ATTACHMENT B
Construction Agreement
1 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
CONSTRUCTION AGREEMENT
BY AND BETWEEN
THE CITY OF VICTORVILLE
AND
CONTRACTORS CONNECT, INC. DBA
MOE’S LANDSCAPING
FOR
BRENTWOOD BEAUTIFICATION PROJECT,
PROJECT CC25-071
THIS CONSTRUCTION AGREEMENT (the “Agreement”) dated this ________ day of ______________, 20___, for reference purpose only, is made and entered into by and between the City of Victorville, a municipal corporation located in the County of San Bernardino, State of California, hereinafter referred to as the “City”, and Contractors Connect, Inc. dba Moe’s Landscaping, a California corporation, hereinafter referred to as the “Contractor”. The City and the Contractor are sometimes hereinafter referred to as a “Party” and collectively referred to as the “Parties.”
RECITALS:
WHEREAS, the City requires Brentwood Beautification Project, Project CC25- 071 (the Project); and
WHEREAS, in light of the facts set forth above, the City desires to retain Contractor in connection with Brentwood Beautification Project, Project CC25-071; and
NOW, THEREFORE, IN CONSIDERATION OF THE COVENANTS, CONDITIONS, AND
PROMISES CONTAINED HEREIN AND FOR SUCH OTHER GOOD AND VALUABLE CONSIDERATION, THE PARTIES HERETO AGREE AS FOLLOWS:
Section 1. RECITALS
The Recitals set forth above are true and correct and are hereby incorporated into this Agreement by this reference, as though set forth herein.
Section 2. TERM OF AGREEMENT
This Agreement shall commence within Fifteen (15) Calendar Days after issuance of Notice to Proceed (the “Commencement Date”) and shall terminate upon completion of the Project Forty-five (45) Working Days after Commencement Date (the “ Termination Date”), unless sooner terminated in accordance with the provisions of this Agreement (the “Term”). From and after the Termination Date, and upon subsequent agreement by the Parties, this Agreement may continue on a month-to-month basis until terminated pursuant to Section 3 below.
2 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
Section 3. TERMINATION OR SUSPENSION
a. This Agreement may be terminated or suspended without cause by either Party at any time, provided that the Party initiating the termination provides the other Party at least thirty (30) days advance written notice of s uch termination or suspension. In the event of such termination, the City shall only be liable for payment under the payment provisions of this Agreement for satisfactory work rendered or supplies actually furnished prior to the effective date of termination.
b. This Agreement may be terminated or suspended with cause by either Party at any time, provided that the Party initiating termination provides the other Party at least ten (10) days advance written notice of such termination or suspension. In the event of such termination, the City shall only be liable for payment under the payment provisions of this Agreement for satisfactory work rendered or supplies actually furnished prior to the effective date of termination.
Section 4. CONTRACT DOCUMENTS; PRIORITY
a. Contract Documents. The Contract Documents consist of the following documents, all of which are either attached hereto as exhibits or are incorporated herein by this reference.
Said Contact Documents are intended to be correlative and const itute Contractor’s performance obligations:
1. This Agreement.
2. Exhibits A & B.
3. Notice Inviting Bids for the Project.
4. Special Provisions.
5. Faithful Performance and Payment Bond.
6. Non-Collusion Declaration.
7. Guaranty.
b. Interpretation. In the event of any conflict between any of the Contract Documents, the document highest in the order of precedence (from highest to lowest), as set forth in Subsection 4.a above shall control.
Section 5. CONTRACTOR’S OBLIGATIONS
Contractor shall complete the Project as specifically set forth in the Contract Documents.
Contractor shall furnish, at its own cost and expense, all labor, services, material, tools, equipment, supplies, transportation, and any other items and facilities necessary therefore, as provided in the Contract Documents.
Section 6. COMPENSATION
The Contractor agrees to receive and accept the following amount, not to exceed Two Hundred Eighty- seven Thousand Five Hundred and 00/100 Dollars ($287,500.00) , as full compensation for furnishing; all materials, doing all the work contemplated and embraced in this contract, all loss or damage arising out of the nature of the work aforesaid, the action of the elements, any unforeseen difficulties or obstructions w hich may arise or be encountered in the execution of the work until its acceptance by the City, and for all risks of every description connected with the work, all expenses incurred by or in consequence of the suspension or discontinuance of work well and faithfully completing the whole work, thereof, according to the 3 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
requirements of the agreement documents and to the satisfaction of Doug Mathews, Director of Public Works and Water, or his designee to wit: See Exhibit “A”, Scope of Work.
Section 7. BID PROPOSAL FORMS
The City shall pay Contractor as provided in the Bid Proposal Forms, attached hereto as Exhibit “B”, and incorporated herein by this reference as though set forth in full, subject to approval of the City, when applicable.
Section 8. PREVAILING WAGES
a. Compliance with State and Federal Wage Requirements. As a federally funded Project, the work called for in this Contract must be carried out in compliance with both Federal and State prevailing wage rates, together with all other applicable State and Federal labor laws and requirements specified in the Contract Documents. It is further expressly agreed by and between the Parties hereto that should there be any conflict between the terms of this Contract and the Bid Proposal and Price Schedules submitted by Contractor, then this Contract shall control, and nothing herein shall be considered as an acceptance of the terms of said Bid Proposal conflicting with the requirements of this Section.
b. State Wages - In accordance with the provisions of California Labor Code Sections (1720,1770- 1776, 1810, 1813 and 1815, as amended and applicable), the Sta te Director of Industrial Relations has determined the general prevailing rates of per diem wages in the locality where the Project is to be done. Copies of the updated Wage Determination rates are available from the CITY and the State of California via the internet at www.dir.ca.gov.
Additionally, copies of the prevailing rate of per diem wages and federal wage decision rates are on file at the City of Victorville Finance Department and shall be made available for review to any interested party on reques t. Notwithstanding anything in the Contract Documents to the contrary, Contractor and all subcontractors shall pay not less than said specified State of California rates to all workers employed by them in the execution of the work contemplated by this Contract. Contractor shall be responsible for using the correct and current prevailing wage rates.
c. AB219 (as applicable) adds Section 1720.9 to the Labor Code, the hauling and delivery of ready-mixed concrete to carry out a public works contract, with respect to contracts involving state agency or any political subdivision of the state. Section 1720.9 defines the term “ready-mixed” concrete and specifies that the rate of pay shall be the current prevailing wage “for the geographical area in which the factory or batching plant is located” as determined by the DIR. The statute also requires a written agreement between the party hauling or delivering the ready-mixed concrete and the party that engaged its services. Nothing in Section 1720.9 shall cause any company to be treated as a contractor or subcontractor for any purpose other than the application of this chapter of the Labor Code.
d. The delivery company shall provide certified payroll records under Labor Code section 1776(a) to the party that engaged its services and to the general contractor within five working days after the employee has been paid, accompanied by a written time record within five working days after the employee has been paid, accompanied by a written time record. The time record must be certified by each driver for the performance of job duties.
e. Federal Wages – In accordance with the provisions of the Davis -Bacon Act, and related Federal labor requirements in the Contract Documents with which Contractor has 4 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
agreed to comply , the Secretary of Labor has determined the general prevailing wage rates, applicable to federally funded construction projects. A copy of the current General Federal Wage Decision applicable to the work to be performed on this Project is attached to this Contract as Exhibit “C”. Contractor and all subcontractors shall pay not less than said specified Federal rates to all workers employed by them in the execution of the work under this Contract.
Contractor shall be responsible for using the correct and current Federal prevailing wage rates.
f. Payment of State Wages Required when Higher. Notwithstanding the provisions of Subsection c above, payment of State Prevailing Wage Rates when higher than Federal Wage Rates, are required whenever federally funded or assisted projects are controlled or carried out by California awarding bodies of any sort. The City is considered a California awarding body. Therefore, the higher of State Prevailing Wage and Federal Wage Rates shall apply to this Project and shall be paid by Contractor and all subcontractors.
g. Contractor shall be solely responsible for using the correct wage decision or determination and performing accordingly. An error on the part of any awarding body does not relieve the Contractor from the responsibility for payment of the correct State prevailing wage and compliance with the maintenance and inspection of payroll records, posting of prevailing wage rates at work site, employment of apprentices, and other requirements of California Labor Code Section 1720, et seq.; California Code of Regulations, Title 8, Section 16000 et seq.; and all other applicable State labor laws. Contractor further acknowledges and agrees that it will be independently responsible for reviewing the applicable laws and regulations and effectuating compliance with those laws. Contractor will require the same of all its subcontractors.
h. Contractor shall provide completed WEEKLY CERTIFIED PAYROLL and DAILY SIGN IN SHEETS with each invoice presented to the CITY, substantially in the form and containing the information set forth on the sample Weekly Certified Payroll and Daily Sign In Sheets provided in the Contract Documents. Payment of said invoices WILL be delayed absent these documents.
i. Contractor shall provide completed EMPLOYEE INFORMATION SHEETS, substantially in the f orm and containing the information set forth on the sample Employee Information Sheets provided in the Contract Documents, for each employee listed on the Weekly Certified Payroll or Daily Sign -In Sheets prior to, or along with the first invoice. This document is required only once per employee. Payment of said invoices WILL be delayed absent these documents.
j. The statutory penalties for failure to pay prevailing wage or to comply with St ate wage and hour laws will be enforced. Contractor must forfeit to CITY TWENTY -FIVE DOLLARS ($25.00) per day for each worker who works in excess of the minimum working hours when Contractor does not pay overtime. In accordance with the provisions of Labor Code Sections 1810 et seq., eight (8) hours is the legal working day.
Section 9. W ORKERS’ COMPENSATION INSURANCE
Contractor shall procure and maintain, at its own expense, during the Term of this Agreement, workers’ compensation insurance, providing coverage as required by the California State Workers’ Compensation Law. If any class of employees employed by Contractor is not protected by the California State Workers’ Compensation Law, Contractor shall provide adequate insurance for the protection of such employees to the satisfaction of the City.
