Attachment A
Engineering FY 2026
Q4 Quarterly Update
City of Victorville
Engineering Department
April 1, 2026 through June 30, 2026
Your Engineering Department worked very hard in the fourth and final quarter of Fiscal Year 2026. As we get ready to start Fisca l Year 2027, I am proud to report on the progress of your Engineering Department this last quarter:
• Engineering staff completed our street improvement project on Ridgecrest Road from Bear Valley Road to Pahute Avenue. The pr oject mostly addressed the deficient pavement but also increased walkability by constructing new sidewalk on the east side of Ridgecrest Road north of Bear Valley Road and extended the median at the intersection. • Similarly, Engineering staff completed our street i mprovement project on Roy Rogers Drive from Amargosa Road to I-15. The pr oject reconstructed the failed pavement and constructed a new raised ce nter median east of Civic Drive.
• Engineering staff was present at our annual Spring Festival & Egg Hunt at Hook Park on Saturday March 27 th . It was great to see our public and talk to you about our upcoming projects. We look forward to meeting you in person at our Concerts in the Park this summer.

I wanted to take a minute and explain the reason wh y we constructed the raised center medians on Ridgecrest Road and Roy Ro gers Drive: Safety .

According to the Federal Highway Administration (FH WA) vehicular crashes decrease by approximately 40% to 53% when raised me dians are constructed and they reduce pedestrian crashes by 46% at marked crosswalks and by 39% at unmarked locations. These improvements make Vict orville safer and that is why we invest in them.

As we head into the summer, Engineering staff will have multiple projects that will soon begin construction including the construction offire hydrants on La Mesa Road, the installation of approximately 16,000 linearfeet of CIPP sewer main lining, the installation of Rectangular Rapid Flashing Beacons (RRFB) at nine separate locations, the construction of block walls atmultiple well sites, the construction of a 1 Million Gallon tank for our recycled water at SCLA, the installation of 8,000 LF of water pipeline on Amethyst Road that will connect the City’s domestic water system to the State Water Project.

To say we will be busy in the next 6 months is an understatement.

A Message from the City Engineer Our engineers, surveyors, plan checkers, inspectors , drafters, and admin staff work very hard to ensure that the City’s infr astructure is improved each day.

Lastly, I would like to dedicate this Quarterly Repo rt to Senior Civil Engineer Victor Fajardo who retired on June 30 th . Victor was with us for over 20 years and he completed quite a few projects in his tenure . Wishing you a long and blessed retirement, Victor. Thank you very much.

Thank you,
Fredy A. Bonilla, City Engineer

Project
Updates Q4

CONSTRUCTION

COMPLETED

CAPITAL IMPROVEMENT PROJECTS

This project reconstructed portions of Roy Rogers Drive in addition to constructing a median in place of existing delineators across the street from In-N-Out to increase safety.

Bid Opening Date: August 12, 2025
Contractor: Vance Corporation
Contract Amount: $2,285,522.24
Contract Award: August 19, 2025
Start of Construction: March 2026
Completion Date: June 2026
Roy Rogers Drive Pavement Reconstruction
and Rehabilitation Project - From I-15 to
Amargosa Road
Roy Rogers Dr
Amargosa Rd
This project reconstructed Ridgecrest Road between Bear Valley Road and Pahute Avenue, and it will close existing infrastructure gaps on the east side of the road by providing ADA compliant curb ramps, curb & gutter, fire hydrants, and crosswalks.

Bid Opening Date: August 12, 2025
Contractor: Vance Corporation
Contract Amount: $1,712,110.42
Contract Award: August 19, 2025
Start of Construction: March 2026
Completion Date: June 2026
Ridgecrest Road Reconstruction
and Improvement Project - Bear
Valley Road to Pahute Ave
Ridgecrest Rd

CONSTRUCTION

IN PROGRESS

CAPITAL IMPROVEMENT PROJECTS

Sewer Lining Project – Phase 3
This project will rehabilitate about 16,000 linear feet of existing 8-inch and 10-inch sewer pipelines using cured-in- place pipe (CIPP) lining, along with approximately 326 top-hat service lateral repairs at various locations throughout the City. This project also includes spot repairs of broken or deteriorated pipe segments identified through CCTV
inspections conducted in compliance with the City’s Sewer System Maintenance Plan throughout the City.

