RESOLUTION NO. 2026-040

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF VERNON

APPROVING AND ADOPTING THE VERNON PUBLIC UTILITIES
DEPARTMENT RESOURCE ADEQUACY PLAN FOR 2027, WHICH

INCLUDES THE COINCIDENT PEAK DEMAND FORECAST, THE

PLANNING RESERVE MARGIN, THE QUALIFYING CAPACITY

CRITERIA, AND THE QUALIFYING CAPACITY FROM SUCH
RESOURCES, THE CITY’S RESOURCE ADEQUACY AND SUPPLY

DATA, APPROVING THE RESOURCES USED TO SATISFY THE
CALIFORNIA INDEPENDENT SYSTEM OPERATOR’S TARIFF
REQUIREMENTS AND REPEALING RESOLUTION NO. 2025-028
SECTION 1. Recitals.

A. The City of Vernon (City) is a chartered municipal corporation of the State of California that owns and operates a system for the generation, purchase, transmission, distribution, and sale of electric capacity and energy.

B. The City has executed a Metered Subsystem Agreement (MSS Agreement) with the California Independent System Operator (CAISO).

C. The City is considered a Load Serving Entity (LSE) under certain terms of the CAISO’s Tariff (Tariff).

D. The Tariff requires each LSE to establish and submit to CAISO an annual Resource Adequacy Plan, which includes a coincident peak Demand Forecast, a Planning Reserve Margin, Qualifying Capacity Criteria, and a Supply Plan.

E. The Tariff also requires each LSE to submit monthly Resource Adequacy Plans and Supply Plans.

F. The City has reviewed the historical and expected demand for and supplies of electricity within its distribution system, including the likely peak demand for electricity within the City’s distribution system throughout 2027, the available generation and other capacity to serve that demand, and constraints which might impact the availability of capacity to serve the City’s projected peak demand.

G. Based upon staff analysis, no load growth adjustment is appropriate for 2027.

H. The City finds that the default 15% Reserve Margin set forth in the Resource Adequacy provisions of the Market Redesign and Technology Upgrade (MRTU) Tariff is sufficient for planning purposes.

I. The City finds that the Projected Load forecast specified in the City of Vernon Resolution No. 2026-040

Page 2 of 24 ends

_______________________
Demand Forecast for 2027, Planning Reserve Margin, and the Qualifying Capacity Criteria are sufficient and appropriate to be used in determining the amount of Qualifying Capacity needed to meet the Annual Resource Adequacy and Supply Plan requirement.

J. Staff recommends City Council’s adoption of the following requirements for the annual and monthly submittals: (a) annual submittals must demonstrate that (i) 90% of the total system Coincident Peak Demand Forecast, plus Planning Reserve Margin and Flexible Resource Adequacy Capacity Requirement has been secured, and (ii) 100% of the total local Resource Adequacy requirement has been secured; and (b) monthly submittals must demonstrate that 100% of the Coincident Peak Demand Forecast plus planning Reserve Margin, Flexible Resource Adequacy Capacity Requirement and local Resource Adequacy requirement has been met.

NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF VERNON AS FOLLOWS:

SECTION 2. The City Council of the City of Vernon hereby finds and determines that the above recitals are true and correct.

SECTION 3. The City Council of the City of Vernon finds that this action is exempt from California Environmental Quality Act (CEQA) review, because it is an administrative and fiscal activity that will not result in direct or indirect physical changes in the environment, and therefore does not constitute a “project” as defined by CEQA Guidelines Section 15378.

SECTION 4. The City Council of the City of Vernon hereby approves and adopts the Vernon Public Utilities Resource Adequacy Plan for Calendar Year 2027 (Annual Resource Adequacy Plan), which includes the coincident peak Demand Forecast, the Planning Reserve Margin, the Qualifying Capacity Criteria and the Qualifying Capacity from such resources, the annual Resource Adequacy and Supply data, and the Resource Adequacy resources that will be used to satisfy the City’s Local Capacity Requirement for 2026, which is attached hereto as Exhibit A.

SECTION 5. The City Council of the City of Vernon also adopts the following Annual Resource Plan requirements: (a) annual submittals must demonstrate that (i) 90% of the total system Coincident Peak Demand Forecast, plus Planning Reserve Margin and Flexible Resource Adequacy Capacity Requirement has been secured; and (ii) 100% of the total local Resource Adequacy requirement has been secured; and (b) monthly submittals must demonstrate that 100% of the Coincident Peak Demand Forecast plus planning Reserve Margin, Flexible Resource Adequacy Capacity Requirement and local Resource Adequacy requirement has been met.

Resolution No. 2026-040

Page 3 of 24 ends

_______________________
SECTION 6. All resolutions or parts of resolutions, specifically Resolution No. 2025-028, not consistent with or in conflict with this resolution, are hereby repealed.

SECTION 7. The City Clerk, or Deputy City Clerk, shall certify the passage and adoption of this resolution and enter it into the book of original resolutions.

APPROVED AND ADOPTED October 6, 2026.

MELISSA YBARRA, Mayor
ATTEST:

GENOVEVA ROCHA, City Clerk
APPROVED AS TO FORM:

ZAYNAH MOUSSA-MILWARD,
City Attorney
Resolution No. 2026-040

Page 4 of 24 ends

_______________________

CERTIFICATION

STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss.