5 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
In conformance with current statutory requirements of Section 1860 et seq., of the Labor Code of the State of California, the undersigned confirms the following as their certification:
I am aware of the provisions of Section 3700 of the Labor Code which requires every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions before commencing the performance of the work of this contract.
Section 10. NOTICE TO PROCEED
No work, service, material, or equipment shall be performed or furnished under this Contract unless and until a Notice to Proceed has been given to the Contractor by the City.
Contractor shall commence work pursuant to the Contract Documents as directed by the City in the Notice to Proceed, and to diligently execute the same to completion within the time limits set forth in the Contract Documents.
Section 11. COMPLIANCE WITH LAWS
Contractor shall comply with all local, state, and federal laws and regulations applicable to the performance of the work required by the Contract Documents, including any rule, regulation, or bylaw governing the conduct or performance of Contractor, its employees, officers, board members, agents, independent contractors, and subcontractors. Unless otherwise specified in the Contract Documents, all required permits and licenses shall be held or obtained by the Contractor at its sole expense.
Section 12. COMMERCIAL GENERAL AND AUTOMOBILE LIABILITY
INSURANCE
Contractor shall procure and maintain at its own expense, during the term of this Agreement, com mercial general liability insurance, of not less than One Million Dollars ($1,000,000) per occurrence, and Two Million Dollars ($2,000,000) in the aggregate, for bodily injury, personal injury, death, loss, or damage resulting from the wrongful or negligent acts by the Contractor or its officers, employees, servants, volunteers, and agents and independen t contractors.
Contractor shall further procure and maintain, at its own expense, during the Term of this Agreement, commercial vehicle liability insurance covering personal injury and property damage, of not less than One Million Dollars ($1,000,000) Combined Single Limit, covering any vehicle(s) utilized by Contractor or its officers, employees, servants, volunteers, or agents and independent contractors in performing the services required by this Agreement.
Section 13. POLLUTION LIABILITY
Contractors Pollution Liability and/or Asbestos Pollution Liability and/or Errors & Omissions applicable to the work being performed, with a limit no less than $1,000,000 per claim or occurrence and $1,000,000 aggregate per policy period of one year.
Section 14. INSTALLATION FLOATER
Contractor, and or any of its subcontractors, suppliers, vendors, employees, or person whom it performing any work under this agreement shall purchase, and maintain insurance to the full contract and insurable value thereof commonly referred to as an Installation Floater 6 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
policy that offers “Installation” coverage for all materials, supplies, equipment, and property obtained by, or for Contractor, which is to become part of the work while such equipment and property is stored at the jobsite, at temporary locations, or while in transit to the project from such temporary locations. Contractor, and or any of its subcontractors, suppliers, vendors, employees, or person whom is performing any work under this agreement shall also be responsible for insuring their owned, leased/rented or borrowed equipment. Insurance shall name the City as a Loss Payee as their interest may appear and include a Waiver of Subrogation Endorsement(s) in favor of the City of Victorville.
Section 15. ADDITIONAL INSURED
Notwithstanding any inconsistent statement in any required insurance policies or any subsequent endorsements attached thereto, the protection offered by all policies, except for Workers' Compensation coverage, shall bear an endorsement whereby it is provided that, the City and its officers, employees, servants, volunteers, and agents and independent contractors, including, without limitation, the City Attorney, are named as Additional Insureds.
Section 16. WAIVER OF SUBROGATION RIGHTS
Contractor shall require the carriers of all required insurance policies to waive all rights of subrogation against the City and its officers, volunteers, employees, contractors, and subcontractors. Each policy of insurance shall be endorsed to reflect such waiver.
Section 17. PROOF OF INSURANCE COVERAGE; REQUIRED PRIOR TO
COMMENCEMENT OF SERVICES
a. Contractor shall secure from a good and responsible company or companies authorized to do insurance business in the State of California the policies of insurance required by this Agreement and furnish to the City Clerk certificates of said insurance at least one (1) day prior to the commencement of any services to be performed under this Agreement.
b. The certificates of insurance shall bear an endorsement whereby it is provided that, in the event of cancellation or amendment of any required insurance policy for any reason whatsoever, the City shall be notified by mail, postage prepaid, not less than thirty (30) days before the cancellation or amendment is effective. In the case of non -payment, ten (10) days’ advance written notice shall be given.
c. The certificates of insurance shall bear an endorsement whereby it is provided that the respective insurance policy shall not be terminated or expire without first providing thirty (30) days written notice to the City of such termination or expiration.
d. The certificates of insurance shall indicate that the respective insurance policy will be maintained throughout the Term of this Agreement.
e. The commercial general liability and vehicle liability policies shall be endorsed to contain the following provision: “For any claims related to this contract, the Contractor’s insurance coverage shall be primary and non-contributory and at least as broad as ISO CG 20 01 04 13 as respects the City, its officers, officials, employees, and volunteers. Any insurance or self -insurance maintained by the City, its officers, officials, employees, or volunteers shall be excess of the Contractor’s insurance and shall not contribute with it. This requirement shall also apply to any Excess or Umbrella liability policies.” 7 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
Section 18. TIME OF THE ESSENCE
Time is of the essence in the performance of this Agreement.
Section 19. INDEMNIFICATION
Notwithstanding the limits of any insurance, Contractor shall indemnify the City, its officials, officers, agents, volunteers and employees against, and will hold and save them and each of them harmless from, any and all actions, suits, claims, damages to persons or property, losses, costs, penalties, obligations, errors, omissions or liabilities, (herein "claims or liabilities") that may be asserted or claimed by any person, firm or entity arising or alleged to arise out of or in connection with the negligent performance of the work, operations or activities of Contractor, its agents, employees, subcontractors, or invitees, provided for herein, or arising or alleged to arise from the negligent acts or omissions of Contractor hereunder, or arising or alleged to arise from Contractor's negligent performance of or failure to perform any term, provision, covenant or condition of this Agreement, but excluding such claims or liabilities or portion of such claims or liabilities arising or alleged to arise from the negligence or willful misconduct of the City its officials, officers, agents, volunteers or employees, and in connection therewith:
a. Contractor will defend any action or actions filed in connection with any of said claims or liabilities and will pay all costs and expenses, including legal costs and attorneys' fees incurred in connection therewith;
b. Contractor will promptly pay any judgment rendered against the City, its officials, officers, agents or employees for any such claims or liabilities arising or alleged to arise out of or in connection with Contractor's (or its agents', employees', subcontractors' or invitees') negligent performance of or failure to perform such work, operations or activities hereunder; and Contractor agrees to save and hold the City, its officials, volunteers, officers, agents, and employees harmless there from;
c. In the event the City, its officials, officers, agents, volunteers or employees is made a Party to any action or proceeding filed or prosecuted against Contractor for such damages or other claims arising or alleged to arise out of or in connection with the negligent performance of or failure to perform the work, operation or activities of Contractor hereunder, Contractor shall pay to the City, its officials, volunteers officers, agents or employees, any and all costs and expenses incurred by the City, its officers, agents or employees in such action or proceeding, including but not limited to, legal costs and attorneys' fees for counsel acceptable to City;
d. Contractor's duty to defend and indemnify as set out in this Section shall include any claims, liabilities, obligations, losses, demands, actions, penalties, suits, costs, expenses or damages or injury to persons or property arising or alleged to arise from, in connection with, as a consequence of or pursuant to any state or federal law or regulation regarding hazardous substances, including but not limited to the Federal Insecticide, Fungicide and Rodenticide Act ("FIFRA"), Comprehensive Environmental Response, Compensation and Liability Act of 1980 ("CERCLA"), Resource Conservation and Recovery Act of 1976 ("RCRA"), the Hazardous and Solid Waste Amendments of 1984, the Hazardous Material Transportation Act, the Toxic Substances control Act, the Clean Air Act, the Clean Water Act, the California Hazardous Substance Account Act, the California Hazardous Waste Control Law or the Porter -Cologne Water Quality Control Act, as any of those statutes may be amended from time to time;
8 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
The Contractor's indemnification obligations pursuant to this Section shall survive the termination of this Agreement. Contractor shall require the same indemnification from all subcontractors.
Section 20. REPORTS
Upon request by Doug Mathews, Director of Public Works and Water, or his designee, Contractor shall prepare and submit reports concerning Contractor's performance of the work required by this Agreement.
Section 21. RECORDS
a. Contractor shall keep such books and records as shall be necessary to perform the services required by this Agreement and enable Doug Mathews, Director of Public Works and Water, or his designee, to evaluate the cost and the performance of such services.
b. Books and records pertaining to costs shall be kept and prepared in accordance with generally accepted accounting principles. Doug Mathews, Director of Public Works and Water, or his designee, shall have full and free access to such books and records at all reasonable times, including the right to inspect, copy, audit, and make records and transcripts from such records.
c. Doug Mathews, Director of Public Works and Water, or his designee, shall have full and free access to such books and records at all reasonable times, including the right to inspect, copy, audit, and make records and transcripts from such records.
d. Records and supporting documents pertaining to the use of f unds paid to Contractor hereunder shall be retained by Contractor and made available to Doug Mathews, Director of Public Works and Water, or his designee, for purposes of performing an audit for a period of five (5) years from the date of termination of this Agreement.
Section 22. MODIFICATIONS AND AMENDMENTS
This Agreement may be modified or amended only by a written instrument signed by both Parties.
Section 23. ENTIRE AGREEMENT
a. This Agreement supersedes any and all prior or contemporaneous agreements, either oral or written, between the City and Contractor with respect to the subject matter of this Agreement.
b. The Contract Documents contain all of the covenants and agreements between the Parties with respect to the subjec t matter herein, and each Party acknowledges that no representations, inducements, promises, or agreements have been made by or on behalf of any Party, except those covenants and agreements in this Agreement and the Contract Documents.
c. No agreement, statement, or promise with respect to the subject matter of the Contract Documents, which is not contained in the Contract Documents, or in a valid modification or amendment to the Contract Documents, shall be valid or binding on either Party. 9 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
Section 24. AMBIGUITIES
This Agreement is in all respects intended by each Party hereto to be deemed and construed to have been jointly prepared by the Parties and the Parties hereby expressly agree that any uncertainty or ambiguity existing herein shall not be interpreted against either of them.