Bid Opening Date: February 19, 2026
Contractor: Insituform Technologies, LLC
Contract Amount: $2,224,346
Contract Award: April 7, 2026
Start of Construction: August 2026
Estimated Completion Date: December 2026

Crosswalk Enhancement Project
This project will improve the safety of nine (9) intersections by installing rectangular rapid flashing beacons with additional pavement markings and signage.

Material Procurement Status: Completed
Lowest Bidder: Gentry General Engineering, Inc.

Construction Contract: $501,912.50
Contract Award: April 21, 2026
Start of Construction: June 22, 2026
Estimated Completion Date: August 2026
Project will be completed by the Traffic Division of the Public Works & Water Department with contractor support for concrete improvements at each location.

CAPITAL IMPROVEMENT PROJECTS

UPCOMING

CONSTRUCTION

PROJECTS
La Mesa Fire Hydrant Addition Project – Phase 2
This project will install two additional hydrants along La Mesa Road between El Rio Road and El Evado Road to address insufficient fire protection coverage.

Contractor: Capo A General Contracting
Contract Amount: $77,777.77
Start of Construction: August 2026
Estimated Construction Completion: September 2026

Industrial Wastewater Treatment Plant (IWWTP)
Direct Connection Outlet 1 and 2
This project will improve two manholes and associated piping at the City of Victorville’s Industrial Wastewater Treatment Plant (IWWTP) through minor reconfiguration, along with replacement of deteriorated equipment, to support smoother, more reliable operation.

Design Status: 90%
Engineer’s Estimate: $400,000
Start of Construction: Fall 2026
Estimated Completion Date: Summer 2027

Block Wall Project –
Well Sites: 128, 131 and 201
This project will enhance safety and security at Well Sites 128, 131, and 201 by replacing existing chain-link fencing with 6-foot concrete masonry unit (CMU) block walls topped with 4-foot anti-climb spike extensions.

In addition to improving site security, the new block walls and automated gates will enhance the visual appearance of these critical infrastructure sites, supporting the District’s goals for improved aesthetics in public-facing areas.

Bid Opening: April 28, 2026
Contractor: KNC Construction, Inc.

Contract Amount: $709,008
Contract Award: June 2, 2026
Start of Construction: August 2026
Estimated Completion Date: December 2026

1MG SCLA Reclaimed Water Reservoir 2 Project
The project includes construction of a new 1-million-gallon (MG) prestressed concrete circular reclaimed water reservoir at SCLA to replace the existing 600,000-gallon open pond, which has maintenance challenges, algae growth, debris accumulation, and evapor ation losses. The work also includes construction of a new pump station, extension of a potable water backup supply line, installation of overflow facilities, and on-site improvements of a massiveextent.

Engineer’s Estimate: $7,000,000 - $9,000,000
Bid Opening Date: July 9, 2026
Start of Construction: October 2026
Estimated Completion Date: Summer 2028

Turnout 5 Project
This project will construct the Victorville Water District’s third connection to the Mojave Water Agency’s Regional Recharge and Recovery (R3) system, including a connection to the R3 pipeline, approximately 1.25 miles of 24-inch water main, and a new metering facility at the Amethyst Pump Station. The project will provide State Water Project (SWP) water through the R3 system as a supplemental water supply to the City’s domestic water system, serving Pressure Zone 3290 and adjacent pressure zones.

The project will also allow SWP water to be blended with groundwater to reduce arsenic concentrations, support regulatory compliance, and reduce reliance on arsenic treatment facilities.

Advertisement Date: July 1, 2026
Bid Opening Date: August 5, 2026
Engineer’s Estimate: $6,000,000
Start of Construction: October 2026
Estimated Completion Date: June 2027

HWY 395 Water Relocation Project
SBCTA is the lead agency on a project to widen US-395 from two lanes to four lanes, approximately 3.3 miles of which lies within the jurisdictional boundaries of the City of Victorville. To accommodate the roadway improvements, the City of
Victorville has developed the HWY 395 Water Relocation Project to relocate and modify existing water facilities that will be impacted by the highway widening. The project includes relocation of 24-inch and 16-inch backbone transmission mains, installation of 12-inch, 8-inch, and 6-inch water mains, customer service laterals, and associated appurtenances to protect and maintain reliable water service during and after construction.

