Caltrans Project UpdatesSR-63 Mooney Blvd RehabSR-63 N Dinuba Blvd Bike LanesSR-99 Caldwell Ave Interchange John Liu, Deputy District Director
Caltrans District 6 Maintenance and Operations
January 31, 2022

Presentation
Complete streets policy
Safe System Approach
Class II bike lane
State Route 63 Mooney Blvd Capital Preventative Maintenance Project (CAPM) State Route 63 N Dinuba Blvd Bike Lane Project
Avenue 280 (Caldwell Avenue) interchange project on State Route 99

Complete Streets
The California Department of Transportation (Caltrans) recognizes that walking, biking, transit, and passenger rail are integral to our vision of delivering a brighter future for all through a world-class transportation network. Additionally, Caltrans recognizes that streets are not only used for transportation but are also valuable community spaces. Accordingly, in locations with current and/or future pedestrian, bicycle, or transit needs, all transportation projects funded or overseen by Caltrans will provide comfortable, convenient, and connected complete streets facilities for people walking, biking, and taking transit or passenger rail unless an exception is documented and approved.

Safe System Approach
Principles
Death/serious injury is unacceptable
Humans make mistakes
Humans are vulnerable
Responsibility is shared
Safety is proactive
Redundancy is crucial

Safe System Approach
Elements
Safe road users
Safe vehicles
Safe speeds
Safe roads
Safety is proactive
Post-cash care

Class II Bike Lane
Typical 5-foot wide bike lane
Green paint placed in conflict areas
Sharrows will be placed in right-turn lanes

SR-63 Mooney Blvd CAPM

SR-63 Mooney Blvd CAPM

2.2-mile segment of Mooney Blvd from 0.2 miles south of Caldwell Avenue to SR-198 Remove and replace 1.8 inches of asphalt concrete pavement Upgrade traffic signals, sign panels, and curb ramps
5-foot Class II bike lanes will be added by narrowing travel lanes from 12 feet to 11 feet in general, with green paint in conflict areas $11.8 million construction cost
Construction scheduled for fall of 2023

SR-63 Mooney Blvd Pavement Rehab

SR-63 Mooney Blvd Pavement Rehab

SR-63 N Dinuba Blvd Bike Lanes

0.8-mile segment of N Dinuba Blvd from W Houston Avenue to W Robin Drive Slurry seal will be placed, and travel lanes will be narrowed from 12 feet to 10 or 11 feet 5-foot Class II bike lanes with green paint in conflict areas Construction anticipated in the fall of 2022 or spring of 2023

SR-63 N Dinuba Blvd Bike Lanes

SR-63 N Dinuba Blvd Bike Lanes

Caldwell Ave Interchange Project
Replacement of existing interchange with a tight diamond interchange with roundabouts Existing bridge replaced with a wider bridge with more vertical clearance to the freeway To accelerate the construction schedule and reduce costs, a full closure of the bridges over SR-99 and the railroad is being proposed while the new bridges are being constructed; some ramp movements will be available at different construction stages $42 million construction cost
Construction scheduled to begin at the end of 2023

Caldwell Ave Interchange Project

Stage 1

Stage 2

Stage 3

Stage 4