the westbound I980/Jackson Street on-ramp, widening northbound I-880/Oak Street off-ramp, installing a horseshoe-shaped ramp connecting the Posey Tube to northbound I-880, and restriping and reconfigurations of local roadways adjacent to I-880. In addition, the project will provide significant active transportation facilities and safety enhancements, including various bikeways, sidewalks, bulb-outs, crosswalks, and widening of the Webster Tube Walkway. The project also supports a freight mode shift by accommodating additional rail capacity. Finally, proposed improvements include implementation of follow up landscaping work to restore removed vegetation required by the highway improvements.

CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 4 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION • San Mateo County Transit District (SamTrans) Emission Zero Project, $14,824,000 – in the City of San Carlos, San Mateo County, the project will construct core transit infrastructure improvements at SamTrans’ South Base Maintenance Facility. The project scope includes infrastructure required for the first set of SamTrans’ zeroemission buses, including the construction of electrical charging infrastructure and bus charging bays, procurement and installation of an overhead pantograph charging dispenser, and construction of an electrical power distribution network that is scalable for future Battery Electric Bus system expansion. Charging infrastructure for thirty-seven Battery Electric Buses is proposed under this project to enable successful deployment and safe operations of SamTrans’ new fleet of 40-foot Battery Electric Buses to be delivered by 2025. The bus network at South Base serves bus routes to the 14 cities of San Mateo County.
• Foothill Boulevard Complete Street Project, $2,400,000 – in the City of Rancho Cucamonga, San Bernadino County, the project will add important bike/pedestrian facilities to Foothill Boulevard within existing Right-of-Way by narrowing the existing vehicle lanes and rehabilitating approximately 1,950 linear feet of failing pavement between Grove Avenue/San Bernardino Road. The project will construct a multi-use path along the south side of Foothill Boulevard and a new sidewalk on the north side that will be expanded to a multi-use path by future development. Safety improvements include the installation of streetlights, a traffic signal at a realigned intersection with Red Hill Country Club Drive, and enhanced pedestrian and crosswalk markings at the intersection.
• Mountain View Transit Center Grade Separation and Access Project, $25,000,000 – in the City of Mountain View, Santa Clara County, the project will eliminate the Caltrain vehicle at-grade crossing at Castro Street, re-direct vehicular traffic from Castro Street to Shoreline Boulevard via a ramp from West Evelyn Avenue and modify traffic movements at the Central Expressway/Moffett Boulevard intersection. Unsafe situations arise at the project area daily for pedestrians and cyclists with two pedestrian fatalities in 2019. The project will provide new access to and from the Mountain View Transit Center and downtown via a wide, well-lit shared use pathway and vertical circulation for pedestrians and bicycles under the tracks and Central Expressway, eliminating the safety hazard and delay of crossing the busy roadway and train tracks. New loading areas for shuttles will be provided to serve vehicles that will be impacted by the Castro Street vehicle closure.

Baseline Agreement Requirements:

All agencies with projects included in the 2022 Local Partnership Competitive Program, Program of Projects must comply with the Commission’s adopted 2022 Local Partnership Program Guidelines and the revised Senate Bill 1 Accountability and Transparency Guidelines, adopted by the Commission on March 23, 2023. This includes the requirement that all projects with a total project cost of $25 million or greater or 2022 Local Partnership Competitive Program funds of $10 million or greater must enter into a baseline agreement. The development of the baseline agreement will be initiated upon adoption of the program. The baseline agreement will set forth the scope, expected benefits, delivery schedule, and project CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 5 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION cost and funding plan. The executed baseline agreement will become the basis by which accountability will be measured and reported on.

Background:

On April 28, 2017, Governor Brown signed legislation creating the Local Partnership Program (Senate Bill 1 [Chapter 5, Statutes of 2017]). Assembly Bill 115 (Chapter 20, Statutes of 2017) clarified Senate Bill 1 language regarding local and regional transportation agency eligibility and expanded the types of projects eligible for the program. Senate Bill 1 authorizes $200 million annually to fund the Local Partnership Program.

The Local Partnership Program provides funding to counties, cities, districts, and regional transportation agencies in which voters have approved fees or taxes dedicated solely to transportation improvements or that have imposed fees, including uniform developer fees, dedicated solely to transportation improvements.

In August 2021, the Commission initiated the process to develop the 2022 Local Partnership Competitive Program Guidelines. The Commission held seven workshops between August 2021 and April 2022 to solicit input on the development of the 2022 Local Partnership Competitive Program Guidelines. These workshops included consultation with Caltrans, the California Air Resources Board, the California Department of Housing and Community Development, the Commission’s Equity Advisory Roundtable, regional transportation planning agencies, local agencies, transportation advocates, and other stakeholders. The Commission’s 2022 Local Partnership Competitive Program Guidelines, adopted at its August 17, 2022 meeting, describe the policy, standards, criteria and procedures for the development, adoption and management of the 2022 Local Partnership Competitive Program.

Between the months of February 2022 and April 2022, the Commission held office hour sessions with applicant agencies to provide technical assistance. Agencies that requested and attended office hour sessions were able to provide a brief overview of their project proposal(s) which could have included visuals like maps, plans, photos and/or videos. This allowed Commission staff to get a better understanding of the project(s) and provide more projectspecific feedback and responses to agency questions. Office hour sessions lasted one to two hours and were attended by Senate Bill 1 Commission Program Managers and applicant agency staff.