CITY OF VERNON )
I do hereby certify that the attached is a true copy of Resolution No. 2026-040 that was passed and adopted at the Special Meeting held on October 6, 2026, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:
__________________________
GENOVEVA ROCHA, City Clerk

CITY OF VERNON
PUBLIC UTILITIES DEPARTMENT’S

RESOURCE ADEQUACY PLAN
CALENDAR YEAR 2027
2027 Resource Adequacy Plan
1 of 20

EXHIBIT A
Resolution No. 2026-040

Page 5 of 24 ends

________________________
Background:

The Resource Adequacy (RA) provisions of the California Independent System Operator’s (CAISO) tariff require the Scheduling Coordinator (SC) of a Load Serving Entity (LSE), such as the City of Vernon, to establish and submit the following information upon approval from its Local Regulatory Authority:

1. Coincident Peak Demand Forecast for its load,

2. Planning Reserve Margin,

3. Qualifying Capacity Criteria that will be used for determining qualifying resource types and the Qualifying Capacity from such resources,

4. an annual/monthly RA and supply data, and

5. a list of resources used to satisfy the LSE’s Local Capacity Requirement and Flexible Resource Adequacy Capacity Requirement.

Staff has prepared the attached “City of Vernon Public Utilities Department’s Resource Adequacy Plan for Calendar Year 2027,” which is consistent with the CAISO Tariff requirements. The following is a discussion of each of the CAISO Tariff requirements and how the City will meet each requirement.

Coincident Peak Demand Forecast:

Vernon’s municipal load resides within the CAISO control area. CAISO, as the balancing authority, is responsible for meeting reliability criteria established by the Western Electricity Coordinating Council (WECC). As such CAISO has entered into agreements with various market participants, Generators, Scheduling Coordinators, Participating Transmission Owners, Utility Distribution Companies, and Metered Subsystems (MSS), which impose certain responsibilities on parties to establish a reliable system. One of those responsibilities is to have operating reserves that meet the WECC minimum requirements.

The CAISO’s goal in considering reserve requirements is to balance available capacity with demand across the entire CAISO control area, and therefore, CAISO’s primary concern is with the time and amount of peak demand on the CAISO controlled transmission system (the “system peak”). In order to reduce demand during the period of the system peak (and therefore, to lower the peak demand on the transmission system), utilities generally offer retail rate structures designed to encourage load shifting away from the on-peak period. Such efforts are intended to achieve on-peak demand reduction and lower the need to build new generation to meet peak demand. Vernon has adopted a rate structure that has successfully shifted the peak demand period for Vernon’s system to a time that is generally earlier than the time of the CAISO system peak.

Vernon’s share of the capacity needed to meet CAISO’s control area capacity requirements may be established by determining the amount of Vernon’s load that contributes to the CAISO system peak. Vernon’s load that contributes to the CAISO system peak is the City of Vernon coincident peak Demand. The process to establish 2027 Resource Adequacy Plan
2 of 20
Resolution No. 2026-040

Page 6 of 24 ends

________________________
Vernon’s monthly coincident peak Demand Forecast consists of the following three steps:

1. Establish Monthly Vernon System Peak Demand Forecast for 2027 To establish the City of Vernon’s system peak demand forecast, Staff performs an analysis on annual changes in the City’s energy demand peaks during a five-year period. Based on the results of the analysis, Staff forecasts a load growth rate for the upcoming calendar year (Exhibit 1). This year’s analysis of the City of Vernon’s system peak demand demonstrates an inconsistent trend year after year between 2022 and 2026. Closer review of Exhibit 1 reveals that more recently, the growth rate from 2023 to 2026 decreased by 0.4%. Based on the current load trend and recent years of inconsistencies, Staff concluded that a zero-load growth adjustment is an appropriate forecast for calendar year 2027. Exhibit 2 shows the determination of the projected system peak demand for 2027 based on no load growth adjustment. The projected system peak demand for the City of Vernon is shown below in Table 1.

Table 1
Projected
Load
2027 MW
January 157.53
February 158.51
March 173.14
April 161.77
May 166.22
June 171.92
July 183.39
August 186.85
September 173.86
October 166.14
November 164.99
December 164.73

2. Establish Coincidental Peak Factor
The coincidental peak factor is the percentage of the City of Vernon’s energy demand at the time of the CAISO system peak demand. As set forth in Section 40 of the CAISO Tariff, the coincidental peak factor for each month has been calculated and provided to the City annually by the California Energy Commission (CEC). The monthly coincidental peak factor is shown in column C of Exhibit 3. 2027 Resource Adequacy Plan
3 of 20
Resolution No. 2026-040

Page 7 of 24 ends

________________________

3. Calculate Monthly Coincident Peak Demand Forecast
The City of Vernon’s Coincident Peak Demand forecast is calculated as the mathematical product of the City of Vernon’s forecasted System peak demand and the coincidental peak factor. This reflects the City of Vernon’s projected demand at the time of the CAISO system’s peak demand for each month. The monthly Coincident Peak Demand Forecast is calculated and listed in column D of Exhibit 3 for the period of January through December 2027. It is also shown below in Table 2.

Table 2
Demand
Forecast
2027 MW
January 126.5
February 121.8
March 137.1
April 132.2
May 125.5
June 139.2
July 148.9
August 151.3
September 142.2
October 137
November 140.4
December 139.5
Planning Reserve Margin:

The Planning Reserve Margin is the amount of Resource Adequacy Capacity that an LSE must maintain above its coincident peak Demand Forecast. Historically, the City of Vernon has established its Planning Reserve Margin at 15%. Staff recommends that the City Council maintain the Planning Reserve Margin at 15%. The 15% Planning Reserve Margin is used to establish the monthly Resource Adequacy obligation for the City of Vernon as listed in column E of Exhibit 3.

