ATTACHMENT A
RESOLUTION NO. 24-004
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF VICTORVILLE, CALIFORNIA, APPROVING THE ANNUAL AB 1600 DEVELOPMENT IMPACT FEE REPORT FOR FISCAL YEAR 2022-2023
WHEREAS, in 1987 the California State Legislature adopted AB 1600 which established Government Code § 66000-66025 (the “Mitigation Fee Act”, which has been subsequently amended) establishing a process by which local agencies may impose development impact fees and capacity charges on new development to finance various public improvements to mitigate the impacts of new development; and
WHEREAS, pursuant to the Mitigation Fee Act, the City Council of the City of Victorville (“City Council”) adopted Ordinance No. 1031 (as subsequently amended and currently codified in Victorville Municipal Code Section 16- 5.01.080) which established the authority to impose Development Impact Fees (“ DIF”) and Capacity Charges for Sewer and Water Improvements (“Capacity Charge(s)”) on new developments within the City to mitigate the impacts of development upon public infrastructure and various public facilities; and
WHEREAS, Government Code Sections 66006(a) and 66013(c) require all local agencies that collect DIF and Capacity Charges to deposit the fees into separate capital facility accounts in a manner that avoids commingling of DIF and Capacity Charges collected with other funds of the local agency; and
WHEREAS, Government Code Sections 66006(b)(1) and 66013(d) require all local agencies that collect DIF and Capacity Charges to make available for public review a report specifying information about the DIF and Capacity Charge accounts, including but not limited to the amount of fees/charges, the amount collected each year, a list of expenditures from the account, and the beginning and ending balances in each account, within 180 days after the last day of each fiscal year (the “AB 1600 Report”); and
WHEREAS, the City of Victorville (“ City”) hired NBS Government Finance Group to prepare the AB 1600 Report for Fiscal Year 2022- 2023, attached hereto as Exhibit A, which substantially contains the information required by Government Code Sections 66006(b)(1) and 66013(d) and has been made available for public review.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF VICTORVILLE DOES HEREBY RESOLVE AS FOLLOWS.
SECTION 1. The recitals set forth above are true and correct and are incorporated into this Resolution by reference together with any definitions set forth therein.
SECTION 2. The City Council has conducted a public meeting, pursuant to Government Code Section 66006(b)(2), to review the AB 1600 Report for Fiscal Year 2022- 2023, attached hereto as Exhibit A, and incorporated herein by this reference.
SECTION 3. Upon review of the AB 1600 Report for Fiscal Year 2022- 2023, the City Council finds that the report contains the information required by Government Code Sections 66006(b)(1) and 66013(d) and outlines the required findings relative to Government Code Section 66001(d)(1), which are incorporated herein by this reference.
SECTION 4. That this Resolution shall take effect immediately upon its adoption.
SECTION 5. The City Clerk shall certify to the passage an adoption of this Resolution; shall enter the same in the book of original resolutions; and shall make a minute of passage and adoption thereof in the records of the proceedings, in the minutes of the meeting at which this Resolution is passed and adopted.
EXHIBIT A
Annual Development Impact Fee Report
Fiscal Year Ended June 30, 2023
December 21 , 2023
Prepared by:
NBS
for the
CITY OF VICTORVILLE
City of Victorville
C
ity Officials
Elizabeth Becerra, Mayor
Blanca Gomez, Council Member
Bob Harriman, Council Member
Leslie Irving, Council Member
Debra Jones, Council Member
Officers
Jennifer Thompson, City Clerk
A
dministrative Team
Keith Metzler, City Manager
Jenele Davidson, Deputy City Manager
Sophie Smith, Deputy City Manager
Andre De Bortnowsky, City Attorney
Carmen Cun, Director of Finance/City Treasurer
TABLE OF CONTENTS
Development Impact Fee Report ........................................................................ ................................................... ........................... 1
1.1 Annual Report ........................................................................................................... 1
1.2 Five-Year Report ........................................................................................................ 2 Current Impact Fees & Capacity Charges ................................................................. ................................................... ....................... 4
2.1 Types of Impact Fees, Capacity Charges and Associated Funds ............................... 4
2.2 Current Fee Schedule ................................................................................................ 6 Financial Summary Report.............................................................................. ................................................... ............................... 7 Public Improvements .................................................................................. ................................................... .................................. 8 Interfund Loans ...................................................................................... ................................................... ..................................... 10 Refunds ........................................... ................................................... ................................................... ........................................ 11
Attachment 1 - Development Impact Fees Master Fee Schedule in effect between July 1, 2022, and December 31, 2022 Attachment 2 - Development Impact Fees Master Fee Schedule in effect between January 1, 2023, and June 30, 2023
City of Victorville 1
Annual Development Impact Fee Report
Prepared by NBS
DEVELOPMENT IMPACT FEE REPORT
The California Mitigation Fee Act (Government Code Sections 66000 et seq.) mandates procedures for administration of impact fee programs, including collection and accounting, reporting, and refunds. Regarding reporting requirements, the Mitigation Fee Act requires annual reporting for each impact fee fund, and a separate five-year reporting process. This report meets the requirements described in 1.1 Annual Report, below. A combined Annual and Five-Year Report will be provided in future years when needed to meet required reporting timelines.
1.1 Annual Report
Section 66006 (b) (1) requires that once each year, within 180 days of the close of the fiscal year, the local agency must make available to the public the following information for each separate account established to receive impact fee revenues:
1. A brief description of the type of fee in the account or fund; (report section 2)
2. The amount of the fee; (report section 2 and attachment)
3. The beginning and ending balance of the account or fund; (report section 3)
4. The amount of the fees collected and interest earned; (report section 3)
5. Identification of each public improvement on which fees were expended and the amount of the expenditures on each improvement, including the percentage of the cost of the public improvement that was funded with fees; (report section 4)
6. Identification of the approximate date by which the construction of a public improvement will commence, if the City determines sufficient funds have been collected to complete financing of an incomplete public improvement; An identification of each public improvement identified in a previous report and whether construction began on the approximate date noted in the previous report. For a project identified pursuant for which construction did not commence by the approximate date provided in the previous report, the reason for the delay and a revised approximate date that the local agency will commence construction . (report section 4)
7. A description of each inter-fund transfer or loan made from the account or fund, including interest rates, repayment dates, and a description of the improvement on which the transfer or loan will be expended; (report section 5)
8. The amount of any refunds or allocations made pursuant to Section 66001, paragraphs (e) and (f). (report section 6)
The annual report must be reviewed by the City Council at its next regularly scheduled public meeting, but not less than 15 days after the statements are made public, per Section 66006 (b) (2).
City of Victorville 2
Annual Development Impact Fee Report
Prepared by NBS
Section 66013(d) has similar requirements for capacity charges in that, within 180 days after the close of each fiscal year, the local agency must make available to the public the following information:
1. A description of the charges deposited in the fund; ( report section 2)
2. The beginning and ending balance of the fund and the interest earned from investment of moneys in the fund; (report section 3)
3. The amount of charges collected in that fiscal year; (report section 3)
4. An identification of:
a. Each public improvement on which charges were expended and the amount of expenditure for each improvement, including the percentage of the total cost of the public improvement that was funded with those charges if more than one source of funding was used; (report section 4)
b. Each public improvement on which charges were expended that was completed during that fiscal year; (report section 4) c. Each public improvement that is anticipated to be undertaken in the following fiscal year; (report section 4)
5. A description of each interfund transfer or loan made from the capital facilities fund, including the public improvement on which the transferred or loaned charges are or will be expended and, in the case of an interfund loan, the date on which the loan will be repaid and the rate of interest that the fund will receive on the loan. (report section 6 )
1.2 Five-Year Report
Prior to 1996, The Mitigation Fee Act required that a local agency collecting impact fees was required to expend or commit impact fee revenue within five years or make findings to justify a continued need for the money. Otherwise, those funds had to be refunded. SB 1693, adopted in 1996 as an amendment to the Mitigation Fee Act, changed that requirement in material ways.
Now, Section 66001 (d) requires that, for the fifth fiscal year following the first deposit of any impact fee revenue into an account or fund as required by Section 66006 (b), and every five years thereafter, the local agency shall make all of the following findings for any fee revenue that remains unexpended, whether committed or uncommitted:
1. Identify the purpose to which the fee will be put;
2. Demonstrate the reasonable relationship between the fee and the purpose for which it is charged;
3. Identify all sources and amounts of funding anticipated to complete financing of incomplete improvements for which impact fees are to be used;
City of Victorville 3
Annual Development Impact Fee Report
Prepared by NBS
4. Designate the approximate dates on which the funding necessary to complete financing of those improvements will be deposited into the appropriate account or fund.
Those findings are to be made in conjunction with the annual reports discussed above. If such findings are not made as required by Section 66001, the local agency could be required to refund the moneys in the account or fund, per Section 66001 (d).
Once the agency determines that sufficient funds have been collected to complete financing on incomplete improvements for which impact fee revenue is to be used, it must, within 180 days of that determination, identify an approximate date by which construction of the public improvement will be commenced (Section 66001 (e)). If the agency fails to comply with that requirement, it must refund impact fee revenue in the account according to procedures specified in Section 66001 (d).
City of Victorville 4
Annual Development Impact Fee Report
Prepared by NBS
CURRENT IMPACT FEES & CAPACITY CHARGES
Development impact fees (DIFs) in the City of Victorville are one-time charges levied on new development in Victorville to fund various infrastructure, facilities, vehicles, and equipment. The basis for these impact fees is presented in the several development impact fee study reports:
Development Impact Fee Justification Study, Regional Drainage Facilities, (Drainage DIF Report), competed by DTA on May 9, 2022 and adopted by City Council June 7, 2022
Development Impact Fee Study, Final Report (NBS DIF Report) completed by NBS on May 6, 2022. Fees documented in the DIF Report were adopted by City Council on June 7, 2022 and were effective during the majority of Fiscal Year 2022-23.
2.1 Types of Impact Fees, Capacity Charges and Associated Funds The fees documented in the body of this Annual Development Impact Fee Report (Report) include the following fees listed below. The revenue and expenditures for each fee type is tracked by the City in a separate fund.