Attachments:
• Attachment A: Resolution G-23-47
• Attachment B: 2022 Local Partnership Competitive Program Adoption – Program of Projects
• Attachment C: Comment letters
Reference No.: 4.6
June 28-29, 2023
Attachment A

CALIFORNIA TRANSPORTATION COMMISSION
2022 LOCAL PARTNERSHIP COMPETITIVE PROGRAM

PROGRAM OF PROJECTS
RESOLUTION G-23-47

1.1 WHEREAS, on April 28, 2017, Governor Brown signed Senate Bill (SB) 1 (Beall, Chapter 5, Statutes of 2017), enacted as the Road Repair and Accountability Act of 2017, creating the Local Partnership Program to provide funding to jurisdictions that have sought and received voter-approved taxes and enacted fees for road maintenance and rehabilitation and other transportation improvement projects; and

1.2 WHEREAS, on June 27, 2017, Governor Brown signed Assembly Bill (AB) 115 (Ting, Chapter 20, Statutes of 2017) which clarified language in SB 1 regarding local and regional transportation agency eligibility and expanded the types of projects eligible for program funding; and

1.3 WHEREAS, the California Transportation Commission (Commission) adopted the 2022 Local Partnership Program Guidelines on August 17, 2022; and

1.4 WHEREAS, the Commission adopted revisions to the SB 1 Accountability and Transparency Guidelines on March 23, 2023, that govern and outline the Commission’s responsibility for the accountability and transparency of SB 1 program funds under its purview; and

1.5 WHEREAS, the 2020 Local Partnership Competitive Program was over programmed by $25,800,000 and received redistributed funds totaling $12,000,000 from set-aside Incentive funds for fiscal years 2020-21 and 2021-22 reducing the overprogrammed amount leaving a remaining over-programmed amount of $13,800,000.

1.6 WHEREAS, any 2020 Local Partnership Competitive Program over-programmed amount will be deducted from the 2022 Local Partnership Competitive Program; and

1.7 WHEREAS, the Commission established the 2022 Local Partnership Competitive Program as a two-year, $144,000,000 (fiscal years 2023-24 through 2024-25) program.

1.8 WHEREAS, the 2022 Local Partnership Competitive Program funding capacity was reduced by the 2020 Local Partnership Competitive Program overprogrammed amount of $13,800,000, leaving a balance of $130,200,000 for the 2022 Local Partnership Competitive Program; and
California Transportation Commission Reference No.:4.6
Resolution G-23-47 June 28-29, 2023
Attachment A

Page 2 of 3 ends

1.9 WHEREAS, staff anticipates the redistribution of $6,000,000 from set-aside Incentive funds from Fiscal Year 2022-23 to occur in August 2023 and has increased the available funding capacity for the 2022 Local Partnership Competitive Program to $136,200,000; and

1.10 WHEREAS, Commission Staff prepared program recommendations that included $142,453,000 for 11 projects with total project costs valued at $610,257,000; and

1.11 WHEREAS, the over-subscribed amount totaling $6,253,000 included in the initial program recommendations will be funded with anticipated fiscal year 2023- 24 unused incentive funding or project cost savings; and

1.12 WHEREAS, any 2022 Local Partnership Competitive Program over-programmed amount will be deducted from the Local Partnership Competitive Program in the subsequent programming cycle; and

1.13 WHEREAS, the Commission staff recommendations for the 2022 Local Partnership Competitive Program were published on the Commission’s website on June 8, 2023; and

1.14 WHEREAS, the Commission considered the staff recommendations and public testimony at its June 28-29, 2023, meeting.

2.1 NOW THEREFORE BE IT RESOLVED, that the Commission hereby adopts the 2022 Local Partnership Competitive Program, as reflected in the attached staff recommendations (Attachment B); and

2.2 BE IT FURTHER RESOLVED, that the project amounts approved for funding shall be considered as a "not to exceed amount" and that any increases in cost estimates beyond the levels reflected in the adopted program are the responsibility of the appropriate agency; and

2.3 BE IT FURTHER RESOLVED, that a project included in the adopted 2022 Local Partnership Competitive Program must be in compliance with the 2022 Local Partnership Competitive Program Guidelines and the revised SB 1 Accountability and Transparency Guidelines, adopted March 23, 2023; and

2.4 BE IT FURTHER RESOLVED, that a project included in the adopted 2022 Local Partnership Competitive Program with a total project cost of $25 million or greater, or a total programmed amount of $10 million or greater, must enter into a Baseline Agreement to be approved by the Commission within six months of program adoption. The Commission may delete a project for which no Baseline Agreement is executed; and
California Transportation Commission Reference No.:4.6
Resolution G-23-47 June 28-29, 2023
Attachment A

Page 3 of 3 ends

2.5 BE IT FURTHER RESOLVED, if a recommended project requires a Baseline Agreement and requests allocation in the period between the June 2023 Commission meeting and the October 2023 Commission meeting, the project applicant must submit a Baseline Agreement for approval by the October 2023 Commission meeting. All other Baseline Agreements must be submitted by the December 2023 Commission Meeting, and the Commission will not consider approval of a project allocation without an approved Baseline Agreement if it requires one; and

2.6 BE IT FURTHER RESOLVED, Commission staff, in consultation with Caltrans and project sponsors, are authorized to make minor technical changes as needed to the 2022 Local Partnership Competitive Program in order to reflect the most current information, or to clarify the Commission's programming commitments, and shall request Commission approval of any substantive changes; and

2.7 BE IT FURTHER RESOLVED, that the Commission directs staff to post the 2022 Local Partnership Competitive Program of Projects on the Commission's website.

