A
ttachment A
Engineering FY 2026 Q3
Quarterly Update
City of Victorville
Engineering Department
January 1, 2026 through March 31, 2026
We hope you enjoyed a wonderful holiday season. Your Engineering Department is off to a great start in this third quarter of Fiscal Year (FY) 2025/2026. I am very proud to report on the progress of your Engineering Department. We have:
• Completed the Pressure Zone Change in Area 7 at Bear Valley and Balsam Roads, improving water pressure and fire flow for 440 customers by rezoning from Pressure Zone 3170 to 3290. Now that the project has been completed, 440 existing customers now have increa sed water pressure and improved fire flow. This project was identified in the Water Master Plan and rate study. • Began construction on Roy Rogers Driv e f r o m A m a r g o s a R o a d t o I - 1 5 a n d Ridgecrest Road from Bear Valley Road to Pahute Avenue. These projects were deferred to spring for optimal conditions. Road closures and detours are in place, and we appreciate the public's patience as we continue to invest in our roads.
• Opened bids for Sewer Lining Phase 3, with award anticipated in April. Work i n c l u d e s a p p r o x i m a t e l y 1 6 , 0 0 0 l i n e a r f e e t o f C I P P s e w e r m a i n l i n i n g , rehabilitation of 326 laterals, a service replacement at 7th Street and A Street, and related restoration. CIPP extends pipe life by about 50 years, reduces maintenance, and prevents groundwater infiltration. Completion is anticipated this fall.
• Opened bids and awarded a contract for the 2025 Rectangular Rapid Flashing Beacons (RRFB) Project, including AD A-compliant curb ramps, sidewalk improvements, and curb and gutter upgrades at nine crosswalks citywide.
RRFB systems enhance pedestrian safety , with driver yield rates up to 98% and crash reductions up to 47%. Completion is anticipated this summer during the school break.
• Made significant progress to finalize the plans for the 2026 Citywide Street Improvement Project that will improve Mojave Drive from Amargosa Road to I- 15, reconstruct Third Avenue from Nisqualli Road to Field Street, replace manhole frames and covers on Green Tree Boulevard and Hesperia Road, and restripe Bear Valley Road Br idge over I-15. Combining multiple projects into a single bid improves efficiency and cost-effectiveness, allowing us to maximize available funding.
A Message from the City Engineer
• Completed the design and will soon advertise the City’s new 1-million- gallon (MG) prestressed concrete reclaimed water reservoir at Southern California Logistics Airport (SCLA). The new tank will replace the existing 600,000-gallon in-ground pond, whic h is prone to algae, debris, and evaporation losses. Upon completion, the existing pond and associated infrastructure will be removed, improv ing system reliability, operational efficiency, and water quality. The use of reclaimed water for dust control and irrigation helps preserve domestic water supplies for residents.
On a personal note, we participated in MLB Opening Day and enjoyed a team jersey day, as shown in the photo below. The Department also participated in the Victor Valley High School Career Fa ir, speaking with se niors about career opportunities in civil engineering, su rveying, inspection, and administrative services.
Additionally, I would like to highlight th at our Survey Technician Bradley East passed the National Council of Examiners for Engineering and Surveying (NCEES) Principles and Practice of Su rveying (PS) exam. This achievement marks an important step toward becoming a licensed surveyor in the State of California. Congratulations to him on this accomplishment.
We will continue to work hard to impr ove infrastructure citywide and look forward to meeting you at the Concerts in the Park, and other City-sponsored events. Your feedback is valued and helps plan future projects.
Thank you,
Fredy A. Bonilla, City Engineer
Victor Valley High School Career Fair
Project
UpdatesQ3
CONSTRUCTION
COMPLETED
CAPITAL IMPROVEMENT PROJECTS
The Victorville Water District reconfigured the existing water system in the northeastern area of Bear Valley Road and Balsam Road to address low water pressure and inadequate fire flow by rezoning the area from Pressure Zone 3170 to Pressure Zone 3290.
Contractor: Hemet Manufacturing Company, Inc (DBA Genesis Construction)
Original Contract Amount: $2,011,621.00
Final Contract Amount: $1,985,5293.27
Contract Award: February 4, 2025
Start of Construction: May 12, 2025
Completion Date: January 21, 2026
Pressure Zone Change Project – Area 7
CONSTRUCTION
IN PROGRESS
CAPITAL IMPROVEMENT PROJECTS
Roy Rogers Drive Pavement
Reconstruction and Rehabilitation
Project - From I-15 to Amargosa Road
This project will reconstruct portions of Roy Rogers Drive in addition to constructing a median in place of existing delineators across the street from In-N-Out to increase safety.
