Cities Index.
Attachment 3 - Construction Sequence

Visalia City Council
June 6, 2022

Document
Attachment 3 - Construction Sequence
Meeting
June 6, 2022
Body
Visalia City Council
Original file
3.6 MB
Text extracted from the city's file for reading and search. Open the original on visalia.legistar1.com. That file is the official record.

Silty SandSoil with Clay BinderExisting Undisturbed Road AsphaltAvenue 288 Reconstruction Project – Construction Sequence Not to Scale

0. Existing Conditions
Silty SandSoil with Clay BinderExisting Undisturbed Road Pulverized Asphalt (New Base Layer)Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

1. Pulverize Existing Asphalt to reuse as Base Layer
Base LayerGeogridSubgradeSilty SandSoil with Clay BinderCurrent Roadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

2. Prepare Subgrade & Place Geogrid
Base LayerGeogridSubgradeSilty SandSoil with Clay BinderRoadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

3. Place Asphalt
Asphalt
Base LayerGeogridSubgradeSilty SandSoil with Clay BinderCurrent Roadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

2.1 Pumping Roadway Encountered

Base LayerGeogridSubgradeSilty SandSoil with Clay BinderCurrent Roadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

2.2 Causes of Pumping – Heavy Loading & Saturated SoilWheel Loading Saturated SoilRising Water
Base LayerGeogridSubgradeSilty SandSoil with Clay BinderCurrent Roadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

2.3 Causes of Pumping – Clay Binder
Water held by Clay Binder
Base LayerGeogridSilty SandSoil with Clay BinderCurrent Roadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

2.5 Change Order Repairs – Digout Wet Materials & “Bridge” Over Saturated Soil Base LayerGeogrid

Base LayerGeogridSilty SandSoil with Clay BinderCurrent Roadway SectionExisting Undisturbed Soil Avenue 288 Reconstruction Project – Construction Sequence Not to Scale

3. Place Asphalt
Base LayerGeogrid
Asphalt

← All documents from this meeting