County Nominating Agency Implementing Agency Project Title Project Description Fiscal Year Total Project Cost Recommended Funding Voter
Approved (V)
or Imposed
Fee (I)
Population
Category
El Dorado El Dorado County El Dorado County Pioneer Trail/US Hwy 50 Intersection Safety Improvement Project In Meyers, convert a signalized T‐intersection at the U.S. Highway 50/State Route 89 into a three‐leg modern roundabout. Includes 3 intersection improvements; 11 channelizations; 0.8 miles pedestrian/bicycle facilities. 2023‐24 $ 9,127 $ 3,055 I IV San Bernadino Rancho Cucamonga, City of Rancho Cucamonga, City of Foothill Blvd Complete Street Project On Foothill Blvd, narrow existing vehicle lanes, rehab approx. 1,950 linear ft of pavement, and construct 0.81 miles of multi‐use path and new sidewalk; includes streetlights, a traffic signal, and enhanced pedestrian and crosswalk markings. 2023‐24 $ 4,800 $ 2,400 I IV
Sonoma Sonoma Co Transportation Authority (SCTA) Caltrans D4 US 101/Hearn Ave Regional Multimodal Interchange In the City of Santa Rosa, demolish and replace US 101/Hearn Ave overcrossing, includes traffic operation improvements; one mile of new bicycle lanes and sidewalks; ADA elements.
2023‐24 $ 43,675 $ 8,600 V III
Alameda Alameda County Transportation Commission (Alameda CTC) Caltrans Oakland Alameda Access Project In the Cities of Oakland and Alameda, improved traffic ops along I‐880 and in and around the Webster and Posey Tubes including: 12.2 roadway lane miles; 2 trafficmonitoring detection stations; 3 miles of bile lanes; 110,523 square feet of new bridges/tunnels; and implementation of follow up landscaping work. 2024‐25 $ 129,900 $ 25,000 V I
Yuba Yuba County Yuba County North Beale Road Complete Streets / Safety Project ‐  Phase III In Linda, 2 miles of local road rehabilitation including: raised medians; left‐turnlanes; storm drains; new streetlights; curbs; gutters; thermoplastic centerline andedge‐line striping; and a new traffic signal; one mile of eight‐foot wide sidewalks;

7.5‐foot wide paved bicycle lanes.
2023‐24 $ 7,711 $ 3,000 V V
Santa Clara Santa Clara Valley Transportation Authority (VTA) Peninsula Corridor Joint Powers Board (Caltrain) Mountain View Transit Center Grade Separation and Access Project In Mountain View, eliminate the Caltrain vehicle at‐grade crossing; re‐direct vehicular traffic and modify traffic movements; construct 0.43 miles of shared usepathway and vertical circulation from non‐motorized traffic to/from the TransitCenter and Downtown; construct new shuttle loading areas. 2024‐25 $ 136,000 $ 25,000 V I
Sacramento Sacramento Transportation Authority (STA) Sacramento, County of US 50 Gold Line Corridor Enhancement Project ‐ Hazel Ave/US 50 Interchange 2024‐25 $ 132,726 $ 25,000 V I Hazel Avenue / US 50 Interchange
In Sacramento, converts 29 Gold Line light rail station platforms to fit low floorvehicles; grade separation includes 3 interchange modifications, 19,190 square feetof new bridges/tunnels, and adds 0.74 miles of grade‐separated Class I path.

Gold Line Light Rail Platform Modifications ‐ Phase 2 In Sacramento, converts 29 Gold Line light rail station platforms to fit low floor vehicles, phase 2 conversion.

Tulare Tulare County Association of Governments (TCAG) Caltrans D6 SR99/Caldwell Ave Interchange, Safety and Multi‐Modal Project In Tulare County, reconstruct the Avenue 280 (Caldwell Avenue) Interchange. Includes 0.8 miles auxiliary lane, 1.1 miles of bicycle lane, 0.9 miles sidwalk. 2023‐24 $ 68,227 $ 15,000 V VMendocino Ukiah, City of Ukiah, City of Urban Core Rehabilitation and Transportation Project In Ukiah, reconstruct 4.8 miles of local road and 2.9 miles of bicycle lanes,including: replacement of water and sewer utilities; construction of ADA accessiblecurb ramps; bulb‐outs and the installation of a traffic signal and bike lanes. 2023‐24 $ 14,356 $ 6,074 V V
San Mateo San Mateo County Transit District (SamTrans) San Mateo County Transit District (SamTrans) SamTrans Emission Zero Project In San Carlos, construct zero‐emission bus electrical charging infrastructure and bus charging bays; procure and install overhead pantograph charging dispenser; and construction of an electrical power distribution network; includes charging infrastructure for thirty‐seven Battery Electric Buses. 2023‐24 $ 32,605 $ 14,824 V II
Los Angeles Los Angeles County Metropolitan Transportation Authority (LA Metro) Los Angeles County Metropolitan Transportation Authority (LA Metro) Southeast Los Angeles Transit Improvements Project (SELA TIP) 2024‐25 $ 31,130 $ 14,500 V I Southeast Los Angeles Transit Improvements Project
(Transit Signal Priority)
In southeast Los Angeles County, purchase, design, and install 114 cloud‐based transit signal priority systems in NextGen Tier 1 and 2 high frequency corridorsthroughout the I‐710 South communities.