Bid Opening Date: August 12, 2025
Contractor: Vance Corporation
Contract Amount: $2,285,522.24
Contract Award: August 19, 2025
Start of Construction: March 2026
Estimated Completion Date: Summer 2026
Ridgecrest Road Reconstruction and
Improvement Project - Bear Valley
Road to Pahute Ave
This project will reconstruct Ridgecrest Road between Bear Valley Road and Pahute Avenue, and it will close existing infrastructure gaps on the east side of the road by providing ADA compliant curb ramps, curb & gutter, fire hydrants, and crosswalks.
Bid Opening Date: August 12, 2025
Contractor: Vance Corporation
Contract Amount: $1,712,110.42
Contract Award: August 19, 2025
Start of Construction: March 2026
Estimated Completion Date: Summer 2026
Sewer Lining Project – Phase 3
This project will rehabilitate about 16,000 linear feet of existing 8-inch and 10-inch sewer pipelines using cured-in- place pipe (CIPP) lining, along with approximately 326 top-hat service lateral repairs at various locations throughout the City. This project also includes spot repairs of broken or deteriorated pipe segments identified through CCTV
inspections conducted in compliance with the City’s Sewer System Maintenance Plan throughout the City.
Bid Opening Date: January 22, 2026
Contractor: Insituform Technologies, LLC
Contract Amount: $2,224,346.00
Contract Award: April 7, 2026
Start of Construction: May 2026
Estimated Completion Date: Fall 2026
CAPITAL IMPROVEMENT PROJECTS
UPCOMING
CONSTRUCTION
PROJECTS
La Mesa Fire Hydrant Addition Project – Phase 2
This project will install two additional hydrants along La Mesa Road between El Rio Road and El Evado Road to address insufficient fire protection coverage.
Contractor: Capo A General Contracting
Contract Amount: $77,777.77
Start of Construction: May 2026
Estimated Construction Completion: June 2026
Crosswalk Enhancement Project
This project will improve the safety of nine (9) intersections by installing rectangular rapid flashing beacons with additional pavement markings and signage.
Material Procurement Status: Completed
Bid Opening: February 26, 2026 (Concrete Work Only)
Lowest Bidder Gentry General Engineering, Inc.
Construction Contract: $501,912.50
Start of Construction: May 2026
Estimated Completion Date: Summer 2026
Project will be completed by the Traffic Division of the Public Works & Water Department with contractor support for concrete improvements at each location.
Industrial Wastewater Treatment Plant (IWWTP)
Direct Connection Outlet 1 and 2
This project will improve two manholes and associated piping at the City of Victorville’s Industrial Wastewater Treatment Plant (IWWTP) through minor reconfiguration, along with replacement of deteriorated equipment, to support smoother, more reliable operation.
Bid Opening: April 16, 2026
Engineer’s Estimate: $350,000
Start of Construction: June 2026
Estimated Completion Date: October 2026
Block Wall Project –
Well Sites: 128, 131 and 201
This project will enhance safety and security at Well Sites 128, 131, and 201 by replacing existing chain-link fencing with 6-foot concrete masonry unit (CMU) block walls
topped with 4-foot anti-climb spike extensions. In addition to improving site security, the new block walls and
automated gates will enhance the visual appearance of
these critical infrastructure sites, supporting the District’s goals for improved aesthetics in public-facing areas.
Bid Opening: April 28, 2026
Engineer’s Estimates: $450,000
Start of Construction: June 2026
Estimated Completion Date: September 2026
1MG SCLA Reclaimed Water Reservoir 2 Project
The project includes construction of a new 1-million-gallon (MG) prestressed concrete circular reclaimed water reservoir at SCLA to replace the existing 600,000-gallon open pond, which has maintenance challenges, algae growth, debris accumulation, and evaporation losses. The work also includes construction of a new pump station, extension of a potable water backup supply line, installation of overflow facilities, and on-site improvements of a massive extent.
Engineer’s Estimate: $9,000,000
Start of Construction: September 2026
Estimated Completion Date: December 2027
PROJECTS IN
DESIGN PHASE
CAPITAL IMPROVEMENT PROJECTS
Mojave Drive Improvements from Amargosa
Road to I-15 Freeway (Phase I)
This project will reconstruct Mojave Drive from Amargosa Road to I-15 Right of Way.
