City of Visalia - Engineering Division
FY 19-20 SB1 Street Rehab - Goshen Avenue
RFB No. 21-22-35 - Bid Summary
No. Items Qty Unit Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total 1 Mobilization/Demobilization, including final site clean-up 1 LS $55,000.80 $55,000.80 $50,000.00 $50,000.00 $40,000.00 $40,000.00 $60,000.00 $60,000.00 $125,000.00 $125,000.00 $150,000.00 $150,000.00 2 Water Pollution Prevention 1 LS $1,500.00 $1,500.00 $2,200.00 $2,200.00 $3,000.00 $3,000.00 $1,000.00 $1,000.00 $1,500.00 $1,500.00 $11,000.00 $11,000.00 3 Clearing and Grubbing 1 LS $25,000.00 $25,000.00 $2,600.00 $2,600.00 $1,000.00 $1,000.00 $20,000.00 $20,000.00 $5,000.00 $5,000.00 $9,000.00 $9,000.00 4 Public Outreach 1 LS $550.00 $550.00 $750.00 $750.00 $3,000.00 $3,000.00 $2,000.00 $2,000.00 $2,000.00 $2,000.00 $1,600.00 $1,600.00 5 Traffic Control 1 LS $140,000.00 $140,000.00 $13,000.00 $13,000.00 $25,000.00 $25,000.00 $122,000.00 $122,000.00 $350,000.00 $350,000.00 $64,000.00 $64,000.00 6 Construction Notification Signs 2 EA $2,200.00 $4,400.00 $220.00 $440.00 $660.00 $1,320.00 $2,000.00 $4,000.00 $750.00 $1,500.00 $1,750.00 $3,500.00 7 Lower Existing SS Manhole Below Milling Depth 7 EA $400.00 $2,800.00 $620.00 $4,340.00 $465.00 $3,255.00 $600.00 $4,200.00 $800.00 $5,600.00 $850.00 $5,950.00 8 Lower Existing SD Manhole Below Milling Depth 3 EA $400.00 $1,200.00 $620.00 $1,860.00 $465.00 $1,395.00 $600.00 $1,800.00 $800.00 $2,400.00 $940.00 $2,820.00 9 Remove/Dispose of Existing Pavement and Base Rock (Digout)30,000 SF $2.00 $60,000.00 $1.60 $48,000.00 $1.25 $37,500.00 $1.00 $30,000.00 $2.00 $60,000.00 $3.14 $94,200.00 10 Replace Digout Section (6" AC Plug) 30,000 SF $5.00 $150,000.00 $4.30 $129,000.00 $5.25 $157,500.00 $5.00 $150,000.00 $5.00 $150,000.00 $5.83 $174,900.00 11 Cold Mill and Remove Asphalt Concrete 125,650 SF $0.20 $25,130.00 $0.18 $22,617.00 $0.25 $31,412.50 $0.30 $37,695.00 $0.25 $31,412.50 $0.22 $27,643.00 12 Paving Mat 342,340 SF $0.28 $95,855.20 $0.28 $95,855.20 $0.30 $102,702.00 $0.30 $102,702.00 $0.25 $85,585.00 $1.38 $472,429.20 13 Hot Mix Asphalt (Type B, 3/4 ") for 3" Overlay 6,850 TON $97.00 $664,450.00 $110.00 $753,500.00 $110.00 $753,500.00 $120.00 $822,000.00 $115.00 $787,750.00 $95.50 $654,175.00 14 Survey Monuments 4 EA $600.00 $2,400.00 $550.00 $2,200.00 $800.00 $3,200.00 $1,000.00 $4,000.00 $1,000.00 $4,000.00 $1,400.00 $5,600.00 15 Adjust SS Manhole Covers and Boxes to Finish Grade 7 EA $1,200.00 $8,400.00 $1,650.00 $11,550.00 $600.00 $4,200.00 $1,200.00 $8,400.00 $900.00 $6,300.00 $1,500.00 $10,500.00 16 Adjust SD Manhole Covers and Boxes to Finish Grade 3 EA $1,200.00 $3,600.00 $1,650.00 $4,950.00 $600.00 $1,800.00 $1,200.00 $3,600.00 $900.00 $2,700.00 $1,500.00 $4,500.00 17 Striping and Pavement Markings 1 LS $6,200.00 $6,200.00 $6,100.00 $6,100.00 $5,900.00 $5,900.00 $6,000.00 $6,000.00 $15,800.00 $15,800.00 $8,500.00 $8,500.00 18 Raised Pavement Markers 1 LS $1,600.00 $1,600.00 $1,600.00 $1,600.00 $1,500.00 $1,500.00 $1,500.00 $1,500.00 $500.00 $500.00 $1,350.00 $1,350.00 $1,248,086.00 $1,150,562.20 $1,177,184.50 $1,380,897.00 $1,637,047.50 $1,701,667.20 No. Items Qty Unit Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total 1 Mobilization/Demobilization, including final site clean-up 1 LS $25,000.00 $25,000.00 $50,000.00 $50,000.00 $40,000.00 $40,000.00 $1,000.00 $1,000.00 $56,000.00 $56,000.00 $5,000.00 $5,000.00 2 Water Pollution Prevention 1 LS $1,000.00 $1,000.00 $2,200.00 $2,200.00 $2,000.00 $2,000.00 $500.00 $500.00 $500.00 $500.00 $5,000.00 $5,000.00 3 Clearing and Grubbing 1 LS $8,200.00 $8,200.00 $1,500.00 $1,500.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $65,000.00 $65,000.00 $13,000.00 $13,000.00 4 Public Outreach 1 LS $550.00 $550.00 $750.00 $750.00 $2,500.00 $2,500.00 $100.25 $100.25 $500.00 $500.00 $1,500.00 $1,500.00 5 Traffic Control 1 LS $25,000.45 $25,000.45 $30,000.00 $30,000.00 $39,000.00 $39,000.00 $40,000.00 $40,000.00 $89,000.00 $89,000.00 $32,000.00 $32,000.00 6 Construction Notification Signs 2 EA $950.00 $1,900.00 $220.00 $440.00 $650.00 $1,300.00 $1,000.00 $2,000.00 $750.00 $1,500.00 $1,750.00 $3,500.00 7 Remove Concrete Ramp and Adjoining Sidewalk, Curb and Gutter 2,365 SF $4.00 $9,460.00 $3.00 $7,095.00 $2.00 $4,730.00 $5.00 $11,825.00 $5.00 $11,825.00 $3.60 $8,514.00 8 Lower Existing SS Manhole Below Milling Depth 4 EA $400.00 $1,600.00 $620.00 $2,480.00 $465.00 $1,860.00 $600.00 $2,400.00 $800.00 $3,200.00 $860.00 $3,440.00 9 Lower Existing SD Manhole Below Milling Depth 6 EA $400.00 $2,400.00 $620.00 $3,720.00 $465.00 $2,790.00 $600.00 $3,600.00 $800.00 $4,800.00 $1,750.00 $10,500.00 10 Modify Existing Drain Inlet 1 EA $10,000.00 $10,000.00 $4,300.00 $4,300.00 $4,000.00 $4,000.00 $8,000.00 $8,000.00 $2,900.00 $2,900.00 $5,800.00 $5,800.00 11 Double Modified ADA Ramp with Detectable Surface and Adjoining Sidewalk, Curb and Gutter (3,332 SF)4 EA $8,000.00 $32,000.00 $8,700.00 $34,800.00 $10,500.00 $42,000.00 $12,000.00 $48,000.00 $2,850.00 $11,400.00 $11,000.00 $44,000.00 12 Landscape Construction Modification 1 LS $2,000.00 $2,000.00 $2,600.00 $2,600.00 $1,100.00 $1,100.00 $2,000.00 $2,000.00 $12,000.00 $12,000.00 $11,000.00 $11,000.00 13 Remove/Dispose of Existing Pavement and Base Rock (Digout) 