Bus Shelters Purchase and install 100 bus shelters with real‐time display and security lighting.

Lighting Purchase and install 100 solar‐powered lighting upgrades.

Termini/Layover Construction of 3 bus termini/layovers at Norwalk, Artesia, and Compton Stations.ZEB Charging Purchase and install 10 zero emission bus charging masts.

TOTAL $ 610,257 $ 142,453
Amount Over‐Programmed $ 6,253
2022 Local Partnership Competitive Program
Program of Projects - Projects Recommended for Funding
Resolution G-23-47
($1,000s)
Attachment B
Reference No.: 4.6
June 28-29, 2023

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION Memorandum
To: CHAIR AND COMMISSIONERS CTC Meeting: June 28-29, 2023 From: TANISHA TAYLOR, Interim Executive Director
Reference Number: 4.6, Action
Prepared By: Leishara Ward
Associate Deputy Director
Published Date: June 16, 2023
Subject: 2022 Local Partnership Competitive Program Adoption – Program of Projects, Resolution G-23-47
Recommendation:

Staff recommends the California Transportation Commission (Commission) adopt the 2022 Local Partnership Competitive Program, as presented in Attachment B and consistent with the Resolution G-23-47 (Attachment A).

Issue:

The Commission established the 2022 Local Partnership Competitive Program as a two-year, $144 million program across fiscal years 2023-24 through 2024-25. The 2022 Local Partnership Competitive Program proposes 11 projects for a total of $142,453,000 in funding with a combined total project cost of approximately $610 million.

The 2020 Local Partnership Competitive Program was over-programmed by $25,800,000. It received redistributed set-aside Inventive funds totaling $12,000,000 for fiscal years 2020-21 and 2021-22, leaving a remaining over-programmed amount of $13,800,000. The 2020 Local Partnership Competitive Program over-programming amount will be deducted from the 2022 Local Partnership Competitive Program, leaving a balance of $130,200,000 for the 2022 Local Partnership Competitive Program. Staff anticipates that the redistribution of $6,000,000 from set-aside Incentive funds from fiscal year 2022-23 will be redistributed in August 2023 and increase the available funding capacity for the 2022 Local Partnership Competitive Program to the final amount of $136,200,000.

Therefore, the recommended 2022 Program of Projects includes an over-programmed amount of $6,253,000, to be funded with future unused Incentive funds that are set-aside each fiscal year, if available or project cost savings generated over the two-year program. The anticipated, unused Incentive funding available for fiscal year 2023-24 is $8,000,000, which could be redistributed to the 2022 Local Partnership Competitive Program in August 2024. Any remaining over-programmed amount by the end of fiscal year 2024-25 will be deducted from the Local Partnership Competitive Program in the subsequent programming cycle.

CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 2 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION The recommended Program of Projects includes a variety of project types that collectively will enhance and maintain roadways, including: the construction of a roundabout and replacement of a highway interchange; construction of active transportation and complete street improvements; construction of bridge improvements; improvements to bus and rail public transit; implementation of traffic management system enhancements; and rehabilitation of local road infrastructure.

The recommended Program of Projects was posted on the Commission’s website on June 8, 2023, and is included in the book item as Attachment B.

Development of Staff Recommendations
The Commission received 37 project nominations seeking a total of $560.3 million in 2022 Local Partnership Competitive Program funds.

Evaluation teams consisting of Commission and Caltrans staff reviewed project nominations based on the screening and evaluation criteria set forth in the Commission’s adopted 2022 Local Partnership Competitive Program Guidelines. In addition, applications were reviewed by the Department of Housing and Community Development staff for the Transportation, Land Use and Housing criteria, as well as members of the Interagency Equity Advisory Committee for the Community Engagement evaluation criteria. Due to the competitive nature of this program, staff evaluations were limited to documentation submitted with the application package including the required performance metrics outlined in the program guidelines.

The 11 projects recommended in the Program of Projects were determined to best address the criteria outlined in the guidelines and are anticipated to provide the following benefits:
• Reduce thousands of vehicle miles traveled
• Reduce thousands of tons of greenhouse gas emissions
• Save person-hours of travel time
• Create nearly 10,000 thousand jobs
The projects proposed for funding meet the following program requirements: the nominating agencies have established eligibility with either a voter-approved tax, toll or fee, or an imposed fee within their jurisdiction that solely dedicates revenue to transportation; the fund request is for construction in an eligible fiscal year; each project’s construction phase has a full funding commitment, including any potential cost increases. All applications were organized into eligibility types (voter-approved tax, toll, or fee or imposed fee) and population categories pursuant to the 2022 Local Partnership Competitive Guidelines. The recommended Program of Projects resembles a similar proportion of these types and categories when compared to all projects submitted.

Projects not recommended for funding were considered less competitive for a variety of reasons, including: the start of the construction phase was outside of the program cycle; inconsistent or ineligible funding plan; lack of local match; low community engagement; less benefit demonstrated when compared to cost; or project was fully funded from another state or federal discretionary program. Lastly, one project was deemed ineligible based on information provided in the application. The projects not recommended for funding are, by and large, worthy projects, though not as competitive for this program cycle.

CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 3 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION Project Highlights:

The recommended Program of Projects will deliver a variety of benefits that include reduction of vehicle miles traveled; safety improvements for motorized and non-motorized users; transition to electric bus fleets; increased mobility and accessibility; bridge improvements; improved pavement conditions; reduction of greenhouse gas emissions; and advance transportation and housing goals.