Design Status: 100% Complete
Projected Advertisement Date: August 2026
Engineer’s Estimate: $9,000,000
Anticipated Start of Construction: November 2026
Estimated Completion Date: August 2027

PROJECTS IN

DESIGN PHASE

CAPITAL IMPROVEMENT PROJECTS

2026 Citywide Pavement Preservation and
Maintenance Project
This project is part of the annual pavement preservation and maintenance program, which includes slurry sealing streets throughout the City.

Design Status: 100 % Complete
Projected Advertisement Date: Summer 2026

Ridgecrest Road at Bluff Crest Street and Vista Poi nt
Drive Traffic Signal
This project will install a traffic signal at Ridgecrest Road at Bluff Crest Street and Vista Point Drive Intersection.

A Cooperative Agreement with San Bernardino County was fully executed on February 10, 2026.

Design Status: Received 7 proposals on May 28, 2026
Engineering will recommend that the City Council approve entering into a Professional Services Agreement with David Evans and Associates, Inc. at the August 18, 2026, City Council meeting for the design services associated with the project.

Mojave Drive Improvements from Amargosa
Road to I-15 Freeway (Phase I)
This project will reconstruct Mojave Drive from Amargosa Road to I-15 Right of Way.

Between Condor Road and Amargosa Road, the roadway will be wi dened along the north side. Improvements include new curb and gutter, sidewalk, ADA-compliant curb ramps, driveway approaches, fire hydrants, crosswalks, street lighting, and signage. Sidewalk improvements are contingent upon right-of-way acquisition and will not be constructed where right-of-way cannot be secured. Any resulting sidewalk gaps will be addressed in Phase III.

A landscaped raised median will also be constructed betweenAmargosa Road and Don Roberto Road.

In-house Design Status: 95% Complete
Projected Advertisement Date: Summer 2026
Phase I
Third Avenue Street Improvements Project
from Nisqualli Road to Field Street
This project will rehabilitate 3rd Avenue from Nisqualli Road to Field Street. Improvements include drainage, street lighting, pavement section upgrades, and enhancements to driveways and curb ramps.

Design Status: 99% Complete
Projected Advertisement Date: Summer 2026

Green Tree Sewer Manhole Replacement
This project will replace existing composite manhole covers with cast iron covers at a minimum of 12 locations along Green Tree Boulevard.

Design Status: 100% Complete
Projected Advertisement Date: Summer 2026

Bear Valley Re Stripe Project
This project includes restriping of Bear Valley Road over the I-15 freeway to provide an additional left-turn lane at the Amargosa Road intersection, improving traffic operations and capacity.

Design Status: 100% Complete
Projected Advertisement Date: Summer 2026

Mojave Drive Improvement Project
from US-395 to Amargosa Road (Phase II)
The Mojave Drive Improvements Project will rehabilitate Mojave Drive from US 395 to Amargosa Road. The project also includes construction of curb, gutter, and sidewalk, along with improvements to driveway approaches and curb ramps east of El Evado Road.

Design Status: Preliminary Design
Estimated Design Duration: 12 Months
Phase II
Mojave Drive Improvement Project
from Condor Road to Seventh Street (Phase III)
From Condor Road to Caltrans I-15 right-of-way includes right-of-way (ROW) acquisition, roadway widening, and expansion from four to six travel lanes, where feasible. The project will also replace existing traffic signals to accommodate the widening and construct new ADA-compliant driveway approaches and sidewalks.

From La Paz Drive to Seventh Street, the project will reconstruct the roadway section, install a new traffic signal at 6th Street, and upgrade curb ramps, sidewalks, and driveways to meet ADA standards.

In addition, the project will address missing sidewalk segments that were not constructed during Phase I due to ROW constraints.

Project was selected to receive a Surface Transportation Block Grant (STBG). The City anticipates releasing a Request for Proposals (RFP) by Fall 2026 to hire a consultant for design and ROW acquisition services. The City is currently coordinating with the Southern California Association of Governments (SCAG) to execute the funding agreement and obligate the grant funds.

Phase III
Bear Valley Road Street Improvements Project
from Monte Vista Road to US-395
This project will rehabilitate and widen Bear Valley Road from Monte Vista Road to US-395 to include one lane in
each direction and a center (turning) lane. This project will also optimize drainage along this segment of roadway.