Table 1. Impact Fees and Impact Fee Funds
Fund No. Facility Fee Name Purpose and Use of the Fee
350 Public Buildings
The purpose of the Public Buildings Impact Fee is to mitigate the impact of new development on the need for public buildings and general government vehicles and equipment in Victorville. Impact fees will be used to provide additional public buildings, vehicles, and equipment to mitigate the impact of new development on the need for those facilities in the City. 351 Fire Safety
The purpose of Fire Protection Facilities Impact Fee is to mitigate the impact of new development on the need for fire facilities provided by the City of Victorville. Impact fees will be used to provide additional fire facilities to mitigate the impact of new development on the need for those facilities in the City.
City of Victorville 5
Annual Development Impact Fee Report
Prepared by NBS
Fund No. Facility Fee Name Purpose and Use of the Fee
352 Roads
The purpose of the Road Improvements Impact Fee is to mitigate the impact of new development on the need for road, bridge, interchange and traffic signal improvements in Victorville. Impact fees calculated in this chapter will be used to provide additional road, bridge, interchange and traffic signal improvements to mitigate the impact of new development on the need for those facilities in the City. The list of eligible improvement projects for roadway projects is included in Table 9.1 of the DIF Report.
Note funds 355 and 356, are reported as combined with Fund 352. The purpose of the Fund 355 Nisqualli impact fee is to mitigate the impact of new development within an area served by the I-15 / Nisqualli Rd. / La Mesa Rd. Interchange. Impact fees have been and will be used to pay for the interchange improvements. The purpose of the Fund 356 Goodwill impact fee is to mitigate the impact of new development within an area served by the Goodwill (I-15 / Roy Rogers) Interchange.
Impact fees have been and will be used to pay for the interchange improvements. 353 Police
The purpose of Police Facilities Impact Fee is to mitigate the impact of new development on the need for police facilities in Victorville. Impact fee funding will be used to provide additional police facilities to mitigate the impact of new development on the need for those facilities in the City. 354 Parks and Recreation
The purpose of the Parks and Recreation Facilities Impact Fee is to mitigate the impact of new development on the need for parks and recreation facilities in Victorville. Fee revenues will be used to fund additional parks and recreation facilities to mitigate the impacts of new development in the City.
357 Storm Drainage
The purpose of the Storm Drainage Impact Fee is to ensure that all new development pays its fair share of cost of new infrastructure. Impact fee funds will finance new development’s share of future drainage facilities to meet the demands of new development in the City through 2050. The list of eligible improvement projects for storm drainage impact fee funding is included in Appendix A of the Drainage DIF Report.
City of Victorville 6
Annual Development Impact Fee Report
Prepared by NBS
Fund No. Facility Fee Name Purpose and Use of the Fee
414 and 415 Water System Improvements
Water Capacity Charges are one-time charges to new development connecting to the City of Victorville/Victorville Water District’s water system. System improvements include water distribution pipelines, additional operational and emergency reservoir storage and additional ground water wells. The list of eligible improvement projects for water capacity fee funding is included in Tables 8.1 and 8.4 of the NBS DIF Report.
A component of the Water Capacity Charges also includes the cost of acquiring rights to additional ground water or alternative sources of supply. The water rights component of the overall water system capacity charge will be used to acquire additional ground water rights, or to purchase permanent supplemental water if ground water rights are not available. Revenues may also be used for projects and technology that would provide permanent supplemental water to the basin in lieu of ground water rights.
425 Sewer
The purpose of the sewer capacity charge is to fund the new connections attributable to the impact from new development. Sewer Capacity Charges are one-time charges to new development or existing development first connecting to the City of Victorville’s sewer system. The list of eligible planned capital projects funded by sewer capacity charges is shown in the NBS DIF Report, Appendix D, Figure 6.
2.2 Current Fee Schedule
During Fiscal Year 2022-23, the Victorville City Council adopted Resolutions 22-055 and VWD 22-008 on June 7, 2022, which included a Development Impact Fee Study and updated Master Fee Schedule, and a phased in approach to update fees to the full amount identified in the study. Prior to January 1, 2023, the City’s impact fees that were established in the “Development Impact Fee 2006 Update Study” (2006 Study) report, completed by AGAJANIAN & Associates remained in effect.
Attachment 1 to this report includes Victorville’s Development Impact Fee Schedule in effect between July1, 2022, and December 31, 2022 Attachment 2 to this report includes Victorville’s Development Impact Fee Schedule in effect between January 1, 2023, and June 30, 2023
City of Victorville 7
Annual Development Impact Fee Report
Prepared by NBS
FINANCIAL SUMMARY REPORT
The following financial summary provides an annual statement of revenues, and changes in fund balance for each impact fee fund, for the Fiscal Year End June 30, 2023. Figures shown in the table below are unaudited as of the date of this report.
Table 2. Financial Summary Fiscal Year 2023
Fund No. 350 351 352 353 354 357 414, 415 416
Description
Public
Buildings Fire Safety Roads Police
Parks and
Recreation Storm Drain Water Sewer
REVENUES
Fees 787,252 161,172 3,238,508 79,071 2,188,256 189,695 1,974,075 2,097,200 Interest 6,582 10,225 122,405 21,828 377,944 55,118 188,754 43,005 Total Revenues 793,833 171,397 3,360,912 100,899 2,566,200 244,813 2,162,829 2,140,205 Fund Balance, Beginning of the Year 1 (717,,280)09 416,,75654 72,9060 1 ,37,8503 1,642,6033 5,4220,28 ,9187 ,4435 - Fund Balance, End of the Year 1
(713,,185)81 312,,68188 44,3043 1 ,38,8592 1,809,4300 5,9602,49 ,1234 ,3333 ,241,5002 3 Beginning&Ending Fund Balance per financial reports provided by the City's Finance Department.
City of Victorville 8
Annual Development Impact Fee Report
Prepared by NBS
PUBLIC IMPROVEMENTS
This section of the Annual Report identifies each public improvement on which fees were expended and the amount of the expenditures on each improvement, including the percentage of the cost of the public improvement that was funded with fees.
Table 3. Public Improvements Fiscal Year 2023
Government Code Section 66006 (b)(1)(F)(i) also requires Identification of the approximate date by which the construction of a public improvement will commence, if the City determines sufficient funds have been collected to complete financing of an incomplete public improvement.
The City has identified public improvement projects that have sufficient impact fee funds available to complete, including approximate dates (fiscal year) of construction, as follows:
Fund: 354 Parks
Project: 81032 Sports Complex Feasibility Study
o Project Start: Fiscal Year 2022-23
o Project Finish: Fiscal Year 2024-25
o Total Project Funding: $100,000, 100% DIF
Fund Fund
Name Proj. # Project Name Project
Start
Project
Finish
Project
Phase
Total Project
Funding
Total Impact
Fee Funded
Amount
% Impact
Fee Funded
Total Prior
Year Impact
Fee
Expenditures
FY 2023 Impact
Fee
Expenditures
Impact Fee
Funding
Remaining
352 Road 60005 NISQ/I15 INTERCHANGE-ST CONST Ongoing O ngoing Active $ $ 40,906,88430,826,722 47% $ $ 30,826,722 65,722 $ )65,72(2 352 Road 30013 Green Tree Blvd Extension FY 2021/22 FY 2022/23 Completed $ $ 46,705,50839,350,091 24% $ $ 88,201,99 15,910,45 $ 45,139,63 352 Road 60014 Bear Valley Road Bridge over BNSF Rail way FY 2021 FY 2024 Active $ $ 76,123,932 04,130,74 20% $ $ 82,244,7108,7357 $ 23,150,22 352 Road NA Local Traffic Signal Improvements Ongoing O ngoing Active $ $ 00,041,48100,041,481 100% $ $ 80-,851 $ 29,189,381 354 Parks 81033 Brentwood Restroom FY 2022/23 FY 2022/2 3 Completed $ $ 00,005300,0053 100% $ $ 21,7242 - $ 88,2701 354 Parks 81034 Eagle Ranch Restroom FY 2022/23 FY 2024 /25 Active $ $ 00,005300,0053 100% $ $ - 719 $ 38,0943 354 Parks 80058 Hook Track Lighting FY 2022/23 FY 2024/ 25 Active $ $ 00,003500,0035 100% $ $ 06-,558 $ 04,4444 354 Parks 81005 New Shade Structure FY 2022/23 FY 2022/ 23 Completed $ $ 00,005100,0051 100% $ $ 69,9531 - $ 40,041 414 Water 74419 Project Area 31- Pipeline Replacement F Y 2021/22 FY 2022/23 Completed $ $ 00,005,51 84,8996 45% $ $ 14,8396 392 $ 51,75 $ $ 53,878,6471 $48,156,966 36,172,433 ,38 $ $ 96,734 252,49,152 Development Impact Fees
TOTAL
City of Victorville 9
Annual Development Impact Fee Report
Prepared by NBS
Project: 81004 Dog Park
o Project Start: Fiscal Year 2022-23
o Project Finish: Fiscal Year 2024-25
o Total Project Funding: $150,000, 100% DIF
Project: 81006 New Rectangular Fields
o Project Start: Fiscal Year 2022-23
o Project Finish: Fiscal Year 2024-25
o Total Project Funding: $350,000, 100% DIF
Project: 81008 New Walking Path
o Project Start Date: Fiscal Year 2024-25
o Project Finish: Fiscal Year 2025-26
o Total Project Funding: $150,000, 100% DIF
Government Section 66013(d) has similar requirements for water and wastewater capacity charges to identify each public improvement that is anticipated to be undertaken in the following fiscal year. There will be one future project funded from Fund 414 - Water Capacity Charges in the amount of $4.3 Million for 74338 Pipeline - Area 28 - MWA Turnout #5, to be completed by December 2025, this project will be added during the mid-year Capital Improvement Project budgeting process for Fiscal Year 2024.
C
ity of Victorville 10
Annual Development Impact Fee Report
Prepared by NBS
I NTERFUND LOANS
The Mitigation Fee Act requires a description of each inter-fund transfer or loan made from the account or fund, including interest rates, repayment dates, and a description of the improvement on which the transfer or loan will be expended. There were no new interfund transfers or loans made between impact fee funds in Fiscal Year 2022-23.
