Attachment A
Engineering FY 2024 Q4
Quarterly Update
City of Victorville
Engineering Department
Q4 REPORT 2024
April 1, 2024 through June 30, 2024
As we wrap up the Fiscal Year 2023-24, I am extremely proud of the work that our Engineering Department has completed this past fiscal year. In addition to the project highlights that are forthcoming, here are some of our major
accomplishments this past Fiscal Year:
• Completed the Bear Valley Road Bridge Widening over
BNSF Tracks. The $12M project widened both sides of the bridge on Bear Valley Road over the BNSF Railroad,
provided additional turn pockets from Bear Valley Road to Ridgecrest Road, replaced traffic signal poles to
accommodate the widened road, constructed sidewalk
and adequate pavement width for future bike lanes to
cross over the bridge, and repaved a significant portion of Bear Valley Road.
• Completed the installation of a new traffic signal at Village Drive and TawneyRidge Lane.
• Rehabilitated 22,000 Linear Feet (LF) of sewer mains and replaced 11,000 LF of aging, leak-prone, fire flow deficient, small diameter pipelines within Old Town Victorville.
• Closed out eight residential housing tracts that were left partially completed by the Great Recession of 2008.
As we look to the future, we will continue to work on
our aggressive Capital Improvement Program that includes the construction of a new signal at Village Drive
and Puesta del Sol, five traffic signal modifications on 7th Street, additional street lighting improvements in Old Town Victorville, replacing over 600 water services, new water and sewer main capacity improvements, a one-
million recycled water tank at SCLA, multiple sidewalk
projects to improve accessibility, and four street
improvement projects on Mojave Drive, Roy Rogers Drive, Ridgecrest Road, and Bear Valley Road. In looking towards the future, our Department is in great hands.
We have a great young core of engineers that are not only learning the Victorville way of designing and managing
projects but delivering projects each and every day. We will continue to invest and mentor our young core so that we can ensure the future of our department. This group
includes two PE’s and four EITs, and it gives me great
pleasure to state that without a doubt our future is indeed very bright.
Fredy A. Bonilla, PE
City Engineer
ORGANIZATIONAL STRUCTURE
Project
UpdatesQ4
CONSTRUCTION
COMPLETED
CAPITAL IMPROVEMENT PROJECTS
Bear Valley Road Bridge
Widening over BNSF Tracks
Contractor: Riverside Construction
Construction Cost: $11,999,134.84
Construction Completed: January 17, 2024
Council Acceptance: June 18, 2024
Before
Keurig DrPepper
Improvements
Developer: Keurig DrPepper
Work Completed: Pavement widening, curb & gutter,
sidewalk and landscaping improvements on
Momentum Road and sidewalk and landscaping
improvements on Gateway Drive.
Construction Completed: June 2024
AFTER
AFTER
BEFORE
Momentum Rd
Adelanto Rd
Keurig Dr
Pepper
BEFORE
Tract 16774 Street
Improvements
Developer: Frontier Communities
Tract 16774: 150 Single Family Residential Units
Work Completed: New Class 1 Bike Lane on La Mesa Road
with Landscaping & Irrigation Improvements, Reconstruction of Peña Road with Landscaping & Irrigation Improvements.
Construction Completed: April 2024
Tract 14741 Street
Improvements
Developer: K. Hovanian Homes
Tract 14741: 159 Single Family Residential Units
Work Completed: Glass paving of interior street
including Luna and Topaz Roads.
Construction Completed: June 2024
FICUS / DAWN RIDGE
DAWN RIDGE / EVASTON
Before
After
CONSTRUCTION
IN PROGRESS
CAPITAL IMPROVEMENT PROJECTS
Bear Valley Road Reconstruction Project
This project will reconstruct Bear Valley Road from Amethyst Road to Hwy 395.
Contractor: C.A. Rasmussen
Contract Amount: $8,944,073
Contract Award: October 17, 2023
Start of Construction: March 18, 2024
Estimated Construction Completion: July 2024
Traffic Signal Installation at
Mojave Drive/Condor Road
This project will install a traffic signal at the intersection of Mojave Dr. and Condor Rd.
