Attachment A

City of Victorville
Engineering Department
Q3 REPORT 2024
January 1, 2024 through March 31, 2024
Welcome to the inaugural Engineering Department
Quarterly update for the third quarter of Fiscal Y ear2024. We are working very hard to deliver many infrastructure projects this calendar year, but for my initial discussion, I wanted to pay our respects to our former City Engineer, Mr. Brian W.

Gengler, who sadly passed away on March 16th.

Brian retired in September 2023 after having served the City of Victorville for 22 years. He joined the City as our Traffic Engineer in 2002 and was promoted to Assistant City Engineer just six months later. Brian served as our City Engineer for 11 years prior to his retirement. Brian's career in public service spanned 34 years with prior service to the cities of Hermosa Beach, Loma Linda, and Big Bear Lake.

Brian was a tremendous part of our success and had a
huge impact on our City. He oversaw major infrastructure projects like the Green Tree Extension and Bear Valley Road Bridge Widening as well as the La Mesa/Nisqualli
Interchange, and the Nisqualli Road Reconstruction.

Brian was a great engineer, mentor, and friend. In the
words of one of our Public Works Inspectors, “It was an honor to walk this Earth with him. He will be very truly missed. The High Desert owes him a thank you and will be less of a place without him.” Brian thank you for the great projects that you delivered to the City of Victorville, but most importantly for taking the time to mentor the engineers in our office. We will continue to work hard (as you did) to deliver quality projects to our residents in your honor.

Fredy A. Bonilla, PE
City Engineer

ORGANIZATIONAL STRUCTURE

Project
UpdatesQ3
AWARDS

RECEIVED

CONSTRUCTION

COMPLETED

CAPITAL IMPROVEMENT PROJECTS

New Traffic Signal at
Village Drive & T awney
Ridge
Awarded Contract Amount: $ 601,714
Final Construction Cost: $ 567,918
Construction Completed: January2024
AFTER
BEFORE
AFTER
BEFORE
Awarded Contract Amount: $ 298,439
Final Construction Cost: $ 287,894
Notice of Completion Recorded
on February 6, 2024
Now that the entire gas
pipeline infrastructure at the
Southern California Logistics
Airport (SCLA) has been
replaced, we are proceeding
with the next phase of work,
which is a direct metered
connection to Kern River Gas
Transmission system.

AFTER
BEFORE
VMUS Gas Pipeline
Replacement Project
Phase 4
Sewer Lining Project
Phase 2
This project rehabilitated approximately
23,822 lineal feet of structurally
deficient sanitary sewer pipelines and
511 sewer laterals in Old Town
Victorville.

Final Construction Cost: $ 1,813,690
Construction Completed: January 2024
SCLA Connection 1
Final Construction Cost: $ 97,820
Construction Completed: March 2024
This project connected the
recycled water discharge pipeline
from SCLA’s Industrial Waste -
Water Treatment Plant (IWWTP) to
the existing Victor Valley
Wastewater Reclamation
Authority’s (VVWRA) sewer system
to be able to handle recycled
water flows that exceed the
existing storage capacity.

CONSTRUCTION IN

PROGRESS

CAPITAL IMPROVEMENT PROJECTS

Bear Valley Road Reconstruction Project
Contractor: C.A. Rasmussen
Contract Amount: $ 8,944,073
Construction Start Date: March 22, 2024
Expected Construction Completion: Summer2024

Pressure Reducing Valve
Installation at Mojave Drive and
Amethyst Road (2 nd Feed to SCLA)
This project will provide an additional potable water feed to the Southern California Logistic Airport (SCLA) by
interconnecting pressure zone 3290 to pressure zone 3170.

Construction Estimate: $ 370,000
Estimated Construction Completion: Summer 2024

This project will replace 638, 40-year old PVC
water service lines with copper piping.

Construction Estimate: $ 2,800,000
Estimated Construction Completion: Fall 2024
Water Service Replacement Project
Area 6 – Golden Triangle Area

3rd Avenue Extension to Bear Valley
Road Project
This project will extend 3rd Avenue from the existing end to Bear Valley Road. Project also includes the installation of a new traffic signal at the Bear Valley Road/3rd Avenue
Intersection.

Improvement to be fully funded by a private developer
Estimated Completion Date: Fall 2024

CAPITAL IMPROVEMENT PROJECTS

UPCOMING

CONSTRUCTION

PROJECTS
7th Street
Traffic Signal Modifications Project
Contract Amount: $ 2,876,393
HSIP Grant Amount: $1,320,000
Contractor: Belco Elecnor
Construction Start Date: June 2024
Expected Completion: Fall 2024
New Traffic Signal at Village Drive and
Puesta Del Sol Project
Contract Amount: $ 1,120,480
HSIP Grant Amount: $526,500
Contractor: Belco Elecnor
Construction Start Date: June 2024
Expected Completion: Fall 2024
Old Town Septic to Sewer Conversion
Project (SEP Program)
Legend
New Sewer Line
This project will connect three residences in Old Town
Victorville to the municipal sewer system to prevent
environmental degradation of groundwater. The new
sewer connection also includes a lift station.

Contractor:Kerns,Inc.

Contract Amount: $ 724,223
Estimated Construction Completion: Fall2024
VMUS - Kern River
Gas Interconnect Project
This project will provide a new interconnect directly to Kern River Gas Transmission Company which will result in
increased capacity and optimum pressures at a lower cost supporting SCLA's ultimate natural gas demands.

Contractor: Arizona Pipeline
Construction Estimate: $ 709,025
Estimated Construction Completion: Fall2024

PROJECTS IN

DESIGN PHASE

CAPITAL IMPROVEMENT PROJECTS

PROJECTS IN DESIGN PHASE

ESTIMATED

CONSTRUCTION

START DATE
1MG Recycled Water Storage Tank Project FY 2024/2025
Sewer Capacity Improvement Project C2&C3 FY 2024/2025
Eucalyptus Street Drainage and Roadway
Improvement Project
FY 2024/2025

DEVELOPMENT

ENGINEERING

DEVELOPMENT REVIEW
Permit
Type
Issued
EUTL 110
EROW 12
TRAN 57
EWTR 138
Review of Hydrology, Geotechnical, WQMP ,
Water/Sewer Feasibility, and Traffic Studies
Issuance of Conditions of Approval
Review of Civil Improvement Plans
Issuance of Public ROW Permits
Inspection during Construction
Project acceptance
Development
Type
Number of Plan Checks
Completed In Review
Residential 7 Tracts 12 SFR / 4 Tracts
Commercial 2 17
Number of Inspections Completed: 1,322
Engineering
Planning
Building

DEVELOPMENT ENGINEERING

SURVEYING /

MAPPING

SURVEYING / MAPPING
Surveying Support Completed
Developer Document Reviews 16
Engineering Department CIP 8
Public Works 4
SCLA 1
VMUS 1
Economic Development 1

TRAFFIC

MAINTENANCE

TRAFFIC MAINTENANCE
Activity Total
#
Preventive Maintenance 127
USA’s Checked/Marked 59
Signal Emergency Repair 55
Pole Knock Downs 2
Street Light Repairs 21
Signs Maintained 885
Signs Fabricated 390
New Signs Installed 71
Gallons of Paint Used 41
Red Curb Footage Painted 8,780
Standby Calls 67