Table 4. Fiscal Year 2023 Interfund Loan Statuses
Date of
Loan
Maturity
Date Purpose of Loan
Original
Advance Lender Borrower
Balance
06/30/2023
Interest
Rate 1
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 7,725,000 352 Roads 350 Public Buildings $ 7,030,226 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 1,150,000 353 Public Safety 350 Public Buildings $ 1,046,571 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 4,375,000 354 Recreation 350 Public Buildings $ 3,981,520 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 570,000 352 Roads 350 Public Buildings $ 518,735 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 920,000 352 Roads 350 Public Buildings $ 837,257 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 3,675,000 357 Storm Drain DIF 350 Public
Buildings $ 3,344,477 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 280,000 358 Street Lighting 350 Public Buildings $ 254,817 1.37%
06/30/11 06/30/26 City Hall Expansion Project #98005 $ 395,000 359 Fire Hydrant 350 Public Buildings $ 359,474 1.37%
City of Victorville 11
Annual Development Impact Fee Report
Prepared by NBS
REFUNDS
The refunding requirements for the Mitigation Fee Act are summarized as follows:
Refunds under the Mitigation Fee Act: If the City determines that sufficient funds have been collected to complete financing on incomplete improvements for which impact fee revenue is to be used, it must, within 180 days of that determination, identify an approximate date by which construction of the public improvement will be commenced (Government Code Section 66001 (e)). If the agency fails to comply with that requirement, it must refund impact fee revenue in the account according to procedures specified in Section 66001 (d).
As discussed in Section 4 of this report, throughout the Fiscal Year 2022-2023 the City has made progress on several active public improvement projects that are funded by impact fees. Also, through the 2023-24 budgeting process, the City made a determination regarding sufficient funds collected to complete several improvements and a construction schedule has been identified. Therefore, no refunds were made or required.
Disclaimer: In preparing this report and any analys is and findings included herein, NBS has relied on several principal assumptions and considerations re garding financial matters, conditions and events th at occurred or may occur in the future. This informat ion and assumptions, including the City’s budgets, financial reports, capital project data, and other information were provided by sources we believe to be reliable; however, NBS has not independently verifi ed such information and assumptions. While we belie ve NBS’ use of such information and assumptions is reasonable for the purpose of this report, some assumptions will invariably not materialize as stat ed herein and may vary due to unanticipated events and circumstances.
_______________________________________________________________________________________ City of Victorville
ATTACHMENT 1
_______________________________________________________________________________________
City of Victorville Development Impact Fees Master Fee Schedule in effect between July 1, 2022, and December 31, 2022
1 City of Victorville
Development Department
Planning
Building
BUILDING FEES
In order to assist you in
estimating
the permit fees for your project, several tables and charts have been compiled and are included in this package. By following the steps listed below, a reasonable estimate may be made.
THE FOLLOWING BUILDI
NG VALUATION DATA RE
ADJUSTED ANNUALLY AS
RELEASED BY THE INTE
OF PERMIT FEES.
STEP 1
–
Find the type of project below and determine the value per square foot. Multiply this figure by the This will be the project valuation.
Typical single family dwellings are Type 5B construction.
Construction Group
1A
R
-
2 Residential, multi
-
family
$165.05
R
-
3 Residential, one
-
and two
-
family
$154.04
R
-
4 Residential, care/assist. living
facility
$194.98
U Garages
$83.66
All Occupan
c
ies
–
Sprinklers
$
2. 40
All Occupancies
–
Porch / Patio
$
20.20 STEP 2
–
Find the valuation of the project on page 2, and then add the fees for plan review and construction permit. Determine the St Motion Implementation Program (SMIP) fee and add to the total, as follows:
$5,000 valuation = .50 SMIP;
STEP 3
–
Review page 3 for miscellaneous plumbing, electrical, and mechanical fees.
Note that a separate permit is required for each independent structure, even Additional Fees
D
evelopment Impact Fee
s
-
$
11,327.00
per single
parks, roads, and public safety capital improvement costs.
Development Impact Fee Type
Single Family Cost
Facilities
Fire
Parks
Police
Roads
Victor Val
ley Water Reclamation Authority (VVWRA)
f
ees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 4.
Sewer
Capacity
Fees
–
Fees are generally figured at a minimum of $350.00 per house connection.
Water Connection Fees
–
Please contact
the Engineering Department for questions regarding costs.
Other Special Assessments
–
Depending on the location of the project, there may also be special assessment fees to cover storm drains, bridges, road widening, street lighting, and fire hydrant insta regarding special assessment districts.
School District Fees
–
A Certificate of Compliance from the school district must be submitted to the Development Department.
Technology Fee
–
M
ultiply the Plan Review, Building Permit, Mechanical Permit, Electrical Permit, and Plumbing Permit fees by 4.8% (.048) to determine the Technology Fee.
Green Building Fee
–
Senate Bill 1473 which provides for the creation of the Building Standards $1
–
25,000
$25,001
–
50,000
$50,001
–
75,000
$75,001
–
100,000
Every $25,000 or fraction thereof above $100,000
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
RESIDENTIAL
the permit fees for your project, several tables and charts have been compiled and are included in this package. By following the steps listed below, a reasonable estimate may be made.
NG VALUATION DATA RE
PRESENTS AVERAGE COS
TS FOR MO
ST BUILDINGS. THIS
RELEASED BY THE INTE
RNATIONAL CODE COUNC
IL AND USED SOLELY F
Find the type of project below and determine the value per square foot. Multiply this figure by the
total square footage of the project.
Typical single family dwellings are Type 5B construction.
Construction Type
1B
2A
2B
3A
3B
$165.05
$158.44
$152.98
$145.27
$132.00
$127.61
$145.37
$154.04
$149.85
$145.98
$142.32
$137.11
$133.50
$139.93
$194.98
$188.36
$182.90
$175.20
$161.40
$157.01
$175.29
$83.66
$79.00
$74.06
$70.37
$63.47
$59.32
40 $
2. 40
$
2.40 $
2.40 $
2.40 $
2.40 20.20
$
20.20 $
20.20 $
20.20 $
20.20 $
20.20 Find the valuation of the project on page 2, and then add the fees for plan review and construction permit. Determine the St Motion Implementation Program (SMIP) fee and add to the total, as follows:
$5,000 valuation = .50 SMIP;
$5,000 valuation x .0001
3 (.00028 if over 3 stories)
= SMIP
Review page 3 for miscellaneous plumbing, electrical, and mechanical fees.
Note that a separate permit is required for each independent structure, even though they may be located on the same parcel.
per single
-
family dwelling unit, and $
7,639.00
per multi
-
family dwelling unit. This fee is used for
parks, roads, and public safety capital improvement costs.
Following is a break
-
down of these fees:
Single Family Cost
per
Dwelling Unit
Multi Family Cost
$1,334.35
$328.81
$5,045.87
$139.07
$4,469.90
ley Water Reclamation Authority (VVWRA)
or
Industrial Waste Water Treatment Plant
(IWWTP)
Fees
ees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 4.
Fees are generally figured at a minimum of $350.00 per house connection.
the Engineering Department for questions regarding costs.
Depending on the location of the project, there may also be special assessment fees to cover storm drains, bridges, road widening, street lighting, and fire hydrant insta llation. Please contact the
Development Department
A Certificate of Compliance from the school district must be submitted to the Development Department. ultiply the Plan Review, Building Permit, Mechanical Permit, Electrical Permit, and Plumbing Permit fees by 4.8% (.048) to Senate Bill 1473 which provides for the creation of the Building Standards Administration Special Revolving Fund.
Permit Valuation
Fee
$1
$2
$3
$4
Every $25,000 or fraction thereof above $100,000
Add $1
Updated
1/30/2019
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760)
269
-
0073
the permit fees for your project, several tables and charts have been compiled and are included in this ST BUILDINGS. THIS
CHART IS
IL AND USED SOLELY F
OR THE DETERMINATION
total square footage of the project.
4 –
HT
5 A
5 B
$145.37
$115.18
$110.68
$139.93
$128.29
$120.75
$175.29
$144.58
$140.08
$67.24
$50.19
$47.80
$
2.40 $
2.40 $
2.40 $
20.20 $
20.20 $
20.20 Find the valuation of the project on page 2, and then add the fees for plan review and construction permit. Determine the St rong
= SMIP
though they may be located on the same parcel.
family dwelling unit. This fee is used for
Multi Family Cost
per
Dwelling Unit
$716.95
$232.13
$3,847.12
$98.18
$2,744.62
Fees
–
VVWRA
and
IWWTP
ees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 4.
Depending on the location of the project, there may also be special assessment fees to cover storm drains, Development Department
for more information
A Certificate of Compliance from the school district must be submitted to the Development Department.
ultiply the Plan Review, Building Permit, Mechanical Permit, Electrical Permit, and Plumbing Permit fees by 4.8% (.048) to Administration Special Revolving Fund.
