ATTACHMENT C
COFFMAN SPECIALTIES,
INC.
PROPOSAL
Coffman Specialties, Inc. (Job No. 25-0010/ RCO 001) 7/7/2026 Runway 17/35 Reconstruction Project Phase VI CP
ITEM SS DESCRIPTION QTU U/M UNIT COST TOTAL
A2 G-201 ADMIN DELAYS 1.00 LS 65,000.00 $ 65,000.00$ A3 C-102 ADDITIONAL SOIL EROSION 1.00 LS 49,601.20 $ 49,601.20$ 207 G-301 REMOVE ASPHALT CONCRETE AND CRUSH TO P-208 PER SPECS 860.00 TN 25.00$ 21,500.00$ 206 P-101 COLD MILL 0.21 SHOULDER CUT 2,736.00 SF 5.00$ 13,680.00$ 208 G-301 SALVAGE EXISTING AGGREGATES BASE AND CRUSH TO P-220 PER SPECS 1,500.00 TN 17.50$ 26,250.00$ 209 P-152 OVER-EXCAVATION AND RECOMPACTION P-152 740.00 CY 16.50$ 12,210.00$ 210 P-152 HAUL AND STOCKPILE EXCESS OR UNSUITABLE RUNWAY EXCAVATION 1,570.00 CY 18.30$ 28,731.00$ 212 P-208 PLACE 6" AGGREGATES BASE COURSE P-208 52,050.00 SF 0.75$ 39,037.50$ 215 P-403 PROVIDE HOT-MIX-ASPHALT 36,365.00 SF 7.80$ 283,647.00$ 216 P-501 PROVIDE NON-REINFORCED PORTLAND CEMENT CONCRETE PAVEMENT 7,800.00 SF 11.75$ 91,650.00$ 221 P-153 PCCP EDGE CLSM BACKFILL 1,080.00 LF 74.10$ 80,028.00$ 1004 G-301 REMOVE ASPHALT CONCRETE AND CRUSH TO P-208 PER SPECS 804.00 TN 23.75$ 19,095.00$ 1006 P-152 HAUL AND STOCKPILE EXCESS OR UNSUITABLE RUNWAY EXCAVATION 198.00 CY 24.10$ 4,771.80$ 2006 P-101 COLD MILL 0.21 SHOULDER CUT 8,915.00 SF 5.00$ 44,575.00$ 2009 P-152 OVER-EXCAVATION AND RECOMPACTION P-152 2,506.00 CY 7.00$ 17,542.00$ 2010 P-152 HAUL AND STOCKPILE EXCESS OR UNSUITABLE RUNWAY EXCAVATION 1,080.00 CY 19.00$ 20,520.00$ 2015 P-403 PROVIDE HOT-MIX-ASPHALT 98,500.00 SF 2.75$ 270,875.00$ 2016 P-501 PROVIDE NON-REINFORCED PORTLAND CEMENT CONCRETE PAVEMENT 8,750.00 SF 10.50$ 91,875.00$ 2021 P-153 PCCP EDGE CLSM BACKFILL 1,987.00 LF 64.50$ 128,161.50$ 1,308,750.00$
PROPOSAL