Except as expressly limited by this paragraph, all of the applicable rules of interpretation of contract shall govern the interpretation of any uncertainty or ambiguity of this Agreement.
Notwithstanding the foregoing, the Parties agree that Exhibit “B” is attached hereto for reference purposes and to the extent there are any ambiguities, inconsistencies or conflicts between the terms of this Construction Agreement and Exhibit “ B” the terms of this Construction Agreement shall control and nothing set forth in Exhibit “B” shall be deemed to supersede any of the provisions of this Construction Agreement.
Section 25. NOTICES
a. Any notice to be provided pursuant to this Agreement shall be in writing, and all such notices shall be delivered by personal service or by deposit in the United States mail, certified or registered, return receipt requested, with postage prepaid, and addressed to the Parties as follows:
To the City: Doug Mathews, Director of Public Works & Water Public Works and Water Department
City of Victorville
14343 Civic Drive
Victorville, CA 92392
To Contractor: Mohammed Abdown, CEO
Contractors Connect, Inc. dba
Moe’s Landscaping
14060 Estero Road
Victorville, CA 92392
b. Notices, payments, and other documents shall be deemed delivered upon receipt by personal service or as of the second (2nd) day after deposit in the United States mail.
Section 26. NON-LIABILITY OF CITY OFFICERS AND EMPLOYEES
No officer or employee of the City shall be personally liable to Contractor, or any successor in interest, in the event of any default or breach by the City or for any amount, which may become due to Contractor or to its successor(s), or for any breach of any obligation of the terms of this Agreement.
Section 27. REVIEW BY ATTORNEYS
Each Party hereto has had its attorneys review this Agreement and all related documents. Each Party hereto has consulted with its attorneys and has negotiated the terms of this Agreement based on such consultation.
10 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
Section 28. CARE OF WORK
Contractor must adopt reasonable methods during the life of the Agreement to furnish continuous protection to the work, and the equipment, materials, papers, documents, plans, studies and other components to prevent losses or damages, and will be responsible for all damages, to persons or property, until acceptance of the work by the City, except those losses or damages as may be caused by the City’s own negligence. The performance of the work by Contractor or the payment of money by the City shall not relieve Contractor from any obligation to correct any incomplete, inaccurate, or defective work at no further cost to the City, when such inaccuracies are due to the negligence of Contractor.
Section 29. CAPTIONS AND HEADINGS
The captions and headings contained in this Agreement are provided for identification purposes only and shall not be interpreted to limit or define the content of the provisions described under the respective caption or heading.
Section 30. SUCCESSORS, HEIRS, AND ASSIGNS
Except as otherwise expressly provided herein, this Agreement shall be binding upon the successors, endorsees, assigns, heirs, and personal representatives of each of the Parties to this Agreement and, likewise, shall inure to the benefit of the successors, endorsees, assigns, heirs, and personal representatives of each of the Parties.
Section 31. GENDER; PLURAL
In this Agreement, unless the context clearly requires otherwise, the masculine, feminine and neuter genders and the singular and the plural shall include one another.
Section 32. SEVERABILITY
If any one or more of the sentences, clauses, paragraphs, or sections contained herein is declared invalid, void, or unenforceable by a court of competent jurisdiction, the same shall be deemed severable from the remainder of this Agreement and shall not affect, impair, or invalidate any of the remaining sentences, clauses, paragraphs, or sections contained herein.
Section 33. GOVERNING LAW
The validity of this Agreement and any of its terms or provisions, as well as the rights and duties of the Parties under this Agreement, shall be construed pursuant to and in accordance with California law.
Section 34. CUMULATIVE REMEDIES
Except with respect to rights and remedies expressly declared to be exclusive in this Agreement, the rights and remedies of the Parties are cumulative and the exercise by either Party of one or more of such rights or remedies shall not preclude the exercise by it, at the same or different times, of any other rights or remedies for the same default of any other default by the other Party.
11 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
Section 35. VENUE
All proceedings involving disputes over the terms, provisions, covenants, or conditions contained in this Agreement and all proceedings involving any enforcement action related to this Agreement shall be initiated and conducted in the applicable court or forum in San Bernardino County, California.
Section 36. ATTORNEY'S FEES
Should any litigation, specifically including but not limited to, arbitration and other non- judicial resolution of disputes be commenced between the Parties to this agreement concerning this agreement or the rights and duties of either i n relation thereto, the Parties prevailing in such litigation or other proceeding shall be entitled, in addition to such other relief as may be granted, to a reasonable sum as and for attorney fees in such litigation where the proceeding which, if not agreed upon by the Parties, shall be determined by the court or other entity in which such litigation or other proceeding is brought.
Section 37. EFFECTIVENESS OF AGREEMENT
This Agreement shall not be binding upon the City, until signed by the authorized representative(s) of Contractor , approved by the City’s Risk Manager, and executed by the authorized City personnel or Mayor.
Section 38. REPRESENTATIONS OF PARTIES AND PERSONS
EXECUTING AGREEMENT
a. Each of the Parties to this Agreement hereby represents that all necessary and appropriate actions of their governing bodies have been taken to make this Agreement a binding obligation of each of the Parties hereto.
b. The persons executing this Agreement warrant that they are duly authorized to execute this Agreement on behalf of and bind the Parties each purports to represent.
Section 39. COUNTERPARTS
This Agreement may be executed by the Parties in counterparts, and when executed by each of the Parties, each counterpart shall be deemed to be a part of this Agreement.
Section 40. CARB COMPLIANCE OBLIGATIONS
a. CARB Regulations. Contractor is aware of the California Air Resources Board (“CARB”) regulations mandating various emission reduction requirements. Contractor agrees to comply with all applicable CARB regulations (Title 13, Division 3 of the California Code of Regulations (“CCR”) prior to commencing any work hereunder and maintain compliance throughout the duration of this Contract.
(1) Vehicles with a Gross Vehicle Weight Rating (GVWR) greater than 8,500 lbs. and light -duty package delivery vehicles operated in California may be subject to CARB’s Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, please visit the CARB Advanced Clean Fleets (ACF) webpage at https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets. 12 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071 (2) E ffective January 1, 2024, CARB implemented amendments to the I n-Use Off- Road Diesel -Fueled Fleets Regulation (13 CCR Section 2449 et seq., the “Off- Road Regulation”) which apply broadly to all self -propelled off road diesel vehicles 25 horsepower or greater and other forms of equipment used in California (including any vehicles or equipment that is rented or leased). The Off - Road Regulation is available at:
https://ww2.arb.ca.gov/sites/default/files/barcu/regact/2022/offroaddiesel/appa-1.pdf. b. C
ontractor must comply with all CARB regulations and requirements, including without limitation, all applicable sections of the Off -Road Regulation (as codified in 13 CCR Section 2449 et seq.) throughout the term of the Project and this Contract. Contractor shall be solely liable for all costs associated with complying with the regulations, as well as for any and all penalties, fines, damages, or costs associated with violations or failures t o comply with the regulations. Contractor shall defend, indemnify, and hold harmless the City of Victorville, its elected and appointed officials, officers, agents, and employees from and against any and all claims, liabilities, costs, penalties, interest or other damages arising out of Contractor’s failure or alleged failure to comply with CARB regulations.
(
END OF THIS PAGE)
13 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
IN WITNESS WHEREOF, the Parties hereto have caused this Agreement to be executed as of the dates written below.
THE CITY OF VICTORVILLE CONTRACTORS CONNECT, INC. DBA
MOE’S LANDSCAPING
By: ________________________________ By: _______________________________ Elizabeth Becerra, Mohammed Abdown,
Mayor CEO
Dated: ______________________________ Dated: ______________________________
ATTEST
By: ________________________________
Jennifer Thompson,
City Clerk
Dated: _____________________________
By: ________________________________
Sandra Bostick,
Risk Manager
Dated: ______________________________
APPROVED AS TO STANDARD FORM
By: ________________________________
Andre de Bortnowsky,
City Attorney
Dated: _____________________________
14 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
EXHIBIT A
SCOPE OF WORK
City agrees to engage Contractor and Contractor agrees to furnish all necessary labor, tools, materials, and equipment for and do the Work for the Project. The Work shall be performed in accordance with: (i) as generally described in the Request for Bid, P roject Number CC25-071 and applicable Addenda for the Project, portions of which are attached hereto for ease of reference as Exhibit "A", and the entirety of which is currently on file in office of the City Clerk); and (ii) the prices set forth in Contractor’s Bid Proposal (attached as Exhibit "B").
CC25-071 BRENTWOOD BEAUTIFICATION PROJECT
CITY OF VICTORVILLE
PROJECT NUMBER CC25-071
BRENTWOOD BEAUTIFICATION PROJECT
SCOPE OF WORK
Zeros
cape Landscape Maintenance Assessment District 3 (LMAD 3) This scope of work outlines the landscape conversion to zeroscaping for LMAD 3. The project aims to implement a sustainable zeroscape approach to landscape maintenance within the designated district. The contractor will install zeroscape landscaping, retrofitting the existing irrigation system to support the newly installed features, which will include decomposed granite, rocks, boulders, trees, and shrubs.
Location:
This site is located off Hook Blvd., directly across from Brentwood Elementary, covering approximately 35,570 square feet.
Cont
ractor to provide:
• Materials List
Contractor shall perform the scope of work as follows:
• Reduc
e water consumption and promote sustainable landscaping practices. • Remove all ornamental turf and vegetation.
• Retrofit the existing irrigation system to suit the new landscape, using Schedule 40 PVC pipes with Schedule 80 PVC fittings. Install one bubbler per plant and tree; drip irrigation is not permitted.
• Obtain necessary permits through the D evelopment Department and Engineering Departments.
• Contractor is responsible for calling in all Dig Alerts and will be held accountable for any utility damages.
