Attachment B
Securities Table
Securities Table
Water, Drainage, Sewer, Street, LMAD and Monumentation Bonds
Faithful Performance Security
Water Improvement - 08BSIM2747 Labor & Materials Security Water Improvement - 08BSIM2747
Amount of ORIGINAL Security: $1,313,211.79 Amount of ORIGINAL Security: $656,605.90 Amount of Security CURRENTLY: $1,313,211.79 Amount of Security CURRENTLY: $656,605.90 Amount of Security being REDUCED: $0.00 Amount of Security being REDUCED: $0.00 Amount of Security REMAINING: $1,313,211.79 Amount of Security REMAINING: $656,605.90 Faithful Performance Security
Drainage Improvement – 08BSIM2746 Labor & Materials Security Drainage Improvement - 08BSIM2746
Amount of ORIGINAL Security: $296,483.28 Amount of ORIGINAL Security: $148,241.64 Amount of Security CURRENTLY: $296,483.28 Amount of Security CURRENTLY: $148,241.64 Amount of Security being REDUCED: $0.00 Amount of Security being REDUCED: $0.00 Amount of Security REMAINING: $296,483.28 Amount of Security REMAINING: $148,241.64 Faithful Performance Security
Sewer Improvement – 08BSIM2748 Labor & Materials Security Sewer Improvement - 08BSIM2748
Amount of ORIGINAL Security: $1,481,640.49 Amount of ORIGINAL Security: $740,820.25 Amount of Security CURRENTLY: $1,481,640.49 Amount of Security CURRENTLY: $740,820.25 Amount of Security being REDUCED: $0.00 Amount of Security being REDUCED: $0.00 Amount of Security REMAINING: $1,481,640.49 Amount of Security REMAINING: $740,820.25 Faithful Performance Security
Street Improvement - 08BSBIP9683 Labor & Materials Security Street Improvement - 08BSBIP9683
Amount of ORIGINAL Security: $4,728,217.05 Amount of ORIGINAL Security: $2,391,108.53 Amount of Security CURRENTLY: $4,728,217.05 Amount of Security CURRENTLY: $2,391,108.53 Amount of Security being REDUCED: $0.00 Amount of Security being REDUCED: $0.00 Amount of Security REMAINING: $4,728,217.05 Amount of Security REMAINING: $2,391,108.53
Developer:
LGI Homes – California, LLC
495 E Rincon St Unit #101
Corona, Ca 92897
Faithful Performance Security
LMAD Improvement – 08BSBIP9684 Labor & Materials Security LMAD Improvement - 08BSBIP9684
Amount of ORIGINAL Security: $927,962.31 Amount of ORIGINAL Security: $463,981.16 Amount of Security CURRENTLY: $927,962.31 Amount of Security CURRENTLY: $463,981.16 Amount of Security being REDUCED: $742,369.85 Amount of Security being REDUCED: $0.00 Amount of Security REMAINING: $185,592.46 Amount of Security REMAINING: $463,981.16 Faithful Performance Security
Monumentation Improvement - 30104510
Amount of ORIGINAL Security: $95,500.00
Amount of Security CURRENTLY: $95,500.00
Amount of Security being REDUCED: $0.00
Amount of Security REMAINING: $95,500.00