Contractor: Belco Elecnor
Contract Amount: $795,622
Contract Award: September 5, 2023
Start of Construction: May 13, 2024
Estimated Construction Completion: August 2024
Installation of Retroreflective Tape
This project will install retroreflective border around 96 traffic signal backplates to improve safety.
Completed to Date: 9 out of 96
Estimated Construction Completion: Summer 2025
3rd Avenue Extension to Bear Valley
Road Project
This project will extend 3rd Avenue from the existing end to Bear Valley Road. Project also includes the installation of a new traffic signal at the Bear Valley Road/3rd Avenue
Intersection. The extension of 3rd Avenue will now fully connect Bear Valley Road to Green Tree Boulevard.
Improvement to be fully funded by a private developer
Estimated Completion Date: August 2024
Pressure Reducing Valve
Installation at Mojave Drive and
Amethyst Road (2
nd Feed to SCLA)
This project will provide an additional potable water feed to the Southern California Logistic Airport (SCLA) by
interconnecting pressure zone 3290 to pressure zone 3170.
Contractor: Kirtley Construction Inc (TK Construction)
Contract Amount: $365,600
Contract Award: November 7, 2023
Start of Construction: April 6, 2024
Estimated Construction Completion: July 2024
This project will replace 638, 40-year old PVC water service lines with copper piping.
Contractor: Christensen Brothers General Engineering Inc.
Contract Amount: $2,631,405
Contract Award: October 17, 2023
Start of Construction: April 15, 2024
Estimated Construction Completion: Fall 2024
Phase I – Completed June 14, 2024
Phase II – 50% Complete
Water Service Replacement Project
Area 6 – Golden Triangle Area
Old Town Septic to Sewer Conversion
Project (SEP Program)
Legend
New Sewer Line
This project will connect three residences in Old Town
Victorville to the municipal sewer system to prevent
environmental degradation of groundwater. The new
sewer connection also includes a lift station.
Contractor: Kerns, Inc.
Contract Amount: $724,223
Contract Award: April 16, 2024
Start of Construction: June 24, 2024
Estimated Construction Completion: Fall 2024
VMUS - Kern River
Gas Interconnect Project
This project will provide a new interconnect directly to Kern River Gas Transmission Company which will result in
increased capacity and optimum pressures at a lower cost supporting SCLA's ultimate natural gas demands.
Contractor: Arizona Pipeline
Construction Estimate: $709,025
Contract Awarded: May 7, 2024
Start of Construction: June 17, 2024
Estimated Construction Completion: Fall 2024
CAPITAL IMPROVEMENT PROJECTS
UPCOMING
CONSTRUCTION
PROJECTS
New Traffic Signal at Village Drive and
Puesta Del Sol Project
This project will install a traffic signal at the Village/Puesta Del Sol Intersection.
Contractor: Belco Elecnor
Contract Amount: $1,120,480
HSIP Grant Amount: $526,500
Contract Award: March 19, 2024
Estimated Start of Construction: July 2024
Estimated Construction Completion: Spring 2025
Puesta Del Sol Dr
7th Street
Traffic Signal Modifications Project
This project will increase safety by replacing
outdated traffic signal equipment, improving
detection, accessibility, and lighting.
Contractor: Belco Elecnor
Contract Amount: $2,876,393
HSIP Grant Amount: $1,320,000
Contract Award: March 19, 2024
Estimated Start of Construction: July 2024
Estimated Construction Completion: Spring 2025
Eucalyptus Street Infrastructure
Restoration Project
This project will relocate a potable water line
and repair an existing RCP storm drain.
Open Bid Date: July 11, 2024
Estimated Start of Construction: Fall 2024
Estimated Completion Date: Spring 2025
Mojave Drive
Citywide Pavement Preservation and
Maintenance Project
Mojave Drive
This project will include micro-surfacing and slurry
seal treatment for 14 miles of City streets and 2
City Park parking lots.
Open Bid Date: July 30, 2024
Estimated Start of Construction: Fall 2024
Estimated Completion Date: Spring 2025
Mojave/Village Drive Pipeline Repair
Project
This project will re-route an existing leaking
potable water line currently located under the
sidewalk by the north-east corner of Mojave
and Village Drive.
