Item Description of Work Quantity Unit Unit Price Total Unit Price Total Unit Price Total 1 Mobilization and Demobilization 1 LS 1,800.00 $ 1,800.00$ 4,850.00$ 4,850.00$ 10,000.00$ 10,000.00$ 2 Traffic Control 1 LS 4,000.00 $ 4,000.00$ 8,325.00$ 8,325.00$ 15,000.00$ 15,000.00$ 3 Construction Notification Signs 2 EA 600.00 $ 1,200.00$ 2,150.00$ 4,300.00$ 3,000.00$ 6,000.00$ 4 Single Direction Detector without confirmation light (4090-1-SD) 10 EA 500.00$ 5,000.00$ 690.00$ 6,900.00$ 2,600.00$ 26,000.00$ 5 Preemption Installation at Hall St & Murray Ave 1 LS 14,052.00$ 14,052.00$ 15,600.00$ 15,600.00$ 14,300.00$ 14,300.00$ 6 Preemption Installation at Divisadero St & Murray Ave 1 LS 14,052.00 $ 14,052.00$ 15,600.00$ 15,600.00$ 14,300.00$ 14,300.00$ Schedule A: Base Bid Subtotal = 40,104.00$ 55,575.00$ 85,600.00$ 7 Traffic Control 1 LS 900.00 $ 900.00$ 4,175.00$ 4,175.00$ 2,700.00$ 2,700.00$ 8 Construction Notification Signs 1 EA 100.00 $ 100.00$ 2,150.00$ 2,150.00$ 3,000.00$ 3,000.00$ 9 Preemption Installation at Giddings St & Murray Ave 1 LS 19,575.00 $ 19,575.00$ 15,600.00$ 15,600.00$ 14,300.00$ 14,300.00$ Schedule A: Alt Bid 1 Subtotal = 20,575.00$ 21,925.00$ 20,000.00$ 10 Traffic Control 1 LS 900.00 $ 900.00$ 4,175.00$ 4,175.00$ 2,700.00$ 2,700.00$ 11 Construction Notification Signs 1 EA 100.00 $ 100.00$ 2,150.00$ 2,150.00$ 3,000.00$ 3,000.00$ 12 Preemption Installation at Willis St & Murray Ave 1 LS 19,575.00 $ 19,575.00$ 15,600.00$ 15,600.00$ 14,300.00$ 14,300.00$ Schedule A: Alt Bid 2 Subtotal = 20,575.00$ 21,925.00$ 20,000.00$ 13 Traffic Control 1 LS 900.00 $ 900.00$ 4,175.00$ 4,175.00$ 2,700.00$ 2,700.00$ 14 Construction Notification Signs 1 EA 100.00 $ 100.00$ 2,150.00$ 2,150.00$ 3,000.00$ 3,000.00$ 15 Preemption Installation at Woodland St & Tulare Ave 1 LS 19,575.00 $ 19,575.00$ 15,600.00$ 15,600.00$ 14,300.00$ 14,300.00$ Schedule A: Alt Bid 3 Subtotal = 20,575.00$ 21,925.00$ 20,000.00$ 16 Traffic Control 1 LS 900.00 $ 900.00$ 4,175.00$ 4,175.00$ 2,700.00$ 2,700.00$ 17 Construction Notification Signs 1 EA 100.00 $ 100.00$ 2,150.00$ 2,150.00$ 3,000.00$ 3,000.00$ 18 Preemption Installation at Divisadero St & Tulare Ave 1 LS 19,575.00 $ 19,575.00$ 15,600.00$ 15,600.00$ 14,300.00$ 14,300.00$ Schedule A: Alt Bid 4 Subtotal = 20,575.00$ 21,925.00$ 20,000.00$ Schedule A: Base Bid Total = 40,104.00$ 55,575.00 $ 85,600.00 $ Schedule A: Base Bid, Alt 1 Total = 60,679.00$ 77,500.00 $ 105,600.00 $ Schedule A: Base Bid, Alt 1-2 Total = 81,254.00$ 99,425.00 $ 125,600.00 $ Schedule A: Base Bid, Alt 1-3 Total = 101,829.00$ 121,350.00 $ 145,600.00 $ Schedule A: Base Bid, Alt 1-4 Total = 122,404.00$ 143,275.00 $ 165,600.00 $ Schedule B: Base Bid Total = 74,900.00$ 85,680.00 $ 150,000.00 $ Schedule B: Base Bid, Alt 1 Total = 83,000.00$ 94,330.00 $ 165,000.00 $ Schedule B: Base Bid, Alt 1-2 Total = 91,100.00$ 102,980.00 $ 180,000.00 $ Schedule B: Base Bid, Alt 1-3 Total = 99,200.00$ 111,722.00 $ 195,000.00 $ Schedule B: Base Bid, Alt 1-4 Total = 107,300.00$ 120,464.00 $ 210,000.00 $ Schedule B: Base Bid, Alt 1-5 Total = 115,400.00$ 129,206.00 $ 225,000.00 $ Schedule B: Base Bid, Alt 1-6 Total = 123,500.00$ 137,856.00 $ 240,000.00 $ Schedule B: Base Bid, Alt 1-7 Total = 131,600.00$ 146,506.00 $ 255,000.00 $ Schedule B: Base Bid, Alt 1-8 Total = 139,700.00$ 155,156.00 $ 270,000.00 $ Schedule B: Base Bid, Alt 1-9 Total = 147,800.00$ 163,806.00 $ 285,000.00 $ Schedule B: Base Bid, Alt 1-10 Total = 155,900.00$ 172,456.00 $ 300,000.00 $ Schedule B: Base Bid, Alt 1-11 Total = 164,000.00$ 181,106.00 $ 315,000.00 $ Schedule B: Base Bid, Alt 1-12 Total = 172,100.00$ 189,756.00 $ 330,000.00 $ Schedule B: Base Bid, Alt 1-13 Total = 180,200.00$ 198,498.00 $ 345,000.00 $ Schedule B: Base Bid, Alt 1-14 Total = 188,300.00$ 207,240.00 $ 360,000.00 $ Basis of Award: Base Bid A + Base Bid B = 115,004.00$ 141,255.00$ 235,600.00$ Bid Schedule A, Alternative Bid 4