Qualifying Capacity:

An LSE must provide the CAISO with a description of the criteria that will be used to determine the type of resources that can be used to meet its capacity obligation and the amount of capacity (Qualifying Capacity) from such resources. Historically, Vernon has used the following criterion to determine whether a resource qualifies: It qualifies if Vernon has a contractual right to the power or has an interruptible service 2027 Resource Adequacy Plan
4 of 20
Resolution No. 2026-040

Page 8 of 24 ends

________________________
agreement with a customer. The following eight resources are among those that meet this criterion and provide Qualifying Capacity. The eligible Qualifying Capacity for the eight applicable resource types is as follows:

1. CAISO IST-enabled Product. Power supply contract/s entered through WSPP Agreement (MRTU Amendment) and defined as any SC-to-SC traded product for which an IST (Inter-SC Trades) can be submitted and for which CAISO will make payment or issue an invoice, including Energy, Tier I IFM Bid Cost Recovery Obligations, and Ancillary Service Obligation trades, as each is defined in the Tariff.

2. Palo Verde. Vernon Purchase Power Contract with SCPPA for 4.9% of SCPPA’s share of Palo Verde Nuclear Generating Station (Palo Verde) shall be eligible as Qualifying Capacity. The power is scheduled as an import generally at Westwing Substation through CAISO’s entitlement of transmission from Westwing to SP-15.

3. Boulder Canyon. Contract NO 16-DSR-12650 between United States Department of Energy Western Area Power Administration Boulder Canyon Project and City of Vernon, California for Electric Service shall be eligible to count as Qualifying Capacity. The power is scheduled as an import at Mead Substation generally through CAISO’s entitlement of transmission from Mead Substation to SP-15. The amount of Qualifying Capacity will be based on the most current schedule for the available capacity from the Boulder Canyon Project at the time of submittal of the Resource Adequacy Plan.

4. Vernon Units. Generating units and system units (excluding Vernon diesel generating units) within Vernon’s MSS, including the Malburg Generating Station and the City-owned H. Gonzales units, as reflected in Schedule 14 of Vernon’s MSS Agreement with CAISO shall be eligible to count as Qualifying Capacity. The amount of Qualifying Capacity of such units shall not exceed the Net Qualifying Capacity (NQC) as determined and listed annually by the CAISO.

5. Long-Term Power Purchase Contracts. Long-term power supply contracts (5 years or greater) entered through a power purchase agreement shall be eligible to count as Qualifying Capacity. The amount of Qualifying Capacity will be based on the City of Vernon’s percentage share of the Net Qualifying Capacity of each contract. For the upcoming year, the following contracts will count as Qualifying Capacity, Antelope DSR 1 Solar Project, Astoria 2 Solar Project, Daggett Solar Project and Puente Hills Landfill Gas-To-Energy Facility.

6. Other Units. All other capacity from a Participating Generator, a System Unit, or a System Resource, as defined in the CAISO Tariff, shall be eligible as Qualifying Capacity. System Resources, however, must be located in the CAISO control area or have a firm transmission path from source to the CAISO control area. Such criteria for firm transmission facilities over the CAISO control area can be satisfied with the possession of a firm transmission right from the 2027 Resource Adequacy Plan
5 of 20
Resolution No. 2026-040

Page 9 of 24 ends

________________________
CAISO on the path associated with the System Resource. Firm transmission rights provide a physical priority right to schedule over congested paths.

7. Interruptible Service Agreements. Interruptible Service Agreements with the City’s Electrical customers. Currently, Vernon has an Interruptible Service Agreement where the customer agrees to interrupt up to 27 MW of load within a 30-minute notification. A period of interruption can occur upon notification from the Independent System Operator (ISO) requiring the City to shed load or upon the unscheduled outage of the Malburg Generating Station (MGS) or any other generating unit internal to the City’s system.

8. Battery Energy Storage System (Non-Generator Resources). Power Supply contracts for BESS or Non-Generator Resource, as defined by the CAISO, entered through a power purchase agreement, shall be eligible to count as Qualifying Capacity. The amount of Qualifying Capacity shall be based on Vernon’s percentage share of the Net Qualifying Capacity of each contract.

Local Capacity Area Resources:

In accordance with Section 40.3 of the CAISO Tariff, CAISO annually publishes a Local Capacity Technical Study that determines the amount of local capacity needed in the Los Angeles Basin area that must be available to CAISO. Based on the Local Capacity Technical Study, the CAISO allocates responsibility for Local Capacity Area Resources to the Scheduling Coordinators of the LSEs. The CAISO validates that the Scheduling Coordinator lists enough local resources in its Resource Adequacy data templates to satisfy its obligation. Staff have prepared the Resource Adequacy data templates (Exhibit 4), which list the Resource Adequacy Resources, including the Malburg Generating Station, Puente Hills Landfill Gas-To-Energy Facility, and the Cityowned H. Gonzales units that will be counted on to satisfy the Local Area Capacity requirement for the City of Vernon. Additionally, any Interruptible Service Agreements with the City’s electric customers shall count towards the City’s Local Capacity requirement.

