ATTACHMENT A

VMUS Operating Summary and Highlights
Gas
Connections
VMUS registered an average
of 219,102 gas therms
sold monthly.

COMPLETED GAS PROJECTS:
· Kern River Interconnection
and meter station facilities
UPCOMING ELECTRIC PROJECTS:
· Foxborough Industrial Park—
System Impact Study to upgrade
capacity
Electric
Connections
VMUS’ highest peak of
combined usage was 20.45 MW
and 11,229 MWh delivered.

COMPLETED ELECTRIC PROJECTS:
· Goodyear Tire - One larger size
electric service connection -

1.3 million sq ft warehouse
UPCOMING GAS PROJECTS:
· Kern River Interconnection—
Final segment will be con-
verted

VMUS Annual Electric and Gas Operating Results
For FY 2025, VMUS sold 2,629,222 therms for $3,246,437. Compared to FY 2024, VMUS sold 2,453,352 therms for $3,925,047.

For FY 2025, VMUS sold 115,970 MWh for $21,222,809.21. Compared to FY 2024, VMUS sold 111,975 MWh for $20,111,162.14.