Attachment A
Resolution No. 26-026
RESOLUTION NO. 26-026
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
VICTORVILLE, CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2026-27 TO BE FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi -modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of the City of Victorville (“City”) are aware of the projects proposed for funding in the City and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City, will receive an estimated $3,956,617.00 in RMRA funding in Fiscal Year 2026-27 from SB 1; and
WHEREAS, this is the tenth year in which the City is receiving SB 1 funding, which will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities/the project list; and
WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the City’s priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate roads throughout the City this year and similar projects into the future; and
WHEREAS, the 2023 California Statewide Local Streets and Roads Needs Assessment found that the City streets and roads are estimated to be in a low risk condition and this revenue will help the City increase the overall quality of its road system and over the next decade will bring City streets and roads into a “good” condition; and
WHEREAS, the SB 1 project list and overall investment in the City’s local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure , and using cutting- edge technology, materials and practices, will have significant positive co-benefits Statewide.
NOW, THEREFORE , THE CITY COUNCIL OF THE CITY OF VICTORVILLE DOES HEREBY RESOLVE, DETERMINE AND ORDER AS FOLLOWS:
Section 1. That the recitals set forth above are true and correct and are her eby incorporated in their entirety by this reference.
Section 2. The following list of newly proposed projects to be funded in-part or solely with Fiscal Year 2026-27 Road Maintenance and Rehabilitation Account revenues:
Project Title: Air Expressway Street Improvements
Project Description: The project will reconstruct, and rehabilitate the structural section of approximately 2.5 miles of Air Expressway.
Project Location: On Air Expressway from George Blvd to National Trails Hwy.
Estimated Project Schedule: Start (04/27)– Completion ( 11/27) based on the component being funded with RMRA funds.
Estimated Project Useful Life: The following estimated useful life for each rehabilitation method area as follows: 30 years for reconstruction; and 15 years for asphalt concrete overlays.
Project Title: Bear Valley Road Street Improvements
Project Description: The project will reconstruct, and rehabilitate the structural section of approximately 1.0 miles of Bear Valley Road.
Project Location: On Bear Valley Road from Bellflower St to US-395.
Estimated Project Schedule: Start (04/27)– Completion ( 11/27) based on the component being funded with RMRA funds.
Estimated Project Useful Life: The following estimated useful life for each rehabilitation method area as follows: 30 years for reconstruction; and 15 years for asphalt concrete overlays.
Section 3. The following previously proposed and adopted projects may also utilize Fiscal Year 20 26-27 Road Maintenance and Rehabilitation Account revenues in their delivery. With the relisting of these projects in the adopted fiscal year resolution, the City is reaffirming to the public and the State our intent to fund these projects with Road Maintenance and Rehabilitation Account revenues:
Project Title: Mojave Drive Street Improvements
Project Description: The project will rehabilitate and reconstruct the structural section of approximately 1.9 miles of Mojave Dr. In addition, non- standard ADA curb ramps & drive approaches will be removed and replaced.
Project Location: On Mojave Dr from El Evado Rd to La Paz Dr.
Estimated Project Schedule: Start (05/26)– Completion ( 11/26) based on the component being funded with RMRA funds.
Estimated Project Useful Life: The following estimated useful life for each rehabilitation method area as follows: 30 years for reconstruction; and 15 years for asphalt concrete overlays.
Project Title: Mojave Drive Street Improvements
Project Description: The project will reconstruct, and rehabilitate the structural section of approximately 3.8 miles of Mojave Dr. In addition, the scope of work will include road widening , and the construction of curb, gutter, sidewalk, and bike lanes on segments of the road missing these feature in City easements.
Furthermore, work may include reconstruction of non-standard ADA curb ramps & drive approaches.
Project Location: On Mojave Dr from Seventh Street to US – 395 excluding El Evado Rd to La Paz Dr.
Estimated Project Schedule: Start (05/26)– Completion ( 11/26) based on the component being funded with RMRA funds.
Estimated Project Useful Life: The following estimated useful life for each rehabilitation method area as follows: 30 years for reconstruction; and 15 years for asphalt concrete overlays.
Section 4. That this resolution shall be effective immediately as of the date of adoption.
Section 5. That the City Clerk shall certify to the passage and adoption of this Resolution; shall enter the same in the book of original Resolutions of the City; and shall make a minute of passage and adoption thereof in the records of the proceedings of the City Council, in the minutes of the meeting at which this Resolution is passed and adopted.