2 City of Victorville
Development Department
Planning
Building
BUILDING FEES
Total Valuation
Plan
Review
Permit
Total Valuation
$1.00
-
$2,000.00
$29.25
$45.00
$270,001.00
$2,001.00
-
$5,000.00
$46.80
$72.00
$275,001.00
$5,001.00
-
$10,000.00
$76.05
$117.00
$280,001.00
$10,001.00
-
$15,000.00
$105.30
$162.00
$285,001.00
$15,001.00
-
$20,000.00
$134.55
$207.00
$290,001.0
$20,001.00
-
$25,000.00
$163.80
$252.00
$295,001.00
$25,001.00
-
$30,000.00
$184.93
$284.50
$300,001.00
$30,001.00
-
$35,000.00
$206.05
$317.00
$305,001.00
$35,001.00
-
$40,000.00
$227.18
$349.50
$310,001.00
$40,001.00
-
$45,000.00
$248.30
$382.00
$315,001.0
$45,001.00
-
$50,000.00
$269.43
$414.50
$320,001.00
$50,001.00
-
$55,000.00
$284.05
$437.00
$325,001.00
$55,001.00
-
$60,000.00
$298.68
$459.50
$330,001.0
$60,001.00
-
$65,000.00
$313.30
$482.00
$335,001.00
$65,001.00
-
$70,000.00
$327.93
$504.50
$340,001.0
$70,001.00
-
$75,000.00
$342.55
$527.00
$345,001.00
$75,001.00
-
$80,000.00
$357.18
$549.50
$350,001.00
$80,001.00
-
$85,000.00
$371.80
$572.00
$355,001.0
$85,001.00
-
$90,000.00
$386.43
$594.50
$360,001.00
$90,001.00
-
$95,000.00
$401.05
$617.00
$365,001
$95,001.00
-
$100,000.00
$415.68
$639.50
$370,001.00
$100,001.00
-
$105,000.00
$427.05
$657.00
$375,001.00
$105,001.00
-
$110,000.00
$438.43
$674.50
$380
,001.00
$110,001.00
-
$115,000.00
$449.80
$692.00
$385,001.00
$115,001.00
-
$120,000.00
$461.18
$709.50
$390
,001.00
$120,001.00
-
$125,000.00
$472.55
$727.00
$395,001.00
$125,001.00
-
$130,000.00
$483.93
$744.50
$400,001.00
$130,001.00
-
$135,000.00
$495.30
$762.00
$405,001.00
$135,001.00
-
$140,000.00
$506.68
$779.50
$410,001.00
$140,001.00
-
$145,000.00
$518.05
$797.00
$415
,001.00
$145,001.00
-
$150,000.00
$529.43
$814.50
$420,001.00
$150,001.00
-
$155,000.00
$540.80
$832.00
$425,001.00
$155,001.00
-
$160,000.00
$552.18
$8
49.50 $430,001.00
$160,001.00
-
$165,000.00
$563.55
$867.00
$435,001.00
$165,001.00
-
$170,000.00
$574.93
$884.50
$440
,001.00
$170,001.00
-
$175,000.00
$586.30
$902.00
$445,001.00
$175,001.00
-
$180,000.00
$597.68
$919.50
$450,001.00
$180,001.00
-
$185,000.00
$609.05
$9
37.00 $455,001.00
$185,001.00
-
$190,000.00
$620.43
$954.50
$460,001.00
$190,001.00
-
$195,000.00
$631.80
$972.00
$465
,001.00
$195,001.00
-
$200,000.00
$643.18
$989.50
$470,001.00
$200,001.00
-
$205,000.00
$654.55
$1,007.00
$475,001.00
$205,001.00
-
$210,000.00
$665
.93
$1,024.50
$480,001.00
$210,001.00
-
$215,000.00
$677.30
$1,042.00
$485,001.00
$215,001.00
-
$220,000.00
$688.68
$1,059
.50
$490,001.00
$220,001.00
-
$225,000.00
$700.05
$1,077.00
$495,001.00
$225,001.00
-
$230,000.00
$711.43
$1,094.50
$500,001.00
$230,001.00
-
$235,000.00
$722.80
$1,112.00
$510,001.00
$235,001.00
-
$240,000.00
$734.18
$1,129.50
$520,001.00
$240,001.00
-
$245,000.00
$745.55
$1,14
7.00 $530,001.00
$245,001.00
-
$250,000.00
$756.93
$1,164.50
$540,001.00
$250,001.00
-
$255,000.00
$768.30
$1,182.00
$550,001.00
$255
,001.00
-
$260,000.00
$779.68
$1,199.50
$560,001.00
$260,001.00
-
$265,000.00
$791.05
$1,217.00
$570,001.00
$265,001.00
-
$270,000.00
$802.43
$1,2
34.50 $580,001.00
*B
UILDINGS PROVIDED WITH AUTOMATIC SPRINKLER SYST
WILL BE GIVEN AN ADDITIONAL
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
RESIDENTIAL
Project Valuation
Total Valuation
Plan
Review
Permit
Total Valuation
$270,001.00
-
$275,000.00
$813.80
$1,252.00
$590,001.00
-
$600,000.00
$275,001.00
-
$280,000.00
$825.18
$1,269.50
$600,001.00
-
$610,000.00
$280,001.00
-
$2
85,000.00
$836.55
$1,287.00
$610,001.00
-
$620,000.00
$285,001.00
-
$290,000.00
$847.93
$1,304.50
$620,001.00
-
$630,000.00
$290,001.0
0 -
$295,000.00
$859.30
$1,322.00
$630,001.00
-
$640,000.00
$295,001.00
-
$300,000.00
$870.68
$1,339.50
$640,001.00
-
$650,000.00
$300,001.00
-
$305,000.00
$882.05
$1,357.00
$650,001.00
-
$660,000.00
$305,001.00
-
$310,000.00
$893.43
$1,374.50
$660,001.00
-
$670,000.00
$310,001.00
-
$315,000.00
$904.80
$1,392.00
$670,001.00
-
$680,000.00
$315,001.0
0 -
$320,000.00
$916.18
$1,409.50
$680,001.00
-
$690,000.00
$320,001.00
-
$325,000.00
$927.55
$1,427.00
$690,001.00
-
$700,000.00
$325,001.00
-
$330,000.00
$938.93
$1,444.50
$700,001.00
-
$710,000.00
$330,001.0
0 -
$335,000.00
$950.30
$1,462.00
$710,001.00
-
$720,000.00
$335,001.00
-
$340,000.00
$961.68
$1,479.50
$720,001.00
-
$730,000.00
$340,001.0
0 -
$345,000.00
$973.05
$1,497.00
$730,001.00
-
$740,000.00
$345,001.00
-
$350,000.00
$984.43
$1,514.50
$741,001.00
-
$750,000.00
$350,001.00
-
$355,000.00
$995.80
$1,532.00
$750,001.00
-
$760,000.00
$355,001.0
0 -
$360,000.00
$1,007.18
$1,549.50
$760,001.00
-
$770,000.00
$360,001.00
-
$365,000.00
$1,018.55
$1,567.00
$770,001.00
-
$780,000.00
$365,001
.00
-
$370,000.00
$1,029.93
$1,584.50
$780,001.00
-
$790,000.00
$370,001.00
-
$375,000.00
$1,041.30
$1,602.00
$790,001.00
-
$800,000.00
$375,001.00
-
$380,000.00
$1,052.68
$1,619.50
$800,001.00
-
$810,000.00
,001.00
-
$385,000.00
$1,064.05
$1,637.00
$810,001.00
-
$820,000.00
$385,001.00
-
$390,000.00
$1,075.43
$1,654.50
$820,001.00
-
$830,000.00
,001.00
-
$395,000.00
$1,086.80
$1,672.00
$830,001.00
-
$840,000.00
$395,001.00
-
$400,000.00
$1,098.18
$1,689.50
$840,001.00
-
$850,000.00
$400,001.00
-
$405,000.00
$1,109.55
$1,707.00
$850,001.00
-
$860,000.00
$405,001.00
-
$410,000.00
$1,120.93
$1,724.50
$860,001.00
-
$870,000.00
$410,001.00
-
$415,000.00
$1,132.30
$1,742.00
$870,001.00
-
$880,000.00
,001.00
-
$420,000.00
$1,143.68
$1,759.50
$880,001.00
-
$890,000.00
$420,001.00
-
$425,000.00
$1,155.05
$1,777.00
$890,001.00
-
$900,000.00
$425,001.00
-
$430,000.00
$1,166.43
$1,794.50
$900,001.00
-
$910,000.00
$430,001.00
-
$435,000.00
$1,177.80
$1,812.00
$910,001.00
-
$
920,000.00
$435,001.00
-
$440,000.00
$1,189.18
$1,829.50
$920,001.00
-
$930,000.00
,001.00
-
$445,000.00
$1,200.55
$1,847.00
$930,001.00
-
$940,000.00
$445,001.00
-
$450,000.00
$1,211.93
$1,864.50
$940,001.00
-
$950,000.00
$450,001.00
-
$455,000.00
$1,223.30
$1,882.00
$950,001.00
-
$960,000.00
$455,001.00
-
$460,000.00
$1,234.68
$1,899.50
$960,001.00
-
$970,000.00
$460,001.00
-
$465,000.00
$1,246.05
$1,917.00
$970,001.00
-
$980,000.00
,001.00
-
$470,000.00
$1,257.43
$1,934.50
$980,001.00
-
$990,000.00
$470,001.00
-
$475,000.00
$1,268.80
$1,952.00
$990,001.00
-
$1,000,000.00
$475,001.00
-
$480,000.00
$1,280.18
$1,969.50
$1,000,001.00
-
$1,500,000.00
$480,001.00
-
$485,000.00
$1,291.55
$1,987.00
$1,500,001.00
-
$2,000,000.00
$485,001.00
-
$490,000.00
$1,302.93
$2,004.50
$2,000,001.00
-
$2,500,000.00
$490,001.00
-
$495,000.00
$1,314.30
$2,022.00
$2,500,001.00
-
$3,000,000.00
$495,001.00
-
$500,000.00
$1,325.68
$2,039.50
$3,000,001.00
-
$3,500,000.00
$500,001.00
-
$510,000.00
$1,345.18
$2,069.50
$3,500,001.00
-
$4,000,000.00
$510,001.00
-
$520,000.00
$1,364.68
$2,099.50
$4,000,001.00
-
$4,500,000.00
$520,001.00
-
$530,000.00
$1,384.18
$2,129.50
$4,500,001.00
-
$5,000,000.00
$530,001.00
-
$540,000.00
$1,403.68
$2,159.50
$5,000,001.00
-
$5,500,000.00
$540,001.00
-
$550,000.00
$1,423.18
$2,189.50
$5,500,001.00
-
$6,000,000.00
$550,001.00
-
$560,000.00
$1,442.68
$2,219.50
$6,000,001.00
-
$6,500,000.00
$560,001.00
-
$570,000.00
$1,462.18
$2,249.50
$6,500,001.00
-
$7,000,000.00
$570,001.00
-
$580,000.00
$1,481.68
$2,279.50
$7,000,001.00
-
$7,500,000.00
$580,001.00
-
$590,000.00
$1,501.18
$2,309.50
$7,500,001.00
-
$8,000,000.00
UILDINGS PROVIDED WITH AUTOMATIC SPRINKLER SYST
EMS
WILL BE GIVEN AN ADDITIONAL
VALUATION OF $2.40 PER SQUARE
FOOT.*
Updated
1/30/2019
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760)
269
-
0073
Total Valuation
Plan
Review
Permit
$600,000.00
$1,520.68
$2,339.50
$610,000.00
$1,540.18
$2,369.50
$620,000.00
$1,559.68
$2,399.50
$630,000.00
$1,579.18
$2,429.50
$640,000.00
$1,598.68
$2,459.50
$650,000.00
$1,618.18
$2,489.50
$660,000.00
$1,637.68
$2,519.50
$670,000.00
$1,657.18
$2,549.50
$680,000.00
$1,676.68
$2,579.50
$690,000.00
$1,696.18
$2,609.50
$700,000.00
$1,715.68
$2,639.50
$710,000.00
$1,735.18
$2,669.50
$720,000.00
$1,754.68
$2,699.50
$730,000.00
$1,774.18
$2,729.50
$740,000.00
$1,793.68
$2,759.50
$750,000.00
$1,813.18
$2,789.50
$760,000.00
$1,832.68
$2,819.50
$770,000.00
$1,852.18
$2,849.50
$780,000.00
$1,871.68
$2,879.50
$790,000.00
$1,891.18
$2,909.50
$800,000.00
$1,910.68
$2,939.50
$810,000.00
$1,930.18
$2,969.50
$820,000.00
$1,949.68
$2,999.50
$830,000.00
$1,969.18
$3,029.50
$840,000.00
$1,988.68
$3,059.50
$850,000.00
$2,008.18
$3,089.50
$860,000.00
$2,027.68
$3,119.50
$870,000.00
$2,047.18
$3,149.50
$880,000.00
$2,066.68
$3,179.50
$890,000.00
$2,086.18
$3,209.50
$900,000.00
$2,105.68
$3,239.50
$910,000.00
$2,125.18
$3,269.50
920,000.00
$2,144.68
$3,299.50
$930,000.00
$2,164.18
$3,329.50
$940,000.00
$2,183.68
$3,359.50
$950,000.00
$2,203.18
$3,389.50
$960,000.00
$2,222.68
$3,419.50
$970,000.00
$2,242.18
$3,449.50
$980,000.00
$2,261.68
$3,479.50
$990,000.00
$2,281.18
$3,509.50
$1,000,000.00
$2,300.68
$3,539.50
$1,500,000.00
$2,950.68
$4,539.50
$2,000,000.00
$3,600.68
$5,539.50
$2,500,000.00
$4,250.68
$6,539.50
$3,000,000.00
$4,900.68
$7,539.50
$3,500,000.00
$5,550.68
$8,539.50
$4,000,000.00
$6,200.68
$9,539.50
$4,500,000.00
$6,850.68
$10,539.50
$5,000,000.00
$7,500.68
$11,539.50
$5,500,000.00
$8,150.68
$12,539.50
$6,000,000.00
$8,800.68
$13,539.50
$6,500,000.00
$9,450.68
$14,539.50
$7,000,000.00
$10,100.68
$15,539.50
$7,500,000.00
$10,750.68
$16,539.50
$8,000,000.00
$11,400.68
$17,539.50
FOOT.*
3 City of Victorville
Development Department
Planning
Building
BUILDING FEES
Plumbing, Electrical, Mechanical Fees
Note: A one
-
time fee of $20.00 will be added to Plumbing, Electrical and Mechanical Permits.