In-house Design Status: 60% Complete
Projected Advertisement Date: Winter 2027
Bear Valley Road

Industrial Wastewater Treatment Plant
(IWWTP) Expansion
The City’s Wastewater Treatment Facility is currently oper ating at 90% capacity. Anticipated growth in residential, commercial, and industrial developments hascreated the need to expand the facility’s capacity. The City retained a consultant to evaluate best expansion alternatives and prepare expansion plans up to a 100% design level.

Selected Consultant: Woodard & Curran, Inc.

Consulting Contract Awarded: August 20, 2024
Start of Design Activities: October 15, 2024
Project Status: Phase 2 of the project (100% Design) has begun. Kickoff meeting was held on June 9, 2026, to discuss the project scope, schedule, and overall design approach. Equipment procurement strategies and other key design considerations are currently being discussed.

National Pollutant Discharge Elimination
System (NPDES) Permit
The City issued a Request for Proposals (RFP) for the preparation of a National Pollutant Discharge Elimination System (NPDES) Permit to explore an alternative option for excess recycled water disposal.

Consulting Contract Awarded: December 17, 2024
Selected Consultant: Larry Walker & Associates
Project Status: Phase 1 of the infiltration testing has been completed, and preparations for Phase 2 are currently underway. Th e Report of Waste Discharge (ROWD) is being prepared for submittal to the Lahontan Regional Water Quality Control Board and discussions with VVWRA regarding a joint outfall option are ongoing.

TRAFFIC

ENGINEERING
A stop ahead sign was installed on the downhill approach to the intersection to give drivers advance notice of the stop sign. This improvement increases driver awareness and provides additional time to reduce speed before reaching the intersection.

Pahute Ave & Tamarisk Rd

Truck restriction signs were installed to prohibit trucks over 12,000 GVW or 96 inches in width from entering the roadway.

These signs help protect the pavement from excessive wear, reduces conflicts with local traffic, and improves overall roadway safety as Green Tree Boulevard is not a designated truck route.

Green Tree Blvd & Hesperia Rd and
Bear Valley Rd & Ridgecrest Rd

Following a resident complaint, an advanced intersection warning sign was installed to alert drivers of the upcoming right-side street. A yellow diamond marker sign was also installed at the corner to make the turn more visible and easier for drivers to identify, improving o verall intersection safety.

Bear Valley Rd & Pluto Dr

Pansy Rd & El Evado Rd
In response to a resident complaint regarding unaut horized off-road vehicle activity and shortcut traffic, road markers were installed to block vehic le access, and a no trespassing sign was added.

These improvements help prevent unauthorized access , reduce dust and debris impacting nearby homes, and preserve the surrounding area.

DEVELOPMENT

ENGINEERING

DEVELOPMENT REVIEW
Issued Permit Type
91 Utility
9Right-of-Way
90 Transportation
114 Water
Review of Hydrology, Geotechnical, Water Quality
Management Plans (WQMP), Water/Sewer Feasibility,
and Traffic Studies
Issuance of Conditions of Approval
Review of Civil Improvement Plans
Issuance of Public ROW Permits
Inspection During Construction
Project Acceptance
Number of Permit Plan Checks
Development
Type In Review Completed
263 Residential
15 107 Commercial
Number of Inspections Completed: 1,423
Engineering
Planning
Building

DEVELOPMENT ENGINEERING
Somerset
KB Homes EROW 24-00103
La Mesa Rd
Luna Rd
West Creek
Dr. Horton EROW 24-00047
Mojave Dr
Lanes Crossing EROW 23-00006
LGI
Mesa St
Dutch Brothers / Quick Quack Car Wash
Palmdale Rd and Cantina EROW 25-00033
Palmdale Rd
Legacy Homes
Mojave and Onyx EROW 24-00105
Mojave Dr
Richmond America
Mesa View / Olivine EROW 24-00104
Olvine Rd
Bear Valley Rd
Richmond America
3rd and Ottawa
Ottawa St

SURVEYING /

MAPPING

SURVEYING / MAPPING
CompletedSurveying Support
Developer Document Reviews 9
Engineering Department CIP 2
Public Works 3
SCLA 2
VMUS 0
Economic Development 2