Flexible Resource Adequacy Capacity:

In accordance with Section 40.10 of the CAISO Tariff, CAISO annually conducts a study to determine the Flexible Capacity Need for the CAISO Balancing Authority Area for each month of the next calendar year and provides the results of the study to each Local Regulatory Authority in the CAISO Balancing Authority Area. Flexible resources are resources with the potential to ramp up and down quickly and have the capability to start and shut down multiple times per day. The need for flexible capacity is a result of the CAISO managing a “greener” grid. The increase of variable energy resources and distributed generation has presented significant challenges to grid reliability. These types of resources have continued to grow and have increased supply and load variability and unpredictability within the CAISO system. In order for the CAISO to efficiently operate the grid, it needs measures to ensure that flexible resources are economically bid into the CAISO markets so that they may be optimally dispatched.
2027 Resource Adequacy Plan
6 of 20
Resolution No. 2026-040

Page 10 of 24 ends

________________________
The CAISO study calculates the total system amount of Flexible Capacity needed for each of the three Flexible Capacity categories: (1) Base ramping flexibility; (2) Peak ramping flexibility; and (3) Super-peak ramping flexibility. Section 40.10.3 of the CAISO Tariff sets the criteria needed by resources to qualify for each category. For the Calendar Year 2027, CAISO has determined the system-wide Flexible Capacity needs and has notified each LSE of their monthly requirement. Exhibit 7 lists the City’s Flexible Capacity requirement by month and category. Furthermore, CAISO has established the Effective Flexible Capacity for each resource and the category of Flexible Capacity each resource will qualify for the upcoming compliance year. For Calendar Year 2027, CAISO has established 105 MW of category 1 base ramping flexible resources adequacy capacity for Malburg Generating Station, and 5.75 MW category 1 base ramping flexible resource adequacy capacity for both H. Gonzales Units (Exhibit 8). CAISO Tariff Section 40.10.5.1 requires the Scheduling Coordinators of LSEs to identify the resources they will rely on to satisfy their Flexible Resource Adequacy Capacity on both the annual and monthly Resource Adequacy data templates.

Staff prepared the Resource Adequacy data templates (Exhibit 4), which list the Resource Adequacy Resources, including the Malburg Generating Station and the City-owned H. Gonzales units, that will be counted on to satisfy the Flexible Resource Adequacy Capacity requirement for the City of Vernon.

Annual and Monthly Resource Adequacy and Supply data:

The CAISO Tariff requires that the scheduling coordinator of an LSE provide an annual and a monthly Resource Adequacy Plan (Section 40.2.2.4) using the required templates and submitted on the set schedules. Furthermore, the scheduling coordinator of a resource providing resource adequacy must submit both an annual and monthly Supply Plan (Section 40.4.7.1) using the required templates and submitted on the set schedules.

Staff asks that City Council adopt the following two requirements for both the annual and monthly Supply Plan submittals:

1. Annual: submittals must demonstrate that 90% of the forecasted coincident peak demand plus planning reserves margin and flexible resource adequacy requirement has been secured; and 100% of the total local resource adequacy requirement has been secured.

2. Monthly: submittals must demonstrate 100% of the forecasted coincident peak Demand plus planning reserves margin, flexible resource adequacy requirement, and local resource adequacy requirement have been met. Data on the monthly plans may be adjusted for seasonal variations in the City’s load or changes in its contracted/owned resources.

Therefore, as required by the CAISO, the City of Vernon, as an LSE and a scheduling coordinator for resource adequacy resources, must submit a Resource Adequacy 2027 Resource Adequacy Plan
7 of 20
Resolution No. 2026-040

Page 11 of 24 ends

________________________
and Supply Plan on the set schedules. Staff prepared the Annual Resource Adequacy (Exhibit 5) and Supply data (Exhibit 6 & 7) for calendar year 2027. Staff will submit the monthly Resource Adequacy and Supply data to the CAISO as they become due.

The data to be submitted on the monthly plans will demonstrate that 100% of applicable requirements have been met and may be adjusted from the annual Resource Adequacy and Supply Plan for seasonal variations, as well as load and resource changes. The monthly plan is due to the CAISO 45 days prior to the beginning of the month.
2027 Resource Adequacy Plan
8 of 20
Resolution No. 2026-040

Page 12 of 24 ends

________________________
Exhibit 1
Year Peak % Inc./Dec.
(A) (B) (C)
1 2022 187.4
2 2023 176.1 -5.989%
3 2024 175.5 -0.341%
4 2025 167.4 -4.660%
5 2026 183.4 9.585%
6 Average 178.0 -0.4%
A Year
B Source: (City Historical Sytem Peak Load Data)
C % Increase/Decrease from previous year.

Note: The five year system peak demand average will not be used in this year's RA Plan.

It has been determined that no load growth is appropriate for calendar 2027. 5 year Sytem Peak Demand Analysis
2027 Resource Adequacy Plan
9 of 20
Resolution No. 2026-040

Page 13 of 24 ends

________________________
Exhibit 2
Month
Forecast based
2025-2026
(Actual City
System Load)
2027
Projected
System Peak
Load
(A) (B) (C)
1 January '26 157.53 157.53
2 February '26 158.51 158.51
3 March '26 173.14 173.14
4 April '26 161.77 161.77
5 May '26 166.22 166.22
6 June '26 171.92 171.92
7 July '26 183.39 183.39
8 August '26 186.85 186.85
9 September '25 173.86 173.86
10 October '25 166.14 166.14
11 November '25 164.99 164.99
12 December '25 164.73 164.73
A Month and Year
B Source: (Forecasted Peak Based on Historical System Peak Load Data) C Projected Load for 2027 (no load growth is applied)
January - December 2027 Projected Load
2027 Resource Adequacy Plan
10 of 20
Resolution No. 2026-040