Bathtub
Clothes Washer
Dishwasher
Drinking Fountain
Floor Drain
Floor Sink
Gas System
Hose Bib
Irrigation System
Lavatory
Lawn Sprinkler
Electrical Fees
Construction Power
Fixtures / Receptacles
Garage / Carport Square Feet
Light Standards
Motors < 10 HP
Motors 10
-
50 HP
Motors > 50
Patio / Porch Square Feet
Residential Square Feet
Service < 200 AMP
Services > 200 < 1000 AMP
Service > 1000 AMP
Subpanel
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
RESIDENTIAL
Plumbing, Electrical, Mechanical Fees
time fee of $20.00 will be added to Plumbing, Electrical and Mechanical Permits.
Plumbing Fees
$7.00
Septic System
$7.00
Sewer System
$7.00
Shower
$7.00
Sink
$7.00
Swimming Pool / Spa
$7.00
Toilet
$5.00
Urinal
$5.00
Waste Interceptor
$7.00
Water Closet w/ Flushometer
$7.00
Water Heater
$7.00
Water System
Mechanical Fees
$
15.00 Boiler, Hot Water
$
2.00 Boiler, Steam
$
0.015
Evaporative Cooler
$
10.00 Exhaust Duct
$
5.00 FAU < 100 MBTU
$
12.30 FAU
> 100 MBTU
$
49.00 Generator
$0.
015
HVAC < 8
$
0.035
HVAC > 8
$
30.50 Mechanical Fireplace
$
62.50 Vent System
$124.30
$23.50
Updated
1/30/2019
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760)
269
-
0073
time fee of $20.00 will be added to Plumbing, Electrical and Mechanical Permits.
$40.00
$15.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
Mechanical Fees
$
14.70 $
14.70 $
10.65 $
10.65 $
14.80 $
14.80 $
14 .
65 $
14.80 $
18.20 $
10.65 $
7.25 4
City of Victorville
Development Department
Planning
Building
BUILDING FEES
Victor Valle
y Water Reclamation Authority Fee (
Industr
ial Waste Water Treatment Plant Fee (
Note:
The fee assessed
is based
o
n the location of the project. Please contact
Single Family Residence
Multi
-
Family
Units
Number of Units:
_____
______
____
Fixtures
Bar Sink
Bathtub (With or Without Shower
Dishwasher
Floor Drain
Laundry Tub or Clotheswasher (Each Pair
Faucets)
Lavatory (Bathroom)
–
Dual Basins
Lava
t
or
y (
Bathroom)
–
Single Basin
R.V. Dump Station
Shower Stall (Each Set of Faucets)
Sink (Kitchen/Utility, Includes
Garbage
Disposal)
Water Closet (Flush Tank)
Total Number of Fix
ture Units: __________
(IWWTP)
=
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
RESIDENTIAL
y Water Reclamation Authority Fee (
VVWRA)
or
ial Waste Water Treatment Plant Fee (
IWWTP
)
n the location of the project. Please contact
the Development Department for
more information
.
Type of Unit
Condo
Mobile Home
Other:
___________________________________
No. of Fixtures
x
No. of
Equivalent
Fixture Units
=
1 2
2 2
Laundry Tub or Clotheswasher (Each Pair
2 2
1 4
2 Garbage
2 4
ture Units: __________
x
$200.00 (VVWRA)
OR
x
$187.50
Updated
1/30/2019
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760)
269
-
0073
the Development Department for
___________________________________
Fixture Units
Total
No.
of
Fixture Units
$
1 City of Victorville
Development Department
Planning
Building
BUILDING FEES
In order to assist you in
estimating
the permit fees for your project, several tables and charts have been compiled and are included in this package. By following the steps listed below, a reasonable estimate may be made.
STEP 1
–
Review page 2 for type of project and determine the value p footage of the project.
STEP 2
–
Find the valuation of the project on page 3, and then add the fees for plan review and construction permit.
STEP 3
–
Review page 4 for miscellaneous plumbing, ele
Note that a separate permit is required for each independent structure, even though they may be located on the same parcel.
Additional Permit Fees
Development Impact Fee
–
$9.28 per square foot for commercial projects, $3.44
$1.87 per square foot for industrial high cube projects. This fee is used for Following is a break
-
down of these fees:
Development Impact Fee
Type
Commerical
Cost per Square Foot
Facilities
$
1.34 Fire
$
0.17 Police
$
0.17 Roads
$
7.60 VVWRA
(Victor Valley Water Reclamation Authority)
IWWTP fees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 5.
The fee assessed is based on the location of the project. Please contac Sewer
Capacity
Fees
–
Commercial projects are figured on an equivalent dwelling unit basis by using the following calculations:
Total number of fixture units (using form on page 5), divided by 20, and mul Other Special Assessments
–
Depending on the location of the project, there may also be special assessment fees to cover storm drains, bridges, road widening, street lighting, and fire hydrant installation. Please contact the Developme for more information regarding special assessment districts.
School District Fees
–
A Certificate of Compliance from the school district must be submitted to the Development Department.
Strong Motion Implementation Program (SMIP)
.50. Projects with a valuation greater than $2,381 should multiply the valuation by .0002 Technology
Fee
–
Multiply the
Plan Review, Building Permit, Mechanical
4.8% (.048) to
determine the
Technology F
ee.
Green Building Fee
–
Senate Bill 1473 which provides for the creation of the Building Standards Administration Special Revolving Fund.
$1
–
25,000
$25,001
–
50,000
$50,001
–
75,000
$75,001
–
100,000
Every $25,000 or fraction thereof above $100,000
T
HESE FEES ARE FOR ES
TIMATION PURPOSES ON
OFFICIAL FEES CAN BE
ASSESSED.
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
COMMERCIAL
the permit fees for your project, several tables and charts have been compiled and are included in this package. By following the steps listed below, a reasonable estimate may be made.
Review page 2 for type of project and determine the value p er square foot. Multiply this figure by the total square Find the valuation of the project on page 3, and then add the fees for plan review and construction permit.
Review page 4 for miscellaneous plumbing, ele
ctrical, and mechanical fees.
Note that a separate permit is required for each independent structure, even though they may be located on the same parcel. $9.28 per square foot for commercial projects, $3.44
per square foot for industrial projects and
$1.87 per square foot for industrial high cube projects. This fee is used for
roads
and public safety capital improvement costs.
Commerical
Cost per Square Foot
Industrial
Cost per Square Foot
Industrial High Cube
Cost per Square Foot
1.34 $
0.44 0.17
$
0.01 0.17
$
0.01 7.60
$
2.98 (Victor Valley Water Reclamation Authority)
or
IWWTP (Industrial Waste Water Treatment Plant)
IWWTP fees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 5.
The fee assessed is based on the location of the project. Please contac t the Development Department for more information.
Commercial projects are figured on an equivalent dwelling unit basis by using the following Total number of fixture units (using form on page 5), divided by 20, and mul tiplied by $350.00.
Depending on the location of the project, there may also be special assessment fees to cover storm drains, bridges, road widening, street lighting, and fire hydrant installation. Please contact the Developme for more information regarding special assessment districts.
A Certificate of Compliance from the school district must be submitted to the Development Department.
Strong Motion Implementation Program (SMIP)
Fee
–
Projects with a valuation less than $2,381 will receive a SMIP fee of .50. Projects with a valuation greater than $2,381 should multiply the valuation by .0002 8 to determine SMIP.
Plan Review, Building Permit, Mechanical
Permit, Electrical Permit, and Plumbing Permit fees by
ee.
Senate Bill 1473 which provides for the creation of the Building Standards Administration Special Permit Valuation
Fee
$1
$2
$3
$4
Every $25,000 or fraction thereof above $100,000
Add $1
TIMATION PURPOSES ON
LY. ALL PLANS MUST
BE SUBMITTED AND APP
Updated
1 /
3 0
/
2 0
1 9
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760) 269
-
0073
the permit fees for your project, several tables and charts have been compiled and are er square foot. Multiply this figure by the total square Find the valuation of the project on page 3, and then add the fees for plan review and construction permit.