• Follow all traffic control requirements in accordance with the MUTCD and Watch Manual. • Submit a Traffic C ontrol Plan (TCP) to the City Engineering Department for review and approval before any lane delineation work.
• Remove and dispose of all spoils at the City of Victorville's Palmdale yard. • Report all ex posed tree roots to City staff before inspection before improvements are installed.
• Necessary use o f water will be allowed from the City irrigation systems on site. • Work schedule: Monday through Friday.
• Planting of al l plant materials will be in accordance with their seasonal timeline. • Rock s amples and colors will be provided to the City for review and approval prior to installation.
• Call t he City Public Works Department to schedule project inspections. • All decomposed granite that is placed shall have an additive to stabilize material c
reating a durable surface that resists the natural erosive powers of weather or heavy traffic while maintaining a natural aesthetic
• Maintain t he improvements for a 90-day maintenance period, to be monitored, inspected, and approved by the City Development Department • Warranty all improvements for the remaining 9- m onths after turning over the improvements to the City.
EXHIBIT A
15/Construction Agreement/Contractor Conect, Inc. dba Moe’s Landscaping/Project CC25-071 16 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
EXHIBIT B
B
ID PROPOSAL FORMS
S
ee Attachment
EXHIBIT B
17/Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
EXHIBIT B
18/Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
EXHIBIT B
19/Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071 16 Construction Agreement/Contractor Connect, Inc. dba Moe’s Landscaping/Project CC25-071
EXHIBIT C
G
eneral Federal Wage Decision
See Attachment
"General Decision Number: CA20250026 01/10/2025
Superseded General Decision Number: CA20240026
State: California
Construction Types: Building, Heavy (Heavy and Dredging) and Highway
County: San Bernardino County in California.
BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
______________________________________________________________ |If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. |
|renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate |
| | listed on this wage |
| | determination, if it is |
| | higher) for all hours |
| | spent performing on the |
| | contract in 2025. |
|______________________________|_____________________________| |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. |
|contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the |
| | applicable wage rate listed|
| | on this wage determination,|
| | if it is higher) for all |
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 1/32
| | hours spent performing on | | | that contract in 2025. | |______________________________|_____________________________| The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a
conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at
http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/03/2025
1 01/10/2025
ASBE0005-002 09/01/2023
Rates Fringes
Asbestos Workers/Insulator
(Includes the application of
all insulating materials,
protective coverings,
coatings, and finishes to all
types of mechanical systems).....$ 49.58 25.27 Fire Stop Technician
(Application of Firestopping
Materials for wall openings
and penetrations in walls,
floors, ceilings and curtain
walls)...........................$ 36.97 20.36 ---------------------------------------------------------------- ASBE0005-004 07/04/2022
Rates Fringes
Asbestos Removal
worker/hazardous material
handler (Includes
preparation, wetting,
stripping, removal,
scrapping, vacuuming, bagging
and disposing of all
insulation materials from
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 2/32
mechanical systems, whether
they contain asbestos or not)....$ 23.52 13.37 ---------------------------------------------------------------- BOIL0092-003 01/01/2024
Rates Fringes
BOILERMAKER......................$ 51.98 42.11 ---------------------------------------------------------------- * BRCA0004-011 05/01/2024
Rates Fringes
BRICKLAYER; MARBLE SETTER........$ 45.53 20.29 *The wage scale for prevailing wage projects performed in Blythe, China lake, Death Valley, Fort Irwin, Twenty-Nine Palms, Needles and 1-15 corridor (Barstow to the Nevada State Line) will be Three Dollars ($3.00) above the
standard San Bernardino/Riverside County hourly wage rate ---------------------------------------------------------------- BRCA0018-004 06/01/2023
Rates Fringes
MARBLE FINISHER..................$ 40.21 15.23 TILE FINISHER....................$ 34.78 13.64 TILE LAYER.......................$ 48.29 19.18 ---------------------------------------------------------------- BRCA0018-010 09/01/2023
Rates Fringes
TERRAZZO FINISHER................$ 39.95 14.65 TERRAZZO WORKER/SETTER...........$ 47.85 15.14 ---------------------------------------------------------------- CARP0213-001 01/01/2024
Rates Fringes
CARPENTER
(1) Carpenter, Cabinet
Installer, Insulation
Installer, Hardwood Floor
Worker and acoustical
installer...................$ 48.86 22.88
(2) Millwright..............$ 49.36 22.88
(3) Piledrivermen/Derrick
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 3/32
Bargeman, Bridge or Dock
Carpenter, Heavy Framer,
Rock Bargeman or Scowman,
Rockslinger, Shingler
(Commercial)................$ 48.99 22.88
(4) Pneumatic Nailer,
Power Stapler...............$ 51.85 16.28
(5) Sawfiler...............$ 51.69 16.28
(6) Scaffold Builder.......$ 40.77 22.38
(7) Table Power Saw
Operator....................$ 51.70 16.28
FOOTNOTE: Work of forming in the construction of open cut sewers or storm drains, on operations in which horizontal lagging is used in conjunction with steel H-Beams driven or placed in pre- drilled holes, for that portion of a lagged trench against which concrete is poured, namely, as a
substitute for back forms (which work is performed by
piledrivers): $0.13 per hour additional.
---------------------------------------------------------------- CARP0213-002 07/01/2021
Rates Fringes
Diver
(1) Wet.....................$ 834.40 16.28
(2) Standby.................$ 445.84 16.28
(3) Tender..................$ 437.84 16.28
(4) Assistant Tender........$ 413.84 16.28
Amounts in ""Rates' column are per day
---------------------------------------------------------------- CARP0213-004 01/01/2024
Rates Fringes
Drywall
DRYWALL INSTALLER/LATHER....$ 48.86 22.88
STOCKER/SCRAPPER............$ 20.80 9.97
---------------------------------------------------------------- CARP0721-001 07/01/2021
Rates Fringes
Modular Furniture Installer......$ 21.85 7.15 ---------------------------------------------------------------- * ELEC0440-004 12/31/2024
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 4/32
COMMUNICATIONS AND SYSTEMS WORK
Rates Fringes
Communications System
Installer...................$ 45.23 3%+19.11
Technician..................$ 33.09 15.89
SCOPE OF WORK:
Installation, testing, service and maintenance of systems utilizing the transmission and/or transference of voice, sound, vision and digital for commercial, educational,
security and entertainment purposes for the following: TV monitoring and surveillance, background-foreground music, intercom and telephone interconnect, inventory control
systems, microwave transmission, multi-media, multiplex, nurse call systems, radio page, school intercom and sound, burglar alarms, fire alarms, and low voltage master clock systems in commercial buildings. Communication Systems that transmit or receive information and/or control systems that are intrinsic to the above listed systems; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding all other data
systems or multiple systems which include control function or power supply; excluding installation of raceway systems, conduit systems, line voltage work, and energy management systems. Does not cover work performed at China Lake Naval Ordnance Test Station.
---------------------------------------------------------------- ELEC0477-002 06/01/2024
Rates Fringes
Electricians:....................$ 53.15 3%+27.48 CABLE SPLICER: $1.50 per hour above Electrician rate.
TUNNEL WORK: 10% above Electrician rate.
ZONE PAY:
Zone A - 80 road miles from Post Office, 455 Orange Show Lane, San Bernardino, will be a free zone for all
contractors
Zone B - Any work performed outside Zone A's 80 road miles, shall add $12.00 per hour to the current wage scale.
---------------------------------------------------------------- ELEC1245-001 06/01/2024
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 5/32
Rates Fringes
LINE CONSTRUCTION
(1) Lineman; Cable splicer..$ 70.16 24.46
(2) Equipment specialist
(operates crawler
tractors, commercial motor
vehicles, backhoes,
trenchers, cranes (50 tons
and below), overhead &
underground distribution
line equipment).............$ 53.30 22.01
(3) Groundman...............$ 40.76 21.51
(4) Powderman...............$ 51.87 18.79
HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day,
Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day
---------------------------------------------------------------- ELEV0018-001 01/01/2024
Rates Fringes
ELEVATOR MECHANIC................$ 66.63 37.885+a+b FOOTNOTE:
a. PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service. b. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.
---------------------------------------------------------------- ENGI0012-004 08/01/2024
Rates Fringes
OPERATOR: Power Equipment
(DREDGING)
(1) Leverman................$ 64.10 38.75
(2) Dredge dozer............$ 58.13 38.75
(3) Deckmate................$ 58.02 38.75
(4) Winch operator (stern
winch on dredge)............$ 57.47 38.75
(5) Fireman-Oiler,
Deckhand, Bargeman,
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 6/32
Leveehand...................$ 56.93 38.75
(6) Barge Mate..............$ 57.54 38.75
---------------------------------------------------------------- ENGI0012-024 07/01/2023
Rates Fringes
OPERATOR: Power Equipment
(All Other Work)
GROUP 1....................$ 53.90 32.80
GROUP 2....................$ 54.68 32.80
GROUP 3....................$ 54.97 32.80
GROUP 4....................$ 56.46 32.80
GROUP 6....................$ 56.68 32.80
GROUP 8....................$ 56.79 32.80
GROUP 10....................$ 56.91 32.80
GROUP 12....................$ 57.08 32.80
GROUP 13....................$ 57.18 32.80
GROUP 14....................$ 57.21 32.80
GROUP 15....................$ 57.29 32.80
GROUP 16....................$ 57.41 32.80
GROUP 17....................$ 57.58 32.80
GROUP 18....................$ 57.68 32.80
GROUP 19....................$ 57.79 32.80
GROUP 20....................$ 57.91 32.80
GROUP 21....................$ 58.08 32.80
GROUP 22....................$ 58.18 32.80
GROUP 23....................$ 58.29 32.80
GROUP 24....................$ 58.41 32.80
GROUP 25....................$ 58.58 32.80
OPERATOR: Power Equipment
(Cranes, Piledriving &
Hoisting)
GROUP 1....................$ 55.25 32.80
GROUP 2....................$ 56.03 32.80
GROUP 3....................$ 56.32 32.80
GROUP 4....................$ 56.46 32.80
GROUP 5....................$ 56.68 32.80
GROUP 6....................$ 56.79 32.80
GROUP 7....................$ 56.91 32.80
GROUP 8....................$ 57.08 32.80
GROUP 9....................$ 57.25 32.80
GROUP 10....................$ 58.25 32.80
GROUP 11....................$ 59.25 32.80
GROUP 12....................$ 60.25 32.80
GROUP 13....................$ 61.25 32.80
OPERATOR: Power Equipment
(Tunnel Work)
GROUP 1....................$ 55.75 32.80
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 7/32
GROUP 2....................$ 56.53 32.80
GROUP 3....................$ 56.82 32.80
GROUP 4....................$ 56.96 32.80
GROUP 5....................$ 57.18 32.80
GROUP 6....................$ 57.29 32.80
GROUP 7....................$ 57.41 32.80
PREMIUM PAY:
$10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval
Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp
Pendleton
Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator.