Between Condor Road and Amargosa Road, the roadway will be widened along the north side. Improvements include new curb and gutter, sidewalks, ADA-compliant curb ramps, driveway approaches, fire hydrants, crosswalks, street l ighting, and signage. Sidewalk improvements are contingent upon right-of-way acquisition and will not be constructed where right-of-way cannot be secured. Any resulting sidewalk gaps will be addressed in Phase III.
A landscaped raised median will also be constructed between Amargosa Road and Don Roberto Road.
In-house Design Status: 95% Complete
Projected Advertisement Date: Spring 2026
Phase I
Mojave Drive Improvement Project
from US-395 to Amargosa Road (Phase II)
The Mojave Drive Improvements Project will rehabilitate Mojave Drive from US 395 to Amargosa Road. The project also includes construction of curb, gutter, and sidewalk, along with improvements to driveway approaches and curb ramps east of El Evado Road.
Design Status: Preliminary Design
Estimated Design Duration: 24 Months
Phase II
Mojave Drive Improvement Project
from Condor Road to Seventh Street (Phase III)
From Condor Road to Caltrans I-15 right-of-way includes right-of-way (ROW) acquisition, roadway widening, and expansion from four to six travel lanes, where feasible. The project will also replace existing traffic signals to accommodate the widening and construct new ADA-compliant driveway approaches and sidewalks.From From La Paz Drive to Seventh Street, the project will reconstruct the roadway section, install a new traffic signal at 6th Street, and upgrade curb ramps, sidewalks, and driveways to meet ADA standards.
In addition, the project will address missing sidewalk segments that were not constructed during Phase I due to ROW constraints.
Project was selected to received a Surface Transportation Block Grant (STBG). The City anticipates releasing a Request for Proposals (RFP) by Fall 2026 to hire a consultant for design and ROW acquisition services. The City is currently coordinating with the Southern California Association of Governments (SCAG) to execute the funding agreement and obligate the grant funds.
Phase III
Third Avenue Street Improvements Project
from Nisqualli Road to Field Street
This project will rehabilitate 3rd Avenue from Nisqualli Road to Field Street. Improvements include drainage, street lighting, pavement section upgrades, and enhancements to driveways and curb ramps.
Design Status: 90% Complete
Projected Advertisement Date: Spring 2026
Green Tree Sewer Manhole Replacement
This project will replace existing composite manhole covers with cast iron covers at a minimum of 12 locations along Green Tree Boulevard.
Design Status: 100% Complete
Projected Advertisement Date: Spring 2026
Bear Valley Re Stripe Project
This project includes restriping of Bear Valley Road over the I-15 freeway to provide an additional left-turn lane at the Amargosa Road intersection, improving traffic operations and capacity.
Design Status: 100% Complete
Projected Advertisement Date: Spring 2026
2026 Citywide Pavement Preservation and
Maintenance Project
This project is part of the annual pavement preservation and maintenance program which includes slurry sealing streets throughout the City.
Design Status: 30% Complete
Projected Advertisement Date: Fall 2026
Ridgecrest Road at Bluff Crest Street and Vista Point
Drive Traffic Signal
This will install a traffic signal at Ridgecrest Road at Bluff Crest Street and Vista Point Drive Intersection.
A Cooperative Agreement with San Bernardino County fully executed on February 10, 2026.
Design Status: The Request for Proposals (RFP) is anticipated to be issued in April 2026.
Bear Valley Road Street Improvements Project
from Monte Vista Road to US-395
This project will rehabilitate and widen Bear Valley Road from Monte Vista Road to US-395 to include one lane in
each direction and a center (turning) lane. This project will also optimize drainage along this segment of roadway.
In-house Design Status: 60% Complete
Projected Advertisement Date: Winter 2027
Projected Construction Period: Summer 2027
Bear Valley Road
Industrial Wastewater Treatment Plant
(IWWTP) Expansion
The City’s Wastewater Treatment Facility is currently operating at 90% capacity. Anticipated growth in residential, commercial, and industrial developments has cr eated the need to expand the facility’s capacity. The City retained a consultant to evaluate best expansion alternatives and prepare expansion plans up to a 100% design level.
Selected Consultant: Woodard & Curran, Inc.
Consulting Contract Awarded: August 20, 2024
Start of Design Activities: October 15, 2024
Project Status: Design Phase 30% Complete / Workshop held on August 12, 2025 30% Design was completed in December 2025, and we have awarded the 100% design in February 2026.