Five of the projects focus on local road improvements including a highway overcrossing, new and modified bridges, complete streets, traffic management system enhancements, and safety improvements.

Two of the projects involve highway improvements including the reconstruction of an existing interchange and replacement of a rural highway intersection with a modern roundabout.

Four of the projects improve public transportation for bus and rail services by reducing vehicle miles traveled and greenhouse gas emissions, and implementing operational improvements that will increase speed, safety, and reliability.

While most of the projects incorporate bicycle and pedestrian facilities, one project has made active transportation and complete streets its main purpose. These projects support the Climate Action Plan for Transportation Infrastructure and the state’s climate, housing, safety, equity, and economic vitality goals as they incorporate multimodal, transit, and active transportation solutions.

The following descriptions highlight a sample of projects contained in the staff recommendations:
• US 101/Hearn Avenue Regional Multimodal Interchange, $8,600,000 – in the City of Santa Rosa, Sonoma County, the project will replace the US 101/Hearn Avenue overcrossing to increase vertical clearance over US 101 and provide two vehicle lanes in each direction, a median, sidewalks, Class II bike lanes, and Class IV protected bikeways. It will also widen the US 101 off-ramp, add lanes at select intersections and add ADA elements and protected intersection facilities for bike crossings. • Oakland Alameda Access Project, $25,000,000 – in the Cities of Oakland and Alameda, Alameda County, the project is located on Interstate 880 and State Route 260 between 5th Avenue Overhead and 5th and 6th Street Viaduct. The project proposes to improve access along I-880 and in and around the Webster and Posey Tubes (SR-260 tunnels under the Oakland Estuary), downtown Oakland, and the City of Alameda by removing the I-880/Broadway northbound off-ramp, realigning the westbound I980/Jackson Street on-ramp, widening northbound I-880/Oak Street off-ramp, installing a horseshoe-shaped ramp connecting the Posey Tube to northbound I-880, and restriping and reconfigurations of local roadways adjacent to I-880. In addition, the project will provide significant active transportation facilities and safety enhancements, including various bikeways, sidewalks, bulb-outs, crosswalks, and widening of the Webster Tube Walkway. The project also supports a freight mode shift by accommodating additional rail capacity. Finally, proposed improvements include implementation of follow up landscaping work to restore removed vegetation required by the highway improvements.

CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 4 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION • San Mateo County Transit District (SamTrans) Emission Zero Project, $14,824,000 – in the City of San Carlos, San Mateo County, the project will construct core transit infrastructure improvements at SamTrans’ South Base Maintenance Facility. The project scope includes infrastructure required for the first set of SamTrans’ zeroemission buses, including the construction of electrical charging infrastructure and bus charging bays, procurement and installation of an overhead pantograph charging dispenser, and construction of an electrical power distribution network that is scalable for future Battery Electric Bus system expansion. Charging infrastructure for thirty-seven Battery Electric Buses is proposed under this project to enable successful deployment and safe operations of SamTrans’ new fleet of 40-foot Battery Electric Buses to be delivered by 2025. The bus network at South Base serves bus routes to the 14 cities of San Mateo County.
• Foothill Boulevard Complete Street Project, $2,400,000 – in the City of Rancho Cucamonga, San Bernadino County, the project will add important bike/pedestrian facilities to Foothill Boulevard within existing Right-of-Way by narrowing the existing vehicle lanes and rehabilitating approximately 1,950 linear feet of failing pavement between Grove Avenue/San Bernardino Road. The project will construct a multi-use path along the south side of Foothill Boulevard and a new sidewalk on the north side that will be expanded to a multi-use path by future development. Safety improvements include the installation of streetlights, a traffic signal at a realigned intersection with Red Hill Country Club Drive, and enhanced pedestrian and crosswalk markings at the intersection.
• Mountain View Transit Center Grade Separation and Access Project, $25,000,000 – in the City of Mountain View, Santa Clara County, the project will eliminate the Caltrain vehicle at-grade crossing at Castro Street, re-direct vehicular traffic from Castro Street to Shoreline Boulevard via a ramp from West Evelyn Avenue and modify traffic movements at the Central Expressway/Moffett Boulevard intersection. Unsafe situations arise at the project area daily for pedestrians and cyclists with two pedestrian fatalities in 2019. The project will provide new access to and from the Mountain View Transit Center and downtown via a wide, well-lit shared use pathway and vertical circulation for pedestrians and bicycles under the tracks and Central Expressway, eliminating the safety hazard and delay of crossing the busy roadway and train tracks. New loading areas for shuttles will be provided to serve vehicles that will be impacted by the Castro Street vehicle closure.

Baseline Agreement Requirements:

All agencies with projects included in the 2022 Local Partnership Competitive Program, Program of Projects must comply with the Commission’s adopted 2022 Local Partnership Program Guidelines and the revised Senate Bill 1 Accountability and Transparency Guidelines, adopted by the Commission on March 23, 2023. This includes the requirement that all projects with a total project cost of $25 million or greater or 2022 Local Partnership Competitive Program funds of $10 million or greater must enter into a baseline agreement. The development of the baseline agreement will be initiated upon adoption of the program. The baseline agreement will set forth the scope, expected benefits, delivery schedule, and project CHAIR AND COMMISSIONERS Reference No.: 4.6
June 28-29, 2023

Page 5 of 5 ends

STATE OF CALIFORNIA CALIFORNIA TRANSPORTATION COMMISSION cost and funding plan. The executed baseline agreement will become the basis by which accountability will be measured and reported on.