Note that a separate permit is required for each independent structure, even though they may be located on the same parcel.
per square foot for industrial projects and
and public safety capital improvement costs.
Industrial High Cube
Cost per Square Foot
$
0.25 $
0.02 $
0.02 $
1.58 IWWTP (Industrial Waste Water Treatment Plant)
–
VVWRA and
IWWTP fees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 5. t the Development Department for more information.
Commercial projects are figured on an equivalent dwelling unit basis by using the following Depending on the location of the project, there may also be special assessment fees to cover storm drains, bridges, road widening, street lighting, and fire hydrant installation. Please contact the Developme nt Department
A Certificate of Compliance from the school district must be submitted to the Development Department.
Projects with a valuation less than $2,381 will receive a SMIP fee of to determine SMIP.
Permit, Electrical Permit, and Plumbing Permit fees by
Senate Bill 1473 which provides for the creation of the Building Standards Administration Special
BE SUBMITTED AND APP
ROVED BEFORE
2 City of Victorville
Development Department
Planning
Building
BUILDING FEES
THE FOLLOWING BUILDI
NG VALUATION DATA RE
BUILDINGS. THIS CHA
RT IS ADJUSTED ANNUA
USED SOLELY FOR THE
DETERMINATION OF PER
OF THESE FEES.
*BUILDINGS PROVIDED
WITH AUTOMATIC SPRIN
Construction Group
1A
A
-
1 Assembly, theaters, with stage
$244.21
A
-
1 Assembly, theaters, w/out stage
$223.45
A
-
2 Assembly, nightclubs
$190.08
A
-
2 Assembly, restaurants, bars,
banquet halls
$189.08
A
-
3 Assembly, churches
$224.47
A
-
3 Assembly, general, community
halls, libraries, museums
$188.77
A
-
4 Assembly, arenas
$222.45
B Business
$195.88
E Educational
$207.44
F
-
1 Factory and industrial, moderate
hazard
$115.30
F
-
2 Factory and industrial, low
hazard
$114.30
H
-
1 High Hazard, explosives
$107.85
H
-
2, 3, 4 High Hazard
$107.85
H
-
5 HPM
$195.88
I
-
1 Institutional, supervised
environment
$194.98
I
-
2 Institutional,
hospitals
$327.69
I
-
2 Institutional, nursing homes
$227.45
I
-
3 Institutional, restrained
$222.66
I
-
4 Institutional, day care facilities
$194.98
M Mercantile
$141.54
R
-
1 Residential, hotels
$196.81
S
-
1 Storage, moderate hazard
$106.85
S
-
2 Storage, low hazard
$105.85
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
COMMERCIAL
NG VALUATION DATA RE
PRESENTS AVERAGE COS
TS FOR MOST NEW CONS
RT IS ADJUSTED ANNUA
LLY AS RELEASED BY T
HE INTERNATIONAL COD
DETERMINATION OF PER
MIT FEES. TENANT IM
P
ROVEMENTS WILL BE VA
WITH AUTOMATIC SPRIN
KLER SYSTEMS WILL BE
GIVEN AN ADDITIONAL
$2.40 PER SQUARE FOO
T.*
Construction Type
1B
2A
2B
3A
3B
4 –
$244.21
$236.18
$230.55
$221.01
$207.82
$201.82
$214.02
$223.45
$215.42
$209.80
$200.25
$187.31
$181.32
$193.26
$190.08
$184.73
$180.34
$172.99
$163.33
$158.82
$166.99
$189.08
$183.73
$178.34
$171.99
$161.33
$157.82
$165.99
$224.47
$216.44
$210.82
$201.27
$189.73
$183.73
$194.28
$188.77
$180.74
$174.11
$165.57
$151.59
$146.63
$158.58
$222.45
$214.42
$207.80
$199.25
$185.31
$180.32
$192.26
$195.88
$188.76
$182.90
$173.98
$159.08
$153.13
$167.31
$207.44
$200.32
$195.11
$186.22
$173.62
$164.85
$179.83
$115.30
$109.99
$103.87
$99.84
$89.72
$85.56
$95.69
$114.30
$108.99
$103.87
$98.84
$89.72
$84.56
$94.69
$107.85
$102.54
$97.43
$92.40
$83.50
$78.33
$88.25
$107.85
$102.54
$97.43
$92.40
$83.50
$78.33
$88.25
$195.88
$188.76
$182.90
$173.98
$159.08
$153.13
$167.31
$194.98
$188.36
$182.90
$175.20
$161.40
$157.01
$175.29
$327.69
$320.57
$314.72
$305.80
$289
.87
$0.00
$299.12
$227.45
$220.33
$214.47
$205.56
$191.65
$0.00
$198.88
$222.66
$215.54
$209.69
$200.77
$187.11
$180.16
$194.09
$194.98
$188.36
$182.90
$175.20
$161.40
$157.01
$175.29
$141.54
$136.19
$130.80
$124.45
$114.24
$110.73
$118.45
$196.81
$190.20
$184.74
$177.03
$162.97
$158.58
$177.13
$106.85
$101.54
$95.43
$91.40
$81.50
$77.33
$87.25
$105.85
$100.54
$95.43
$90.40
$81.50
$76.33
$86.25
Updated
1 /
3 0
/
2 0
1 9
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760) 269
-
0073
TS FOR MOST NEW CONS
TRUCTION
HE INTERNATIONAL COD
E COUNCIL AND
ROVEMENTS WILL BE VA
LUATED AT 20%
GIVEN AN ADDITIONAL
VALUATION OF
–
HT
5 A
5 B
$214.02
$189.83
$182.71
$193.26
$169.33
$162.21
$166.99
$147.83
$142.92
$165.99
$145.83
$141.92
$194.28
$171.74
$164.62
$158.58
$133.64
$127.52
$192.26
$167.33
$161.21
$167.31
$139.76
$133.67
$179.83
$151.63
$147.30
$95.69
$73.79
$69.57
$94.69
$73.79
$68.57
$88.25
$67.57
$0.00
$88.25
$67.57
$62.34
$167.31
$139.76
$133.67
$175.29
$144.58
$140.08
$299.12
$270.56
$0.00
$198.88
$172.34
$0.00
$194.09
$167.80
$159.71
$175.29
$144.58
$140.08
$118.45
$98.74
$94.83
$177.13
$146.15
$141.65
$87.25
$65.57
$61.34
$86.25
$65.57
$60.34
3 City of Victorville
Development Department
Planning
Building
BUILDING FEES
Total Valuation
Plan
Review
Permit
Total Valuation
$1.00
-
$2,000.00
$29.25
$45.00
$270,001.00
$2,001.00
-
$5,000.00
$46.80
$72.00
$275,001.00
$5,001.00
-
$10,000.00
$76.05
$117.00
$280,001.00
$10,001.00
-
$15,000.00
$105.30
$162.00
$285,001.00
$15,001.00
-
$20,000.00
$134.55
$207.00
$290,001.00
$20,001.00
-
$25,000.00
$163.80
$252.00
$295,001.00
$25,001.00
-
$30,000.00
$184.93
$284.50
$300,001.00
$30,001.00
-
$35,000.00
$206.05
$317.00
$305,001.00
$35,001.00
-
$40,000.00
$227.18
$349.50
$310,001.00
$40,001.00
-
$45,000.00
$248.30
$382.00
$315,001.0
$45,001.00
-
$50,000.00
$269.43
$414.50
$320,001.00
$50,001.00
-
$55,000.00
$284.05
$437.00
$325,001.00
$55,001.00
-
$60,000.00
$298.68
$459.50
$330,001.0
$60,001.00
-
$65,000.00
$313.30
$482.00
$335,001.00
$65,001.00
-
$70,000.00
$327.93
$504.50
$340,001.0
$70,001.00
-
$75,000.00
$342.55
$527.00
$345,001.00
$75,001.00
-
$80,000.00
$357.18
$549.50
$350,001.00
$80,001.00
-
$85,000.00
$371.80
$572.00
$355,001.0
$85,001.00
-
$90,000.00
$386.43
$594.50
$360,001.00
$90,001.00
-
$95,000.00
$401.05
$617.00
$365,001
$95,001.00
-
$100,000.00
$415.68
$639.50
$370,001.00
$100,001.00
-
$105,000.00
$427.05
$657.00
$375,001.00
$105,001.00
-
$110,000.00
$438.43
$674.50
$380
,001.00
$110,001.00
-
$115,000.00
$449.80
$692.00
$385,001.00
$115,001.00
-
$120,000.00
$461.18
$709.50
$390
,001.00
$120,001.00
-
$125,000.00
$472.55
$727.00
$395,001.00
$125,001.00
-
$130,000.00
$483.93
$744.50
$400,001.00
$130,001.00
-
$135,000.00
$495.30
$7
62.00 $405,001.00
$135,001.00
-
$140,000.00
$506.68
$779.50
$410,001.00
$140,001.00
-
$145,000.00
$518.05
$797.00
$415
,001.00
$145,001.00
-
$150,000.00
$529.43
$814.50
$420,001.00
$150,001.00
-
$155,000.00
$540.80
$832.00
$425,001.00
$155,001.00
-
$160,000.00
$552.18
$8
49.50 $430,001.00
$160,001.00
-
$165,000.00
$563.55
$867.00
$435,001.00
$165,001.00
-
$170,000.00
$574.93
$884.50
$440
,001.00
$170,001.00
-
$175,000.00
$586.30
$902.00
$445,001.00
$175,001.00
-
$180,000.00
$597.68
$919.50
$450,001.00
$180,001.00
-
$185,000.00
$609.05
$9
37.00 $455,001.00
$185,001.00
-
$190,000.00
$620.43
$954.50
$460,001.00
$190,001.00
-
$195,000.00
$631.80
$972.00
$465
,001.00
$195,001.00
-
$200,000.00
$643.18
$989.50
$470,001.00
$200,001.00
-
$205,000.00
$654.55
$1,007.00
$475,001.00
$205,001.00
-
$210,000.00
$665.93
$1,024
.50
$480,001.00
$210,001.00
-
$215,000.00
$677.30
$1,042.00
$485,001.00
$215,001.00
-
$220,000.00
$688.68
$1,059
.50
$490,001.00
$220,001.00
-
$225,000.00
$700.05
$1,077.00
$495,001.00
$225,001.00
-
$230,000.00