30,000 SF $1.20 $36,000.00 $1.60 $48,000.00 $1.25 $37,500.00 $1.00 $30,000.00 $1.20 $36,000.00 $3.14 $94,200.00 14 Replace Digout Section (6" AC Plug) 30,000 SF $4.40 $132,000.00 $4.30 $129,000.00 $5.25 $157,500.00 $5.00 $150,000.00 $6.00 $180,000.00 $5.55 $166,500.00 15 Cold Mill and Remove Asphalt Concrete 116,910 SF $0.13 $15,198.30 $0.19 $22,212.90 $0.20 $23,382.00 $0.30 $35,073.00 $0.30 $35,073.00 $0.18 $21,043.80 16 Paving Mat 335,175 SF $0.27 $90,497.25 $0.28 $93,849.00 $0.30 $100,552.50 $0.25 $83,793.75 $0.25 $83,793.75 $1.38 $462,541.50 17 Hot Mix Asphalt (Type B, 3/4 ") for 3" Overlay 6,705 TON $98.00 $657,090.00 $110.00 $737,550.00 $111.00 $744,255.00 $112.00 $750,960.00 $115.00 $771,075.00 $93.20 $624,906.00 18 Video Detection Systems 1 LS $51,000.00 $51,000.00 $75,000.00 $75,000.00 $51,000.00 $51,000.00 $50,000.00 $50,000.00 $65,600.00 $65,600.00 $77,700.00 $77,700.00 19 Traffic Signal Box Replacement or Relocation (If Required) 1 LS $22,000.00 $22,000.00 $2,200.00 $2,200.00 $24,000.00 $24,000.00 $1,200.00 $1,200.00 $1,000.00 $1,000.00 $2,200.00 $2,200.00 20 Survey Monuments 8 EA $550.00 $4,400.00 $550.00 $4,400.00 $800.00 $6,400.00 $1,000.00 $8,000.00 $1,000.00 $8,000.00 $1,300.00 $10,400.00 21 Adjust SS Manhole Covers and Boxes to Finish Grade 4 EA $1,000.00 $4,000.00 $1,650.00 $6,600.00 $600.00 $2,400.00 $1,200.00 $4,800.00 $900.00 $3,600.00 $1,600.00 $6,400.00 22 Adjust SD Manhole Covers and Boxes to Finish Grade 6 EA $1,000.00 $6,000.00 $1,650.00 $9,900.00 $600.00 $3,600.00 $1,200.00 $7,200.00 $900.00 $5,400.00 $1,600.00 $9,600.00 23 Striping and Pavement Markings 1 LS $11,500.00 $11,500.00 $12,000.00 $12,000.00 $10,900.00 $10,900.00 $12,000.00 $12,000.00 $19,000.00 $19,000.00 $12,500.00 $12,500.00 24 Raised Pavement Markers 1 LS $1,600.00 $1,600.00 $1,600.00 $1,600.00 $2,000.00 $2,000.00 $1,500.00 $1,500.00 $500.00 $500.00 $1,350.00 $1,350.00 $1,150,396.00 $1,282,196.90 $1,305,769.50 $1,254,952.00 $1,467,666.75 $1,632,595.30 No. Items Qty Unit Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total 1 Mobilization/Demobilization, including final site clean-up 1 LS $21,000.00 $21,000.00 $26,000.00 $26,000.00 $40,000.00 $40,000.00 $1,000.00 $1,000.00 $36,000.00 $36,000.00 $5,000.00 $5,000.00 2 Water Pollution Prevention 1 LS $1,000.00 $1,000.00 $1,100.00 $1,100.00 $2,000.00 $2,000.00 $100.00 $100.00 $500.00 $500.00 $5,400.00 $5,400.00 3 Clearing and Grubbing 1 LS $2,600.00 $2,600.00 $2,600.00 $2,600.00 $100.00 $100.00 $1,000.00 $1,000.00 $5,000.00 $5,000.00 $13,000.00 $13,000.00 4 Public Outreach 1 LS $550.00 $550.00 $750.00 $750.00 $2,600.00 $2,600.00 $100.50 $100.50 $500.00 $500.00 $800.00 $800.00 5 Traffic Control 1 LS $25,000.90 $25,000.90 $8,500.00 $8,500.00 $30,000.00 $30,000.00 $25,000.00 $25,000.00 $50,000.00 $50,000.00 $32,000.00 $32,000.00 6 Construction Notification Signs 2 EA $700.00 $1,400.00 $220.00 $440.00 $650.00 $1,300.00 $700.00 $1,400.00 $750.00 $1,500.00 $1,250.00 $2,500.00 7 Lower Existing SS Manhole Below Milling Depth 7 EA $400.00 $2,800.00 $620.00 $4,340.00 $460.00 $3,220.00 $600.00 $4,200.00 $800.00 $5,600.00 $740.00 $5,180.00 8 Lower Existing SD Manhole Below Milling Depth 3 EA $400.00 $1,200.00 $620.00 $1,860.00 $460.00 $1,380.00 $600.00 $1,800.00 $800.00 $2,400.00 $580.00 $1,740.00 9 Remove/Dispose of Existing Pavement and Base Rock (Digout) 15,000 SF $1.50 $22,500.00 $2.14 $32,100.00 $1.65 $24,750.00 $1.00 $15,000.00 $2.25 $33,750.00 $3.15 $47,250.00 10 Replace Digout Section (6" AC Plug) 15,000 SF $4.65 $69,750.00 $5.35 $80,250.00 $5.50 $82,500.00 $5.00 $75,000.00 $6.00 $90,000.00 $5.59 $83,850.00 11 Cold Mill and Remove Asphalt Concrete 118,105 SF $0.10 $11,810.50 $0.19 $22,439.95 $0.20 $23,621.00 $0.30 $35,431.50 $0.25 $29,526.25 $0.18 $21,258.90 12 Paving Mat 259,680 SF $0.27 $70,113.60 $0.28 $72,710.40 $0.27 $70,113.60 $0.25 $64,920.00 $0.25 $64,920.00 $1.38 $358,358.40 13 Hot Mix Asphalt (Type B, 3/4 ") for 3" Overlay 5,195 TON $96.00 $498,720.00 $110.00 $571,450.00 $107.00 $555,865.00 $110.00 $571,450.00 $115.00 $597,425.00 $96.85 $503,135.75 14 Video Detection Systems 1 LS $51,000.00 $51,000.00 $82,000.00 $82,000.00 $53,000.40 $53,000.40 $50,000.00 $50,000.00 $52,600.00 $52,600.00 $89,000.00 $89,000.00 15 Adjust SS Manhole Covers and Boxes to Finish Grade7 EA $1,000.00 $7,000.00 $1,650.00 $11,550.00 $600.00 $4,200.00 $1,200.00 $8,400.00 $900.00 $6,300.00 $1,700.00 $11,900.00 16 Adjust SD Manhole Covers and Boxes to Finish Grade3 EA $1,000.00 $3,000.00 $1,650.00 $4,950.00 $600.00 $1,800.00 $1,200.00 $3,600.00 $900.00 $2,700.00 $2,400.00 $7,200.00 17 Striping and Pavement Markings 1 LS $8,800.00 $8,800.00 $9,400.00 $9,400.00 $7,000.00 $7,000.00 $8,000.00 $8,000.00 $20,974.40 $20,974.40 $10,500.00 $10,500.00 18 Raised Pavement Markers 1 LS $2,700.00 $2,700.00 $2,700.00 $2,700.00 $2,600.00 $2,600.00 $2,500.00 $2,500.00 $500.00 $500.00 $2,500.00 $2,500.00 $800,945.00 $935,140.35 $906,050.00 $868,902.00 $1,000,195.65 $1,200,573.05 No. Items Qty Unit Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total 1 Mobilization/Demobilization, including final site clean-up 1 LS $5,500.00 $5,500.00 $15,000.00 $15,000.00 $5,000.00 $5,000.00 $1,000.00 $1,000.00 $20,000.00 $20,000.00 $5,000.00 $5,000.00 2 Water Pollution Prevention 1 