SEE ZONE DEFINITIONS AFTER CLASSIFICATIONS
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Bargeman; Brakeman; Compressor operator; Ditch Witch, with seat or similar type equipment; Elevator
operator-inside; Engineer Oiler; Forklift operator
(includes loed, lull or similar types under 5 tons;
Generator operator; Generator, pump or compressor plant operator; Pump operator; Signalman; Switchman
GROUP 2: Asphalt-rubber plant operator (nurse tank
operator);Coil Tubing Rig Operator, Concrete mixer
operator-skip type; Conveyor operator; Fireman; Forklift operator (includes loed, lull or similar types over 5 tons; Hydrostatic pump operator; oiler crusher (asphalt or
concrete plant); Petromat laydown machine; PJU side dum jack; Screening and conveyor machine operator (or similar types); Skiploader (wheel type up to 3/4 yd. without
attachment); Tar pot fireman; Temporary heating plant
operator; Trenching machine oiler
GROUP 3: Asphalt-rubber blend operator; Bobcat or similar type (Skid steer); Equipment greaser (rack); Ford Ferguson (with dragtype attachments); Helicopter radioman (ground); Stationary pipe wrapping and cleaning machine operator
GROUP 4: Asphalt plant fireman; Backhoe operator (mini-max or similar type); Boring machine operator; Boxman or mixerman 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 8/32
(asphalt or concrete); Chip spreading machine operator; Concrete cleaning decontamination machine operator;
Concrete Pump Operator (small portable);Direct Push
Operator (Geoprobe or similar types) Drilling machine
operator, small auger types (Texoma super economatic or similar types - Hughes 100 or 200 or similar types -
drilling depth of 30' maximum); Equipment greaser (grease truck); Guard rail post driver operator; Highline cableway signalman; Hydra-hammer-aero stomper; Micro Tunneling
(above ground tunnel); Power concrete curing machine
operator; Power concrete saw operator; Power-driven jumbo form setter operator; Power sweeper operator; Rock Wheel Saw/Trencher; Roller operator (compacting); Screed operator (asphalt or concrete); Trenching machine operator (up to 6 ft.); Vacuum or much truck
GROUP 6: Articulating material hauler; Asphalt plant
engineer; Batch plant operator; Bit sharpener; Concrete joint machine operator (canal and similar type); Concrete planer operator; Dandy digger; Deck engine operator;
Derrickman (oilfield type); Drilling machine operator,
bucket or auger types (Calweld 100 bucket or similar types - Watson 1000 auger or similar types - Texoma 330, 500 or 600 auger or similar types - drilling depth of 45'
maximum); Drilling machine operator; Hydrographic seeder machine operator (straw, pulp or seed), Jackson track
maintainer, or similar type; Kalamazoo Switch tamper, or similar type; Machine tool operator; Maginnis internal full slab vibrator, Mechanical berm, curb or gutter(concrete or asphalt); Mechanical finisher operator (concrete,
Clary-Johnson-Bidwell or similar); Micro tunnel system
(below ground); Pavement breaker operator (truck mounted); Road oil mixing machine operator; Roller operator (asphalt or finish), rubber-tired earth moving equipment (single engine, up to and including 25 yds. struck); Self-propelled tar pipelining machine operator; Skiploader operator
(crawler and wheel type, over 3/4 yd. and up to and
including 1-1/2 yds.); Slip form pump operator (power
driven hydraulic lifting device for concrete forms);
Tractor operator-bulldozer, tamper-scraper (single engine, up to 100 h.p. flywheel and similar types, up to and
including D-5 and similar types); Tugger hoist operator (1 drum); Ultra high pressure waterjet cutting tool system operator; Vacuum blasting machine operator
GROUP 8: Asphalt or concrete spreading operator (tamping or finishing); Asphalt paving machine operator (Barber Greene or similar type); Asphalt-rubber distribution operator; 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 9/32
Backhoe operator (up to and including 3/4 yd.), small ford, Case or similar types; Cable Bundling Machine Operator
(excluding handheld); Cable Trenching Machine Operator
(Spider Plow or similar types) Cast-in-place pipe laying machine operator; Combination mixer and compressor operator (gunite work); Compactor operator (self-propelled);
Concrete mixer operator (paving); Crushing plant operator; Drill Doctor; Drilling machine operator, Bucket or auger types (Calweld 150 bucket or similar types - Watson 1500, 2000 2500 auger or similar types - Texoma 700, 800 auger or similar types - drilling depth of 60' maximum); Elevating grader operator; Grade checker; Gradall operator; Grouting machine operator; Heavy-duty repairman; Heavy equipment robotics operator; Kalamazoo balliste regulator or similar type; Kolman belt loader and similar type; Le Tourneau blob compactor or similar type; Loader operator (Athey, Euclid, Sierra and similar types); Mobark Chipper or similar; Ozzie padder or similar types; P.C. slot saw; Pneumatic concrete placing machine operator (Hackley-Presswell or similar
type); Pumpcrete gun operator; RCM Cementing Unit Operator, Rail/Switch Grinder Operator (Harsco or similar types)
Rock Drill or similar types; Rotary drill operator
(excluding caisson type); Rubber-tired earth-moving
equipment operator (single engine, caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. up to and including 50 cu. yds. struck);
Rubber-tired earth-moving equipment operator (multiple
engine up to and including 25 yds. struck); Rubber-tired scraper operator (self-loading paddle wheel type-John
Deere, 1040 and similar single unit); Self- propelled curb and gutter machine operator; Shuttle buggy; Skiploader
operator (crawler and wheel type over 1-1/2 yds. up to and including 6-1/2 yds.); Soil remediation plant operator; Surface heaters and planer operator; Tractor compressor drill combination operator; Tractor operator (any type
larger than D-5 - 100 flywheel h.p. and over, or
similar-bulldozer, tamper, scraper and push tractor single engine); Tractor operator (boom attachments), Traveling pipe wrapping, cleaning and bendng machine operator;
Trenching machine operator (over 6 ft. depth capacity,
manufacturer's rating); trenching Machine with Road Miner attachment (over 6 ft depth capacity): Ultra high pressure waterjet cutting tool system mechanic; Water pull
(compaction) operator
GROUP 10: Drilling machine operator, Bucket or auger types (Calweld 200 B bucket or similar types-Watson 3000 or 5000 auger or similar types-Texoma 900 auger or similar
types-drilling depth of 105' maximum); Dual drum mixer, 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 10/32
dynamic compactor LDC350 (or similar types); Monorail
locomotive operator (diesel, gas or electric); Motor
patrol-blade operator (single engine); Multiple engine
tractor operator (Euclid and similar type-except Quad 9 cat.); Rubber-tired earth-moving equipment operator (single engine, over 50 yds. struck); Pneumatic pipe ramming tool and similar types; Prestressed wrapping machine operator; Rubber-tired earth-moving equipment operator (single
engine, over 50 yds. struck); Rubber tired earth moving equipment operator (multiple engine, Euclid, caterpillar and similar over 25 yds. and up to 50 yds. struck), Tower crane repairman; Tractor loader operator (crawler and wheel type over 6-1/2 yds.); Woods mixer operator (and similar Pugmill equipment)
GROUP 12: Auto grader operator; Automatic slip form operator; Drilling machine operator, bucket or auger types (Calweld, auger 200 CA or similar types - Watson, auger 6000 or
similar types - Hughes Super Duty, auger 200 or similar types - drilling depth of 175' maximum); Hoe ram or similar with compressor; Mass excavator operator less tha 750 cu. yards; Mechanical finishing machine operator; Mobile form traveler operator; Motor patrol operator (multi-engine); Pipe mobile machine operator; Rubber-tired earth- moving equipment operator (multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck); Rubber-tired self- loading scraper operator (paddle-wheel-auger type self-loading - two (2) or more units)
GROUP 13: Rubber-tired earth-moving equipment operator
operating equipment with push-pull system (single engine, up to and including 25 yds. struck)
GROUP 14: Canal liner operator; Canal trimmer operator; Remote- control earth-moving equipment operator (operating a second piece of equipment: $1.00 per hour additional); Wheel excavator operator (over 750 cu. yds.)