$711.43
$1,094.50
$500,001.00
$230,0
01.00 -
$235,000.00
$722.80
$1,112.00
$510,001.00
$235,001.00
-
$240,000.00
$734.18
$1,129.50
$520,001.00
$240,001.00
-
$245,000.00
$745.55
$1,14
7.00 $530,001.00
$245,001.00
-
$250,000.00
$756.93
$1,164.50
$540,001.00
$250,001.00
-
$255,000.00
$768.30
$1,182.00
$550,001.00
$255
,001.00
-
$260,000.00
$779.68
$1,199.50
$560,001.00
$260,001.00
-
$265,000.00
$791.05
$1,217.00
$570,001.00
$265,001.00
-
$270,000.00
$802.43
$1,2
34.50 $580,001.00
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
COMMERCIAL
Project Valuation
Total Valuation
Plan
Review
Permit
Total Valuation
$270,001.00
-
$275,000.00
$813.80
$1,252.00
$590,001.00
-
$600,000.00
$275,001.00
-
$280,000.00
$825.18
$1,269.50
$600,001.00
-
$610,000.00
$280,001.00
-
$285,000.00
$836.55
$1,287.00
$610,001.00
-
$620,000.00
$285,001.00
-
$290,000.00
$847.93
$1,304.50
$620,001.00
-
$630,000.00
$290,001.00
-
$295,000.00
$859.30
$1,322.00
$630,001.00
-
$640,000.00
$295,001.00
-
$300,000.00
$870.68
$1,339.50
$640,001.00
-
$650,000.00
$300,001.00
-
$305,000.00
$882.05
$1,357.00
$650,001.00
-
$660,000.00
$305,001.00
-
$310,000.00
$893.43
$1,374.50
$660,001.00
-
$670,000.00
$310,001.00
-
$315,000.00
$904.80
$1,392.00
$670,001.00
-
$680,000.00
$315,001.0
0 -
$320,000.00
$916.18
$1,409.50
$680,001.00
-
$690,000.00
$320,001.00
-
$325,000.00
$927.55
$1,427.00
$690,001.00
-
$700,000.00
$325,001.00
-
$330,000.00
$938.93
$1,444.50
$700,001.00
-
$710,000.00
$330,001.0
0 -
$335,000.00
$950.30
$1,462.00
$710,001.00
-
$720,000.00
$335,001.00
-
$340,000.00
$961.68
$1,479.50
$720,001.00
-
$730,000.00
$340,001.0
0 -
$345,000.00
$973.05
$1,497.00
$730,001.00
-
$740,000.00
$345,001.00
-
$350,000.00
$984.43
$1,514.50
$741,001.00
-
$750,000.00
$350,001.00
-
$355,000.00
$995.80
$1,532.00
$750,001.00
-
$760,000.00
$355,001.0
0 -
$360,000.00
$1,007.18
$1,549.50
$760,001.00
-
$770,000.00
$360,001.00
-
$365,000.00
$1,018.55
$1,567.00
$770,001.00
-
$780,000.00
$365,001
.00
-
$370,000.00
$1,029.93
$1,584.50
$780,001.00
-
$790,000.00
$370,001.00
-
$375,000.00
$1,041.30
$1,602.00
$790,001.00
-
$800,000.00
$375,001.00
-
$380,000.00
$1,052.68
$1,619.50
$800,001.00
-
$810,000.00
,001.00
-
$385,000.00
$1,064.05
$1,637.00
$810,001.00
-
$820,000.00
$385,001.00
-
$390,000.00
$1,075.43
$1,654.50
$820,001.00
-
$830,000.00
,001.00
-
$395,000.00
$1,086.80
$1,672.00
$830,001.00
-
$840,000.00
$395,001.00
-
$400,000.00
$1,098.18
$1,689.50
$840,001.00
-
$850,000.00
$400,001.00
-
$405,000.00
$1,109.55
$1,707.00
$850,001.00
-
$860,000.00
$405,001.00
-
$410,000.00
$1,120.93
$1,724.50
$860,001.00
-
$870,000.00
$410,001.00
-
$415,000.00
$1,132.30
$1,742.00
$870,001.00
-
$880,000.00
,001.00
-
$420,000.00
$1,143.68
$1,759.50
$880,001.00
-
$890,000.00
$420,001.00
-
$425,000.00
$1,155.05
$1,777.00
$890,001.00
-
$900,000.00
$425,001.00
-
$430,000.00
$1,166.43
$1,794.50
$900,001.00
-
$910,000.00
$430,001.00
-
$435,000.00
$1,177.80
$1,812.00
$910,001.00
-
$
920,000.00
$435,001.00
-
$440,000.00
$1,189.18
$1,829.50
$920,001.00
-
$930,000.00
,001.00
-
$445,000.00
$1,200.55
$1,847.00
$930,001.00
-
$940,000.00
$445,001.00
-
$450,000.00
$1,211.93
$1,864.50
$940,001.00
-
$950,000.00
$450,001.00
-
$455,000.00
$1,223.30
$1,882.00
$950,001.00
-
$960,000.00
$455,001.00
-
$460,000.00
$1,234.68
$1,899.50
$960,001.00
-
$970,000.00
$460,001.00
-
$465,000.00
$1,246.05
$1,917.00
$970,001.00
-
$980,000.00
,001.00
-
$470,000.00
$1,257.43
$1,934.50
$980,001.00
-
$990,000.00
$470,001.00
-
$475,000.00
$1,268.80
$1,952.00
$990,001.00
-
$1,000,000.00
$475,001.00
-
$480,000.00
$1,280.18
$1,969.50
$1,000,001.00
-
$1,500,000.00
$480,001.00
-
$485,000.00
$1,291.55
$1,987.00
$1,500,001.00
-
$2,000,000.00
$485,001.00
-
$490,000.00
$1,302.93
$2,004.50
$2,000,001.00
-
$2,500,000.00
$490,001.00
-
$495,000.00
$1,314.30
$2,022.00
$2,500,001.00
-
$3,000,000.00
$495,001.00
-
$500,000.00
$1,325.68
$2,039.50
$3,000,001.00
-
$3,500,000.00
$500,001.00
-
$510,000.00
$1,345.18
$2,069.50
$3,500,001.00
-
$4,000,000.00
$510,001.00
-
$520,000.00
$1,364.68
$2,099.50
$4,000,001.00
-
$4,500,000.00
$520,001.00
-
$530,000.00
$1,384.18
$2,129.50
$4,500,001.00
-
$5,000,000.00
$530,001.00
-
$540,000.00
$1,403.68
$2,159.50
$5,000,001.00
-
$5,500,000.00
$540,001.00
-
$550,000.00
$1,423.18
$2,189.50
$5,500,001.00
-
$6,000,000.00
$550,001.00
-
$560,000.00
$1,442.68
$2,219.50
$6,000,001.00
-
$6,500,000.00
$560,001.00
-
$570,000.00
$1,462.18
$2,249.50
$6,500,001.00
-
$7,000,000.00
$570,001.00
-
$580,000.00
$1,481.68
$2,279.50
$7,000,001.00
-
$7,500,000.00
$580,001.00
-
$590,000.00
$1,501.18
$2,309.50
$7,500,001.00
-
$8,000,000.00
Updated
1 /
3 0
/
2 0
1 9
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760) 269
-
0073
Total Valuation
Plan
Review
Permit
$600,000.00
$1,520.68
$2,339.50
$610,000.00
$1,540.18
$2,369.50
$620,000.00
$1,559.68
$2,399.50
$630,000.00
$1,579.18
$2,429.50
$640,000.00
$1,598.68
$2,459.50
$650,000.00
$1,618.18
$2,489.50
$660,000.00
$1,637.68
$2,519.50
$670,000.00
$1,657.18
$2,549.50
$680,000.00
$1,676.68
$2,579.50
$690,000.00
$1,696.18
$2,609.50
$700,000.00
$1,715.68
$2,639.50
$710,000.00
$1,735.18
$2,669.50
$720,000.00
$1,754.68
$2,699.50
$730,000.00
$1,774.18
$2,729.50
$740,000.00
$1,793.68
$2,759.50
$750,000.00
$1,813.18
$2,789.50
$760,000.00
$1,832.68
$2,819.50
$770,000.00
$1,852.18
$2,849.50
$780,000.00
$1,871.68
$2,879.50
$790,000.00
$1,891.18
$2,909.50
$800,000.00
$1,910.68
$2,939.50
$810,000.00
$1,930.18
$2,969.50
$820,000.00
$1,949.68
$2,999.50
$830,000.00
$1,969.18
$3,029.50
$840,000.00
$1,988.68
$3,059.50
$850,000.00
$2,008.18
$3,089.50
$860,000.00
$2,027.68
$3,119.50
$870,000.00
$2,047.18
$3,149.50
$880,000.00
$2,066.68
$3,179.50
$890,000.00
$2,086.18
$3,209.50
$900,000.00
$2,105.68
$3,239.50
$910,000.00
$2,125.18
$3,269.50
920,000.00
$2,144.68
$3,299.50
$930,000.00
$2,164.18
$3,329.50
$940,000.00
$2,183.68
$3,359.50
$950,000.00
$2,203.18
$3,389.50
$960,000.00
$2,222.68
$3,419.50
$970,000.00
$2,242.18
$3,449.50
$980,000.00
$2,261.68
$3,479.50
$990,000.00
$2,281.18
$3,509.50
$1,000,000.00
$2,300.68
$3,539.50
$1,500,000.00
$2,950.68
$4,539.50
$2,000,000.00
$3,600.68
$5,539.50
$2,500,000.00
$4,250.68
$6,539.50
$3,000,000.00
$4,900.68
$7,539.50
$3,500,000.00
$5,550.68
$8,539.50
$4,000,000.00
$6,200.68
$9,539.50
$4,500,000.00
$6,850.68
$10,539.50
$5,000,000.00
$7,500.68
$11,539.50
$5,500,000.00
$8,150.68
$12,539.50
$6,000,000.00
$8,800.68
$13,539.50
$6,500,000.00
$9,450.68
$14,539.50
$7,000,000.00
$10,100.68
$15,539.50
$7,500,000.00
$10,750.68
$16,539.50
$8,000,000.00
$11,400.68
$17,539.50
4 City of Victorville
Development Department
Planning
Building
BUILDING FEES
Plumbing, Electrical, Mechanical Fees
Note: A one
-
time fee of $20.00 will be added to Plumbing, Electrical Bathtub
Clothes Washer
Dishwasher
Drinking Fountain
Floor Drain
Floor Sink
Gas System
Hose Bib
Interceptor / Trap
Irrigation System
Lavatory
Lawn Sprinkler
Electrical Fees
Commercial Square Feet
Construction Power
Fixtures / Receptacles
Garage / Carport Square Feet
Light Standards
Motors < 10 HP
Motors 10
-
50 HP
Motors > 50
Patio / Porch Square Feet
Residential Square Feet
Service < 200 AMP
Services > 200 < 1000 AMP
Service > 1000 AMP
Subpanel
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
COMMERCIAL
Plumbing, Electrical, Mechanical Fees
time fee of $20.00 will be added to Plumbing, Electrical and Mechanical Permits.