Page 14 of 24 ends

________________________
Exhibit 3
Month
Vernon
System Peak
Demand
Coincidental
Peak Factor
Coincident
Peak Demand
Forecast
RA Capacity
Requirement
(A) (B) (C) (D) (E)
1 January 157.5 80.3% 126.5 145.5
2 February 157.7 76.8% 121.1 139.3
3 March 153.5 79.2% 121.5 139.8
4 April 154.6 81.7% 126.4 145.3
5 May 157.9 75.5% 119.2 137.1
6 June 167.4 81.0% 135.5 155.8
7 July 164.3 81.2% 133.3 153.3
8 August 166.5 81.0% 134.8 155.0
9 September 172.8 81.8% 141.4 162.6
10 October 161.9 82.5% 133.6 153.6
11 November 152.7 85.1% 129.9 149.4
12 December 149.5 84.7% 126.6 145.6
A Month
B Source: (Exhibit 2 Column E)
C Source: CEC
D Product of B and C
E Product of D and 115% (115% reflects Planning Reserve Margin) January - December 2027 Resource Adequacy Requirement
2027 Resource Adequacy Plan
11 of 20
Resolution No. 2026-040

Page 15 of 24 ends

________________________
Report Type Annual (Monthly/ Annual)
Report Date 10/1/2026 (MM/DD/YYYY)
Name of Load Serving Entity (LSE): City of Vernon (Text Field) Scheduling Coordinator (SCID): LVERN (AAAA)
Person who prepared this RA Plan (Name): Efrain Sandoval (Text Field) Title: Principal Resource Scheduler/Trader (Text Field) Primary Contact
Name: Efrain Sandoval (Text Field)
Title: Principal Resource Scheduler/Trader (Text Field) Address: 4305 Santa Fe Ave. (Text Field)
Address 2: (Optional, Text Field)
City: Vernon (Text Field)
State: CA (Text Field)
Zip: 90058 (Numeric)
Telephone: (323) 826-1424 (Numeric)
Email [email protected] (Text Field)
Back-Up Contact
Name: Shawn Sharif (Text Field)
Title: Principal Resource Scheduler/Trader (Text Field) Telephone: (323)826-3625 (Numeric)
Email: [email protected] (Text Field)
Exhibit 4
2027 Resource Adequacy Plan
12 of 20
Resolution No. 2026-040