Contractor: Kelley’s Underground Inc.
Contract Award: June 4, 2024
Contract Amount: $159,197
Estimated Start of Construction: July 2024
Estimated Completion Date: Fall 2024
Mojave Drive
PROJECTS IN
DESIGN PHASE
CAPITAL IMPROVEMENT PROJECTS
PROJECTS IN DESIGN PHASE
ESTIMATED
CONSTRUCTION
START DATE
1MG Recycled Water Storage Tank Project FY 2024/2025
Sewer Capacity Improvement Project C2&C3 FY 2024/2025
Pipeline Replacement Project – Area 7 FY 2024/2025
Solitude Circle Pavement Repair Project FY 2024/2025
Block Wall Project –El Evado Arsenic Treatment Plant FY 2024/2025 Block Wall Project - La Mesa Arsenic Treatment Plant FY 2024/2025 Block Wall Project - VWD Well Site 203 FY 2024/2025
Pipeline Replacement Project – Area 28 FY 2025/2026
Pipeline Replacement Project – Area 6 FY 2025/2026
Santa Fe Wash Sewer Relocation Project FY 2026/2027
Pipeline Replacement Project – Area 5 FY 2026/2027
Doris Davies Park Oro Grande Channel Repair FY 2024/2025 Rectangular Rapid Flashing Beacons FY 2024/2025
Old Town Sidewalk Project – Phase II FY 2024/2025
Village Drive Sidewalk Project FY 2024/2025
La Paz Drive from I-15 NB ramp to 7th Street FY 2025/2026 Bear Valley Road Street Improvements from Bellflower to Montevista Rd FY 2025/2026 Ridgecrest Street Improvements from BVR to Pahute Ave FY 2026/2027 Mojave Drive Street Improvement Project from Amargosa to Condor Rd FY 2027/2028
DEVELOPMENT REVIEW
Grant Program APPLICATION DEADLINE
HSIP September 2024
SS4A - LSRP August 2024
Project Requested
Amount
Award Decision
Made by
Grant
Program
Active Transportation Plan $ 350,000 December 2024 ATP
La Paz Drive Street Improvements
from 7th Street to I-15
$ 628,000 December 2024 ATP
Ridgecrest Street Improvements
from BVR to Pahute
$ 753,000 December 2024 ATP
Mojave Drive Street Improvements
from Amargosa to Condor Road.
$ 3,200,000 December 2024 ATP
FUNDING OPPORTUNITIES
GRANT APPLICATIONS SUBMITTED
FUTURE TARGETED GRANT APPLICATIONS
ATP: Active Transportation Grant Program
HSIP: Local Highway Safety Improvement Grant Program
SS4A: Safe Streets and Roads for All Grant Program
DEVELOPMENT
ENGINEERING
DEVELOPMENT REVIEW
Permit Type Issued
Utility 112
Right-of-Way 15
Transportation 30
Water 133
Review of Hydrology, Geotechnical, WQMP ,
Water/Sewer Feasibility, and Traffic Studies
Issuance of Conditions of Approval
Review of Civil Improvement Plans
Issuance of Public ROW Permits
Inspection during Construction
Project acceptance
Development
Type
Number of Plan Checks
Completed In Review
Residential 41 9
Commercial 32 46
Number of Inspections Completed: 1,054
Engineering
Planning
Building
DEVELOPMENT ENGINEERING
SURVEYING /
MAPPING
SURVEYING / MAPPING
Surveying Support Completed
Developer Document Reviews 12
Engineering Department CIP 6
Public Works 4
SCLA 1
VMUS 1
Economic Development 1
TRAFFIC
MAINTENANCE
TRAFFIC MAINTENANCE
Activity Total
#
Preventive Maintenance 124
USA’s Checked/Marked 57
Signal Emergency Repair 29
Pole Knock Downs 2
Street Light Repairs 2
Signs Maintained 877
Signs Fabricated 272
New Signs Installed 102
Gallons of Paint Used 284
Red Curb Footage Painted 4,264
Standby Calls 62