Background:

On April 28, 2017, Governor Brown signed legislation creating the Local Partnership Program (Senate Bill 1 [Chapter 5, Statutes of 2017]). Assembly Bill 115 (Chapter 20, Statutes of 2017) clarified Senate Bill 1 language regarding local and regional transportation agency eligibility and expanded the types of projects eligible for the program. Senate Bill 1 authorizes $200 million annually to fund the Local Partnership Program.

The Local Partnership Program provides funding to counties, cities, districts, and regional transportation agencies in which voters have approved fees or taxes dedicated solely to transportation improvements or that have imposed fees, including uniform developer fees, dedicated solely to transportation improvements.

In August 2021, the Commission initiated the process to develop the 2022 Local Partnership Competitive Program Guidelines. The Commission held seven workshops between August 2021 and April 2022 to solicit input on the development of the 2022 Local Partnership Competitive Program Guidelines. These workshops included consultation with Caltrans, the California Air Resources Board, the California Department of Housing and Community Development, the Commission’s Equity Advisory Roundtable, regional transportation planning agencies, local agencies, transportation advocates, and other stakeholders. The Commission’s 2022 Local Partnership Competitive Program Guidelines, adopted at its August 17, 2022 meeting, describe the policy, standards, criteria and procedures for the development, adoption and management of the 2022 Local Partnership Competitive Program.

Between the months of February 2022 and April 2022, the Commission held office hour sessions with applicant agencies to provide technical assistance. Agencies that requested and attended office hour sessions were able to provide a brief overview of their project proposal(s) which could have included visuals like maps, plans, photos and/or videos. This allowed Commission staff to get a better understanding of the project(s) and provide more projectspecific feedback and responses to agency questions. Office hour sessions lasted one to two hours and were attended by Senate Bill 1 Commission Program Managers and applicant agency staff.

Attachments:
• Attachment A: Resolution G-23-47
• Attachment B: 2022 Local Partnership Competitive Program Adoption – Program of Projects
• Attachment C: Comment letters
Reference No.: 4.6
June 28-29, 2023
Attachment A

CALIFORNIA TRANSPORTATION COMMISSION
2022 LOCAL PARTNERSHIP COMPETITIVE PROGRAM

PROGRAM OF PROJECTS
RESOLUTION G-23-47

1.1 WHEREAS, on April 28, 2017, Governor Brown signed Senate Bill (SB) 1 (Beall, Chapter 5, Statutes of 2017), enacted as the Road Repair and Accountability Act of 2017, creating the Local Partnership Program to provide funding to jurisdictions that have sought and received voter-approved taxes and enacted fees for road maintenance and rehabilitation and other transportation improvement projects; and

1.2 WHEREAS, on June 27, 2017, Governor Brown signed Assembly Bill (AB) 115 (Ting, Chapter 20, Statutes of 2017) which clarified language in SB 1 regarding local and regional transportation agency eligibility and expanded the types of projects eligible for program funding; and

1.3 WHEREAS, the California Transportation Commission (Commission) adopted the 2022 Local Partnership Program Guidelines on August 17, 2022; and

1.4 WHEREAS, the Commission adopted revisions to the SB 1 Accountability and Transparency Guidelines on March 23, 2023, that govern and outline the Commission’s responsibility for the accountability and transparency of SB 1 program funds under its purview; and

1.5 WHEREAS, the 2020 Local Partnership Competitive Program was over programmed by $25,800,000 and received redistributed funds totaling $12,000,000 from set-aside Incentive funds for fiscal years 2020-21 and 2021-22 reducing the overprogrammed amount leaving a remaining over-programmed amount of $13,800,000.

1.6 WHEREAS, any 2020 Local Partnership Competitive Program over-programmed amount will be deducted from the 2022 Local Partnership Competitive Program; and

1.7 WHEREAS, the Commission established the 2022 Local Partnership Competitive Program as a two-year, $144,000,000 (fiscal years 2023-24 through 2024-25) program.

1.8 WHEREAS, the 2022 Local Partnership Competitive Program funding capacity was reduced by the 2020 Local Partnership Competitive Program overprogrammed amount of $13,800,000, leaving a balance of $130,200,000 for the 2022 Local Partnership Competitive Program; and
California Transportation Commission Reference No.:4.6
Resolution G-23-47 June 28-29, 2023
Attachment A

Page 2 of 3 ends

1.9 WHEREAS, staff anticipates the redistribution of $6,000,000 from set-aside Incentive funds from Fiscal Year 2022-23 to occur in August 2023 and has increased the available funding capacity for the 2022 Local Partnership Competitive Program to $136,200,000; and

1.10 WHEREAS, Commission Staff prepared program recommendations that included $142,453,000 for 11 projects with total project costs valued at $610,257,000; and

1.11 WHEREAS, the over-subscribed amount totaling $6,253,000 included in the initial program recommendations will be funded with anticipated fiscal year 2023- 24 unused incentive funding or project cost savings; and

1.12 WHEREAS, any 2022 Local Partnership Competitive Program over-programmed amount will be deducted from the Local Partnership Competitive Program in the subsequent programming cycle; and

1.13 WHEREAS, the Commission staff recommendations for the 2022 Local Partnership Competitive Program were published on the Commission’s website on June 8, 2023; and

