ESTIMATE NO.

Phone: (559) 651-5800
Fax: (559) 651-5015
TITLE: DATE: 9/19/2022
PROJECT: JOB NO: N/A
TO: Visalia Airport CONTRACT NO: N/A
C/O: Jody Miller PO NO: N/A
9501 W Airport Drive
Visalia, CA 93277
Phone: (559) 713-4282 Fax:

Description:

Documents:

SCOPE
Item Qty. Unit Price
00001 1.00 $2,500.00
00002 1.00 $8,280.00
00003 1.00 $8,500.00
00004 1.00 $3,600.00
00005 1.00 $1,050.00
00006 1.00 $25,465.00
00007 1.00 $38,237.00
00008
Subtotal:
8% OH&P
1% Gen. Liab. Insurance
10% Contingency
Total
APPROVAL:

Name: Date Name: Amal Ortega Date
Firm: Firm:

Project cost savings returned (credited) to Owner.

BJ Perch Construction, Inc.
87,632.00$
7,011.00$
104,284.00$
Notes:

This estimate only covers the direct cost of this items specifically listed above. This estimate is valid for thirty (30) days from the date of issuance and may be revised or rescinded after that date. 877.00$
Excludes any and all City Permits & Fees.

Excludes any and all Architectural / Engineering fees
Excludes any and all concrete or asphalt work.

Excludes any and all painting or concrete sealing / coating - Other than called out above.

Excludes any and all low voltage, fire alarm, security, data or telecommunications. 8,764.00$
Supervision
8,280.00$
8,500.00$ Temp Facilities
Electrical 38,237.00$
-$
Pre Engineered Metal Building 25,465.00$
BJ Perch Construction, Inc.
2022.030.000
7034 W. Pershing Court, Suite A
Visalia, CA 93291
9530 W. Airport Drive Repairs
9530 W. Airport Drive Repairs

DESCRIPTION OF PROPOSAL
Description Net Amount
Repair damaged Pre-Engineered Metal Building. Remove and replace damaged panels, gutter and door. Remove and replace damaged electrical components. New plywood / wood stud backing for electrical components. Paint door.

Excludes any and all lighting modifications or modifications to electrical system not involved with repair work.

All work to be done Monday through Friday, 7:00 AM to 3:30 PM.

Administration
2,500.00$
Excludes any and all security guard(s) and or fire watch.

Rough Carpentry 3,600.00$
Excludes any and all fire sprinkler work.

Includes prevailing wages.

Paint Door 1,050.00$