Plumbing Fees
$7.00
Septic System
$7.00
Sewer System
$7.00
Shower
$7.00
Sink
$7.00
Swimming Pool / Spa
$7.00
Toilet
$5.00
Urinal
$5.00
Waste Interceptor
$7.00
Water Closet w/ Flushometer
$7.00
Water Heater
$7.00
Water System
$7.00
Mechanical Fees
$0.015
Boiler, Hot Water
$15.00
Boiler, Steam
$2.00
Evaporative Cooler
$0.015
Exhaust Duct
$10.00
FAU < 100 MBTU
$5.00
FAU > 100 MBTU
$12.30
Generator
$49.00
HVAC < 8
$0.015
HVAC > 8
$0.035
Mechanical Fireplace
$30.50
Vent System
$62.50
$124.30
$23.50
Updated
1 /
3 0
/
2 0
1 9
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760) 269
-
0073
and Mechanical Permits.
$40.00
$15.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
$7.00
Mechanical Fees
$14.70
$14.70
$10.65
$10.65
$14.80
$14.80
$14.65
$14.80
$18.20
$10.65
$7.25
5 City of Victorville
Development Department
Planning
Building
BUILDING FEES
VVWRA
(Victor Valle
IWWTP (Industrial Waste Water Treatment Plant)
Note:
The fee assessed
is based
on the location of the project. Please contact the Development Department for Commercial
Industrial
Fixtures
Bar Sink
Bathtub (With or Without Shower
)
Dental Unit or Cuspidor
Dishwasher
Drinking Fountain (Each Head)
Floor Drain
Floor Drain (For Emergency Overflows)
Laundry Tub or Clotheswasher (Each Pair Faucets)
Lavatory (Bathroom)
–
Dual Basins
Lavatory (
Bathroom)
–
Single Basin
Lavatory (Dental)
R.V. Dump Station
Recreational Vehicle Spaces
Shower (Each Set of Faucets)
Sink
(Flushing Rim, Clinic)
Sink (Kitchen/Utility)
Sink (Wash Up, Circular Spray)
Sink (Wash Up, Each Set Faucets)
Urinal (Wall)
Water Closet (Flush Tank)
–
Home Style
Water Closet (Flushometer Automatic Valve)
Total Number
of Fixture Units: _______________ x $200.00 (VVWRA)
1. Prison
2. Restaurant
3. Cocktail Bar
4. Hospital
5. Laundromat
6. Day Care Center
7. Convalescent Care Center
City of Victorville
Development Department
Building
Code Enforcement
Business License
Animal Control
BUILDING FEES
–
COMMERCIAL
(Victor Valle
y Water Reclamation Authority)
or
IWWTP (Industrial Waste Water Treatment Plant)
on the location of the project. Please contact the Development Department for information
.
Type of Unit
Hotel / Motel
Other:
____________________
No. of Fixtures x
No. of Equivalent
Fixture Units =
2 4
1 4
1 4
1 Laundry Tub or Clotheswasher (Each Pair Faucets)
4 4
2 1
20 8
4 10
4 4
3 5
6 10
of Fixture Units: _______________ x $200.00 (VVWRA)
OR
x $187.50 (IWWTP) Subtotal
=
Sewage Facility Fees
VVWRA
Amount
IWWTP
Amount
$146.52 / bed
$117.75 / bed
$65.92 / seat
$52.98 / seat
$26.38 / seat
$21.20 / seat
$329.76 / bed
$264.98 / bed
$293.04 /
m
achine
$235.53 / machine
$29.31 /
c
hild
$23.56 / child
$73.26 /
b
ed
$58.88 / bed
VVWRA
OR
IWWTP Subtotal
=
VVWRA
OR
IWWTP GRAND TOTAL
=
Updated
1 /
3 0
/
2 0
1 9
14343 Civic Drive
PO Box 5001
Victorville, CA 92393
-
5001
(760) 955
-
5100
Fax (760) 269
-
0073
on the location of the project. Please contact the Development Department for more
____________________
Total No. of Fixture
Units
$
$
$
$
$
$
$
$
$
$
_______________________________________________________________________________________ City of Victorville
ATTACHMENT 2
_______________________________________________________________________________________
City of Victorville Development Impact Fees Master Fee Schedule in effect between January 1, 2023, and June 30, 2023
Residential Development Unit Parks and
Recreation Fire Protection Police Public Buildings Libraries Road Improvements
Subtotal
[1]
Admin. Fee
(.2% of total)
Single Family Dwelling Unit 5,045.87$ 284.20$ 291.65$ 1,198.47$ 252.72$ 5,213.41$ 12,286.32$ 24.57$ Multi Family Dwelling Unit 4,110.40$ 373.95$ 206.15$ 847.13$ 178.39$ 3,419.60$ 9,135.62$ 18.27$ Mobile Homes Dwelling Unit 3,957.27$ 239.32$ 180.50$ 741.73$ 156.09$ 3,176.54$ 8,451.45$ 16.90$ [1] Subtotal does not include Water System Capacity fee, Sewer fee and Regional Drainage fee.
Residential Development Water System
Capacity Charge
Admin. Fee
(.2% of total)
3/4" Meter 5,686.59$ 11.37$
1" Meter 9,496.61$ 18.99$
1-1/2" Meter 18,936.34$ 37.87$
2" Meter 30,309.52$ 60.62$
3" Meter 56,865.90$ 113.73$
4" Meter 94,795.46$ 189.59$
6" Meter 189,534.04$ 379.07$
8" Meter 303,265.84$ 606.53$
Residential Development Unit Sewer Admin. Fee
(.2% of total)
Single Family EDU 979.25$ 1.96$
Multi Family EDU 979.25$ 1.96$
Mobile Homes EDU 979.25$ 1.96$
Residential Development Unit Regional Drainage Admin. Fee (.2% of total)
Single Family Dwelling Unit 1,102.44$ 2.20$ Multi Family Dwelling Unit 406.87$ 0.81$ Mobile Homes Dwelling Unit 406.87$ 0.81$
CITY OF VICTORVILLE DEVELOPMENT IMPACT FEES
MASTER FEE SCHEDULE
Adopted 6/7/2022
Residential Development
Year 1 - Effective 1/1/2023
Residential - Year 1
Non-Residential Development Unit Fire Protection Police Public Buildings Road Improvements Admin. Fee
(.2% of total)
Retail/Service Commercial KSF 486.13$ 104.50$ 429.42$ 8,600.00$ 19.24$ Professional Office KSF 665.62$ 83.60$ 343.54$ 8,000.00$ 18.19$ Lodging Room 246.80$ 46.55$ 191.29$ 3,694.51$ 8.36$ Industrial/Business Park KSF 52.35$ 27.55$ 113.21$ 4,000.00$ 8.39$ High-Cube Warehouse KSF 7.48$ 19.00$ 78.08$ 972.24$ 2.15$ Self-Service Storage KSF 22.44$ 0.95$ 3.90$ 1,652.81$ 3.36$ Gasoline/Service Station [5] Pump 628.23$ 12.35$ 50.75$ 47,639.71$ 96.66$ Institutional KSF 67.31$ 22.80$ 93.69$ 6,319.55$ 13.01$ Public Facilities KSF 673.10$ 83.60$ 343.54$ 9,139.05$ 20.48$ Non-Residential Development Unit Sewer Admin. Fee
(.2% of total)
Non-Residential
Development
Water System
Capacity Charge
Admin. Fee
(.2% of total)
Retail/Service Commercial EDU 2,867.00$ 5.73$ 3/4" Meter 5,686.59$ 11.37$ Professional Office EDU 2,867.00$ 5.73$ 1" Meter 9,496.61$ 18.99$ Lodging EDU 2,867.00$ 5.73$ 1-1/2" Meter 18,936.34$ 37.87$ Industrial/Business Park EDU 2,867.00$ 5.73$ 2" Meter 30,309.52$ 60.62$ High-Cube Warehouse EDU 2,867.00$ 5.73$ 3" Meter 56,865.90$ 113.73$ Self-Service Storage EDU 2,867.00$ 5.73$ 4" Meter 94,795.46$ 189.59$ Gasoline/Service Station [5] EDU 2,867.00$ 5.73$ 6" Meter 189,534.04$ 379.07$ Institutional EDU 2,867.00$ 5.73$ 8" Meter 303,265.84$ 606.53$ Public Facilities EDU 2,867.00$ 5.73$
Non-Residential Development Unit Regional Drainage Admin. Fee (.2% of total)
Retail/Service Commercial Acre 22,235.00$ 44.47$ Professional Office Acre 22,235.00$ 44.47$
Lodging Acre 22,235.00$ 44.47$
Industrial/Business Park Acre 22,235.00$ 44.47$ High-Cube Warehouse Acre 22,235.00$ 44.47$
Self-Service Storage Acre 22,235.00$ 44.47$
Gasoline/Service Station [5] Acre 22,235.00$ 44.47$ Institutional Acre 22,235.00$ 44.47$
Public Facilities Acre 22,235.00$ 44.47$
[5] Canopy only; Convenience store, carwash, etc. calculated separately at Retail/Service Commercial rates.
CITY OF VICTORVILLE DEVELOPMENT IMPACT FEES
MASTER FEE SCHEDULE
Adopted 6/7/2022
Non-Residential
Effective 1/1/2023
Non-Residential