Page 16 of 24 ends

________________________
Resource ID in CAISO Master File
Local RA
Capacity (MW

00.00 No
Rounding)
System RA
Capacity (MW

00.00 No
Rounding)
Flexible RA
Capacity (MW

00.00 No
Rounding)
Flex
Category
RA Capacity
Effective Start
Date
(mm/dd/yyyy)
RA Capacity
Effective End
Date
(mm/dd/yyyy)
VERNON_6_MALBRG 44 95 105 1 1/1/2027 1/31/2027
VERNON_6_MALBRG 44 95 105 1 2/1/2027 2/28/2027
VERNON_6_MALBRG 44 95 105 1 3/1/2027 3/31/2027
VERNON_6_MALBRG 44 95 105 1 4/1/2027 4/30/2027
VERNON_6_MALBRG 44 95 105 1 5/1/2027 5/31/2027
VERNON_6_MALBRG 44 95 105 1 6/1/2027 6/30/2027
VERNON_6_MALBRG 44 95 105 1 7/1/2027 7/31/2027
VERNON_6_MALBRG 44 95 105 1 8/1/2027 8/31/2027
VERNON_6_MALBRG 44 95 105 1 9/1/2027 9/30/2027
VERNON_6_MALBRG 44 95 105 1 10/1/2027 10/31/2027
VERNON_6_MALBRG 44 95 105 1 11/1/2027 11/30/2027
VERNON_6_MALBRG 44 95 105 1 12/1/2027 12/31/2027
VERNON_6_GONZL1 5.75 5.75 1 1/1/2027 1/31/2027
VERNON_6_GONZL1 5.75 5.75 1 2/1/2027 2/28/2027
VERNON_6_GONZL1 5.75 5.75 1 3/1/2027 3/31/2027
VERNON_6_GONZL1 5.75 5.75 1 4/1/2027 4/30/2027
VERNON_6_GONZL1 5.75 5.75 1 5/1/2027 5/31/2027
VERNON_6_GONZL1 5.75 5.75 1 6/1/2027 6/30/2027
VERNON_6_GONZL1 5.75 5.75 1 7/1/2027 7/31/2027
VERNON_6_GONZL1 5.75 5.75 1 8/1/2027 8/31/2027
VERNON_6_GONZL1 5.75 5.75 1 9/1/2027 9/30/2027
VERNON_6_GONZL1 5.75 5.75 1 10/1/2027 10/31/2027
VERNON_6_GONZL1 5.75 5.75 1 11/1/2027 11/30/2027
VERNON_6_GONZL1 5.75 5.75 1 12/1/2027 12/31/2027
VERNON_6_GONZL2 5.75 5.75 1 1/1/2027 1/31/2027
VERNON_6_GONZL2 5.75 5.75 1 2/1/2027 2/28/2027
VERNON_6_GONZL2 5.75 5.75 1 3/1/2027 3/31/2027
VERNON_6_GONZL2 5.75 5.75 1 4/1/2027 4/30/2027
VERNON_6_GONZL2 5.75 5.75 1 5/1/2027 5/31/2027
VERNON_6_GONZL2 5.75 5.75 1 6/1/2027 6/30/2027
VERNON_6_GONZL2 5.75 5.75 1 7/1/2027 7/31/2027
VERNON_6_GONZL2 5.75 5.75 1 8/1/2027 8/31/2027
VERNON_6_GONZL2 5.75 5.75 1 9/1/2027 9/30/2027
VERNON_6_GONZL2 5.75 5.75 1 10/1/2027 10/31/2027
VERNON_6_GONZL2 5.75 5.75 1 11/1/2027 11/30/2027
VERNON_6_GONZL2 5.75 5.75 1 12/1/2027 12/31/2027
VERN_MEAD230_I_UC_IMS001 22 1/1/2027 1/31/2027
VERN_MEAD230_I_UC_IMS001 22 2/1/2027 2/28/2027
VERN_MEAD230_I_UC_IMS001 22 3/1/2027 3/31/2027
VERN_MEAD230_I_UC_IMS001 22 4/1/2027 4/30/2027
VERN_MEAD230_I_UC_IMS001 22 5/1/2027 5/31/2027
VERN_MEAD230_I_UC_IMS001 22 6/1/2027 6/30/2027
VERN_MEAD230_I_UC_IMS001 22 7/1/2027 7/31/2027
VERN_MEAD230_I_UC_IMS001 22 8/1/2027 8/31/2027
VERN_MEAD230_I_UC_IMS001 22 9/1/2027 9/30/2027
VERN_MEAD230_I_UC_IMS001 22 10/1/2027 10/31/2027
VERN_MEAD230_I_UC_IMS001 22 11/1/2027 11/30/2027
VERN_MEAD230_I_UC_IMS001 22 12/1/2027 12/31/2027
VERN_WESTWING500_I_UC_IMS001 11.59 1/1/2027 1/31/2027
VERN_WESTWING500_I_UC_IMS001 11.59 2/1/2027 2/28/2027
VERN_WESTWING500_I_UC_IMS001 11.59 3/1/2027 3/31/2027
VERN_WESTWING500_I_UC_IMS001 11.59 4/1/2027 4/30/2027
VERN_WESTWING500_I_UC_IMS001 11.59 5/1/2027 5/31/2027
VERN_WESTWING500_I_UC_IMS001 11.59 6/1/2027 6/30/2027
VERN_WESTWING500_I_UC_IMS001 11.59 7/1/2027 7/31/2027
VERN_WESTWING500_I_UC_IMS001 11.59 8/1/2027 8/31/2027
VERN_WESTWING500_I_UC_IMS001 11.59 9/1/2027 9/30/2027
VERN_WESTWING500_I_UC_IMS001 11.59 10/1/2027 10/31/2027 VERN_WESTWING500_I_UC_IMS001 11.59 11/1/2027 11/30/2027 VERN_WESTWING500_I_UC_IMS001 11.59 12/1/2027 12/31/2027 CMBLND_2_DS2BT2 30 60 1 1/1/2027 1/31/2027
CMBLND_2_DS2BT2 30 60 1 2/1/2027 2/28/2027
CMBLND_2_DS2BT2 30 60 1 3/1/2027 3/31/2027
CMBLND_2_DS2BT2 30 60 1 4/1/2027 4/30/2027
CMBLND_2_DS2BT2 30 60 1 5/1/2027 5/31/2027
CMBLND_2_DS2BT2 30 60 1 6/1/2027 6/30/2027
CMBLND_2_DS2BT2 30 60 1 7/1/2027 7/31/2027
CMBLND_2_DS2BT2 30 60 1 8/1/2027 8/31/2027
CMBLND_2_DS2BT2 30 60 1 9/1/2027 9/30/2027
CMBLND_2_DS2BT2 30 60 1 10/1/2027 10/31/2027
CMBLND_2_DS2BT2 30 60 1 11/1/2027 11/30/2027
CMBLND_2_DS2BT2 30 60 1 12/1/2027 12/31/2027
CMBLND_2_DS2SR2 0.09 1/1/2027 1/31/2027
CMBLND_2_DS2SR2 0.09 2/1/2027 2/28/2027
CMBLND_2_DS2SR2 0.09 3/1/2027 3/31/2027
2027 Resource Adequacy Plan
13 of 20
Resolution No. 2026-040