1.14 WHEREAS, the Commission considered the staff recommendations and public testimony at its June 28-29, 2023, meeting.

2.1 NOW THEREFORE BE IT RESOLVED, that the Commission hereby adopts the 2022 Local Partnership Competitive Program, as reflected in the attached staff recommendations (Attachment B); and

2.2 BE IT FURTHER RESOLVED, that the project amounts approved for funding shall be considered as a "not to exceed amount" and that any increases in cost estimates beyond the levels reflected in the adopted program are the responsibility of the appropriate agency; and

2.3 BE IT FURTHER RESOLVED, that a project included in the adopted 2022 Local Partnership Competitive Program must be in compliance with the 2022 Local Partnership Competitive Program Guidelines and the revised SB 1 Accountability and Transparency Guidelines, adopted March 23, 2023; and

2.4 BE IT FURTHER RESOLVED, that a project included in the adopted 2022 Local Partnership Competitive Program with a total project cost of $25 million or greater, or a total programmed amount of $10 million or greater, must enter into a Baseline Agreement to be approved by the Commission within six months of program adoption. The Commission may delete a project for which no Baseline Agreement is executed; and
California Transportation Commission Reference No.:4.6
Resolution G-23-47 June 28-29, 2023
Attachment A

Page 3 of 3 ends

2.5 BE IT FURTHER RESOLVED, if a recommended project requires a Baseline Agreement and requests allocation in the period between the June 2023 Commission meeting and the October 2023 Commission meeting, the project applicant must submit a Baseline Agreement for approval by the October 2023 Commission meeting. All other Baseline Agreements must be submitted by the December 2023 Commission Meeting, and the Commission will not consider approval of a project allocation without an approved Baseline Agreement if it requires one; and

2.6 BE IT FURTHER RESOLVED, Commission staff, in consultation with Caltrans and project sponsors, are authorized to make minor technical changes as needed to the 2022 Local Partnership Competitive Program in order to reflect the most current information, or to clarify the Commission's programming commitments, and shall request Commission approval of any substantive changes; and

2.7 BE IT FURTHER RESOLVED, that the Commission directs staff to post the 2022 Local Partnership Competitive Program of Projects on the Commission's website.

County Nominating Agency Implementing Agency Project Title Project Description Fiscal Year Total Project Cost Recommended Funding Voter
Approved (V)
or Imposed
Fee (I)
Population
Category
El Dorado El Dorado County El Dorado County Pioneer Trail/US Hwy 50 Intersection Safety Improvement Project In Meyers, convert a signalized T‐intersection at the U.S. Highway 50/State Route 89 into a three‐leg modern roundabout. Includes 3 intersection improvements; 11 channelizations; 0.8 miles pedestrian/bicycle facilities. 2023‐24 $ 9,127 $ 3,055 I IV San Bernadino Rancho Cucamonga, City of Rancho Cucamonga, City of Foothill Blvd Complete Street Project On Foothill Blvd, narrow existing vehicle lanes, rehab approx. 1,950 linear ft of pavement, and construct 0.81 miles of multi‐use path and new sidewalk; includes streetlights, a traffic signal, and enhanced pedestrian and crosswalk markings. 2023‐24 $ 4,800 $ 2,400 I IV
Sonoma Sonoma Co Transportation Authority (SCTA) Caltrans D4 US 101/Hearn Ave Regional Multimodal Interchange In the City of Santa Rosa, demolish and replace US 101/Hearn Ave overcrossing, includes traffic operation improvements; one mile of new bicycle lanes and sidewalks; ADA elements.
2023‐24 $ 43,675 $ 8,600 V III
Alameda Alameda County Transportation Commission (Alameda CTC) Caltrans Oakland Alameda Access Project In the Cities of Oakland and Alameda, improved traffic ops along I‐880 and in and around the Webster and Posey Tubes including: 12.2 roadway lane miles; 2 trafficmonitoring detection stations; 3 miles of bile lanes; 110,523 square feet of new bridges/tunnels; and implementation of follow up landscaping work. 2024‐25 $ 129,900 $ 25,000 V I
Yuba Yuba County Yuba County North Beale Road Complete Streets / Safety Project ‐  Phase III In Linda, 2 miles of local road rehabilitation including: raised medians; left‐turnlanes; storm drains; new streetlights; curbs; gutters; thermoplastic centerline andedge‐line striping; and a new traffic signal; one mile of eight‐foot wide sidewalks;

7.5‐foot wide paved bicycle lanes.
2023‐24 $ 7,711 $ 3,000 V V
Santa Clara Santa Clara Valley Transportation Authority (VTA) Peninsula Corridor Joint Powers Board (Caltrain) Mountain View Transit Center Grade Separation and Access Project In Mountain View, eliminate the Caltrain vehicle at‐grade crossing; re‐direct vehicular traffic and modify traffic movements; construct 0.43 miles of shared usepathway and vertical circulation from non‐motorized traffic to/from the TransitCenter and Downtown; construct new shuttle loading areas. 2024‐25 $ 136,000 $ 25,000 V I
Sacramento Sacramento Transportation Authority (STA) Sacramento, County of US 50 Gold Line Corridor Enhancement Project ‐ Hazel Ave/US 50 Interchange 2024‐25 $ 132,726 $ 25,000 V I Hazel Avenue / US 50 Interchange
In Sacramento, converts 29 Gold Line light rail station platforms to fit low floorvehicles; grade separation includes 3 interchange modifications, 19,190 square feetof new bridges/tunnels, and adds 0.74 miles of grade‐separated Class I path.