GROUP 15: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple
engine-up to and including 25 yds. struck)
GROUP 16: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (single engine, over 50 yds. struck); Rubber-tired earth-moving equipment 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 11/32
operator, operating equipment with push-pull system
(multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
GROUP 17: Rubber-tired earth-moving equipment operator, operating equipment with push-pull system (multiple engine, Euclid, Caterpillar and similar, over 50 cu. yds. struck); Tandem tractor operator (operating crawler type tractors in tandem - Quad 9 and similar type)
GROUP 18: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar
types in any combination, excluding compaction units -
single engine, up to and including 25 yds. struck)
GROUP 19: Rotex concrete belt operator (or similar types); Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar types in any
combination, excluding compaction units - single engine, Caterpillar, Euclid, Athey Wagon and similar types with any and all attachments over 25 yds.and up to and including 50 cu. yds. struck); Rubber-tired earth-moving equipment
operator, operating in tandem (scrapers, belly dumps and similar types in any combination, excluding compaction
units - multiple engine, up to and including 25 yds. struck) GROUP 20: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar
types in any combination, excluding compaction units -
single engine, over 50 yds. struck); Rubber-tired
earth-moving equipment operator, operating in tandem
(scrapers, belly dumps, and similar types in any
combination, excluding compaction units - multiple engine, Euclid, Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
GROUP 21: Rubber-tired earth-moving equipment operator, operating in tandem (scrapers, belly dumps and similar
types in any combination, excluding compaction units -
multiple engine, Euclid, Caterpillar and similar type, over 50 cu. yds. struck)
GROUP 22: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system
(single engine, up to and including 25 yds. struck)
GROUP 23: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system
(single engine, Caterpillar, Euclid, Athey Wagon and
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 12/32
similar types with any and all attachments over 25 yds. and up to and including 50 yds. struck); Rubber-tired
earth-moving equipment operator, operating with the tandem push-pull system (multiple engine, up to and including 25 yds. struck)
GROUP 24: Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system
(single engine, over 50 yds. struck); Rubber-tired
earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid,
Caterpillar and similar, over 25 yds. and up to 50 yds. struck)
GROUP 25: Concrete pump operator-truck mounted; Rubber-tired earth-moving equipment operator, operating equipment with the tandem push-pull system (multiple engine, Euclid,
Caterpillar and similar type, over 50 cu. yds. struck); Spyder Excavator Operator, with all attachments
CRANES, PILEDRIVING AND HOISTING EQUIPMENT CLASSIFICATIONS GROUP 1: Engineer oiler; Fork lift operator (includes loed, lull or similar types)
GROUP 2: Truck crane oiler
GROUP 3: A-frame or winch truck operator; Ross carrier
operator (jobsite)
GROUP 4: Bridge-type unloader and turntable operator;
Helicopter hoist operator
GROUP 5: Hydraulic boom truck; Stinger crane (Austin-Western or similar type); Tugger hoist operator (1 drum)
GROUP 6: Bridge crane operator; Cretor crane operator; Hoist operator (Chicago boom and similar type); Lift mobile
operator; Lift slab machine operator (Vagtborg and similar types); Material hoist and/or manlift operator; Polar
gantry crane operator; Self Climbing scaffold (or similar type); Shovel, backhoe, dragline, clamshell operator (over 3/4 yd. and up to 5 cu. yds. mrc); Tugger hoist operator GROUP 7: Pedestal crane operator; Shovel, backhoe, dragline, clamshell operator (over 5 cu. yds. mrc); Tower crane
repair; Tugger hoist operator (3 drum)
GROUP 8: Crane operator (up to and including 25 ton
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 13/32
capacity); Crawler transporter operator; Derrick barge
operator (up to and including 25 ton capacity); Hoist
operator, stiff legs, Guy derrick or similar type (up to and including 25 ton capacity); Shovel, backhoe, dragline, clamshell operator (over 7 cu. yds., M.R.C.)
GROUP 9: Crane operator (over 25 tons and up to and including 50 tons mrc); Derrick barge operator (over 25 tons up to and including 50 tons mrc); Highline cableway operator; Hoist operator, stiff legs, Guy derrick or similar type (over 25 tons up to and including 50 tons mrc); K-crane operator; Polar crane operator; Self erecting tower crane operator maximum lifting capacity ten tons
GROUP 10: Crane operator (over 50 tons and up to and
including 100 tons mrc); Derrick barge operator (over 50 tons up to and including 100 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 50 tons up to and including 100 tons mrc), Mobile tower crane operator (over 50 tons, up to and including 100 tons M.R.C.);
GROUP 11: Crane operator (over 100 tons and up to and
including 200 tons mrc); Derrick barge operator (over 100 tons up to and including 200 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 100 tons up to and including 200 tons mrc); Mobile tower crane operator (over 100 tons up to and including 200 tons mrc) ; Tower crane operator and tower gantry
GROUP 12: Crane operator (over 200 tons up to and including 300 tons mrc); Derrick barge operator (over 200 tons up to and including 300 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 200 tons, up to and
including 300 tons mrc); Mobile tower crane operator (over 200 tons, up to and including 300 tons mrc)
GROUP 13: Crane operator (over 300 tons); Derrick barge operator (over 300 tons); Helicopter pilot; Hoist operator, stiff legs, Guy derrick or similar type (over 300 tons); Mobile tower crane operator (over 300 tons)
TUNNEL CLASSIFICATIONS
GROUP 1: Skiploader (wheel type up to 3/4 yd. without
attachment)
GROUP 2: Power-driven jumbo form setter operator
GROUP 3: Dinkey locomotive or motorperson (up to and
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 14/32
including 10 tons)
GROUP 4: Bit sharpener; Equipment greaser (grease truck); Slip form pump operator (power-driven hydraulic lifting device for concrete forms); Tugger hoist operator (1 drum); Tunnel locomotive operator (over 10 and up to and including 30 tons)
GROUP 5: Backhoe operator (up to and including 3/4 yd.); Small Ford, Case or similar; Drill doctor; Grouting machine operator; Heading shield operator; Heavy-duty repairperson; Loader operator (Athey, Euclid, Sierra and similar types); Mucking machine operator (1/4 yd., rubber-tired, rail or track type); Pneumatic concrete placing machine operator (Hackley-Presswell or similar type); Pneumatic heading
shield (tunnel); Pumpcrete gun operator; Tractor compressor drill combination operator; Tugger hoist operator (2 drum); Tunnel locomotive operator (over 30 tons)
GROUP 6: Heavy Duty Repairman
GROUP 7: Tunnel mole boring machine operator
ENGINEERS ZONES
$1.00 additional per hour for all of IMPERIAL County and the portions of KERN, RIVERSIDE & SAN BERNARDINO Counties as defined below:
That area within the following Boundary: Begin in San
Bernardino County, approximately 3 miles NE of the intersection of I-15 and the California State line at that point which is the NW corner of Section 1, T17N,m R14E, San Bernardino Meridian. Continue W in a straight line to that point which is the SW corner of the northwest quarter of Section 6, T27S, R42E, Mt. Diablo Meridian. Continue North to the intersection with the Inyo County Boundary at that point which is the NE corner of the western half of the northern quarter of Section 6, T25S, R42E, MDM. Continue W along the Inyo and San
Bernardino County boundary until the intersection with Kern County, as that point which is the SE corner of Section 34, T24S, R40E, MDM. Continue W along the Inyo and Kern County boundary until the intersection with Tulare County, at that point which is the SW corner of the SE quarter of Section 32, T24S, R37E, MDM. Continue W along the Kern and Tulare County boundary, until that point which is the NW corner of T25S, R32E, MDM. Continue S following R32E lines to the NW corner of T31S, R32E, MDM. Continue W to the NW corner of T31S, R31E, MDM. Continue S to the SW corner of T32S, R31E, MDM. Continue 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 15/32
W to SW corner of SE quarter of Section 34, T32S, R30E, MDM.
Continue S to SW corner of T11N, R17W, SBM. Continue E along south boundary of T11N, SBM to SW corner of T11N, R7W, SBM.
Continue S to SW corner of T9N, R7W, SBM. Continue E along south boundary of T9N, SBM to SW corner of T9N, R1E, SBM.
Continue S along west boundary of R1E, SMB to Riverside County line at the SW corner of T1S, R1E, SBM. Continue E along south boundary of T1s, SBM (Riverside County Line) to SW corner of T1S, R10E, SBM. Continue S along west boundary of R10E, SBM to Imperial County line at the SW corner of T8S, R10E, SBM.
Continue W along Imperial and Riverside county line to NW corner of T9S, R9E, SBM. Continue S along the boundary between Imperial and San Diego Counties, along the west edge of R9E, SBM to the south boundary of Imperial County/California state line. Follow the California state line west to Arizona state line, then north to Nevada state line, then continuing NW back to start at the point which is the NW corner of Section 1, T17N, R14E, SBM
$1.00 additional per hour for portions of SAN LUIS OBISPO, KERN, SANTA BARBARA & VENTURA as defined below:
That area within the following Boundary: Begin approximately 5 miles north of the community of Cholame, on the Monterey County and San Luis Obispo County boundary at the NW corner of T25S, R16E, Mt. Diablo Meridian. Continue south along the west side of R16E to the SW corner of T30S, R16E, MDM. Continue E to SW corner of T30S, R17E, MDM. Continue S to SW corner of T31S, R17E, MDM. Continue E to SW corner of T31S, R18E, MDM.
Continue S along West side of R18E, MDM as it crosses into San Bernardino Meridian numbering area and becomes R30W. Follow the west side of R30W, SBM to the SW corner of T9N, R30W, SBM.
Continue E along the south edge of T9N, SBM to the Santa Barbara County and Ventura County boundary at that point whch is the SW corner of Section 34.T9N, R24W, SBM, continue S along the Ventura County line to that point which is the SW corner of the SE quarter of Section 32, T7N, R24W, SBM. Continue E along the south edge of T7N, SBM to the SE corner to T7N, R21W, SBM. Continue N along East side of R21W, SBM to Ventura County and Kern County boundary at the NE corner of T8N, R21W.
Continue W along the Ventura County and Kern County boundary to the SE corner of T9N, R21W. Continue North along the East edge of R21W, SBM to the NE corner of T12N, R21W, SBM. Continue West along the north edge of T12N, SBM to the SE corner of T32S, R21E, MDM. [T12N SBM is a think strip between T11N SBM and T32S MDM]. Continue North along the East side of R21E, MDM to the Kings County and Kern County border at the NE corner of T25S, R21E, MDM, continue West along the Kings County and Kern County Boundary until the intersection of San Luis Obispo 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 16/32
County. Continue west along the Kings County and San Luis Obispo County boundary until the intersection with Monterey County. Continue West along the Monterey County and San Luis Obispo County boundary to the beginning point at the NW corner of T25S, R16E, MDM.