Page 17 of 24 ends

________________________
Resource ID in CAISO Master File
Local RA
Capacity (MW

00.00 No
Rounding)
System RA
Capacity (MW

00.00 No
Rounding)
Flexible RA
Capacity (MW

00.00 No
Rounding)
Flex
Category
RA Capacity
Effective Start
Date
(mm/dd/yyyy)
RA Capacity
Effective End
Date
(mm/dd/yyyy)
CMBLND_2_DS2SR2 0.29 4/1/2027 4/30/2027
CMBLND_2_DS2SR2 0.9 5/1/2027 5/31/2027
CMBLND_2_DS2SR2 25.51 6/1/2027 6/30/2027
CMBLND_2_DS2SR2 29.54 7/1/2027 7/31/2027
CMBLND_2_DS2SR2 29.54 8/1/2027 8/31/2027
CMBLND_2_DS2SR2 23.37 9/1/2027 9/30/2027
CMBLND_2_DS2SR2 9.54 10/1/2027 10/31/2027
CMBLND_2_DS2SR2 0.09 11/1/2027 11/30/2027
CMBLND_2_DS2SR2 0.09 12/1/2027 12/31/2027
WALNUT_6_HILLGEN 3.64 1/1/2027 1/31/2027
WALNUT_6_HILLGEN 3.61 2/1/2027 2/28/2027
WALNUT_6_HILLGEN 3.59 3/1/2027 3/31/2027
WALNUT_6_HILLGEN 3.56 4/1/2027 4/30/2027
WALNUT_6_HILLGEN 3.54 5/1/2027 5/31/2027
WALNUT_6_HILLGEN 3.51 6/1/2027 6/30/2027
WALNUT_6_HILLGEN 3.49 7/1/2027 7/31/2027
WALNUT_6_HILLGEN 3.47 8/1/2027 8/31/2027
WALNUT_6_HILLGEN 3.44 9/1/2027 9/30/2027
WALNUT_6_HILLGEN 3.42 10/1/2027 10/31/2027
WALNUT_6_HILLGEN 3.39 11/1/2027 11/30/2027
WALNUT_6_HILLGEN 3.37 12/1/2027 12/31/2027
ASTORA_2_SOLAR2 0.04 1/1/2027 1/31/2027
ASTORA_2_SOLAR2 0.04 2/1/2027 2/28/2027
ASTORA_2_SOLAR2 0.04 3/1/2027 3/31/2027
ASTORA_2_SOLAR2 0.14 4/1/2027 4/30/2027
ASTORA_2_SOLAR2 0.4 5/1/2027 5/31/2027
ASTORA_2_SOLAR2 12.75 6/1/2027 6/30/2027
ASTORA_2_SOLAR2 20.18 7/1/2027 7/31/2027
ASTORA_2_SOLAR2 16.44 8/1/2027 8/31/2027
ASTORA_2_SOLAR2 11.69 9/1/2027 9/30/2027
ASTORA_2_SOLAR2 4.77 10/1/2027 10/31/2027
ASTORA_2_SOLAR2 0.04 11/1/2027 11/30/2027
ASTORA_2_SOLAR2 0.04 12/1/2027 12/31/2027
BIGSKY_2_SOLAR7 0.05 1/1/2027 1/31/2027
BIGSKY_2_SOLAR7 0.05 2/1/2027 2/28/2027
BIGSKY_2_SOLAR7 0.05 3/1/2027 3/31/2027
BIGSKY_2_SOLAR7 0.12 4/1/2027 4/30/2027
BIGSKY_2_SOLAR7 0.05 5/1/2027 5/31/2027
BIGSKY_2_SOLAR7 10.63 6/1/2027 6/30/2027
BIGSKY_2_SOLAR7 16.83 7/1/2027 7/31/2027
BIGSKY_2_SOLAR7 13.7 8/1/2027 8/31/2027
BIGSKY_2_SOLAR7 9.74 9/1/2027 9/30/2027
BIGSKY_2_SOLAR7 3.98 10/1/2027 10/31/2027
BIGSKY_2_SOLAR7 0.05 11/1/2027 11/30/2027
BIGSKY_2_SOLAR7 0.05 12/1/2027 12/31/2027
2027 Resource Adequacy Plan
14 of 20
Resolution No. 2026-040

Page 18 of 24 ends

________________________
Report Type Annual
Report Date 8/31/2026
Name of Supplier: City of Vernon
Scheduling Coordinator: VERN
Person who prepared this RA Plan (Name): Efrain Sandoval (Text Field) Title: Principal Resource Scheduler/Trader (Text Field) Primary Contact
Name: Efrain Sandoval (Text Field)
Title: Principal Resource Scheduler/Trader (Text Field) Address: 4305 Santa Fe Ave. (Text Field)
Address 2: (Optional, Text Field)
City: Vernon (Text Field)
State: CA (Text Field)
Zip: 90058 (Numeric)
Telephone: (323) 826-1424 (Numeric)
Email [email protected] (Text Field)
Back-Up Contact
Name: Shawn Sharif (Text Field)
Title: Principal Resource Scheduler/Trader (Text Field) Telephone: (Numeric)
Email: [email protected] (Text Field)
Exhibit 5
2027 Resource Adequacy Plan
15 of 20
Resolution No. 2026-040

Page 19 of 24 ends

________________________
Resource ID in CAISO Master File
Local RA
Capacity (MW

00.00 No
Rounding)
System RA
Capacity (MW

00.00 No
Rounding)
Flexible RA
Capacity (MW

00.00 No
Rounding)
Flexible
Category
1,2,3
RA Capacity
Effective Start Date
(mm/dd/yyyy)
RA Capacity
Effective End Date
(mm/dd/yyyy)
SCID of
Load
Serving
Entity
VERNON_6_MALBRG 44 95 105 1 1/1/2027 1/31/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 2/1/2027 2/28/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 3/1/2027 3/31/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 4/1/2027 4/30/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 5/1/2027 5/31/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 6/1/2027 6/30/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 7/1/2027 7/31/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 8/1/2027 8/31/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 9/1/2027 9/30/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 10/1/2027 10/31/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 11/1/2027 11/30/2027 LVERN
VERNON_6_MALBRG 44 95 105 1 12/1/2027 12/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 1/1/2027 1/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 2/1/2027 2/28/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 3/1/2027 3/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 4/1/2027 4/30/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 5/1/2027 5/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 6/1/2027 6/30/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 7/1/2027 7/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 8/1/2027 8/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 9/1/2027 9/30/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 10/1/2027 10/31/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 11/1/2027 11/30/2027 LVERN
VERNON_6_GONZL1 5.75 5.75 1 12/1/2027 12/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 1/1/2027 1/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 2/1/2027 2/28/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 3/1/2027 3/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 4/1/2027 4/30/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 5/1/2027 5/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 6/1/2027 6/30/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 7/1/2027 7/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 8/1/2027 8/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 9/1/2027 9/30/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 10/1/2027 10/31/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 11/1/2027 11/30/2027 LVERN
VERNON_6_GONZL2 5.75 5.75 1 12/1/2027 12/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 1/1/2027 1/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 2/1/2027 2/28/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 3/1/2027 3/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 4/1/2027 4/30/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 5/1/2027 5/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 6/1/2027 6/30/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 7/1/2027 7/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 8/1/2027 8/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 9/1/2027 9/30/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 10/1/2027 10/31/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 11/1/2027 11/30/2027 LVERN
VERN_MEAD230_I_UC_IMS001 22 12/1/2027 12/31/2027 LVERN
VERN_WESTWING500_I_UC_IMS001 11.59 1/1/2027 1/31/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 2/1/2027 2/28/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 3/1/2027 3/31/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 4/1/2027 4/30/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 5/1/2027 5/31/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 6/1/2027 6/30/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 7/1/2027 7/31/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 8/1/2027 8/31/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 9/1/2027 9/30/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 10/1/2027 10/31/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 11/1/2027 11/30/2027 LVERN VERN_WESTWING500_I_UC_IMS001 11.59 12/1/2027 12/31/2027 LVERN 2027 Resource Adequacy Plan
16 of 20
Resolution No. 2026-040