Gold Line Light Rail Platform Modifications ‐ Phase 2 In Sacramento, converts 29 Gold Line light rail station platforms to fit low floor vehicles, phase 2 conversion.

Tulare Tulare County Association of Governments (TCAG) Caltrans D6 SR99/Caldwell Ave Interchange, Safety and Multi‐Modal Project In Tulare County, reconstruct the Avenue 280 (Caldwell Avenue) Interchange. Includes 0.8 miles auxiliary lane, 1.1 miles of bicycle lane, 0.9 miles sidwalk. 2023‐24 $ 68,227 $ 15,000 V VMendocino Ukiah, City of Ukiah, City of Urban Core Rehabilitation and Transportation Project In Ukiah, reconstruct 4.8 miles of local road and 2.9 miles of bicycle lanes,including: replacement of water and sewer utilities; construction of ADA accessiblecurb ramps; bulb‐outs and the installation of a traffic signal and bike lanes. 2023‐24 $ 14,356 $ 6,074 V V
San Mateo San Mateo County Transit District (SamTrans) San Mateo County Transit District (SamTrans) SamTrans Emission Zero Project In San Carlos, construct zero‐emission bus electrical charging infrastructure and bus charging bays; procure and install overhead pantograph charging dispenser; and construction of an electrical power distribution network; includes charging infrastructure for thirty‐seven Battery Electric Buses. 2023‐24 $ 32,605 $ 14,824 V II
Los Angeles Los Angeles County Metropolitan Transportation Authority (LA Metro) Los Angeles County Metropolitan Transportation Authority (LA Metro) Southeast Los Angeles Transit Improvements Project (SELA TIP) 2024‐25 $ 31,130 $ 14,500 V I Southeast Los Angeles Transit Improvements Project
(Transit Signal Priority)
In southeast Los Angeles County, purchase, design, and install 114 cloud‐based transit signal priority systems in NextGen Tier 1 and 2 high frequency corridorsthroughout the I‐710 South communities.

Bus Shelters Purchase and install 100 bus shelters with real‐time display and security lighting.

Lighting Purchase and install 100 solar‐powered lighting upgrades.

Termini/Layover Construction of 3 bus termini/layovers at Norwalk, Artesia, and Compton Stations.ZEB Charging Purchase and install 10 zero emission bus charging masts.

TOTAL $ 610,257 $ 142,453
Amount Over‐Programmed $ 6,253
2022 Local Partnership Competitive Program
Program of Projects - Projects Recommended for Funding
Resolution G-23-47
($1,000s)
Attachment B
Reference No.: 4.6
June 28-29, 2023
36 Appendix II: Performance Metrics and Required Back-Up Information Measure Metric Project Type Build Future
No Build
Change Increase
or
decrease
Congestion
Reduction
Person Hours of
Travel Time
Saved per Year -
Transit Riders
Transit Signal
Prioritization
(192,064) - (192,064) decrease
Person Hours of
Travel Time
Saved per Year -
Transit Drivers
Transit Signal
Prioritization
788,223 725,165 (63,058) decrease
Change in Daily
Vehicle Miles
Travelled
Transit Signal
Prioritization

N/A N/A N/A N/A
Throughput Bicyclist and
Pedestrian Screen
Line Counts
(Optional)
Active
Transportatio
n

N/A N/A N/A N/A
System
Reliability
Peak Period Travel
Time Reliability
Index
Hwy Road N/A N/A N/A N/A
Level of Transit
Delay
Transit N/A N/A N/A N/A
Safety Number of
Fatalities
All N/A N/A N/A N/A
Number of Serious
Injuries
All N/A N/A N/A N/A
Rate of Fatalities All N/A N/A N/A N/A
Rate of Serious
Injuries
All N/A N/A N/A N/A
Economic
Development
Jobs Created All 362.4 - 362.4 Increase
Air Quality Particulate Matter
(PM 2.5 PM 10)
ZEV Charging 5.36 5.64 (0.3) decrease
Carbon Dioxide
(CO2)
ZEV Charging 4,113 71,030 (66,917) decrease
Volatile Organic
Compounds (VOC)
ZEV Charging - 2.63 (2.6) decrease
Sulphur Oxides
(SOx)
ZEV Charging - 0.51 (0.5) decrease
Carbon Monoxide
(CO)
ZEV Charging - 1,102 (1,102) decrease
37 Nitrogen Oxides
(NOx)
ZEV Charging - 7.13 (7.1) decrease
Cost
Effectiveness
Benefit Cost Ratio All N/A N/A 4.36 Increase
Accessibility Number of Jobs
Accessible by
Mode
All N/A N/ N/A N/A
Access to Key
Destinations by
Mode
All N/A N/ N/A N/A
Percent of
Population Defined
as Low Income or
Disadvantaged
within ½ mile of rail
station, ferry
terminal, or highfrequency bus stop
All N/A N/A N/A N/A
System
Preservation
(Pavement
and Bridge
Rehabilitation
only)
Pavement
Condition Index
Local Road
Hwy Road

N/A N/A N/A N/A
Bridge Condition
Rating for Bridge
Deck,
Superstructure,
Substructure
Local Road
Hwy Road

N/A N/A N/A N/A
Noise Level
Sound walls
only
(For reporting
only)
Number of
Receptors
Sound walls N/A N/A N/A N/A
Properties Directly
Benefited
Sound walls N/A N/A N/A N/A
Number of
Decibels
Sound walls N/A N/A N/A N/A