Presentation to City of Visalia
City Council
April 18, 2022
East Side Regional Park &
Groundwater Recharge Project
Funding Update
Funding Update: Basin ‘G’ & ‘F’
Master planned 242 Acres Regional Park and Groundwater Recharge Project
Location: East of McAuliff Street, at State Route 198 - bounded by the future Tower Street, Houston Avenue, Mineral King Avenue, and Road 152.
Purpose:
1. To provide ground water recharge east and upgradient of the City. (Groundwater flows from east to west)
2. To create a new regional park to provide space for healthy lifestyles, outdoor recreation facilities, play areas, cultural activities, and historic preservation.
2 3
Basin G - CP0185
Estimated Total Project Cost: $5,992,728
Grant Funding Source = $1,568,708 City Funding Sources = $4,424,020 • California Proposition 1Urban
Rivers Grant
• 132 Measure R Trails
• 211 Recreation Facilities
• 224 Groundwater Recharge
• 261 Waterways Capital
26% of Estimated Total Project Cost 74% of Estimated Total Project Cost 4 5
Basin F - CP0371
Estimated Total Project Cost: $7,919,040
Grant Funding Source = $1,878,680
(reduced from $2.4M)
City Funding Sources = $6,040,370
• Land & Water Conservation Fund
Grant
• Max Grant: $2,448,588
• 111 Gas Tax
• 132 Measure R Trails
• 211 Recreation Facilities
• 224 Groundwater Recharge
• 261 Waterways Capital
Estimated Total Eligible Project Cost:
$3,757,346
24% of Estimated Total Project Cost
City Match:
$1,878,671 (Eligible Costs)
$4,161,694 (Non-Eligible Costs)
76% of Estimated Total Project Cost
6 Federal Funding administered by the National Park Service (NPS), requires NEPA review.
In California, funds administered by the California State Parks Office of Grants and Local Services (OGALS)
City notified in 2019 of recommendation of $2,448,588 grant award by the National Park Service.
Estimated review time by NPS was 12-18 months.
Grant application included Basin G as part of the match. Design commenced in anticipation of funding.
Due to critical Basin G funding deadline, the two projects have now been separated (other than the recreation equipment). 7 Basin F CP0371
Option 5
Funding
% Amount Needed Current Budget
Additional
Appropriation
Needed
(if LWCF Grant kept)
Match Funding: 76%
111 Gas Tax 0% 172,660.00$ 36,641.00$ 136,019.00$ 132 Measure R Trails 11% 346,750.00$ 219,851.00$ 126,899.00$ 211 Rec Facilities Park Impact Fund 34% 2,378,320.00$ 1,768,803.00$ 609,517.00$ 224 Groundwater Recharge Fund 53% 3,076,040.00$ 1,612,236.00$ 1,463,804.00$ 261 Waterways Capital Fund 1% 66,600.00$ 36,641.00$ 29,959.00$ Total 100% 6,040,370.00$ 3,674,172.00$ 2,366,198.00$ LWCF Grant Funding
(reduced to 50% of amount eligible) 24% 1,878,680.00$ 1,878,680.00$ -$ Total Project Cost 100% $7,919,038
Total Appropriation Requested 2,366,198.00$
8 Project as scoped in the application has been altered. Basin G has been removed as the match.
All groundwater recharge elements included in the original scope are not eligible for reimbursement or to be used as a match. This results in a decrease of the grant reimbursement. Groundwater Recharge elements are needed and not funded with grant.
Grant requires area be placed in a federal land deed restriction. 9 10
I move to appropriate the funds as identified in the
Staff Report for Basin G; authorize the City
Manager to decline a grant of approximately $2.4
million from the Federal Land and Water
Conservation Fund (LWCF); authorize staff to
complete design of Basin F and release any
remaining City match funds back to the funds; and
to pursue appropriate grant funding for the
construction of groundwater recharge Basin F.