LS $1,500.00 $1,500.00 $1,100.00 $1,100.00 $100.00 $100.00 $500.00 $500.00 $250.00 $250.00 $1,000.00 $1,000.00 3 Clearing and Grubbing 1 LS $6,500.00 $6,500.00 $550.00 $550.00 $100.00 $100.00 $500.00 $500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 4 Traffic Control 1 LS $21,000.00 $21,000.00 $1,600.00 $1,600.00 $15,000.00 $15,000.00 $5,000.00 $5,000.00 $60,000.00 $60,000.00 $10,000.00 $10,000.00 5 Furnish and Install No. 6E Pull Box 32 EA $1,900.00 $60,800.00 $3,200.00 $102,400.00 $2,000.00 $64,000.00 $1,800.00 $57,600.00 $3,800.00 $121,600.00 $3,350.00 $107,200.00 6 Furnish and Install 3" HDPE Conduit 15,950 LF $43.00 $685,850.00 $42.80 $682,660.00 $45.00 $717,750.00 $42.00 $669,900.00 $45.00 $717,750.00 $44.40 $708,180.00 7 Furnish and Install N48 (30"x48") Splice Vault 3 EA $4,800.00 $14,400.00 $4,300.00 $12,900.00 $4,900.00 $14,700.00 $5,000.00 $15,000.00 $4,800.00 $14,400.00 $4,440.00 $13,320.00 $795,550.00 $816,210.00 $816,650.00 $749,500.00 $939,000.00 $849,700.00 $3,994,977.00 $4,184,109.45 $4,205,654.00 $4,254,251.00 $5,043,909.90 $5,384,535.55 ALTERNATE BID 3 : Traffic Signal Interconnect Total
Bid Total (Base Bid + Alt Bid 1 + Alt Bid 2 + Alt Bid 3) - Discrepancy in the Contractor's Bid Schedule. Per the Special Provision and the Standard Specifications, in case of a discrepancy between unit price and total, the unit price shall prevail. The value shown here was adjusted using the unit price amount.
AJ Excavation, Inc.
Fresno, CA
AJ Excavation, Inc.
Fresno, CA
AJ Excavation, Inc.
Fresno, CA
AJ Excavation, Inc.
Fresno, CA
BASE BID : Goshen Avenue from Shirk to Akers Total
ALTERNATE BID 1 : Goshen Avenue from Akers to Demaree Total ALTERNATE BID 2 : Goshen Avenue from Demaree to Mooney Total Papich Construction
Arroyo Grande, CA
ALTERNATE BID 3 : Traffic Signal Interconnect Don Berry Construction Kingsburg, CA
Agee Construction
Clovis, CA
Avison Construction
Madera, CA
Cal Valley Construction
Fresno, CA
Papich Construction
Arroyo Grande, CA
Agee Construction
Clovis, CA
Agee Construction
Clovis, CA
ALTERNATE BID 2 : Goshen Avenue from Demaree to Mooney Don Berry Construction Kingsburg, CA
Agee Construction
Clovis, CA
Avison Construction
Madera, CA
Cal Valley Construction
Fresno, CA
BASE BID : Goshen Avenue from Shirk to Akers
ALTERNATE BID 1 : Goshen Avenue from Akers to Demaree
Papich Construction
Arroyo Grande, CA
Papich Construction
Arroyo Grande, CA
Don Berry Construction
Kingsburg, CA
Don Berry Construction
Kingsburg, CA
Avison Construction
Madera, CA
Avison Construction
Madera, CA
Cal Valley Construction
Fresno, CA
Cal Valley Construction
Fresno, CA
1 of 1 4/15/2022