RFB 21-22-04 Bid Tabulation: Bid Schedule A - Traffic Signal Preemption Pelagic Engineering
Oxnard, CA
A-C Electric
Bakersfield, CA
Alfaro Communications
Compton, CA Bid Schedule A, Base Bid
Bid Schedule A, Alternative Bid 1
Bid Schedule A, Alternative Bid 2
Bid Schedule A, Alternative Bid 3
Item Description of Work Quantity Unit Unit Price Total Unit Price Total Unit Price Total 1 Mobilization and Demobilization 1 LS 2,000.00 $ 2,000.00$ 7,150.00$ 7,150.00$ 15,000.00$ 15,000.00$ 2 Traffic Control 1 LS 1,800.00 $ 1,800.00$ 680.00$ 680.00$ 45,000.00$ 45,000.00$ 3 Furnish and Install a Battery Backup System at Hall St & Murray Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 4 Furnish and Install a Battery Backup System at Divisadero St & Murray Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 5 Furnish and Install a Battery Backup System at Giddings St & Murray Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 6 Furnish and Install a Battery Backup System at Willis St & Murray Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 7 Furnish and Install a Battery Backup System at Woodland St & Tulare Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 8 Furnish and Install a Battery Backup System at Divisadero St & Tulare Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 9 Furnish and Install a Battery Backup System at Jacob St & Murray Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 10 Furnish and Install a Battery Backup System at Center Ave & Giddings St 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ 11 Furnish and Install a Battery Backup System at Center Ave & Willis St 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Base Bid Subtotal = 74,900.00$ 85,680.00$ 150,000.00$ 12 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 13 Furnish and Install a Battery Backup System at Giddings St & Mineral King Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 1 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 14 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 15 Furnish and Install a Battery Backup System at Conyer St & Noble Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 2 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 16 Traffic Control 1 LS 200.00 $ 200.00$ 92.00$ 92.00$ 5,000.00$ 5,000.00$ 17 Furnish and Install a Battery Backup System at Giddings St & Tulare Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 3 Subtotal = 8,100.00$ 8,742.00$ 15,000.00$ 18 Traffic Control 1 LS 200.00 $ 200.00$ 92.00$ 92.00$ 5,000.00$ 5,000.00$ 19 Furnish and Install a Battery Backup System at Conyer St & Tulare Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 4 Subtotal = 8,100.00$ 8,742.00$ 15,000.00$ 20 Traffic Control 1 LS 200.00 $ 200.00$ 92.00$ 92.00$ 5,000.00$ 5,000.00$ 21 Furnish and Install a Battery Backup System at Court St & Tulare Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 5 Subtotal = 8,100.00$ 8,742.00$ 15,000.00$ 22 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 23 Furnish and Install a Battery Backup System at Giddings St & Whitendale Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 6 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 24 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 25 Furnish and Install a Battery Backup System at Chinowth St & Mineral King Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 7 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 26 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 27 Furnish and Install a Battery Backup System at Chinowth St & Noble Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 8 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 28 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 29 Furnish and Install a Battery Backup System at Linwood St & Noble Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 9 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 30 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ Bid Schedule B, Alternative Bid 9
