Presentation to
City of Visalia City Council
January 18, 2022
Caltrans Project 06-0W900
CITY OF VISALIA:
Nick Mascia, Assistant City Manager
Frank Senteno, City Engineer
Rebecca Keenan, Senior Civil Engineer
CALTRANS:
Hussein Senan, Project Manager
Ernie Penuna, Design Office Chief
Irene Lee, Design Manager
YeshiAmente, Design Project Engineer
2 CITY OF VISALIA:
Caltrans Process & Brief Project Review to
PA&ED phase.
CALTRANS:
Project Approval & Environmental Document (PA
& ED) Phase close-out update
Review of Hybrid Analysis
PS&E and RW updates
NEXT STEPS
QUESTIONS
3 4
5 • Widen to
standard lane
width and
shoulders.
• Remove stop
control at off
ramp
• Close Mineral
King at Buck Rd.
• Extend storage
length for both
ramps.
6 7
8 Estimated Construction Costs
$19,700,000
Project Milestone Milestone
Completion Date
Right of Way acquisition complete April 2023
PS&E Design complete May 2023
Advertise for Construction July 2023
Construction to Begin October 2023
Construction Complete January 2025
9 10
Recommended Motion:
“I move to accept the
presentation from staff
and Caltrans on the
Lovers Lane Roadway
Rehabilitation and
Operational
Improvements Project.”
END
11 DRAFT Alternatives