$2.00 additional per hour for INYO and MONO Counties and the Northern portion of SAN BERNARDINO County as defined below:
That area within the following Boundary: Begin at the
intersection of the northern boundary of Mono County and the California state line at the point which is the center of Section 17, T10N, R22E, Mt. Diablo Meridian. Continue S then SE along the entire western boundary of Mono County, until it reaches Inyo County at the point which is the NE corner of the Western half of the NW quarter of Section 2, T8S, R29E, MDM.
Continue SSE along the entire western boundary of Inyo County, until the intersection with Kern County at the point which is the SW corner of the SE 1/4 of Section 32, T24S, R37E, MDM.
Continue E along the Inyo and Kern County boundary until the intersection with San Bernardino County at that point which is the SE corner of section 34, T24S, R40E, MDM. Continue E along the Inyo and San Bernardino County boundary until the point which is the NE corner of the Western half of the NW quarter of Section 6, T25S, R42E, MDM. Continue S to that point which is the SW corner of the NW quarter of Section 6, T27S, R42E, MDM.
Continue E in a straight line to the California and Nevada state border at the point which is the NW corner of Section 1, T17N, R14E, San Bernardino Meridian. Then continue NW along the state line to the starting point, which is the center of Section 18, T10N, R22E, MDM.
REMAINING AREA NOT DEFINED ABOVE RECIEVES BASE RATE
---------------------------------------------------------------- IRON0433-006 01/01/2024
Rates Fringes
IRONWORKER
Fence Erector...............$ 42.53 26.26
Ornamental, Reinforcing
and Structural..............$ 47.45 34.90
PREMIUM PAY:
$9.00 additional per hour at the following locations:
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 17/32
China Lake Naval Test Station, Chocolate Mountains Naval Reserve-Niland,
Edwards AFB, Fort Irwin Military Station, Fort Irwin Training Center-Goldstone, San Clemente Island, San Nicholas Island, Susanville Federal Prison, 29 Palms - Marine Corps, U.S. Marine Base - Barstow, U.S. Naval Air Facility - Sealey, Vandenberg AFB Army Defense Language Institute - Monterey, Fallon Air Base, Naval Post Graduate School - Monterey, Yermo Marine Corps Logistics Center
Port Hueneme, Port Mugu, U.S. Coast Guard Station - Two Rock ---------------------------------------------------------------- LABO0300-005 07/01/2024
Rates Fringes
Asbestos Removal Laborer.........$ 43.88 25.13 SCOPE OF WORK: Includes site mobilization, initial site cleanup, site preparation, removal of asbestos-containing material and toxic waste, encapsulation, enclosure and
disposal of asbestos- containing materials and toxic waste by hand or with equipment or machinery; scaffolding,
fabrication of temporary wooden barriers and assembly of decontamination stations.
---------------------------------------------------------------- LABO0345-001 07/01/2022
Rates Fringes
LABORER (GUNITE)
GROUP 1.....................$ 48.50 21.37
GROUP 2.....................$ 47.55 21.37
GROUP 3.....................$ 44.01 21.37
FOOTNOTE: GUNITE PREMIUM PAY: Workers working from a
Bosn'n's Chair or suspended from a rope or cable shall receive 40 cents per hour above the foregoing applicable classification rates. Workers doing gunite and/or
shotcrete work in a tunnel shall receive 35 cents per hour above the foregoing applicable classification rates, paid on a portal-to-portal basis. Any work performed on, in or above any smoke stack, silo, storage elevator or similar type of structure, when such structure is in excess of 75'-0"" above base level and which work must be performed in whole or in part more than 75'-0"" above base level, that 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 18/32
work performed above the 75'-0"" level shall be compensated for at 35 cents per hour above the applicable
classification wage rate.
GUNITE LABORER CLASSIFICATIONS
GROUP 1: Rodmen, Nozzlemen
GROUP 2: Gunmen
GROUP 3: Reboundmen
---------------------------------------------------------------- LABO0783-002 07/01/2022
Rates Fringes
LABORER (TUNNEL)
GROUP 1.....................$ 45.68 23.30
GROUP 2.....................$ 46.00 23.30
GROUP 3.....................$ 46.46 23.30
GROUP 4.....................$ 47.15 23.30
LABORER
GROUP 1.....................$ 36.39 21.04
GROUP 2.....................$ 36.94 21.04
GROUP 3.....................$ 37.49 21.04
GROUP 4.....................$ 39.04 21.04
GROUP 5.....................$ 39.39 21.04
LABORER CLASSIFICATIONS
GROUP 1: Cleaning and handling of panel forms; Concrete screeding for rough strike-off; Concrete, water curing; Demolition laborer, the cleaning of brick if performed by a worker performing any other phase of demolition work, and the cleaning of lumber; Fire watcher, limber, brush loader, piler and debris handler; Flag person; Gas, oil and/or
water pipeline laborer; Laborer, asphalt-rubber material loader; Laborer, general or construction; Laborer, general clean-up; Laborer, landscaping; Laborer, jetting; Laborer, temporary water and air lines; Material hose operator
(walls, slabs, floors and decks); Plugging, filling of shee bolt holes; Dry packing of concrete; Railroad maintenance, repair track person and road beds; Streetcar and railroad construction track laborers; Rigging and signaling; Scaler; Slip form raiser; Tar and mortar; Tool crib or tool house laborer; Traffic control by any method; Window cleaner; Wire mesh pulling - all concrete pouring operations
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 19/32
GROUP 2: Asphalt shoveler; Cement dumper (on 1 yd. or larger mixer and handling bulk cement); Cesspool digger and
installer; Chucktender; Chute handler, pouring concrete, the handling of the chute from readymix trucks, such as walls, slabs, decks, floors, foundation, footings, curbs, gutters and sidewalks; Concrete curer, impervious membrane and form oiler; Cutting torch operator (demolition); Fine grader, highways and street paving, airport, runways and similar type heavy construction; Gas, oil and/or water
pipeline wrapper - pot tender and form person; Guinea
chaser; Headerboard person - asphalt; Laborer, packing rod steel and pans; Membrane vapor barrier installer; Power broom sweeper (small); Riprap stonepaver, placing stone or wet sacked concrete; Roto scraper and tiller; Sandblaster (pot tender); Septic tank digger and installer(lead); Tank scaler and cleaner; Tree climber, faller, chain saw
operator, Pittsburgh chipper and similar type brush
shredder; Underground laborer, including caisson bellower GROUP 3: Buggymobile person; Concrete cutting torch; Concrete pile cutter; Driller, jackhammer, 2-1/2 ft. drill steel or longer; Dri-pak-it machine; Gas, oil and/or water pipeline wrapper, 6-in. pipe and over, by any method, inside and out; High scaler (including drilling of same); Hydro seeder and similar type; Impact wrench multi-plate; Kettle person, pot person and workers applying asphalt, lay-kold,
creosote, lime caustic and similar type materials
(""applying"" means applying, dipping, brushing or handling of such materials for pipe wrapping and waterproofing); Operator of pneumatic, gas, electric tools, vibrating
machine, pavement breaker, air blasting, come-alongs, and similar mechanical tools not separately classified herein; Pipelayer's backup person, coating, grouting, making of joints, sealing, caulking, diapering and including rubber gasket joints, pointing and any and all other services; Rock slinger; Rotary scarifier or multiple head concrete chipping scarifier; Steel headerboard and guideline setter; Tamper, Barko, Wacker and similar type; Trenching machine, hand-propelled
GROUP 4: Asphalt raker, lute person, ironer, asphalt dump person, and asphalt spreader boxes (all types); Concrete core cutter (walls, floors or ceilings), grinder or sander; Concrete saw person, cutting walls or flat work, scoring old or new concrete; Cribber, shorer, lagging, sheeting and trench bracing, hand-guided lagging hammer; Head rock
slinger; Laborer, asphalt- rubber distributor boot person; Laser beam in connection with laborers' work; Oversize
concrete vibrator operator, 70 lbs. and over; Pipelayer 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 20/32
performing all services in the laying and installation of pipe from the point of receiving pipe in the ditch until completion of operation, including any and all forms of tubular material, whether pipe, metallic or non-metallic, conduit and any other stationary type of tubular device used for the conveying of any substance or element, whether water, sewage, solid gas, air, or other product whatsoever and without regard to the nature of material from which the tubular material is fabricated; No-joint pipe and stripping of same; Prefabricated manhole installer; Sandblaster
(nozzle person), water blasting, Porta Shot-Blast
GROUP 5: Blaster powder, all work of loading holes, placing and blasting of all powder and explosives of whatever type, regardless of method used for such loading and placing; Driller: All power drills, excluding jackhammer, whether core, diamond, wagon, track, multiple unit, and any and all other types of mechanical drills without regard to the form of motive power; Toxic waste removal
TUNNEL LABORER CLASSIFICATIONS
GROUP 1: Batch plant laborer; Changehouse person; Dump
person; Dump person (outside); Swamper (brake person and switch person on tunnel work); Tunnel materials handling person; Nipper; Pot tender, using mastic or other materials (for example, but not by way of limitation, shotcrete, etc.) GROUP 2: Chucktender, cabletender; Loading and unloading agitator cars; Vibrator person, jack hammer, pneumatic
tools (except driller); Bull gang mucker, track person; Concrete crew, including rodder and spreader
GROUP 3: Blaster, driller, powder person; Chemical grout jet person; Cherry picker person; Grout gun person; Grout mixer person; Grout pump person; Jackleg miner; Jumbo person; Kemper and other pneumatic concrete placer operator; Miner, tunnel (hand or machine); Nozzle person; Operating of
troweling and/or grouting machines; Powder person (primer house); Primer person; Sandblaster; Shotcrete person; Steel form raiser and setter; Timber person, retimber person, wood or steel; Tunnel Concrete finisher
GROUP 4: Diamond driller; Sandblaster; Shaft and raise work ---------------------------------------------------------------- LABO0783-005 07/01/2022
Rates Fringes
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 21/32
Brick Tender.....................$ 37.32 21.45 ---------------------------------------------------------------- LABO1184-001 07/01/2022
Rates Fringes
Laborers: (HORIZONTAL
DIRECTIONAL DRILLING)
(1) Drilling Crew Laborer...$ 40.69 18.25
(2) Vehicle Operator/Hauler.$ 40.86 18.25
(3) Horizontal Directional
Drill Operator..............$ 42.71 18.25
(4) Electronic Tracking
Locator.....................$ 44.71 18.25
Laborers: (STRIPING/SLURRY
SEAL)
GROUP 1.....................$ 41.90 21.32
GROUP 2.....................$ 43.20 21.32
GROUP 3.....................$ 45.21 21.32
GROUP 4.....................$ 46.95 21.32
LABORERS - STRIPING CLASSIFICATIONS
GROUP 1: Protective coating, pavement sealing, including repair and filling of cracks by any method on any surface in parking lots, game courts and playgrounds; carstops; operation of all related machinery and equipment; equipment repair technician
GROUP 2: Traffic surface abrasive blaster; pot tender - removal of all traffic lines and markings by any method (sandblasting, waterblasting, grinding, etc.) and
preparation of surface for coatings. Traffic control
person: controlling and directing traffic through both
conventional and moving lane closures; operation of all related machinery and equipment
GROUP 3: Traffic delineating device applicator: Layout and application of pavement markers, delineating signs, rumble and traffic bars, adhesives, guide markers, other traffic delineating devices including traffic control. This
category includes all traffic related surface preparation (sandblasting, waterblasting, grinding) as part of the
application process. Traffic protective delineating system installer: removes, relocates, installs, permanently
affixed roadside and parking delineation barricades,
fencing, cable anchor, guard rail, reference signs,
monument markers; operation of all related machinery and 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 22/32
equipment; power broom sweeper
GROUP 4: Striper: layout and application of traffic stripes and markings; hot thermo plastic; tape traffic stripes and markings, including traffic control; operation of all
related machinery and equipment
---------------------------------------------------------------- LABO1414-003 08/03/2022
Rates Fringes
LABORER
PLASTER CLEAN-UP LABORER....$ 38.92 23.32
PLASTER TENDER..............$ 41.47 23.32
Work on a swing stage scaffold: $1.00 per hour additional.