National Pollutant Discharge Elimination
System (NPDES) Permit
The City issued a Request for Proposals (RFP) for the preparation of a National Pollutant Discharge Elimination System (NPDES) Permit to explore an alternative option for excess recycled water disposal.
Consulting Contract Awarded: December 17, 2024
Selected Consultant: Larry Walker & Associates
Status: City staff will meet with the regulators in April 2026
ESTIMATED
CONSTRUCTION
START DATE
PROJECTS IN DESIGN PHASE
FY 2025/2026 Pipeline Replacement Project – Area 28
FY 2025/2026 Mojave Drive Reconstruction Project from I-15 to 7th St (con more like Jan 2028) FY 2025/2026 Pipeline Replacement Project – Area 5
FY 2026/2027Pipeline Replacement Project – Area 6
FY 2026/2027 Sewer Capacity Improvement Project C2&C3
FY 2026/2027La Paz Drive Project from I-15 NB ramp to 7th Street FY 2027/2028Santa Fe Wash Sewer Relocation Project
TRAFFIC
ENGINEERING
A resident reported limited access to Rocky Knoll Lane for eastbound traffic on Mojave Drive, resulting in vehicles turning left onto West Trail and utilizing an unpaved path, creating safety concerns.
To address this issue, a U-turn sign and signal head was installed on Mojave Drive at the E Trail traffic signal to provide a safer and more appropriate access route.
Mojave Dr at East Trail
A concern was identified regarding illegal outbound left-turn movements from the development on the north side of Mojave Drive, resulting in safety and operational issues.
To mitigate this, yellow delineators we re installed, along with yellow paint applied to the median nose to reinforce channelization and discourage improper turning movements.
Mojave Dr west of El Evado Rd
A concern was identified regarding limi ted sight distance due to roadway grade, as well as potential driver confusion at the intersection.
To mitigate these issues, “Cross Traffic Does Not Stop” (W4-4P) plaques were installed beneath the existing stop signs.
Additionally, intersection warning (W2-1) signs were installed just 300 feet east from 1st Avenue to enhance driver awareness and improve overall intersection safety.
Ottawa St at First Ave
Silica Dr & Glen Canyon Ln
Parked vehicles were obstructing sight distance for turning movements, creating as a f e t yc o n c e r n .
T oa d d r e s st h i si s s u e ,“ N oP a r k i n gA n yT i me” signage was installed to maintain clear visibility and improve overall safety.
La Mesa Rd & Mesa View Dr
A concern was identified regarding the placement of the existing stop legend and limit line, which affected proper vehicle positioning and visibility.
To address this issue, the stop legend and limit line were removed and relocated to improve intersection control and overall safety.
DEVELOPMENT
ENGINEERING
DEVELOPMENT REVIEW
IssuedPermit Type
183Utility
39Right-of-Way
70Transportation
89Water
Review of Hydrology, Geotechnical, Water Quality
Management Plans (WQMP), Water/Sewer Feasibility,
and Traffic Studies
Issuance of Conditions of Approval
Review of Civil Improvement Plans
Issuance of Public ROW Permits
Inspection During Construction
Project Acceptance
Number of Permit Plan Checks
Development
Type In ReviewCompleted
856Residential
2493Commercial
Number of Inspections Completed: 1,224
Engineering
Planning
Building
DEVELOPMENT ENGINEERING
DEVELOPMENT ENGINEERING UPCOMING TRACT
Tract 17110 – DR Horton's Westcreek
Major Channel Improvements underway traversing the center of the master tract map.
Tract No. 14132 Street Improvements
Richmond American Homes has completed the extension of Talpa Street from Third Avenue to Arrowhead Drive. The next phase of improvements includes the widening of Third Avenue and the extension of Ottawa Street.
Tract No. 16808 West of 395
Richmond American Homes completed the water, sewer, and street improvements.
Nevada Street Improvements
Our developer, Prologis, LLC has completed the undergrounding of the SCE power poles and repaving of Nevada Street. In April, they will complete the striping of Nevada Street south of Phantom West in SCLA.
SURVEYING /
MAPPING
SURVEYING / MAPPING
CompletedSurveying Support
7Developer Document Reviews
3Engineering Department CIP
2Public Works
3SCLA
0VMUS
2Economic Development
Congratulations to our Survey Technician Bradley East on passing the National Council of Examiners for Engineering and Surveying (NCEES) PS: Principles and Practice of Surveying. Kudos Bradley!