Bid Schedule B, Alternative Bid 1
Bid Schedule B, Alternative Bid 2
Bid Schedule B, Alternative Bid 8
RFB 21-22-04 Bid Tabulation: Bid Schedule B - Battery Backup System Pelagic Engineering
Oxnard, CA
A-C Electric
Bakersfield, CA
Alfaro Communications
Compton, CA Bid Schedule B, Base Bid
Bid Schedule B, Alternative Bid 3
Bid Schedule B, Alternative Bid 4
Bid Schedule B, Alternative Bid 5
Bid Schedule B, Alternative Bid 6
Bid Schedule B, Alternative Bid 7
Bid Schedule B, Alternative Bid 10
31 Furnish and Install a Battery Backup System at Linwood St & Whitendale Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 10 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 32 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 33 Furnish and Install a Battery Backup System at County Center Dr & Mineral King Ave 1 LS 7,900.00$ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 11 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 34 Traffic Control 1 LS 200.00 $ 200.00$ - $ - $ 5,000.00$ 5,000.00$ 35 Furnish and Install a Battery Backup System at Giddings St & Houston Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 12 Subtotal = 8,100.00$ 8,650.00$ 15,000.00$ 36 Traffic Control 1 LS 200.00 $ 200.00$ 92.00$ 92.00$ 5,000.00$ 5,000.00$ 37 Furnish and Install a Battery Backup System at Ben Maddox Way & Main St 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 13 Subtotal = 8,100.00$ 8,742.00$ 15,000.00$ 38 Traffic Control 1 LS 200.00 $ 200.00$ 92.00$ 92.00$ 5,000.00$ 5,000.00$ 39 Furnish and Install a Battery Backup System at Cain St & Houston Ave 1 LS 7,900.00 $ 7,900.00$ 8,650.00$ 8,650.00$ 10,000.00$ 10,000.00$ Schedule B: Alt Bid 14 Subtotal = 8,100.00$ 8,742.00$ 15,000.00$ Schedule B: Base Bid Total = 74,900.00$ 85,680.00 $ 150,000.00 $ Schedule B: Base Bid, Alt 1 Total = 83,000.00$ 94,330.00 $ 165,000.00 $ Schedule B: Base Bid, Alt 1-2 Total = 91,100.00$ 102,980.00 $ 180,000.00 $ Schedule B: Base Bid, Alt 1-3 Total = 99,200.00$ 111,722.00 $ 195,000.00 $ Schedule B: Base Bid, Alt 1-4 Total = 107,300.00$ 120,464.00 $ 210,000.00 $ Schedule B: Base Bid, Alt 1-5 Total = 115,400.00$ 129,206.00 $ 225,000.00 $ Schedule B: Base Bid, Alt 1-6 Total = 123,500.00$ 137,856.00 $ 240,000.00 $ Schedule B: Base Bid, Alt 1-7 Total = 131,600.00$ 146,506.00 $ 255,000.00 $ Schedule B: Base Bid, Alt 1-8 Total = 139,700.00$ 155,156.00 $ 270,000.00 $ Schedule B: Base Bid, Alt 1-9 Total = 147,800.00$ 163,806.00 $ 285,000.00 $ Schedule B: Base Bid, Alt 1-10 Total = 155,900.00$ 172,456.00 $ 300,000.00 $ Schedule B: Base Bid, Alt 1-11 Total = 164,000.00$ 181,106.00 $ 315,000.00 $ Schedule B: Base Bid, Alt 1-12 Total = 172,100.00$ 189,756.00 $ 330,000.00 $ Schedule B: Base Bid, Alt 1-13 Total = 180,200.00$ 198,498.00 $ 345,000.00 $ Schedule B: Base Bid, Alt 1-14 Total = 188,300.00$ 207,240.00 $ 360,000.00 $ Bid Schedule B, Alternative Bid 11
Bid Schedule B, Alternative Bid 12
Bid Schedule B, Alternative Bid 13
Bid Schedule B, Alternative Bid 14
Attachment 2 - Bid Summary
Visalia City Council
February 7, 2022
- Document
- Attachment 2 - Bid Summary
- Meeting
- February 7, 2022
- Body
- Visalia City Council
- Original file
- 909 KB
Text extracted from the city's file for reading and search. Open the original on visalia.legistar1.com. That file is the official record.