Work at Military Bases - $3.00 additional per hour:
Coronado Naval Amphibious Base, Fort Irwin, Marine Corps Air Station-29 Palms, Imperial Beach Naval Air Station, Marine Corps Logistics Supply Base, Marine Corps Pickle Meadows, Mountain Warfare Training Center, Naval Air
Facility-Seeley, North Island Naval Air Station, Vandenberg AFB.
---------------------------------------------------------------- PAIN0036-001 07/01/2023
Rates Fringes
Painters: (Including Lead
Abatement)
(1) Repaint (excludes San
Diego County)...............$ 29.59 17.12
(2) All Other Work..........$ 38.52 18.64
REPAINT of any previously painted structure. Exceptions:
work involving the aerospace industry, breweries,
commercial recreational facilities, hotels which operate commercial establishments as part of hotel service, and sports facilities.
---------------------------------------------------------------- PAIN0036-008 09/01/2024
Rates Fringes
DRYWALL FINISHER/TAPER...........$ 49.33 26.82 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 23/32
---------------------------------------------------------------- PAIN0036-015 06/01/2024
Rates Fringes
GLAZIER..........................$ 58.00 26.25 FOOTNOTE: Additional $1.25 per hour for work in a condor, from the third (3rd) floor and up Additional $1.25 per hour for work on the outside of the building from a swing stage or any suspended contrivance, from the ground up
---------------------------------------------------------------- PAIN1247-002 01/01/2024
Rates Fringes
SOFT FLOOR LAYER.................$ 43.20 18.03 ---------------------------------------------------------------- PLAS0200-008 08/03/2022
Rates Fringes
PLASTERER........................$ 47.37 19.64 FORT IRWIN; MARINE CORPS AIR STATION 29 PALMS, AND MARINE CORPS LOGISTICS SUPPLY BASE: $3.00 additional per hour. ---------------------------------------------------------------- PLAS0500-002 07/01/2023
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 44.00 27.11 ---------------------------------------------------------------- PLUM0016-002 09/01/2024
Rates Fringes
PLUMBER, PIPEFITTER,
STEAMFITTER
Work at Edwards AFB.........$ 66.48 26.61
Work at Fort Irwin Army
Base........................$ 67.68 26.51
Work at Marine Corps
Logistic Base at Nebo,
Marine Corps Logistic Base
at Yermo and Twenty-Nine
Palms Marine Base...........$ 66.48 26.61
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 24/32
Work ONLY on new additions
and remodeling of bars,
restaurants, stores and
commercial buildings, not
to exceed 5,000 sq. ft. of
floor space.................$ 53.51 25.28
Work ONLY on strip malls,
light commercial, tenant
improvement and remodel
work........................$ 44.24 23.96
All other work except work
on new additions and
remodeling of bars,
restaurant, stores and
commercial buildings not
to exceed 5,000 sq. ft. of
floor space and work on
strip malls, light
commercial, tenant
improvement and remodel
work........................$ 59.48 26.61
---------------------------------------------------------------- PLUM0345-001 09/01/2023
Rates Fringes
PLUMBER
Landscape/Irrigation Fitter.$ 40.20 25.90
Sewer & Storm Drain Work....$ 44.29 23.28
---------------------------------------------------------------- ROOF0036-002 08/01/2024
Rates Fringes
ROOFER...........................$ 49.43 20.58 FOOTNOTE: Pitch premium: Work on which employees are exposed to pitch fumes or required to handle pitch, pitch base or pitch impregnated products, or any material containing coal tar pitch, the entire roofing crew shall receive $1.75 per hour ""pitch premium"" pay.
---------------------------------------------------------------- SFCA0669-009 01/01/2024
Does not include the northern part of the City of Chino, or the Cities of Montclair and Ontario
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 25/32
Rates Fringes
SPRINKLER FITTER.................$ 45.31 27.91 ---------------------------------------------------------------- SFCA0709-004 09/01/2023
THE NORTHERN PART OF THE CITY OF CHINO, AND THE CITIES OF MONTCLAIR AND ONTARIO:
Rates Fringes
SPRINKLER FITTER (Fire)..........$ 54.29 32.00 ---------------------------------------------------------------- SHEE0105-003 07/01/2024
LOS ANGELES (South of a straight line drawn between Gorman and Big Pines)and Catalina Island, INYO, KERN (Northeast part, East of Hwy 395), MONO ORANGE, RIVERSIDE, AND SAN BERNARDINO COUNTIES Rates Fringes
SHEET METAL WORKER
(1) Commercial - New
Construction and Remodel
work........................$ 59.40 30.34
(2) Industrial work
including air pollution
control systems, noise
abatement, hand rails,
guard rails, excluding
aritechtural sheet metal
work, excluding A-C,
heating, ventilating
systems for human comfort...$ 56.95 30.04
---------------------------------------------------------------- TEAM0011-002 07/01/2024
Rates Fringes
TRUCK DRIVER
GROUP 1....................$ 39.59 34.34
GROUP 2....................$ 39.74 34.34
GROUP 3....................$ 39.87 34.34
GROUP 4....................$ 40.06 34.34
GROUP 5....................$ 40.09 34.34
GROUP 6....................$ 40.12 34.34
GROUP 7....................$ 40.37 34.34
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 26/32
GROUP 8....................$ 40.62 34.34
GROUP 9....................$ 40.82 34.34
GROUP 10....................$ 41.12 34.34
GROUP 11....................$ 41.62 34.34
GROUP 12....................$ 42.05 34.34
WORK ON ALL MILITARY BASES:
PREMIUM PAY: $3.00 per hour additional.
[29 palms Marine Base, Camp Roberts, China Lake, Edwards AFB, El Centro Naval Facility, Fort Irwin, Marine Corps
Logistics Base at Nebo & Yermo, Mountain Warfare Training Center, Bridgeport, Point Arguello, Point Conception, Vandenberg AFB]
TRUCK DRIVERS CLASSIFICATIONS
GROUP 1: Truck driver
GROUP 2: Driver of vehicle or combination of vehicles - 2 axles; Traffic control pilot car excluding moving heavy equipment permit load; Truck mounted broom
GROUP 3: Driver of vehicle or combination of vehicles - 3 axles; Boot person; Cement mason distribution truck; Fuel truck driver; Water truck - 2 axle; Dump truck, less than 16 yds. water level; Erosion control driver
GROUP 4: Driver of transit mix truck, under 3 yds.; Dumpcrete truck, less than 6-1/2 yds. water level
GROUP 5: Water truck, 3 or more axles; Truck greaser and tire person ($0.50 additional for tire person); Pipeline and utility working truck driver, including winch truck and plastic fusion, limited to pipeline and utility work;
Slurry truck driver
GROUP 6: Transit mix truck, 3 yds. or more; Dumpcrete truck, 6-1/2 yds. water level and over; Vehicle or combination of vehicles - 4 or more axles; Oil spreader truck; Dump truck, 16 yds. to 25 yds. water level
GROUP 7: A Frame, Swedish crane or similar; Forklift driver; Ross carrier driver
GROUP 8: Dump truck, 25 yds. to 49 yds. water level; Truck repair person; Water pull - single engine; Welder
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 27/32
GROUP 9: Truck repair person/welder; Low bed driver, 9 axles or over
GROUP 10: Dump truck - 50 yds. or more water level; Water pull - single engine with attachment
GROUP 11: Water pull - twin engine; Water pull - twin engine with attachments; Winch truck driver - $1.25 additional when operating winch or similar special attachments
GROUP 12: Boom Truck 17K and above
---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================ Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at
https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
---------------------------------------------------------------- The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 28/32
determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates
in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the
collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this
classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted 1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 29/32
average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union
prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier. ?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
-----------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on
a wage determination matter
d) an initial conformance (additional classification
and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to [email protected] or by mail to:
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 30/32
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as
conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to [email protected] or by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to [email protected] or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
================================================================ END OF GENERAL DECISION"
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 31/32
1/15/25, 1:45 PM SAM.gov
https://sam.gov/wage-determination/CA20250026/1 32/32