Revisions to Agenda Items 11 & 18
Revision to Agenda Item #11
• Revised the Fiscal Impact and Discussion sections
of the staff report
o Fiscal Impact section now reads: The fiscal
impact for the additional changes to the
employee salary schedule and benefits is
included with the Mid-year 2021-2022 Budget
o Discussion section, under Changes to
Personnel, now reads: A total of 13 full-time
positions have been added, 4 full-time
positions were deleted, and there are 2 title
changes. The total authorized full-time
positions increased from 459 to 468 positions,
reflecting a net increase of 9 positions
• Revised the Summary of Changes to the Table of
Organization to reflect those additions as noted
above
• Revised Resolution No. 22-020 to reflect a total of
468 full-time positions
• Revised the Table of Organization to include
those additions as noted above
• Revised the Table of Compensation to include
those additions as noted above
Redline Version

Clean Version

Revision to Agenda Item #18
• Revised Attachment B
o This revision is a Detailed Scope of Work list
that summaries the scope of work contained
within the Phase 1 contract.

Victorville Wellness Center, Phase I
Detailed Scope of Work

1. Necessary General requirements during the construction of project up to 7/31/2022 (approx. 4 months from NTP) included.
a. Temporary Fences, Dumpsters, SWPPP& Erosion Control Implementation and QSP Inspection
b. Survey will be included as necessary: CMC will provide survey for design + Angeles will provide survey for finish grade
s

2. Earthwork
a. Includes Demolition and Site Clearing
b. Includes Rough & Finish Grading
c. Includes 10,000 CY of soils export only. Any additional excess dirt generated from excavation and grading will be stockpiled within the project site. d. Excludes any excavation, trenching, backfill & compaction for Phase II wo rk

3. Wet + Dry Utilities (On & Off-site)
a. Include all underground Utilities – Water, Sewer, Storm Drain, Fire & Gas b. Include irrigation main related scope, but this does not include irrigation lines in landscape plan
s
c. Include Secondary Sewer line scope from VVWRA (362 LF only & No new manhole and tie-ins to existing
)
d. Utilities are up to POC of each modular building(s)
e. No utility scope of work for Dog Kennel since the design is not done yet.

4. Electrical scope will include underground on-site work only (conduit & pull boxes) a. Excluding wiring
b. Exclude all off-site electrical scope, due to missing SCE design Clarifications & Exclusions
· All Phase II Work (Scope of Work not included above) including Dog Kennel relocation excluded.
· Any RFI & its response from 3/4/22 are excluded except for RFI Response # 40 with using 24” ABS SDR 35 pipe in lieu of 24” RCP
· No compaction at retention basin.
· General lift station will be excluded from Phase 1.
· Grease Interceptor will be excluded from Phase 1.
· Phase 1 scope of work is based on 3rd submittal set of drawings issued by Architect / Engineer on
3/1/22.
· Approximate duration for Phase 1 is 120 days from NTP issuance. Estimated dates of construction for Phase 1: April 1, 2022 to July 31, 2022. Schedule to be provided by Contractor for construction activity details.