Page 20 of 24 ends

________________________
Report Type Annual
Report Date 8/31/2026
Name of Supplier: City of Vernon
Scheduling Coordinator: VDGT
Person who prepared this RA Plan (Name): Efrain Sandoval (Text Field) Title: Principal Resource Scheduler/Trader (Text Field) Primary Contact
Name: Efrain Sandoval (Text Field)
Title: Principal Resource Scheduler/Trader (Text Field) Address: 4305 Santa Fe Ave. (Text Field)
Address 2: (Optional, Text Field)
City: Vernon (Text Field)
State: CA (Text Field)
Zip: 90058 (Numeric)
Telephone: (323) 826-1424 (Numeric)
Email [email protected] (Text Field)
Back-Up Contact
Name: Shawn Sharif (Text Field)
Title: Principal Resource Scheduler/Trader (Text Field) Telephone: (Numeric)
Email: [email protected] (Text Field)
Exhibit 6
2027 Resource Adequacy Plan
17 of 20
Resolution No. 2026-040

Page 21 of 24 ends

________________________
Resource ID in CAISO Master File
Local RA
Capacity (MW

00.00 No
Rounding)
System RA
Capacity (MW

00.00 No
Rounding)
Flexible RA
Capacity (MW

00.00 No
Rounding)
Flexible
Category
1,2,3
RA Capacity
Effective Start Date
(mm/dd/yyyy)
RA Capacity
Effective End Date
(mm/dd/yyyy)
SCID of
Load
Serving
Entity
CMBLND_2_DS2BT2 30 60 1 1/1/2027 1/31/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 2/1/2027 2/28/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 3/1/2027 3/31/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 4/1/2027 4/30/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 5/1/2027 5/31/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 6/1/2027 6/30/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 7/1/2027 7/31/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 8/1/2027 8/31/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 9/1/2027 9/30/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 10/1/2027 10/31/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 11/1/2027 11/30/2027 LVERN
CMBLND_2_DS2BT2 30 60 1 12/1/2027 12/31/2027 LVERN
CMBLND_2_DS2SR2 0.09 1/1/2027 1/31/2027 LVERN
CMBLND_2_DS2SR2 0.09 2/1/2027 2/28/2027 LVERN
CMBLND_2_DS2SR2 0.09 3/1/2027 3/31/2027 LVERN
CMBLND_2_DS2SR2 0.29 4/1/2027 4/30/2027 LVERN
CMBLND_2_DS2SR2 0.09 5/1/2027 5/31/2027 LVERN
CMBLND_2_DS2SR2 25.51 6/1/2027 6/30/2027 LVERN
CMBLND_2_DS2SR2 29.54 7/1/2027 7/31/2027 LVERN
CMBLND_2_DS2SR2 29.54 8/1/2027 8/31/2027 LVERN
CMBLND_2_DS2SR2 23.37 9/1/2027 9/30/2027 LVERN
CMBLND_2_DS2SR2 9.54 10/1/2027 10/31/2027 LVERN
CMBLND_2_DS2SR2 0.09 11/1/2027 11/30/2027 LVERN
CMBLND_2_DS2SR2 0.09 12/1/2027 12/31/2027 LVERN
2027 Resource Adequacy Plan
18 of 20
Resolution No. 2026-040

Page 22 of 24 ends

________________________
Exhibit 7
Effective
Flexible
Capacity
Flexible
Capacity
Category
(A) (B) (C)
1 Malburg Generating Station 105 1
2 H. Gonzalez 1 5.75 1
3 H. Gonzalez 2 5.75 1
A Designated flexible resource
B Designated Effective Flexible Capacity (Qualified Flexible Capacity by each Resource) C Designated Flexible Capacity Category
January - December 2027 Effective Flexible Capacity
2027 Resource Adequacy Plan
19 of 20
Resolution No. 2026-040

Page 23 of 24 ends

________________________
Exhibit 8
Min. Base
Flexibility
Requirement
Peak
Flexibility
Super
Peak
Flexibilty
Total Flexible
RA
Requirement
(A) (B) (C) (D) (E)
1 January 26.53 67.72 4.96 99.21
2 February 24.76 63.20 4.63 92.59
3 March 29.83 76.15 5.58 111.56
4 April 29.94 76.43 5.60 111.96
5 May 47.13 60.51 5.66 113.30
6 June 45.04 57.83 5.41 108.29
7 July 45.95 58.99 5.52 110.46
8 August 47.21 60.62 5.68 113.51
9 September 47.47 60.95 5.71 114.12
10 October 31.05 79.26 5.81 116.11
11 November 29.20 74.54 5.46 109.20
12 December 22.38 57.14 4.19 83.71
A Month
B Requirement for Category 1 - Base Ramping Resources
C Maximum allowed use of Category 2 - Peak Flexibility
D Maximum allowed use of Category 3 - Super Peak Flexibility E Total Flexible RA Requirement for City of Vernon
January - December 2027 Flexible RA Requirement
2027 Resource Adequacy Plan
20 of 20
Resolution No. 2026-040

Page 24 of 24 ends